IR 05000237/2023004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000237/2023004 and 05000249/2023004
ML24033A161
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 02/02/2024
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2023004
Download: ML24033A161 (1)


Text

SUBJECT:

DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3-INTEGRATED INSPECTION REPORT 05000237/2023004 AND 05000249/2023004

Dear David Rhoades:

On December 31, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Dresden Nuclear Power Station, Units 2 and 3. On January 16, 2024, the NRC inspectors discussed the results of this inspection with C. Joseph, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000237 and 05000249 License Nos. DPR-19 and DPR-25

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000237 and 05000249

License Numbers:

DPR-19 and DPR-25

Report Numbers:

05000237/2023004 and 05000249/2023004

Enterprise Identifier:

I2023004-0050

Licensee:

Constellation Energy Generation, LLC

Facility:

Dresden Nuclear Power Station, Units 2 and 3

Location:

Morris, IL

Inspection Dates:

October 01, 2023 to December 31, 2023

Inspectors:

M. Domke, Reactor Inspector

J. Kutlesa, Emergency Preparedness Inspector

M. Porfirio, Illinois Emergency Management Agency

J. Reed, Health Physicist

C. St. Peters, Resident Inspector

J. Steffes, Senior Resident Inspector

Approved By:

Robert Ruiz, Chief

Reactor Projects Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Dresden Nuclear Power Station, Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000237, 05000249/202300401 2/3 Emergency Diesel Generator Output Breaker Opened During Surveillance Testing 71152A Open

PLANT STATUS

Unit 2 began the inspection period in coast down to prepare for refueling outage D2R28.

On October 29, 2023, the unit was shut down to commence D2R28. The unit was synchronized to the grid on November 17, 2023, and ascended to full power the next day.

On November 25, 2023, reactor power was lowered to 69 percent to perform rod pattern adjustment. The unit was returned to full power on November 26, 2023. On December 9, 2023, reactor power was lowered to 64 percent to perform rod pattern adjustment. The unit was returned to full power the next day and remained at or near full power for the remained of the inspection period.

Unit 3 began the inspection period at rated thermal power. On December 30, 2023, reactor power was lowered to 81 percent to perform a rod pattern adjustment. The unit was returned to full power on December 31, 2023, and remained at or near full power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 2 core spray system on November 3-December 20, 2023.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 8.2.5B, Unit 2 Low Pressure Heater Bays Elev. 517' on November 2, 2023

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Unit 2 2A low pressure coolant injection heat exchanger

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

The inspectors evaluated boiling-water reactor nondestructive testing and welding activities by observing and reviewing the following activities from October 30, 2023, to November 7, 2023.

(1)

1. Volumetric, automated, phased array ultrasonic examination of augmented

IGSCC category D jet pump instrumentation nozzle reducer-toreducer weld 2/1/JPIA/N20A5

2. Volumetric, manual, phased array ultrasonic examination of augmented

IGSCC category D isolation condenser, safe end-tonozzle weld, 2/2/1302B12/127

3. Volumetric, manual, phased array ultrasonic examination of augmented

IGSCC category D shutdown cooling pipe-tovalve weld, 2/1/1001B16/1610(A)

4. Volumetric, manual, conventional ultrasonic examination of thermal fatigue

category RA low pressure coolant injection pipe-topipe weld, 2/1/150616/16K4

5. Visual examination, VT3, of ASME class 1 strut support on reactor head

spray piping, 2/1/03042.5/M1167D1

6. Replacement activities for ASME class 2 pressure boundary welds for Unit 2

standby liquid control fittings completed in work order (WO) 05017094

7. Replacement activities for ASME class 2 pressure boundary welds for Unit 2

emergency core cooling jockey pump piping completed in WO 05142586

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during shutdown on October 29, 2023, and startup on November 15, 2023, for refueling outage D2R28.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed crew performance in the simulator during scenarios LT SEG 2302A and LT SEG 2302B on October 18, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 2 isolation condenser valve 21301-3

