MONTHYEARIR 05000271/19990111999-10-0707 October 1999 Insp Rept 50-271/99-11 on 990809-27.No Violations Noted. Major Areas Inspected:Maint & Engineering IR 05000271/19990061999-09-13013 September 1999 Insp Rept 50-271/99-06 on 990621-0801.Noncited Violation Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19990121999-08-19019 August 1999 Insp Rept 50-271/99-12 on 990628-0811.Violation Noted.Major Areas Inspected:Maint Rule Periodic Evaluation Required by 10CFR50.65(a)(3) IR 05000271/19990051999-07-26026 July 1999 Insp Rept 50-271/99-05 on 990510-0620.Noncited Violations Identified.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000271/19990031999-06-14014 June 1999 Insp Rept 50-271/99-03 on 990329-0509.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance,Plant Support & Review of Maint Rule Program Implementation IR 05000271/19990041999-06-0404 June 1999 Insp Rept 50-271/99-04 on 990426-28.No Violations Noted. Major Areas Inspected:Performance of Emergency Response Organization IR 05000271/19990021999-05-0606 May 1999 Insp Rept 50-271/99-02 on 990215-0328.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance & Plant Support IR 05000271/19990011999-03-16016 March 1999 Insp Rept 50-271/99-01 on 990104-0214.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support Re Security Procedures ML20202G2781999-01-28028 January 1999 Insp Rept 50-271/98-14 on 981122-990104.No Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000271/19980131998-12-23023 December 1998 Insp Rept 50-271/98-13 on 981011-1121.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19980121998-11-10010 November 1998 Insp Rept 50-271/98-12 on 980830-1010.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000271/19980111998-09-30030 September 1998 Insp Rept 50-271/98-11 on 980719-0829.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19980101998-08-14014 August 1998 Insp Rept 50-271/98-10 on 980614-0718.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19980801998-07-24024 July 1998 Corrected Page 23 for Insp Rept 50-271/98-80 Issued on 980716.Section E8.2 Was Amended in Order to Be More Consistent W/Findings Documented in Other Sections of Rept & to More Clearly Reflect NRC Conclusion Re LER 98-005 ML20236Q8831998-07-16016 July 1998 Insp Rept 50-271/98-80 on 980518-0605.Violations Noted.Major Areas Inspected:Aspects of Licensee Engineering & Technical Support Operations as They Pertain to C/A Program,Se & Core Engineering Programs & Processes IR 05000271/19980091998-07-10010 July 1998 Insp Rept 50-271/98-09 on 980609-19.Violations Noted.Major Areas Inspected:Personnel Actions & Equipment Response Associated w/980609 Event,In Which There Was Rv High Level Water Level Turbine Trip & Reactor Scram IR 05000271/19980061998-07-0202 July 1998 Insp Rept 50-271/98-06 on 980407-0521.Violations Noted.Major Areas Inspected:Aspects of Licensee Engineering & Technical Support Operations Pertaining to Basis for Maint Operations Process IR 05000271/19980081998-07-0101 July 1998 Insp Rept 50-271/98-08 on 980503-0613.Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering, Maint,Plant Support,Insps by Regional Radiation Protection, Emergency Preparedness & Fire Protection Specialists IR 05000271/19980041998-06-0404 June 1998 Insp Rept 50-271/98-04 on 980315-0502.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support Re Unmonitored Access Into Reactor Bldg Vital Area ML20216F9081998-04-13013 April 1998 Insp Rept 50-271/98-05 on 980316-19.Violations Noted.Major Areas Inspected:Selective Exam of Procedures & Representative Records,Interviews W/Personnel,Performance Tests of Security Equipment & Observations by Inspectors IR 05000271/19980011998-04-13013 April 1998 Insp Rept 50-271/98-01 on 980125-0314.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19970121998-03-0303 March 1998 Insp Rept 50-271/97-12 on 971207-980124.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20202D3431998-02-0505 February 1998 Insp Rept 50-271/97-10 on 970929-1120.Violations Noted.Major Areas Inspected:Engineering & Technical Support Operations IR 05000271/19970111997-12-23023 December 1997 Insp Rept 50-271/97-11 on 971031-1206.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20202E7091997-11-28028 November 1997 Insp Rept 50-271/97-08 on 970907-1031.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19970801997-10-16016 October 1997 Insp Rept 50-271/97-80 on 970728-0822.No Violations Noted But Exercise of Discretion Was Issued to Ack Effort to Correct Violation.Major Areas Inspected:Review of Fire Protection & Engineering IR 05000271/19970061997-10-0101 October 1997 Insp Rept 50-271/97-06 on 970720-0906.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering, Maintenance,& Plant Support IR 05000271/19970071997-09-0404 September 1997 Insp Rept 50-271/97-07 on 970826.No Violations Noted.Major Areas Inspected:Licensee Access Authorization Program ML20210R0151997-08-27027 August 1997 Design Insp Rept 50-271/97-201 on 970505-0613.No Violations Noted.Major Areas Inspected:Lpci & RHRSW Sys IR 05000271/19970051997-08-19019 August 1997 Insp Rept 50-271/97-05 on 970601-07-19.Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20141G9211997-07-0707 July 1997 Insp Rept 50-271/97-04 on 970420-0531.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19970031997-05-0808 May 1997 Insp Rept 50-271/97-03 on 970309-0419.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19970011997-04-23023 April 1997 EP Insp Rept 50-271/97-01 on 970318-20.No Violations Noted. Major Areas Inspected:Licensee Emergency Response Organization Performance During EP Exercise ML20140C5931997-04-0909 April 1997 Insp Rept 50-271/97-02 on 970119-0308.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19960111997-02-12012 February 1997 Insp Rept 50-271/96-11 on 961208-970118.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19960091996-12-0202 December 1996 Insp Rept 50-271/96-09 on 960901-1019.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19960081996-09-24024 September 1996 Insp Rept 50-271/96-08 on 960714-0831.No Violations Noted. Major Areas Inspected:Engineering,Maint & Plant Support ML20149L3431996-02-14014 February 1996 Insp Rept 50-271/95-25 on 951107-951231.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering, Plant Support & Safety Assessment & Quality Verification IR 05000271/19950251995-11-30030 November 1995 Insp Rept 50-271/95-25 on 951113-17.No Violations Noted. Major Areas Inspected:Effectiveness of Management Controls, Alarm Stations & Communications & Testing,Maintenance & Compensatory Measures IR 05000271/19940131994-08-0404 August 1994 Insp Rept 50-271/94-13 on 940515-0625.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering,Plant Support & Safety Assessment & Quality Verification IR 05000271/19930341994-01-12012 January 1994 Insp Rept 50-271/93-34 on 931213-17.No Violations Noted. Major Areas inspected:follow-up of Previously Identified Security Items,Security Mgt Effectiveness & Audits,Protected Area Access Control of Personnel & Security Training IR 05000271/19930301994-01-0303 January 1994 Insp Rept 50-271/93-30 on Stated Dates.No Violations Noted.Major Areas Inspected:Licensee Mgt Control Program in Area of Design Change & Mods,Technical Adequacy of Design Changes & Progress in SE Improvement Program IR 05000271/19930261993-12-22022 December 1993 Insp Rept 50-271/93-26 on 931010-1127.Violation Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19930281993-12-22022 December 1993 Safety Insp 50-271/93-28 on Stated Date.No Violations Noted. Major Areas Inspected:Remp,Mgt Controls,Quality Assurance Audits,Meterological Monitoring Program,Quality Control Program & Implementation of Offsite Dose Calculation IR 05000271/19930311993-12-20020 December 1993 Insp Rept 50-271/93-31 on 931115-19.No Violations Noted. Major Areas Inspected:Personnel Interviews,Surveillance Test Observations & Independent Exam of Selected Procedures, Records & Documents IR 05000271/19930161993-12-15015 December 1993 Insp Rept 50-271/93-16 on 931011-15.No Violations Noted. Major Areas Inspected:Insp of Util GL 89-10,motor-operated Valve Testing Program Conducted in Accordance W/Nrc Temporary Instruction 2515/109 IR 05000271/19930291993-11-18018 November 1993 Safety Insp Rept 50-271/93-29 on 931108-10.Violations Noted. Major Areas Inspected:Safeguards Class 1E Electrical Buses Being in Degraded Operability State of Insufficient Seismic Attachments IR 05000271/19930241993-11-12012 November 1993 Insp Rept 50-271/93-24 on 931004-08.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program Changes,Emergency Facilities,Equipment & Supplies, Organization & Mgt Control & Emergency Response Training IR 05000271/19930271993-11-10010 November 1993 Insp Rept 50-271/93-27 on 931018-22.No Safety Concerns or Violations Noted.Major Areas Inspected:Security Program Plans,Protected Area & Isolation Zone Lighting,Vital Area Physical Barriers & Detection Aids & Security Training IR 05000271/19930211993-11-10010 November 1993 Insp Rept 50-271/93-21 on 930912-1009.Major Areas Inspected: Operations,Maint,Engineering & Plant Support 1999-09-13
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000271/19990111999-10-0707 October 1999 Insp Rept 50-271/99-11 on 990809-27.No Violations Noted. Major Areas Inspected:Maint & Engineering IR 05000271/19990061999-09-13013 September 1999 Insp Rept 50-271/99-06 on 990621-0801.Noncited Violation Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19990121999-08-19019 August 1999 Insp Rept 50-271/99-12 on 990628-0811.Violation Noted.Major Areas Inspected:Maint Rule Periodic Evaluation Required by 10CFR50.65(a)(3) IR 05000271/19990051999-07-26026 July 1999 Insp Rept 50-271/99-05 on 990510-0620.Noncited Violations Identified.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000271/19990031999-06-14014 June 1999 Insp Rept 50-271/99-03 on 990329-0509.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance,Plant Support & Review of Maint Rule Program Implementation IR 05000271/19990041999-06-0404 June 1999 Insp Rept 50-271/99-04 on 990426-28.No Violations Noted. Major Areas Inspected:Performance of Emergency Response Organization IR 05000271/19990021999-05-0606 May 1999 Insp Rept 50-271/99-02 on 990215-0328.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance & Plant Support IR 05000271/19990011999-03-16016 March 1999 Insp Rept 50-271/99-01 on 990104-0214.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support Re Security Procedures ML20202G2781999-01-28028 January 1999 Insp Rept 50-271/98-14 on 981122-990104.No Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000271/19980131998-12-23023 December 1998 Insp Rept 50-271/98-13 on 981011-1121.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19980121998-11-10010 November 1998 Insp Rept 50-271/98-12 on 980830-1010.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000271/19980111998-09-30030 September 1998 Insp Rept 50-271/98-11 on 980719-0829.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19980101998-08-14014 August 1998 Insp Rept 50-271/98-10 on 980614-0718.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19980801998-07-24024 July 1998 Corrected Page 23 for Insp Rept 50-271/98-80 Issued on 980716.Section E8.2 Was Amended in Order to Be More Consistent W/Findings Documented in Other Sections of Rept & to More Clearly Reflect NRC Conclusion Re LER 98-005 ML20236Q8831998-07-16016 July 1998 Insp Rept 50-271/98-80 on 980518-0605.Violations Noted.Major Areas Inspected:Aspects of Licensee Engineering & Technical Support Operations as They Pertain to C/A Program,Se & Core Engineering Programs & Processes IR 05000271/19980091998-07-10010 July 1998 Insp Rept 50-271/98-09 on 980609-19.Violations Noted.Major Areas Inspected:Personnel Actions & Equipment Response Associated w/980609 Event,In Which There Was Rv High Level Water Level Turbine Trip & Reactor Scram IR 05000271/19980061998-07-0202 July 1998 Insp Rept 50-271/98-06 on 980407-0521.Violations Noted.Major Areas Inspected:Aspects of Licensee Engineering & Technical Support Operations Pertaining to Basis for Maint Operations Process IR 05000271/19980081998-07-0101 July 1998 Insp Rept 50-271/98-08 on 980503-0613.Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering, Maint,Plant Support,Insps by Regional Radiation Protection, Emergency Preparedness & Fire Protection Specialists IR 05000271/19980041998-06-0404 June 1998 Insp Rept 50-271/98-04 on 980315-0502.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support Re Unmonitored Access Into Reactor Bldg Vital Area ML20216F9081998-04-13013 April 1998 Insp Rept 50-271/98-05 on 980316-19.Violations Noted.Major Areas Inspected:Selective Exam of Procedures & Representative Records,Interviews W/Personnel,Performance Tests of Security Equipment & Observations by Inspectors IR 05000271/19980011998-04-13013 April 1998 Insp Rept 50-271/98-01 on 980125-0314.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19970121998-03-0303 March 1998 Insp Rept 50-271/97-12 on 971207-980124.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20202D3431998-02-0505 February 1998 Insp Rept 50-271/97-10 on 970929-1120.Violations Noted.Major Areas Inspected:Engineering & Technical Support Operations IR 05000271/19970111997-12-23023 December 1997 Insp Rept 50-271/97-11 on 971031-1206.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20202E7091997-11-28028 November 1997 Insp Rept 50-271/97-08 on 970907-1031.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19970801997-10-16016 October 1997 Insp Rept 50-271/97-80 on 970728-0822.No Violations Noted But Exercise of Discretion Was Issued to Ack Effort to Correct Violation.Major Areas Inspected:Review of Fire Protection & Engineering IR 05000271/19970061997-10-0101 October 1997 Insp Rept 50-271/97-06 on 970720-0906.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering, Maintenance,& Plant Support IR 05000271/19970071997-09-0404 September 1997 Insp Rept 50-271/97-07 on 970826.No Violations Noted.Major Areas Inspected:Licensee Access Authorization Program ML20210R0151997-08-27027 August 1997 Design Insp Rept 50-271/97-201 on 970505-0613.No Violations Noted.Major Areas Inspected:Lpci & RHRSW Sys IR 05000271/19970051997-08-19019 August 1997 Insp Rept 50-271/97-05 on 970601-07-19.Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20141G9211997-07-0707 July 1997 Insp Rept 50-271/97-04 on 970420-0531.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19970031997-05-0808 May 1997 Insp Rept 50-271/97-03 on 970309-0419.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19970011997-04-23023 April 1997 EP Insp Rept 50-271/97-01 on 970318-20.No Violations Noted. Major Areas Inspected:Licensee Emergency Response Organization Performance During EP Exercise ML20140C5931997-04-0909 April 1997 Insp Rept 50-271/97-02 on 970119-0308.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19960111997-02-12012 February 1997 Insp Rept 50-271/96-11 on 961208-970118.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19960091996-12-0202 December 1996 Insp Rept 50-271/96-09 on 960901-1019.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19960081996-09-24024 September 1996 Insp Rept 50-271/96-08 on 960714-0831.No Violations Noted. Major Areas Inspected:Engineering,Maint & Plant Support ML20149L3431996-02-14014 February 1996 Insp Rept 50-271/95-25 on 951107-951231.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering, Plant Support & Safety Assessment & Quality Verification IR 05000271/19950251995-11-30030 November 1995 Insp Rept 50-271/95-25 on 951113-17.No Violations Noted. Major Areas Inspected:Effectiveness of Management Controls, Alarm Stations & Communications & Testing,Maintenance & Compensatory Measures IR 05000271/19940131994-08-0404 August 1994 Insp Rept 50-271/94-13 on 940515-0625.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering,Plant Support & Safety Assessment & Quality Verification IR 05000271/19930341994-01-12012 January 1994 Insp Rept 50-271/93-34 on 931213-17.No Violations Noted. Major Areas inspected:follow-up of Previously Identified Security Items,Security Mgt Effectiveness & Audits,Protected Area Access Control of Personnel & Security Training IR 05000271/19930301994-01-0303 January 1994 Insp Rept 50-271/93-30 on Stated Dates.No Violations Noted.Major Areas Inspected:Licensee Mgt Control Program in Area of Design Change & Mods,Technical Adequacy of Design Changes & Progress in SE Improvement Program IR 05000271/19930261993-12-22022 December 1993 Insp Rept 50-271/93-26 on 931010-1127.Violation Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19930281993-12-22022 December 1993 Safety Insp 50-271/93-28 on Stated Date.No Violations Noted. Major Areas Inspected:Remp,Mgt Controls,Quality Assurance Audits,Meterological Monitoring Program,Quality Control Program & Implementation of Offsite Dose Calculation IR 05000271/19930311993-12-20020 December 1993 Insp Rept 50-271/93-31 on 931115-19.No Violations Noted. Major Areas Inspected:Personnel Interviews,Surveillance Test Observations & Independent Exam of Selected Procedures, Records & Documents IR 05000271/19930161993-12-15015 December 1993 Insp Rept 50-271/93-16 on 931011-15.No Violations Noted. Major Areas Inspected:Insp of Util GL 89-10,motor-operated Valve Testing Program Conducted in Accordance W/Nrc Temporary Instruction 2515/109 IR 05000271/19930291993-11-18018 November 1993 Safety Insp Rept 50-271/93-29 on 931108-10.Violations Noted. Major Areas Inspected:Safeguards Class 1E Electrical Buses Being in Degraded Operability State of Insufficient Seismic Attachments IR 05000271/19930241993-11-12012 November 1993 Insp Rept 50-271/93-24 on 931004-08.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program Changes,Emergency Facilities,Equipment & Supplies, Organization & Mgt Control & Emergency Response Training IR 05000271/19930271993-11-10010 November 1993 Insp Rept 50-271/93-27 on 931018-22.No Safety Concerns or Violations Noted.Major Areas Inspected:Security Program Plans,Protected Area & Isolation Zone Lighting,Vital Area Physical Barriers & Detection Aids & Security Training IR 05000271/19930211993-11-10010 November 1993 Insp Rept 50-271/93-21 on 930912-1009.Major Areas Inspected: Operations,Maint,Engineering & Plant Support 1999-09-13