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Elevated fire risk due to planned work on the 480V MCC breaker for MOV 21501-20B on October 5, 2023
(2) Emergent activities and troubleshooting for Unit 3 drywell cooler C tripping on October 12-16, 2023
(3) Review of plant aggregate risk and risk management actions for the week of October 16, 2023, while Unit 2 isolation condenser and 2A circulating water pump were unavailable
(4) Review of plant aggregate risk and risk management actions for the week of October 23, 2023, while 2/3 service water pump and Division II low pressure coolant injection were unavailable
(5) Review of plant aggregate risk and risk management actions while the 231 vital bus was unavailable
(6) Plant aggregate risk and risk management actions review while Unit 3 offsite power transformer lost control power on November 28-29, 2023
(7) Emergent activities and troubleshooting for the Unit 2 B core spray following a failure of the 2B pump to start during a routine surveillance, on December 12, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 2 station blackout diesel generator functionality review following coolant leak as noted in CR 4706892
(2) Unit 3 offgas system review following high radiation alarm as documented in CR 4719418
(3) Unit 3 high pressure coolant injection (HPCI) functionality review following inability to complete HPCI fast start as documented in CR 4720435

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated refueling outage D2R28 activities from October 29-November 17, 2023.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (10 Samples)

(1) Control room emergency ventilation system fragnet post-maintenance testing, the week of September 25, 2023
(2) Replacement of U3 main steam line D low pressure isolation switch 30261-30D and subsequent test, on October 5, 2023
(3) Replacement of U2 reactor protection system relay 20590-101A and subsequent test, per WO 1283609
(4) Calibration following replacement of Unit 2 reactor high pressure scram pressure transmitter 20263-55B, per WO 1404115
(5) Calibration following replacement of Unit 2 reactor high pressure scram pressure transmitter 20263-55D, per WO 1404120
(6) Local leak rate test following valve maintenance on 1A main steam isolation valve, per WO 5028130
(7) Local leak rate test following valve maintenance on 2C main steam isolation valve, per WO 5028128
(8) Integrated leak rate test on November 13-14, 2023
(9) Hydrostatic testing on November 12, 2023
(10) HPCI steam supply valve inspection and diagnostic testing following valve repack, per WO 4750831

Surveillance Testing (IP Section 03.01) (1 Sample)

(1) U2 Division I under voltage testing on November 6, 2023

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1) Reactor water cleanup inlet isolation valves on November 1, 2023

Reactor Coolant System Leakage Detection Testing (IP Section 03.01) (1 Sample)

(1) Unit 2 drywell unidentified leakage increase from October 25-November 15, 2023

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.0102.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.

§50.54(q) Program Evaluation/Assessment Review Evaluation No.: 2158:

Emergency Action Levels for Dresden Station: EPAA1004 Addendum 3, Revision 13 of November 20, 2021

  • EPAA1004, Addendum 3: Emergency Action Levels for Dresden Station, Revision 13
  • EPAA1004, Addendum 1: Dresden Station OnShift Staffing Technical Basis, Revision 2
  • EPAA1004, Addendum 2: Evacuation Time Estimates for Dresden Generating Station Plume Exposure Pathway Emergency Planning Zone (KLD TR - 634, rev. 0), Revision 01
  • EPAA1004, Radiological Emergency Plan Annex for Dresden Station, Revision 39 This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Focused area drill on December 7,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1) Licensee surveys of potentially contaminated material leaving the radiologically controlled area (RCA)
(2) Workers exiting the RCA during a Unit 2 refueling outage

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated the licensees control of radiological hazards for the following radiological work:

(1) Drywell core spray work
(2) Drywell shielding activities
(3) Turbine building sand blasting activities
(4) Refuel floor activities High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following high radiation areas and very high radiation areas (VHRAs):

(1) Unit 3 high pressure heater room
(2) Unit 2 reactor head stand
(3) Unit 2 RBEDT room Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.03 - InPlant Airborne Radioactivity Control and Mitigation

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices.

OTHER ACTIVITIES-BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 2 (October 1, 2022 through September 30, 2023)
(2) Unit 3 (October 1, 2022 through September 30, 2023)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1) Unit 2 (June 1, 2022 through August 31, 2023)
(2) Unit 3 (June 1, 2022 through August 31, 2023)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) June 1, 2022 through August 31, 2023 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) June 1, 2022 through August 31, 2023

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)2/3 emergency diesel generator output breaker opened during surveillance testing

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in procedure use and adherence that might be indicative of a more significant safety issue.