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000271/19990111999-10-0707 October 1999 Insp Rept 50-271/99-11 on 990809-27.No Violations Noted. Major Areas Inspected:Maint & Engineering IR 05000271/19990061999-09-13013 September 1999 Insp Rept 50-271/99-06 on 990621-0801.Noncited Violation Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19990121999-08-19019 August 1999 Insp Rept 50-271/99-12 on 990628-0811.Violation Noted.Major Areas Inspected:Maint Rule Periodic Evaluation Required by 10CFR50.65(a)(3) IR 05000271/19990051999-07-26026 July 1999 Insp Rept 50-271/99-05 on 990510-0620.Noncited Violations Identified.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000271/19990031999-06-14014 June 1999 Insp Rept 50-271/99-03 on 990329-0509.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance,Plant Support & Review of Maint Rule Program Implementation IR 05000271/19990041999-06-0404 June 1999 Insp Rept 50-271/99-04 on 990426-28.No Violations Noted. Major Areas Inspected:Performance of Emergency Response Organization IR 05000271/19990021999-05-0606 May 1999 Insp Rept 50-271/99-02 on 990215-0328.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance & Plant Support IR 05000271/19990011999-03-16016 March 1999 Insp Rept 50-271/99-01 on 990104-0214.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support Re Security Procedures ML20202G2781999-01-28028 January 1999 Insp Rept 50-271/98-14 on 981122-990104.No Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000271/19980131998-12-23023 December 1998 Insp Rept 50-271/98-13 on 981011-1121.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19980121998-11-10010 November 1998 Insp Rept 50-271/98-12 on 980830-1010.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000271/19980111998-09-30030 September 1998 Insp Rept 50-271/98-11 on 980719-0829.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19980101998-08-14014 August 1998 Insp Rept 50-271/98-10 on 980614-0718.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19980801998-07-24024 July 1998 Corrected Page 23 for Insp Rept 50-271/98-80 Issued on 980716.Section E8.2 Was Amended in Order to Be More Consistent W/Findings Documented in Other Sections of Rept & to More Clearly Reflect NRC Conclusion Re LER 98-005 ML20236Q8831998-07-16016 July 1998 Insp Rept 50-271/98-80 on 980518-0605.Violations Noted.Major Areas Inspected:Aspects of Licensee Engineering & Technical Support Operations as They Pertain to C/A Program,Se & Core Engineering Programs & Processes IR 05000271/19980091998-07-10010 July 1998 Insp Rept 50-271/98-09 on 980609-19.Violations Noted.Major Areas Inspected:Personnel Actions & Equipment Response Associated w/980609 Event,In Which There Was Rv High Level Water Level Turbine Trip & Reactor Scram IR 05000271/19980061998-07-0202 July 1998 Insp Rept 50-271/98-06 on 980407-0521.Violations Noted.Major Areas Inspected:Aspects of Licensee Engineering & Technical Support Operations Pertaining to Basis for Maint Operations Process IR 05000271/19980081998-07-0101 July 1998 Insp Rept 50-271/98-08 on 980503-0613.Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering, Maint,Plant Support,Insps by Regional Radiation Protection, Emergency Preparedness & Fire Protection Specialists IR 05000271/19980041998-06-0404 June 1998 Insp Rept 50-271/98-04 on 980315-0502.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support Re Unmonitored Access Into Reactor Bldg Vital Area ML20216F9081998-04-13013 April 1998 Insp Rept 50-271/98-05 on 980316-19.Violations Noted.Major Areas Inspected:Selective Exam of Procedures & Representative Records,Interviews W/Personnel,Performance Tests of Security Equipment & Observations by Inspectors IR 05000271/19980011998-04-13013 April 1998 Insp Rept 50-271/98-01 on 980125-0314.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19970121998-03-0303 March 1998 Insp Rept 50-271/97-12 on 971207-980124.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20202D3431998-02-0505 February 1998 Insp Rept 50-271/97-10 on 970929-1120.Violations Noted.Major Areas Inspected:Engineering & Technical Support Operations IR 05000271/19970111997-12-23023 December 1997 Insp Rept 50-271/97-11 on 971031-1206.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20202E7091997-11-28028 November 1997 Insp Rept 50-271/97-08 on 970907-1031.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19970801997-10-16016 October 1997 Insp Rept 50-271/97-80 on 970728-0822.No Violations Noted But Exercise of Discretion Was Issued to Ack Effort to Correct Violation.Major Areas Inspected:Review of Fire Protection & Engineering IR 05000271/19970061997-10-0101 October 1997 Insp Rept 50-271/97-06 on 970720-0906.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering, Maintenance,& Plant Support IR 05000271/19970071997-09-0404 September 1997 Insp Rept 50-271/97-07 on 970826.No Violations Noted.Major Areas Inspected:Licensee Access Authorization Program ML20210R0151997-08-27027 August 1997 Design Insp Rept 50-271/97-201 on 970505-0613.No Violations Noted.Major Areas Inspected:Lpci & RHRSW Sys IR 05000271/19970051997-08-19019 August 1997 Insp Rept 50-271/97-05 on 970601-07-19.Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20141G9211997-07-0707 July 1997 Insp Rept 50-271/97-04 on 970420-0531.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19970031997-05-0808 May 1997 Insp Rept 50-271/97-03 on 970309-0419.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19970011997-04-23023 April 1997 EP Insp Rept 50-271/97-01 on 970318-20.No Violations Noted. Major Areas Inspected:Licensee Emergency Response Organization Performance During EP Exercise ML20140C5931997-04-0909 April 1997 Insp Rept 50-271/97-02 on 970119-0308.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19960111997-02-12012 February 1997 Insp Rept 50-271/96-11 on 961208-970118.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19960091996-12-0202 December 1996 Insp Rept 50-271/96-09 on 960901-1019.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19960081996-09-24024 September 1996 Insp Rept 50-271/96-08 on 960714-0831.No Violations Noted. Major Areas Inspected:Engineering,Maint & Plant Support ML20149L3431996-02-14014 February 1996 Insp Rept 50-271/95-25 on 951107-951231.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering, Plant Support & Safety Assessment & Quality Verification IR 05000271/19950251995-11-30030 November 1995 Insp Rept 50-271/95-25 on 951113-17.No Violations Noted. Major Areas Inspected:Effectiveness of Management Controls, Alarm Stations & Communications & Testing,Maintenance & Compensatory Measures IR 05000271/19940131994-08-0404 August 1994 Insp Rept 50-271/94-13 on 940515-0625.