INSPECTION RESULTS

Unresolved Item (Open)2/3 Emergency Diesel Generator Output Breaker Opened During Surveillance Testing URI 05000237,05000249/202300401 71152A

Description:

At 12:55 a.m. Central on January 30, 2023, the 2/3 emergency diesel generator (EDG) was declared inoperable to perform monthly operability surveillance testing. The licensee performed a low idle local start of the EDG, closed in 2/3 diesel output breaker to bus 331 and achieved full load at 1:46 a.m. At 3:06 a.m., the 2/3 EDG breaker to bus 331 tripped open unexpectedly. The EDG responded as expected and achieved idle conditions. At 3:10 a.m., the 2/3 EDG was placed in a secured status, declared inoperable and unavailable and troubleshooting efforts commenced.

During troubleshooting the licensee discovered a loose banana jack in the 2/3 EDG local control panel which is mounted to the side of the 2/3 EDG at TB25C. The licensee was able to tighten the banana jack five turns. The loose banana jack resulted in control circuitry wiring being loose and caused the open circuit conditions observed during unloaded diesel run troubleshooting. Once the banana jack was tightened and the control wiring properly secured, the 2/3 EDG successfully passed the monthly operability surveillance test and was restored to an operable and available status at 4:22 p.m. on February 1, 2023.

The inspectors determined that the banana jack at TB25C had become lose over time from vibrations during diesel operation. This in turn, caused the underlying wiring to become unsecured, resulting in a loss of continuity and causing voltage fluctuations. The fluctuating voltage affected the excitation circuitry and could cause a loss of excitation voltage, preventing the diesel generator from functioning. During the January 30 testing, these voltage fluctuations caused the output breaker to open as a protective measure. During emergency operation, such as a loss of offsite power event, this breaker protective feature is blocked, and the breaker will remain closed; however, the voltage fluctuations could still result in a loss of excitation, and therefore the diesel could not be counted on to reliably function.

During normal operation, relay VSR would pick up, seal in, and energize relays ER and EXC.

The EXC relay contacts ensure proper operation of the excitation circuitry. The voltage fluctuations could result in a loss of voltage to all three relays and, due to the open EXC relay, the loss of the excitor reflashing current. The loss of the reflashing current energized relay RTDG 2/3 and the associated contact caused the output breaker to trip. During an emergency start, such as from a loss of offsite power, the RTDG 2/3 relay is blocked, and the breaker would remain closed. However, the VSR, ER and EXC relays would function as normal, and a loss of excitation could occur preventing the EDG from functioning.

Inspector review identified that the banana jack had been installed on March 26, 2019, under work order 466527806, 2/3 10 Year EDG Time Delay Relay (TDR3) Replacement, in accordance with procedure DIP 210028, Banana Jack Adapter Installation, Revision 15.

Procedure DIP 210028 specified the banana jack installed at terminal block TB25C terminal point 12 torqued snug tight. On July 31, 2020, the licensee documented in condition report 4360154, Procedure Revisions Required - Corporate Torque HIT Actions, that procedure use of torque snug tight was no longer acceptable direction for tightening components and specifically identified that procedure DIP 210028 required revision.

The inspectors determined from further review of CR 4360154 that the licensee had changed torque requirements for the installation of banana jacks from a required torque value to snug tight, when procedure DIP 210028, Banana Jack Adapter Installation, Revision 12 was issued on March 23, 2012. The inspectors reviewed condition reports 957053 Banana Jack Defective, Did Not Install for Pre Outage, 1094898 Banana Jacks Adapters are Defective, Cannot Torque, 1104972 Cannot Achieve Torque Value of Banana Jack, and 1110756 Torque Specs in Procedure Are Not Correct, generated between August 24, 2009, and September 8, 2010, which documented material deficiency issues noted during banana jack installation while attempting to torque the banana jacks to the procedurally required value.

Specifically, the licensee encountered an issue where the plastic hex nut bonded to the banana jack metal part would strip and spin freely during torquing evolutions.

Condition report 1110756 action item 2 was created to review recommended torque values of 10-12 in-lbs as recommended by Vendor against Dresden Design Criteria. The licensee documented that Pomona had originally recommended the 1516 inlbs torque as the maximum torque based on Calculation CMED048403, Evaluation of Pomona Banana Jack Adapters for Terminal Blocks Identified in CECo EM Standards. CMED048403 calculated and documented required thread engagement to ensure the banana jack did not impact system function when installed. The inspectors noted that CMED048403 documented the torque value for #832 screws as 16 inlbs and that the Pomona recommended torque values for adapters were also applicable for existing terminal screws. The inspectors determined that an evaluation against original design requirements had not been provided nor an evaluation of minimum torque requirement established.

The inspectors reviewed alternate part replacement evaluation M19961190-003 which was referenced associated with the establishment of procedure DIP 210028, Revision 0, and documented the review of CMED057854 for the use of banana jack adapters have been analyzed as being better or equal to the original terminal screws for all areas of the plant with exceptions. CMED057854, Calcs. For Eval. the Use of Banana Jack Adapters in Harsh Environments, Revision 1, which stated, in part, that the function of these [Pomona terminal strip banana jack] adapters is to maintain the continuity of the electrical circuit where they are located. This is performed by the threaded portion of the adapter which replaces the screw in a terminal strip. Per CMED-048403 the metal portion of the subject adapters has been evaluated and found to meet the requirements of CECo Standard M-EM-0012. Also, the recommended torque values for the adapters are applicable to the existing terminal screws.

Finally, it was concluded that there is no significant effect on the qualification of the terminal block. Therefore, the properly installed adapters will maintain the continuity of the electrical circuit where they are located. See CMED-048403 for torque and minimum thread engagement requirements.

The licensee reviewed NC0057, Torque Requirements, Revision 2, and chose to change banana jack installation to snug tight based on Section 2.6.2 and 2.4.2 because of the material deficiency concerns encountered during maintenance. Section 2.6.2 stated, Unless otherwise specified on the Electrical Installation Documents, lug connections at terminal blocks shall be tightened snug tight as defined in 2.4.2 (For hardware less than 1/4 in diameter). Section 2.4.2 (For hardware less than 1/4 in diameter) stated, The tightness attained by the force necessary to bring a fastener into acceptable contact/alignment and set the fastener (nut, bolt, screw, etc.) so that is will not loosen by itself. The inspectors determined that the licensee had established the torque value of 15-16 inlbs. based on design analysis and vendor recommendation but had not been provided a similar analysis for the reduction in torque requirement to snug tight to ensure proper thread engagement and therefore circuit continuity were maintained.

The inspectors determined that the licensee did not perform a review of plant equipment which had banana jacks installed in accordance with the superseded snug tight instructions, to determine if these jacks still securely held the underlying wiring. As a result, the banana jacks installed on the 2/3 EDG had loosened over time from diesel operation, causing the underlying wires to become unsecured. The unsecured wires resulted in a loss of continuity causing voltage fluctuations which could affect the operability of the diesel. The licensee performed torque checks on the banana jacks installed on the Unit 2 and 3 diesels and determined that they were secure and met the current requirement of procedure DIP 210028.

Planned Closure Actions: The inspectors previous review identified an issue of concern with respect to design control. In order to determine whether the issue of concern is a performance deficiency or violation, the inspectors plan to review the original design documents associated with the terminal screws and terminal blocks prior to banana jack installation. Additionally, the inspectors will review the process, procedures and documents the licensee used to evaluate the design change from terminal screws to banana jacks.

Finally, the inspectors will request and review all documents generated for use of commercially available parts in a quality application.

Licensee Actions: Corrective actions included, but were not limited to, securing the excitation circuitry wires by installing the banana jack at TB25C to required torque in accordance with procedural requirements and reperforming an operability run of the 2/3 EDG, and performing an extent of condition review for similar conditions on the other two EDGs, as well as the station blackout diesels.