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering,Plant Support & Safety Assessment & Quality Verification IR 05000271/19930341994-01-12012 January 1994 Insp Rept 50-271/93-34 on 931213-17.No Violations Noted. Major Areas inspected:follow-up of Previously Identified Security Items,Security Mgt Effectiveness & Audits,Protected Area Access Control of Personnel & Security Training IR 05000271/19930301994-01-0303 January 1994 Insp Rept 50-271/93-30 on Stated Dates.No Violations Noted.Major Areas Inspected:Licensee Mgt Control Program in Area of Design Change & Mods,Technical Adequacy of Design Changes & Progress in SE Improvement Program IR 05000271/19930261993-12-22022 December 1993 Insp Rept 50-271/93-26 on 931010-1127.Violation Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19930281993-12-22022 December 1993 Safety Insp 50-271/93-28 on Stated Date.No Violations Noted. Major Areas Inspected:Remp,Mgt Controls,Quality Assurance Audits,Meterological Monitoring Program,Quality Control Program & Implementation of Offsite Dose Calculation IR 05000271/19930311993-12-20020 December 1993 Insp Rept 50-271/93-31 on 931115-19.No Violations Noted. Major Areas Inspected:Personnel Interviews,Surveillance Test Observations & Independent Exam of Selected Procedures, Records & Documents IR 05000271/19930161993-12-15015 December 1993 Insp Rept 50-271/93-16 on 931011-15.No Violations Noted. Major Areas Inspected:Insp of Util GL 89-10,motor-operated Valve Testing Program Conducted in Accordance W/Nrc Temporary Instruction 2515/109 IR 05000271/19930291993-11-18018 November 1993 Safety Insp Rept 50-271/93-29 on 931108-10.Violations Noted. Major Areas Inspected:Safeguards Class 1E Electrical Buses Being in Degraded Operability State of Insufficient Seismic Attachments IR 05000271/19930241993-11-12012 November 1993 Insp Rept 50-271/93-24 on 931004-08.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program Changes,Emergency Facilities,Equipment & Supplies, Organization & Mgt Control & Emergency Response Training IR 05000271/19930271993-11-10010 November 1993 Insp Rept 50-271/93-27 on 931018-22.No Safety Concerns or Violations Noted.Major Areas Inspected:Security Program Plans,Protected Area & Isolation Zone Lighting,Vital Area Physical Barriers & Detection Aids & Security Training IR 05000271/19930211993-11-10010 November 1993 Insp Rept 50-271/93-21 on 930912-1009.Major Areas Inspected: Operations,Maint,Engineering & Plant Support 1999-09-13
[Table view] Category:UTILITY
MONTHYEARIR 05000271/19900111990-11-0808 November 1990 Partially Withheld Safeguards Insp Rept 50-271/90-11 on 900829-31 (Ref 10CFR73.21).Violation Noted.Major Areas Inspected:Personnel Access Control IR 05000271/19900091990-09-27027 September 1990 Insp Rept 50-271/90-09 on 900703-0812.Violations Noted.Major Areas Inspected:Plant Operations,Radiological Control, Maint/Surveillance,Emergency Preparedness,Security & Safety Assessment/Quality Verification IR 05000271/19900071990-08-20020 August 1990 Insp Rept 50-271/90-07 on 900716-20.No Violations Noted. Major Areas Inspected:Emergency Preparedness & Partial Participation in Emergency Exercise Conducted on 900718 ML20056A4051990-07-24024 July 1990 Insp Rept 50-271/90-06 on 900618-22.Violations Noted.Major Areas Inspected:Radiological Controls Program,Including Status of Previously Identified Items,Organization,External Exposure Controls & Control of Radioactive Matl IR 05000271/19890121989-09-25025 September 1989 Insp Rept 50-271/89-12 on 890718-0905.No Violations Noted. Major Areas Inspected:Previous Insp Findings,Operational Safety,Security,Plant Operations,Maint & Surveillance, Engineering Support,Lers & Periodic Repts IR 05000271/19890141989-09-18018 September 1989 Insp Rept 50-271/89-14 on 890807-11.No New Violations Noted. Major Areas Inspected:Status of Previously Identified Items & Adequacy of Licensee Actions to Resolve Items IR 05000271/19890151989-09-15015 September 1989 Insp Rept 50-271/89-15 on 890821-25.No Violations Noted. Major Areas Inspected:Plant Mods Performed During Recent Refueling Outage or Planned for Next Refueling Outage & Recent LERs IR 05000271/19890111989-09-14014 September 1989 Insp Rept 50-271/89-11 on 890822-24.No Violations Noted. Major Areas Inspected:Licensee Annual Emergency Exercise ML20246Q0301989-08-10010 August 1989 Insp Repts 50-029/89-14 & 50-271/89-10 on 890717-21.No Violations or Deviations Noted.Major Areas Inspected: Corporate Engineering & Offsite Support for Plants & Implementation of Mods IR 05000271/19890091989-07-31031 July 1989 Insp Rept 50-271/89-09 on 890531-0717.Violations Noted. Major Areas Inspected:Actions on Previous Insp Findings, Operational Safety,Security,Plant Operations,Maint & Surveillance,Engineering Support,Lers & Periodic Repts IR 05000271/19890081989-06-28028 June 1989 Partially Withheld Physical Security Insp Rept 50-271/89-08 on 890515-19 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Security Program Plans & Audit,Protected Area, Detection & Assessment Aids IR 05000271/19890071989-06-14014 June 1989 Insp Rept 50-271/89-07 on 890418-0530.No Violations Noted. Major Areas Inspected:Actions on Previous Insp Findings, Operational Safety,Security,Plant Operations,Maint & Surveillance,Engineering Support & LERs ML20244B4681989-06-0101 June 1989 Maint Team Insp Rept 50-271/89-80 on 890227-0310.Violations Noted.Major Areas Inspected:Maint Program & Program Implementation,Including Review of Maint Documents & Observations of Maint Work in Progress IR 05000271/19890041989-05-17017 May 1989 Insp Rept 50-271/89-04 on 890320-23.Violation Noted.Major Areas Inspected:Review Adequacy & Implementation of Fire Protection Program,Including Combustible Matl Control, Housekeeping Conditions,Surveillances & Testing IR 05000271/19890021989-05-0404 May 1989 Insp Rept 50-271/89-02 on 890214-0417.No Violations Noted. Major Areas Inspected:Actions on Previous Insp Findings, Operational Safety,Security,Plant Operations,Maint, Surveillance & Engineering Support ML20246H3541989-05-0303 May 1989 Insp Rept 50-271/89-05 on 890404-07.No Violations or Deviations Noted.Major Areas Inspected:Implementation of ATWS Rule 10CFR50.62,open Items Identified in Previously Issued Insp Repts & Surveillance & Calibration Program IR 05000271/19890061989-04-26026 April 1989 Insp Rept 50-271/89-06 on 890403-07.No Violations Noted. Major Areas Inspected:Low Level Radwaste Storage Facility & Radiation Protection Supervisor Qualifications IR 05000271/19890031989-04-13013 April 1989 Insp Rept 50-271/89-03 on 890320-24.No Violations Noted. Major Areas Inspected:Inservice Insp Activities to Determine Compliance W/Applicable ASME Code & Regulatory Requirements & Actions on Generic Ltr 88-01 IR 05000271/19890011989-03-19019 March 1989 Insp Rept 50-271/89-01 on 890104-0213.No Violations Noted. Major Areas Inspected:Operational Safety,Security,Plant Operations,Maint & Surveillance,Engineering Support & Radiological Controls.Weakness Noted.Supporting Info Encl IR 05000271/19880141988-11-0404 November 1988 Insp Rept 50-271/88-14 on 880823-1010.Violations & Unresolved Items Noted.Major Areas Inspected:Actions on Previous Insp Findings,Operational Safety,Security,Plant Operations,Maint & Surveillance & Engineering Support IR 05000271/19880181988-11-0303 November 1988 Insp Rept 50-271/88-18 on 881005-07.Violation Noted.Major Areas Inspected:Radiological Controls,Mgt Involvement & Licensee Corrective Actions IR 05000271/19880171988-10-21021 October 1988 Insp Rept 50-271/88-17 on 880926-30.No Violations Noted. Major Areas Inspected:Licensee Radwaste Program,Including Training of Personnel,Procurement of Packaging,Delivery to Carriers,Records & Repts & Waste Classification & Labeling IR 05000271/19880161988-10-0404 October 1988 Insp Repts 50-271/88-16 on 880912-16.No Violations or Deviations Noted.Major Areas Inspected:Implementation of Provisions of Inservice Test Program for safety-related Pumps & Valves IR 05000271/19880131988-10-0303 October 1988 Insp Rept 50-271/88-13 on 880830-0901.No Violations Noted. Major Areas Inspected:Annual Emergency Preparedness Exercise Conducted on 880831 IR 05000271/19880111988-09-30030 September 1988 Emergency Preparedness Insp Rept 50-271/88-11 on 880816-18. No Violations Noted.Major Areas Inspected:Emergency Preparedness Program,Emergency Action Levels,Independent Reviews/Audits & Notifications & Communications IR 05000271/19880121988-09-30030 September 1988 Insp Rept 50-271/88-12 on 880808-12.No Violations Noted. Major Areas Inspected:Confirmatory Measurements,Procedures & Records Associated W/Program for QC of Analytical Measurements & Staffing & Controls ML20154Q6141988-09-16016 September 1988 Insp Rept 50-271/88-10 on 880701-0822.No Violations Noted. Major Areas Inspected:Actions on Previous Insp Findings, Operational Safety Security,Plant Operations,Maint & Surveillance,Lers & Licensee Response to NRC Initiatives IR 05000271/19882001988-07-29029 July 1988 Emergency Operating Procedure Insp Rept 50-271/88-200 on 880601-10.Deficiencies Noted:Inadequate Notification