Corrective Action References: CR 4551179 2/3 EDG Output Breaker Trip, CR 4687009 NRC Question: 2/3 EDG Banana Jacks, CR 4691063 U2 Extent of Condition Review from IR 4551179, CR 4691067 U3 Extent of Condition Review from IR 4551179, CR 4692803 U2 SBO Banana Jack Extent of Condition Walkdown, and CR 4692804 U3 SBO Banana Jack Extent of Condition Walkdown.

Observation: Procedure Use and Adherence Trend Review 71152S The inspectors performed a semiannual review of issues entered into the corrective action program and a cognitive review of plant observations over the period of July 1, 2023, to December 31, 2023, to identify any potential trends that might indicate the existence of a more significant safety issue. In the second half of 2023, the NRC inspectors identified several potential examples of issues with procedure use and adherence.

On July 7, 2023, the inspectors observed operators in the field perform actions during a quarterly surveillance on the diesel generator cooling water pump that should have been marked as N/A, or not applicable. The site identified that those particular steps were not marked as N/A in accordance with procedure HUAA104101, Procedure Use and Adherence. In addition, the site did not include any indication these steps were performed in the record of the surveillance. The inspectors noted the equipment operator entered stop work criteria, and the main control room and infield equipment operators determined the step was not required and should have been N/Ad. The licensee documented the inspectors observation on July 12, 2023, in CR 4690019, NRC ID: Documentation for DOS 660008 Incomplete, performed a fact finding, and issued a site wide human performance (HU) alert to share learnings from the event.

On November 29, 2023, a site employee did not provide the correct reference distance for the U3 HPCI fast initiation start in accordance with the procedure DOS 230007, High Pressure Coolant Injection Fast Initiation. Step E.16. The system engineering was to provide the reference distance that was recorded in step E.16. The reference distance was that measured from the top of gland follower to the bottom of the anti-rotation bar on MO 32301-10, the HPCI test return valve. Valve MO 32301-10 is adjusted to a provided reference distance that will allow the HPCI turbine to demonstrate functionality of its safety function and achieve predefined criteria listed in procedure DOS 230007. The inspectors held discussions with the site where they were informed that the reference distance provided was not for the correct unit, and a peer check was not obtained before the data was provided.

The incorrect value resulted in the site backing out of the surveillance due to expected conditions not being obtained, the surveillance not being credited and rescheduled. The licensee documented this event in CR 4720435 on November 29, 2023. The site noted in discussions with the inspectors that changes are planned to formalize the need for a peer check of the supplied reference distance value and that a fact finding had been performed to better understand the cause.

The inspectors also reviewed CR 4722873, L4 C&TD2R28 LLT/O Restoration Instruction Improvements, generated on December 11, 2023. The site had identified that some tagouts left the restoration instructions to the discretion of the supervisor rather than a prescribed specific lineup. Specifically, containment cooling service water (CCSW) feed to control room emergency ventilation (CREV) refrigeration condensing unit was left to the discretion of the unit supervisor and identified during establishment of the lineup for the CREVs surveillance.

Additionally, the system valve checklist leaves the lineup to the discretion of the unit supervisor. In this event, CREVs was not aligned to the preferred division, Division 2, of CCSW. CCSW provides backup emergency cooling to the Train B refrigeration condensing unit and by proactively aligning to the preferred division of CCSW during restoration; making additional manipulations when initiating CREVs can be avoided. Actions from this CR included, but were not limited to, lining up CREVs to the preferred division, revising DOP 0040M3/M4 to included preferred and alternate lineup, and evaluating creating a standard for use of as required in tagout restoration steps.