of NRC for Deviations from NRC Approved Emergency Procedure Guidelines IR 05000271/19880071988-07-13013 July 1988 Insp Rept 50-271/88-07 on 880523-27.No Violations Noted. Major Areas Inspected:Mgt Effectiveness,Organization, Security Sys Power Supply,Physical Barriers Protected Area & Vital Areas,Lighting & Compensatory Measures ML20151E1381988-07-13013 July 1988 Insp Rept 50-271/88-09 on 880620-24.Unresolved Item Identified.Major Areas Inspected:Offsite Disposal of Sewage Waste Containing Licensed Matl from Jan 1986 - May 1988 IR 05000271/19880081988-07-0808 July 1988 Insp Rept 50-271/88-08 on 880517-0630.No Violations Noted. Major Areas Inspected:Actions on Previous Insp Findings, Operational Safety,Security,Plant Operations,Maint & Surveillance,Engineering Support & Radiological Controls IR 05000271/19880051988-06-0808 June 1988 Insp Rept 50-271/88-05 on 880404-08.Weaknesses Noted.Major Areas Inspected:Facility & Effluent Radiological Controls, Plant Operations,Surveillance Testing,Plant Maint Activities & Design Changes IR 05000271/19880061988-06-0101 June 1988 Insp Rept 50-271/88-06 on 880322-0516.Violations Noted.Major Areas Inspected:Actions on Previous Insp Findings, Operational Safety,Security,Plant Operations,Maint & Surveillance,Ler,Periodic Rept & Engineering Support ML20151C1571988-04-0505 April 1988 Insp Rept 50-271/88-03 on 880209-0321.Violations Noted. Major Areas Inspected:Actions on Previous Findings,Routine Plant Operations,Physical Security,Operational Events,Maint Activities & Licensee Response to NRC Initiatives ML20151C7091988-04-0101 April 1988 Insp Rept 50-271/88-04 on 880208-11.Violations Noted.Major Areas Inspected:Licensee Effort to Comply w/10CFR50,App R Requirements Re Fire Protection Features to Ensure Ability to Achieve & Maintain Safe Shutdown IR 05000271/19870231988-02-26026 February 1988 Insp Rept 50-271/87-23 on 871222-880208.No Violations Noted. Major Areas Inspected:Licensee Action on Previous Insp Findings,Operational Safety,Physical Security,Surveillance Activities,Lers,Operational Events & Maint Activities IR 05000271/19880021988-02-26026 February 1988 Insp Rept 50-271/88-02 on 880201-05.No Violations or Deviations Noted.Major Areas Inspected:Radiological Controls,Including Control of Radioactive Matls,Respiratory Protection & External Exposure Controls IR 05000271/19870161988-02-25025 February 1988 Insp Rept 50-271/87-16 on 870801-1030.Violations Noted. Major Areas Inspected:Licensee Action on Previous Insp Findings,Outage Mgt,Operational Safety Verification,Physical Security Observations,Fitness for Duty Program & LERs IR 05000271/19870211988-01-0808 January 1988 Insp Rept 50-271/87-21 on 871031-1221.No Unacceptable Conditions Noted.Major Areas Inspected:Physical Security, Plant Operations,Maint Activities,Surveillance Activities, Fuel Shipping Operations & NRC Bulletin Responses ML20149M9881988-01-0707 January 1988 Insp Rept 50-271/87-19 on 871019-23.Violations Noted.Major Areas Inspected:Licensee Implementation of Program for Establishing & Maintaining Qualification of Electrical Equipment within Scope of 10CFR50.49 ML20237F1051987-12-18018 December 1987 Insp Rept 50-271/87-14 on 871005-09.No Violations Noted. Major Areas Inspected:Licensee Response to USI A-7 Re Mark I Containment Program,Including Review of Design Analyses & Work Plans for Mods to Torus Suppression Chamber IR 05000271/19870201987-12-17017 December 1987 Partially Withheld Physical Security Insp Rept 50-271/87-20 on 871026-29 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Plan & Implementing Procedures,Program Audits,Testing,Maint,Records,Repts & Physical Barriers IR 05000271/19870221987-12-11011 December 1987 Emergency Preparedness Insp Rept 50-271/87-22 on 871201-04. No Violation Noted.Major Areas Inspected:Emergency Preparedness Insp & 871202 Annual Exercise IR 05000271/19870181987-10-0505 October 1987 Insp Rept 50-271/87-18 on 870824-28.No Violations or Deviations Noted.Major Areas Inspected:Maint Program & Implementation,Including Administrative & Maint Procedures, Trending Program,Records & Preventive Maint Program IR 05000271/19870151987-10-0101 October 1987 Insp Rept 50-271/87-15 on 870817-21.No Violations or Deviations Noted.Major Areas Inspected:Radiological Controls During Outage Operations,Including Outage Planning & Preparation & Control of Radioactive Matl IR 05000271/19870171987-09-18018 September 1987 Insp Rept 50-271/87-17 on 870903-04.No Violations Noted. Major Areas Inspected:Emergency Preparedness,Including Emergency Action Levels,Organization & Mgt & Open Items Identified in Previous Insp Repts IR 05000271/19870111987-08-20020 August 1987 Insp Rept 50-271/87-11 on 870803-07.No Violations Noted. Major Areas Inspected:Preparations for Refueling,Including Refueling Procedure Review,New Fuel Receipt Insp,Training & QA Interface W/Refueling Activities IR 05000271/19870121987-08-19019 August 1987 Insp Rept 50-271/87-12 on 870602-0730.Violation Noted.Major Areas Inspected:Physical Security,Plant Operations,Control Room Habitability Survey,Maint & Spent Fuel Pool Reracking Activities & Actions on Previous Insp Findings IR 05000271/19870131987-08-14014 August 1987 Insp Rept 50-271/87-13 on 870713-17.No Violations or Deviations Noted.Major Areas Inspected:Radioactive Effluents Control Program,Liquids & Liquid Wastes,Gaseous Waste Sys, Process Radiation Monitoring Sys & Auditing Activities IR 05000271/19870091987-06-23023 June 1987 Insp Rept 50-271/87-09 on 870407-0601.No Violations Noted. Major Areas Inspected:Physical Security,Plant Operations, Maint Activities & Fuel Handling Activities.Recurrent Problem in Low Level Radioactive Matl Control Noted 1990-09-27
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000271/19990111999-10-0707 October 1999 Insp Rept 50-271/99-11 on 990809-27.No Violations Noted. Major Areas Inspected:Maint & Engineering IR 05000271/19990061999-09-13013 September 1999 Insp Rept 50-271/99-06 on 990621-0801.Noncited Violation Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20211H0891999-08-19019 August 1999 Notice of Violation from Insp on 990628-0811.Violation Noted:Periodic Assessment Conducted for Period of November 1996 Through May 1998 Did Not Adequately Evaluate Maint Activities as Listed IR 05000271/19990121999-08-19019 August 1999 Insp Rept 50-271/99-12 on 990628-0811.Violation Noted.Major Areas Inspected:Maint Rule Periodic Evaluation Required by 10CFR50.65(a)(3) IR 05000271/19990051999-07-26026 July 1999 Insp Rept 50-271/99-05 on 990510-0620.Noncited Violations Identified.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000271/19990031999-06-14014 June 1999 Insp Rept 50-271/99-03 on 990329-0509.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance,Plant Support & Review of Maint Rule Program Implementation IR 05000271/19990041999-06-0404 June 1999 Insp Rept 50-271/99-04 on 990426-28.No Violations Noted. Major Areas Inspected:Performance of Emergency Response Organization IR 05000271/19993021999-05-28028 May 1999 NRC Operator Licensing Exam Rept 50-271/99-302(including Completed & Graded Tests) for Tests Administered on 990510-11 IR 05000271/19990021999-05-0606 May 1999 Insp Rept 50-271/99-02 on 990215-0328.Non-cited Violations Noted.Major Areas Inspected:Operations,Engineering, Maintenance & Plant Support IR 05000271/19990011999-03-16016 March 1999 Insp Rept 50-271/99-01 on 990104-0214.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support Re Security Procedures ML20202G2781999-01-28028 January 1999 Insp Rept 50-271/98-14 on 981122-990104.No Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000271/19980131998-12-23023 December 1998 Insp Rept 50-271/98-13 on 981011-1121.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000271/19980121998-11-10010 November 1998 Insp Rept 50-271/98-12 on 980830-1010.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support PNO-I-98-048, on 981016,Vermont Yankee Commenced Normal Plant Shutdown,Due to Increasing Steam Leakage from Instrumentation Line on Main Steam High Pressure Drain Sys in Steam Tunnel.Outage Expected to Last Several Days1998-10-16016 October 1998 PNO-I-98-048:on 981016,Vermont Yankee Commenced Normal Plant Shutdown,Due to Increasing Steam Leakage from Instrumentation Line on Main Steam High Pressure Drain Sys in Steam Tunnel.Outage Expected to Last Several Days IR 05000271/19980111998-09-30030 September 1998 Insp Rept 50-271/98-11 on 980719-0829.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000271/19980991998-08-28028 August 1998 SALP Rept 50-271/98-99 for Vermont Yankee Nuclear Power Station for Period of 970119-980718 IR 05000271/19980101998-08-14014 August 1998 Insp Rept 50-271/98-10 on 980614-0718.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000271/19980801998-07-24024 July 1998 Corrected Page 23 for Insp Rept 50-271/98-80 Issued on 980716.Section E8.2 Was Amended in Order to Be More Consistent W/Findings Documented in Other Sections of Rept & to More Clearly Reflect NRC Conclusion Re LER 98-005 ML20236Q8801998-07-16016 July 1998 Notice of Violation from Insp on 980518-0605.Violation Noted:In 1996,SE Performed by Licensee to Support Temporary Mod to MCR HVAC Sys,Did Not Provide Sufficient Basis to Determine That Change Did Not Involve USQ ML20236Q8831998-07-16016 July 1998 Insp Rept 50-271/98-80 on 980518-0605.Violations Noted.Major Areas Inspected:Aspects of Licensee Engineering & Technical Support Operations as They Pertain to C/A Program,Se & Core Engineering Programs & Processes IR 05000271/19980091998-07-10010 July 1998 Insp Rept 50-271/98-09 on 980609-19.Violations Noted.Major Areas Inspected:Personnel Actions & Equipment Response Associated w/980609 Event,In Which There Was Rv High Level Water Level Turbine Trip & Reactor Scram ML20236P9751998-07-10010 July 1998 Notice of Violation from Insp on 980610-0619.Violations Noted:As of 980609,Procedure Ot,Reactor High Level,Rev 9, Did Not Direct or Alert Operators to Place RFW Pump Breaker Control Switches in Pull to Lock to Prevent Start IR 05000271/19980061998-07-0202 July 1998 Insp Rept 50-271/98-06 on 980407-0521.Violations Noted.Major Areas Inspected:Aspects of Licensee Engineering & Technical Support Operations Pertaining to Basis for Maint Operations Process ML20236M2321998-07-0202 July 1998 Notice of Violation from Insp on 980407-0521.Violation Noted:On 970320,licensee Identified That EOPs Directed Operators to Flood Containment to Top of Active Fuel ML20236L3371998-07-0101 July 1998 Notice of Violation from Insp on 980503-0613.Violation Noted:In March 1992,Standby Gas Treatment Sys Fans & Associated Electrical Circuit Breakers Replaced & Not Adequately Translated Into Procedures IR 05000271/19980081998-07-0101 July 1998 Insp Rept 50-271/98-08 on 980503-0613.Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering, Maint,Plant Support,Insps by Regional Radiation Protection, Emergency Preparedness & Fire Protection Specialists PNO-I-98-021, on 980609,automatic Reactor Scram Occurred. Except for Single Control Rod Position Indication Problem, Initial Plant Response to Scram Expected.Licensee Initiated Investigation to Understand Causes of Event Complications1998-06-0909 June 1998 PNO-I-98-021:on 980609,automatic Reactor Scram Occurred. Except for Single Control Rod Position Indication Problem, Initial Plant Response to Scram Expected.Licensee Initiated Investigation to Understand Causes of Event Complications ML20249A1191998-06-0404 June 1998 Notice of Violation from Insp on 980315-0502.Violation Noted:Entrance Pathway to Reactor Bldg Vital Area Was Identified That Was Neither Locked Nor Guarded IR 05000271/19980041998-06-0404 June 1998 Insp Rept 50-271/98-04 on 980315-0502.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support Re Unmonitored Access Into Reactor Bldg Vital Area ML20217B3781998-04-14014 April 1998 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $55,000.Violation Noted:In 1982,licensee Failed to Control Design Interfaces & Failed to Assure That Design Basis for Max Torus Temp Normal Limit,Correctly Translated ML20216F8661998-04-13013 April 1998 Notice of Violation from Insp on 980316-19.Violation Noted: on 980317 During Performance Testing of Protected Area Intrusion Detection Sys,Number of Climbing Attempts,In Multiple Locations,Not Detected That No Alarm Was Generated ML20216F9081998-04-13013 April 1998 Insp Rept 50-271/98-05 on 980316-19.Violations Noted.Major Areas Inspected:Selective Exam of Procedures & Representative Records,Interviews W/Personnel,Performance Tests of Security Equipment & Observations by Inspectors IR 05000271/19980011998-04-13013 April 1998 Insp Rept 50-271/98-01 on 980125-0314.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20247M2441998-04-0909 April 1998 EN-98-021:on 980414,notice of Proposed Imposition of Civil Penalty in Amount of $55,000 Issued to Licensee.Action Based on Problem Involving TS Limit for Max Torus Operating Temp Being Inconsistent W/Plant Design Basis IR 05000271/19970121998-03-0303 March 1998 Insp Rept 50-271/97-12 on 971207-980124.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20216A9921998-03-0303 March 1998 Notice of Violation from Insp on 971207-980224.Violation Noted:Hpci Room App a Fire Barrier Was Found to Be Inoperable on 970113 & Door Would Not Close IR 05000271/19980021998-02-20020 February 1998 NRC Operator Licensing Exam Rept 50-271/98-02OL on 980210. Exam Results:Applicant Passed Simulator Retake Exam & Issued SRO License ML20202D3361998-02-0505 February 1998 Notice of Violation from Insp on 970929-1120.Violation Noted:Prior to 950420,licensee Failed to Assure That Test Instruments Used in RHR Heat Exchanger Performance Testing Were Adequate to Assure Test Requirements Were Satisfied ML20202D3431998-02-0505 February 1998 Insp Rept 50-271/97-10 on 970929-1120.Violations Noted.Major Areas Inspected:Engineering & Technical Support Operations IR 05000271/19970111997-12-23023 December 1997 Insp Rept 50-271/97-11 on 971031-1206.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support IR 07100031/20120061997-12-23023 December 1997 Notice of Violation from Insp on 971031-1206.Violation Noted:Plant Auxiliary Operators Implemented Unapproved Vermont Electric Power Co Switching Order on 971125 to Open 345 Kv Scobie Line 379-3 ML20202E7091997-11-28028 November 1997 Insp Rept 50-271/97-08 on 970907-1031.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20199J4021997-11-22022 November 1997 NRC Operator Licensing Exam Rept 50-271/97-09 for Tests Administered on 970902-04.Two of Four Applicants Passed.One SRO Upgrade Applicant Failed Written & Operating Portion of Exam & One SRO Failed Operating Portion of Exam IR 05000271/19970801997-10-16016 October 1997 Insp Rept 50-271/97-80 on 970728-0822.No Violations Noted But Exercise of Discretion Was Issued to Ack Effort to Correct Violation.Major Areas Inspected:Review of Fire Protection & Engineering ML20217E7011997-10-0101 October 1997 Notice of Violation from Insp on 970720-0906.Violation Noted:Vermont Yankee Staff Failed to Correct Condition Adverse to Quality Involving Standby Gas Treatment Sys over-pressure Vulnerability IR 05000271/19970061997-10-0101 October 1997 Insp Rept 50-271/97-06 on 970720-0906.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering, Maintenance,& Plant Support IR 05000271/19970071997-09-0404 September 1997 Insp Rept 50-271/97-07 on 970826.No Violations Noted.Major Areas Inspected:Licensee Access Authorization Program ML20210R0151997-08-27027 August 1997 Design Insp Rept 50-271/97-201 on 970505-0613.No Violations Noted.Major Areas Inspected:Lpci & RHRSW Sys PNO-I-97-053, on 970826,special Security Insp Will Be Performed,That Will Examine Security Activities at Vermont Yankee,Pilgrim & Indian Point 3.Team Will Include Security Specialists from Region I & NRR1997-08-22022 August 1997 PNO-I-97-053:on 970826,special Security Insp Will Be Performed,That Will Examine Security Activities at Vermont Yankee,Pilgrim & Indian Point 3.Team Will Include Security Specialists from Region I & NRR ML20210S0171997-08-19019 August 1997 Notice of Violation from Insp on 970601-0719.Violation Noted:Reactor Was Placed in Run Mode on 970507,but Atmosphere Oxygen Concentration in Torus Air Space Remained Greater than Four Percent Until Morning of 970512 1999-09-13
[Table view] |
See also: IR 05000271/1989005
Text
. ._ . _ _ _ _ _ _ _ _ __ _
-
'
i ,3 ,.
,
4 e
. .
L :
.
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
Report No. 50-271/89-05
Docket No. 50-271
- License No. DPR-28
Licensee: Vermont Yankee Nuclear Power Corporation
RD 5 Box 169, Ferry Road
Brattleboro, Vermont 05301
'
Facilit'y Name: Vermont Yankee Nuclear power Station
-Inspection At: Vernon, Vermont-
Inspection Conducted: April 4-7, 1989
Inspectors: UW
A. Finkel, S'enior Reactor Engineer date'
b
f
'I 4
W. 0 iveira, Reactor Engineer d' ate '
- Approved by: d Cm [ h
7 'J
N. u'mberg, Ch'ief, Operational Programs
5ection, 08,'DRS / fate /
Inspection Summary: Inspection on April 4-7, 1989 (Inspection Report No.