The inspectors noted that challenges in procedure use and adherence could present challenges to plant operation and equipment. However, for each potential example identified in the previous paragraphs, the site has taken steps and actions to address and attempt to prevent recurrence. The inspectors did not identify any findings or violations associated with the inspection activities.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 16, 2024, the inspectors presented the integrated inspection results to C. Joseph, Site Vice President, and other members of the licensee staff.
  • On November 3, 2023, the inspectors presented the radiation protection inspection results to P Boyle, Site Vice President, and other members of the licensee staff.
  • On November 7, 2023, the inspectors presented the inservice inspection results to R. McCulloch, and other members of the licensee staff.
  • On December 20, 2023, the inspectors presented the emergency action level and emergency plan changes inspection results to A. Clements, Emergency Preparedness Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Drawings

M27

Diagram of Core Spray Piping

AAO

71111.04

Procedures

DOP 1400M1

Unit 2 Core Spray System

71111.05

Fire Plans

135 U2TB38

FZ 8.2.5B Unit 2 Low Pressure Heater Bays

Elev. 517'

AsFound Pictures

2/14/2023

Miscellaneous

As Left Pictures

2/14/2023

NDE Reports

D2R28 2A LPCI Heat Exchanger Eddy Current Examination

Final Report

11/02/2023

CYDR120413

Cooling and Service Water Chemical Injection Systems

CYDR1204131

Raw Water Chemical Feed Equipment Repair and

Preventative Maintenance Program

Procedures

DOS 150002

Containment Cooling Service Water Pump Test and

Inservice Test (IST)