50-271/89-05)
Areas. Inspected: Routine unannounced inspection consisting of the review and
implementation of the ATWS Rule 10 CFR 50.62; open items identified in pre-
viously issued NRC inspection reports; surveillance and calibration program;
and quality assurance / quality control interface with surveillance testing.
Results: Licensee is complying with the ATWS Rule 10 CFR 50.62. The quality
organization appears adequately staffed to support the present operation of
this site. ' Surveillance testing and the calibration program are following the
licensee established program plan. During this inspection unresolved items
85-26-01, 87-08-01 and 87-18-02 were closed. No violations or deviations were
identified.
8905160073 890504
PDR
0 ADOCK 05000271
PDC
- _________-:___-__-_--_____-__---__--___-_-_-__-__-_-_--_____- - _ - _ - _ _ _ -
-_- - ______ _ - - _- . _ _ _ _ _ _ _ . . - - _ _ _ _ _ __ -. __ _ . _ _ _
_ . _ - _ _ __
'
.
.l 4
.
.
1
Details
1.0 Persons Contacted
Vermont Yankee Nuclear Power Corporation
.P. Donnelly, Maintenance Superintendent
- R. Grippardi, Quality Assurance Supervisor
- R. Pagondin, Technical Services Superintendent
- J. Pelletier, Plant Manager
D. Reid, Operations Support Manager
S. Skibniowsky, Chemistry Supervisor
R. Spinney, Training Manager
W. Wiltmer, Construction Superintendent
<
United States Nuclear Regulatory Commission
G. Grant, Senior Resident Inspector
The inspectors also held discussions with other licensee personnel during
the course of this inspection.
- Denotes those present at the exit meeting on April 7, 1989.
2.0 Follow-up of Previous Inspection Findings (92706)
(Closed) Unresolved Item'85-26-01 - Establish qualification and
certification requirements of receiving inspector (QAT) in accordance
with ANSI N45.2.6-78. The job description for the quality assurance
technician (QAT) was revised November 3, 1985 and approved on
January 16, 1986. The revised QAT job description reflects the intent of
ANSI N45.2.6-1978, paragraph 3.5.2, Level II in the area of schooling and
experience. The inspector reviewed the present QAT personnel records and
verified that their qualifications comply with the licensee's revised job
description requirements. This item is closed.
(Closed) Unresolved Item (87-08-01) - QDR Manual Requirements were not
followed during maintenance of the RHR motors. The licensee's equipment
manual recommended that the motor oil be changed at six month intervals.
The maintenance program for the RHR motors required the oil to be
replaced during each refueling cycle. During the third quarter of 1987, ,
General Electric (GE) completed an evaluation of the electric motor a
maintenance program at Vermont Yankee. GE's recommendation to the
licensee on the subject of motor oil lubrication stated that oil
lubricated motors should be sampled every six months and the oil changed
every outage.
I
l
. _ _ . - . ' _ _ - _ _ _ _ . - - - - - _ . _ . . _
_ ._-_._.-.-_--L._.. -- _ . - . - - _ . _ . . _ . . - _
- _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ - _ _ _ _ _ - _ _ _ - _ _ - _ _ - _. _ - _ _ _ - _ _ _ _ _ _ _ _
'
.
. .
.
.
3
The Vermont Yankee maintenance procedures require that oil be changed at i
refueling outages based on plant history records and motor test results.
The Maintenance Department does not plan to. perform cil sampling as
recommended by GE unless their test data indicates a motor problem. Based
on' their historical records and test hta results for their RHR motors,
,
the inspector concurred that their prm*nt oil replacement program is 1
acceptable. This item is closed. j
(Closed) Unresolved Item (87-18-02) - Maintenance Department failed to
classify activities into major-minor inspection criteria as defined in
procedure AP-6025. The licensee specifies the inspection criteria in .
'
their individual department procedures and uses the peer inspection .
process to perform first level inspection of the task. Procedure AP-6025 {
was revised on April 25,.1988 to delete the requirement for using the
'
major-minor method of classifying inspection criteria. The surveillance
'
and audit inspections were performed by the quality organization as
defined in their quality control program for this site.
To ensure that the'Ap-6025 revision removing the requirement for major-minor
classification did not present a safety concern, the inspector reviewed
the QA Surveillance Reports88-130 on the Instrumentation and Control Depart-
ment-and 88-113 on the Mairitenance Department, which evaluated the effective-
ness of the revised AP-6025. These surveillance reports and the inspector's
evaluation of sampled surveillance performed during 1988-1989 indicated <
that the departments were complying with the criteria defined in Ap-6025
without an apparent lessening of work quality or safety. This item is
closed.
3.0 Anticipated Transient Without Scram (ATWS) Rule,10 CFR 50.62 (.2500/20)
3.1 Scope:
The scope of the inspection was to determine that the Vermont Yankee's
(VY) present system design complies with the requirements of 10 CFR
50.62, paragraphs C (3), (4), (5), (d), and that their test programs
l are designed to ensure that the Alternate Rod Injection (ARI), Standby
Liquid Control System (SLCS), and the recirculation pumps will function
as designed under conditions indicative of an ATWS. The documentation
that was reviewed by the inspectors and used in the validation of the
design and test data reviews are listed in Attachment A of this report.
__ __ _ _ _ _ _ _ _ .
_ - _ _ _ _ _ _ - _ _ _ _
-
.
. .
.
.
4
l
!
3.2 Alternate Rod Injection (ARI) System and Recirculation Pumps
3.2.1 Description of Modification:
To comply with the independence criteria of 10 CFR 50.62,
paragraph C, the ARI system is designed so that upon a high
pressure or low water level sigual the system relays, which
are in a de-energized state, will energize and trip the
reactor. The Reactor Prctection System (RPS) upon a high
pressure or low water level signal will de-energize causing a
reactor trip.
The VY ARI has a 10 second time delay added to provide for longer
core flow during level decrease transients, to assure adequate
core cooling, before the recirculation pumps are shut down. The
high reactor vessel pressure trip signals opens the GE AKF-2-25
motor generator (MG) field breakers which supply the voltage for
the recirculation pumps thus causing the pumps to stop and coast
down. Both the RPS and the ARI systems remove the air supply
from their scram valves, causing these solenoids valves to open
thus providing a reactor scram signal. The RPS and the ARI systems
are redundant from the sensors to the activating devices, however,
the level transmitters and the logic cards are the same manufacture
(Rosemount 1152T0280's), but completely redundant.
3.2.2 Finding:
To ensure that the ARI installed system complied with the
system design criteria and that the test program demonstrated
the operation of the system, the inspector verified tne
installed equipment of one train of the ARI system from the
sensor to the tripping relay devices. The inspector also
reviewed the system surveillance test data from 1988 through the
first quarter of 1989; verified that the ARI train was installed
per the design drawings; and verified that the test data
determined that the ARI system was functional. This item is
closed.
3.3 Standby Licuid Control System (SLCS)
3.3.1 Description of Modification:
The ATWS rule, 10 CFR 50.62C, (4), requires all BWR's to modify 4
their SLCS to be equivalent in control capacity to an 86 gpm
injection rate of 13% sodium pentaborate solution. The 86 grita
I
,
__ __-_
,
,
.
, . .
-
4
5
q
and 13% values stated in the ATWS rule were based on a reactor
vessel size of 251-inch diameter. Vermont Yankee's reactor
vissel size is a 205-inch diameter vessel and based on this -
' their safety analysis establish different rates. VY is also
using a higher inventory of Boron-10. The use of Boron-10
isotope provides the neutron absorption (negative reactivity)
required to shutdown the reactor if the RPS and ARI- systems do
not. Yankee Atomic Electric Company calculation (VY C-572)
determined the minimum Boron-10 aton' percent to be 43, based on
a 41 gpm injection rate, to meet the ATWS 10 CFR 50.62C, '4)
rule for SLC equivalency.
'
3.3.2 Fitidings:
The inspector reviewed the pump test and chemistry reports for
1988 through the first quarter of 1989 to ensure that the system
design and the chemistry concentration of the SLCS complied with
the requirements of calculation VY C-572. The pump tests _and
the corrected chemistry data results were within the VY C-572
calculation requirements for this system design.
During this inspection, the refueling SLCS serve 111ance test per
Procedure No. OP4114 was performed. The data had not yet been
,
approved through the licensee's data review system during this
inspection period; however, test data reviewed by the. inspector-
appeared to be within the requirements of the test procedure.
The test data supported the VY C-5'/2 calculations for the pump
injection rate and the chemical concentration of the SLCS tank.
In addition, the refueling surveillance test, OP 4114, also met
the VY C-572 flow criteria. The above data reviewed by the
inspector complied with the VY Technical Specification (TS)
section 3.4 Limiting Condition for Operation and 4.4
Surveillance Requirements. .This item is closed.
4.0 Complex Surveillance (61701) and Testing / Calibration (61725)
4.1 Scope:
The inspector observed selected tests to determine if the tests were:
(1) performed in accordance with approved Instrument and Control
(I&C) and Maintenance surveillance / test procedures; (2) properly
administrative 1y controlled, and (3) were performed by trained and
qualified personnel.
,
- _- _ __ _ _
- _ - - _ _ - _ _ _ _ - -_ ,
,
1%
,' .
"
6
p
4.2 Findirns:
4.2.1 Surveillance / Test Program:
The surveillance / test program was well documented and
administrative 1y controlled by the Engineering Support
Department (ESD), the Maintenance Department, and the I&C
Department. The key procedures for administering the
surveillance program are Administrative Procedures (AP) 0200
(Maintenance), AP 0310 (I&C) and AP 4000 (ESD). Departmental
,
procedures (DPs) provided the details. for implementing the
,
surveillance program. These procedures and other documents
referenced in the inspection report are listed in Attachment A.
4.2.2 Surveillance Program Activities:
The performance of two I&C surveillance tests and one
Maintenance test listed below were observed to assess the
surveillance and test / calibration effort for: administrative
controls) test procedure technical content; planning and timely.
performance of the tests; QA coverage; corrective actions;
reporting and analyzing the results (data); and post test
,
restoration.
-
Vibration tests by the Maintenance Department of the core
spray pump in accordance with OP 4123.
-
Reactor core isolation cooling (RCIC) system A/B isolation
logic test in accordance with OP 4368.
-
Automatic initiation test of the Primary Containment Isolation
System (PCIS) valves in accordance with OP 4334.
The above tests were satisfactorily performed. However, while
observing performance of OP 4334 the inspector noted that step
57 required the actuation of PCIS valves A-20, A-22A and A-228
in the Control Room. The arrangement of Control Room Panel 9-3
was, however, changed by EDCR No.86-411 and these valves were
redesignated NI-20, NI-22A and NI-22B, respectively. AP 6004
and YNSD WE-100 requires procedures and drawings affected by an
EDCR to be corrected. A Plant Operations Review Committee
(PORC) approved EDCR 86-411 without verifying that the "no
procedural changes required," statement of the data package was
correct. Documents AP 0155 and control room drawing 191175,
which designate valve numbers, were not changed per the approved
EDCR 86-411. The licensee acknowledged the error and initiated
actions to correct the error and determine the root cause of why
the EDCR process did not identify these documents. The
inspector had no further questions.
'
.
.
I
_ _ _ _ _ _
.
. .
-
.
7 I
i
4.2.3 QA/QC Interfaces with Surveillance Testing:
.
Five annual QA audit reports and six QA surveillance reports
listed in attachment A sections 2.3 and 2.4 were reviewed j
by the inspector. The reports were comprehensive and the i
corrective action resp 0nses were complete and timely.
A Quality Service Department (, tor was observed
performing surveillance inspection of the PCIS valves
automatic initiation test of OP'4334. The QSD inspector
documented the NRC inspectors concern regarding the PCIS
valves discussed in paragraph 4.2.2 and placed in the
licensee's corrective action system. ;
4.3 Conclusion: j
i
The surveillance / test and calibration effort is documented and !
1mplemented satisfactorily by qualified personnel. The licensee
has initiated action to determine the root cause regarding the
proper implementation of the EDCR process discussed in paragraphs i
4.2.2 and 4.2.3. !
5.0 Exit Interview ,
Licensee management was informed of the scope and purpose of the
inspection at the entrance interview on April 4,1989. At the conclusion I
of the site inspection on April 7, 1989, an exit itterview was conducted
with the licensee's senior site representatives (denoted in section 1).
The fir. dings were identified and the status of previous inspection
findings were discussed.
At no tiCE during this inspection Was written material provided to the
licensee by the inspector. Based on the NRC Region I review of this
report and discussions held with licensee representatives during this
inspection, it was determined that this report does not contain
ir. formation subject to 10~CFR 2.790 restrictions.
1
l
l
1
_ _ _ _ _ _ _ _ _ _ _ _ _ _
.
'
. .
-
.
!
I
I
i
Attachtnent A
1
l
1.0 Anticipated Transient Without Scram (ATWS) 1
l
1.1 Alternate Rod Injection (ARI) Documentation l
l
RPS Instrumentation and Control Drawings 850-851 and 855-856
- AR1 Instrumentation and Control Drawings 860-867
- RPS Level Drawing - Rosemont 1152T0280
- ARI Level Drawing - Rosemont 1152T0280
- RPS Logic Trip Drawings 803-828
- ARI Logic Trip Drawings 862
- RPS/ARI Scram Valve Drawing G;91170
- Operations Procedure (0P) 4337 - Reactor Water Level ECCS
Initiation, Isol, Funct/Cali-
bration, Revision 21,
March 31,1989
- Operations Procedure (OP) 4342 - Rx Pressure RPT/ARI/Eccs
Func/ Calibration, Revision 8,
January 25, 1989
- Operations Procedure (OP) 4369 - RPT/ARI Operational Test,
Revision 3, January 5, 1989
1.2 Standby Liquid Control System (SLCS)
Calculation VYC-572 - Yankee Atomic Electric Company SLCS Design
Calculation
- Operations Procedure (OP) 4611 - Sampling and Treatment of the
Standby Liquid Control System
Sy5. tem Treatment Request
- Operations Procedure (OP) 4611.02 - Analysis of Enriched Boric
Acid, Enriched Sodium
Pentaborate Decahydrate,
Borax and Sodium Pentaborate
Solution for % B-10
Composition
- Operations Procedure (0P) 0630 - Water Chemistry
_
- _ _ _ _ - _ - _ _ _ _ _ _ _ _ - _ .
.
. , ,
'
'
,
'1
Attachment A 2
- Operations Procedure (0P) 2114 - Operation of the Standby
Liquid Control System
Operations Procedure (OP) 4114 - Standby Liquid Control System
Surveillance
Department' Procedure (DP) 0641 - Procedure for Logging Results
of Chemical Analysis i
Drawing 191171 - Standby Liquid Cantrol Flow Diagram
,
SLCS Surveillance Test Reports 1981 - First Quarter 1989 -
1.3 Reactor Recirculating Pumps .
B-19130 (SH702) - Control Wiring Diagram - Reactor Recirculating !
Motor Generator Set MGI-1A Field Breaker
Sensors - Channel Al ;
2.0 Complex Surveillance and Testing / Calibration.
2.1 Administrative Procedures
- Administrative Procedure (AP) 0155 - Current System Valve and
Breaker Lineup and Identification, Revision 11, March 2, 1988
- AP 0200 - Maintenance Program, Revision 11, July 1, 1987
- AP 0310, Surveillance Preventative and Corrective Maintenance
Program, Revisian 3, August 12, 1988
AP 4000 - Surveillance Testing Control, Revision 10,
July 20,1988
AP 6004 - Engineering Design Change Requests, Revision 12,
November 3, 1988
- Yankee Nuclear Services Division Engineering Instruction
WE-190, Engineering Design Change Request, Revision 17,
February 15, 1989
e Quality Assurance Department Procedure 0QA-X-1, Quality
Assurance Surve111ances, Revision 12, December 29, 1987
m
- - _ _ - _ _ _ _
,
'
.
. ..
.
!
Attachment A- 3 )
i
i
Instrument and Control (I&C) Department Procedure (DP) 0301,
Calibration and Control of Measuring ar.d Test Equipment (M/TE),
Revision 11, September 23, 1987
>
2.2 Test Procedures
- Operations Procedure (0P) 4123 - Core Spray System
Surveillance, Revision 18,
February 27, 1989
OP 4334 - Automatic Initiation Test of PCIS Valves, Revision j
11, March 23, 1989
Isolution Logic Test, Revision 18, February 17, 1989
2. 3 Annual QA Audit Reports I
- VY-86-11 - Measuring and Test Equipment, September 19, 1986
- VY-87-11 - M a suring and Test Equipment, June 11, 1987 {
- VY-87-15 - Technical Specifications, July 29, 1987
- VY-88-15 - Technical Specifications, March 11, 1988
- VY-88-11 - Measuring and Test Equipment, September 16, 1988
2.4 QA Surveillance (SURVs)
- SURV 88-0S - Core Spray System Surveillance, January 8, 1987
- SURV 88-36 - Surveillance of Scram Discharge Instrument, Volume
High Water Functional Test, March 4, 1988
- SURV 89-21 - Shutdown to Low Power Standy, February 11, 1989
= SURV 89-22 - Reactor Core Isolation System Injection to Reactor ,
Vessel, February 13, 1989 !
- SURV 89-24 - Battery Performance Test / Preventive Maintenance, ,
February 22, 1989
- SURV 89-45 - Assembly of Reactor and Drywell System for
Operation, March 23, 1989
l
!
l