71111.07A

Work Orders

05305118

D2 Perform HX Thermal Performance

Test - 2A LPCI HX

09/28/2023

04470925

Missed General Visual Exam on ASME Class

MC Valve 28526

01/10/2022

04471230

D2R28 CCSW Piping Replacements

01/11/2022

04534285

D3R27 VT3 ASME Class 3 Support Indications in Crib

House

11/02/2022

04537253

Steam Leak on Unit 2 High Pressure Core Injection Drain

Pot Piping at LS22365

11/16/2022

04550381

Inspect Suction Piping to Valve 23932-500

01/25/2023

Corrective Action

Documents

04714132

D2R28 -ISI Exam Relevant Condition on M1167D1

Support

10/31/2023

D2R28APR04

UT Examination Summary Sheet

11/06/2023

D2R28UT-002

UT Calibration/Examination

10/31/2023

D2R28UT-012

UT Calibration/Examination

11/03/2023

D2R28UT-017

UT Calibration/Examination

11/03/2023

NDE Reports

D2R28UT-019

UT Calibration/Examination

11/04/2023

71111.08G

Procedures

EPRI-DMW-PA1

Procedure for Manual Phased Array Ultrasonic Examination

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

of Dissimilar Metal Welds

ERAA335016

VT3 Visual Examination of Component Supports,

Attachments and Interiors of Reactor Vessels

GEH-PDI-UT2

PDI Generic Procedure for the Ultrasonic Examination of

Austenitic Pipe Welds

GEH-UT258

Procedure for Automated Phased Array Ultrasonic

Examination of Austenitic and Ferritic Similar Metal Piping

Welds with the Topaz

GEH-UT261

Procedure for Automated Ultrasonic Flaw Depth Sizing in

Austenitic and Ferritic Piping Welds with the Topaz

05017094

Need a WO to Replace S4AMC Coded

SBLC Fittings for 2B Train

11/14/2021

Work Orders

05142586

Degraded Piping Off the 21401-4 Jockey Pump

05/04/2022

Miscellaneous

D2R28 Load Profile

10/25/2023

DGP 0101

Unit Startup

208

DGP 0201

Unit Shutdown

177

NFAB720F-1

Control Rod Sequence Review and Approval Sheet

10/26/2023

NFAB720F-1

Control Rod Sequence Review and Approval Sheet

11/14/2023

NFDR7211004

Dresden Unit 2 Rod Sequence

OPAB3001003

ReMa Plan D229001: Unit 2 Startup from All Rods In to

<25% CTP

11/14/2023

71111.11Q

Procedures

OPAB3001003

ReMa Plan D228023: Shutdown for D2R28

10/29/2023

4141412

MOV 21301-3 AsFound Stroke Length High

05/25/2018

Corrective Action

Documents

4456931

Unit 2 Iso Condenser 21301-3 Valve Stroke Length

10/29/2021

2073

Unit 2 Isolation Condenser Valve 21301-3 Opening Setting

Adjustment

2531

Isolation Condenser Expected Heat Removal with 100%

Initial Carryover Fraction Performance

Engineering

Changes

635437

21301-3 Valve Stroke Length Exceeded-Historical

Operability Review

4716611

EM D2 RFL Com MOV Elect Insp & Diagnostic Test 21301-

10/17/2023

71111.12

Work Orders

256862

OP Support MOV 21301-3 Diagnostic + PMT

10/18/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4708978

Unexpected Alarm 9235 E4, U3 Drywell Clr Blower Trip

10/12/2023

4719393

TR32 Transfer Switch Source Available Lights Off

11/23/2023

Corrective Action

Documents

23005

2B Core Spray Pump Fail to Start

2/12/2023

Engineering

Changes

639998

Predictions for U3 Drywell Temperature with a Loss of 3C

Drywell Cooler Fan

Work Week Highlights Week of 10/2/2023

10/05/2023

Miscellaneous

Work Week Highlights Week of 10/23/23 to 10/30/23

10/24/2023

DEP 004027

Megger and Bridge Testing and Acceptance Criteria

MAAA716234

FIN Team Process

OPAA107

Integrated Risk Management

OPAA108111

Adverse Condition Monitoring and Contingency Plan

OPAA108117

Protected Equipment List

10/25/2023

OPDR201012-

1001

Dresden OnLine Fire Risk Management

Procedures

WCAA1011006

OnLine Risk Management and Assessment

2588501

Assist Operations in Breaker Swap Bus 241 Cub 10

2/12/2023

71111.13

Work Orders

2588503

T/S & Repair (C/S 21401-B) 2B Core Spray PP, 21430-

308B (C/S 21401-B) 2B Core Spray PP

Bus 241

2/12/2023

4719661

Operations Crew 3 Clock Reset. Troubleshooting Gland

Seal Condenser Vacuum and Offgas Rads

11/26/2023

Corrective Action

Documents

20435

Unable to Complete U3 HPCI Fast Start per

DOS 230007

11/29/2023

DOS 230003

High Pressure Coolant Injection System Operability and

Quarterly IST Verification Test

20

71111.15

Procedures

DOS 230007

High Pressure Coolant Injection Fast Initiation Test

4712420

Fatigue Assessment

10/25/2023

Corrective Action

Documents

4714371

Fatigue Assessment for Vehicle Incident

11/01/2023

Engineering

Evaluations

640153

D2R28 (FME) Lost Parts Analysis for Reactor Vessel and

Connected Systems

Schedule Reports for Operations 10/2023-11/2023

11/14/2023

71111.20

Miscellaneous

TODI No. DRE

23013

Temporary State Estimator Alarm Setpoints During D2R28

09/22/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

TSP 2023034

Temporary Contact Shielding Permit

11/01/2023

DMP 580018

Load Handling of Heavy Loads and Lifting Devices

DOP 100003

Shutdown Cooling Mode of Operation

DOP 190003

Reactor Cavity, Dryer/Separator Storage Pit and Fuel Pool

Level Control

DOP 650008

Bus 241 to Bus 341 Tie Breaker Operation

DOP 650030

Bus 231 to Bus 331 Tie Breaker Operation

ERAA330001

Section XI Pressure Testing

ERAA335015-

2103

VT2 Visual Examination in Accordance with

ASME 2013 Edition

MAAA716022

Control of Heavy Loads

MAAB756600

Reactor Disassembly

MAAB756601

Reactor Assembly

MADR756600

Dresden Reactor Disassembly

MADR756601

Reactor Assembly

NFAA3301001

Core Verification

Procedures

OPAA108108

Startup Checklist

Corrective Action

Documents

4705708

Unit 2 Entered OPDR108111-1003 for Drywell Floor Drain

Leakage

09/28/2023

Miscellaneous

Adverse

Condition

Monitoring and

Contingency Plan

Unit 2 Drywell Floor Drain Sump InLeakage

09/28/2023

DOS 020101

Unit 2 RPV ASME B & PV Code 1000 PSI System Leakage

Test

DOS 575004

Control Room Train B HVAC and Air Filtration Unit

Surveillance

Procedures

DOS 660006

Bus Undervoltage and ECCS Integrated Functional Test for

Unit 2/3 Diesel Generator to Unit 2

283609

D2 NDO PM RPS 20590-101A Logic Replace Relay

11/09/2023

1308233

Primary Containment (ILRT) Integrated Leak Rate Test

11/14/2023

71111.24

Work Orders

1375034

Ops PMT 2/35741-48A, CCSW Supply Valve Per DOS

160004

09/28/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1687812

Op PMT Leak Check 2/35741-071, Valve Relief

CR HVaC Ref Cond

09/28/2023

248640

AsFound Local Leak Rate Test for Reactor Water Clean Up

Inlet Primary Containment Isolation Valves

11/02/2023

296745

OPS PMT Verify No Leaks at System Pressure

09/27/2023

5354746

IMD Replace PS 30261-30D U3 Main Steam Line D Low

Press Isolation

10/06/2023

5381021

D 2/3 Quarterly TS/com Valve Timing IST

09/28/2023

Calculations

Evaluation No.:

2158

§50.54(q) Program Evaluation/Assessment Review

Evaluation No.: 2158: Emergency Action Levels for

Dresden Station: EPAA1004 Addendum 3

EPAA1004

Radiological Emergency Plan Annex for Dresden Station

EPAA1004

Addendum 3

Emergency Action Levels for Dresden Station

EPAA1004,

Addendum 1

Dresden Station OnShift Staffing Technical Basis

EPAA1004,

Addendum 2

Evacuation Time Estimates for Dresden Generating Station

Plume Exposure Pathway Emergency Planning Zone (KLD

TR - 634, Rev. 0)

71114.04

Procedures

EPDR1000

Dresden Station Radiological Emergency Plan

71114.06

Miscellaneous

4Q2023FAD

Focused Area Drill

2/07/2023

04557060

Fixed Contamination Found Inside Conestoga Trailer

2/23/2023

04692976

Floor Drain Elevated Dose Rates

07/26/2023

Corrective Action

Documents

04698004

Variance Between DLR and ED Dose

08/17/2023

Miscellaneous

23 Alpha

Assessment

RPAA302 Alpha Level Assessment

08/25/2023

NISP-RP005

Access Controls for High Radiation Areas

RPAA3761001

Radiological Posting, Labeling and Marking Standards

RPAA460

Controls for High and Locked High Radiation Areas

Procedures

RPAA460001

Controls for Very High Radiation Areas

23203636

Unit 2 REBDT Room

10/17/2023

23204548

Reactor Cavity Pre-Decon Survey

01/30/2023

71124.01

Radiation

Surveys

23204554

Drywell Basement

10/30/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

23204556

CRD Platform

10/30/2023

23204753

20-64A Piping Cutout

11/01/2023

23204753

Air Sample of 2220-64A Piping Cut Out

11/01/2023

DR0223-00503

D2R28 Drywell Small Scope

DR0223-00505

D2R28 Drywell Temporary Shielding

DR0223-00805

D2R28 Turbine and Generator Sand Blasting Activities

Radiation Work

Permits (RWPs)

DR0223-00906

D2R28 Cavity Decon

04451037

Nuclear Oversite Radiation Protection Audit

11/30/2021

Self-Assessments

467522303

Pre-NRC 71124.01 ALARA

10/23/2023

71124.03

Procedures

RPAA440

Respiratory Protection Program

71151

Miscellaneous

Data Verification Package for Safety System Functional

Failure Performance Indicator, Unit 2 and Unit 3

10/01/2022-

09/30/2023

20435

Unable to Complete U3 HPCI Fast Start per DOS 230007

11/29/2023

Corrective Action

Documents

22873

L4 C&TD2R28 LLT/O Restoration Instruction

Improvements

2/11/2023

Corrective Action

Documents

Resulting from

Inspection

4690019

NRC ID: Documentation for DOS 660008 Incomplete

07/07/2023

HUAA104101

Procedure Use and Adherence

Procedures

RMAA1011008

Processing and Storage of Records

533460039

OPD Div 1 CS Fill/Vent System Following Maintenance

11/17/2023

533460040

OPD Div 2 CS Fill/Vent/Run System Following Maintenance

11/17/2023

71152S

Work Orders

533460042

OPD HPCI Fill/Vent Following Maintenance

11/17/2023