ML17079A526

From kanterella
Jump to navigation Jump to search
NRC Triennial Fire Protection Inspection Report 05000498/2017007 and 05000499/2017007
ML17079A526
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 03/20/2017
From: Greg Werner
NRC/RGN-IV/DRS/EB-2
To: Gerry Powell
South Texas
Werner G
References
IR 2017007
Download: ML17079A526 (28)


See also: IR 05000498/2017007

Text

March 20, 2017

Mr. G. T. Powell

Executive Vice President and Chief Nuclear Officer

STP Nuclear Operating Company

South Texas Project Electric Generating Station

P.O. Box 289

Wadsworth, TX 77483

SUBJECT: SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION,

UNITS 1 AND 2 - NRC TRIENNIAL FIRE PROTECTION INSPECTION

REPORT 05000498/2017007 AND 05000499/2017007

Dear Mr. Powell:

On February 9, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection

at the South Texas Project Electric Generating Station, Units 1 and 2, and discussed the results

of this inspection with you and other members of your staff. The results of this inspection are

documented in the enclosed report.

The NRC team documented one finding of very low safety significance (Green) in this report.

The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a

of the Enforcement Policy.

If you contest the violation or significance of the violation in this report, you should provide a

written response within 30 days of the date of this inspection report, with the basis for your

denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, DC 20555-0001, with copies to the Regional Administrator, Region IV; the Director,

Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001;

and the NRC resident inspector at the South Texas Project Electric Generating Station, Units 1

and 2.

G. Powell 2

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for

Withholding.

Sincerely,

/RA/

Gregory E. Werner, Chief

Engineering Branch 2

Division of Reactor Safety

Docket Nos. 50-498 and 50-499

License Nos. NPF-76 and NPF-80

Enclosure:

Inspection Report No. 05000498/2017007

and 050000499/2017007

w/ Attachment: Supplemental Information

cc w/ encl: Electronic Distribution

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 05000498 and 05000499

License: NPF-76 and NPF-80

Report: 05000498/2017007 and 05000499/2017007

Licensee: STP Nuclear Operating Company

Facility: South Texas Project Electric Generating Station, Units 1 and 2

Location: FM 521 - 8 miles west of Wadsworth

Wadsworth, Texas 77483

Dates: January 23 through February 9, 2017

Team Leader: S. Makor, Acting Senior Reactor Inspector

Inspectors: S. Alferink, Reactor Inspector

J. Drake, Senior Reactor Inspector

C. Stott, Reactor Inspector

J. Watkins, Reactor Inspector

Approved By: Gregory E. Werner, Chief

Engineering Branch 2

Division of Reactor Safety

Enclosure

SUMMARY

IR 05000498/2017007; 05000499/2017007; 01/23/2017- 02/09/2017; South Texas Project

Electric Generating Station, Units 1 and 2; Fire Protection (Triennial)

The report covers a two-week triennial fire protection team inspection by specialist inspectors

from Region IV. One finding, which was a non-cited violation, was documented. The

significance of inspection findings is indicated by their color (i.e., Green, White, Yellow, or Red)

and determined using Inspection Manual Chapter 0609, Significance Determination Process,

dated April 29, 2015. Cross-cutting aspects are determined using Inspection Manual

Chapter 0310, Aspects within the Cross-Cutting Areas, dated December 4, 2014. All

violations of NRC requirements are dispositioned in accordance with the NRCs Enforcement

Policy, dated November 1, 2016. The NRCs program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,

Revision 6.

A. NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

Green. The team identified a non-cited violation of License Condition 2.E for the failure

to provide 8-hour emergency lighting in all areas where operators perform manual

actions required during an alternative shutdown. As a compensatory measure, the

licensee added flashlights to the procedure box in the essential cooling water intake

structure. The team noted that operators were also required to carry a flashlight while

on shift. The licensee entered this issue into their corrective action program as

Condition Report 17-1741.

The failure to provide 8-hour emergency lighting in all areas where operators perform

manual actions required during an alternative shutdown was a performance deficiency.

The performance deficiency was more than minor because it was associated with the

protection against external events (fire) attribute of the Mitigating Systems Cornerstone

and it adversely affected the cornerstone objective of ensuring the availability, reliability,

and capability of systems that respond to initiating events to prevent undesirable

consequences. Specifically, the failure to provide 8-hour emergency lighting could

adversely affect the ability of operators to perform the manual actions required for an

alternative shutdown.

The team determined this finding affected the Mitigating Systems Cornerstone. The

team evaluated this finding using Inspection Manual Chapter 0609, Appendix F, Fire

Protection Significance Determination Process, dated September 20, 2013, because it

affected the ability to reach and maintain safe shutdown conditions in case of a fire. The

team determined this finding was of very low safety significance (Green) in Task 1.3.1

because it had a low degradation rating.

The finding did not have a cross-cutting aspect since it was not indicative of present

performance in that the performance deficiency occurred more than three years ago.

Specifically, the team determined that the performance deficiency existed since original

construction. (Section 1R05.08)

2

B. Licensee-Identified Violations

None

REPORT DETAILS

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R05 Fire Protection (71111.05T)

This report presents the results of a triennial fire protection inspection conducted at

South Texas Project Electric Generating Station, Units 1 and 2 in accordance with NRC

Inspection Procedure 71111.05T, Fire Protection (Triennial), dated January 31, 2013.

The inspection team evaluated the implementation of the approved fire protection

program in selected risk-significant areas with an emphasis on the procedures,

equipment, fire barriers, and systems that ensure the post-fire capability to safely

shutdown the plant.

Inspection Procedure 71111.05T requires the selection of three to five fire areas and one

or more mitigating strategies for review. The inspection team used the fire hazards

analysis section of the South Texas Project Electric Generating Station, Units 1 and 2

Individual Plant Examination of External Events to select the following five risk-significant

fire areas (inspection samples) for review:

  • Fire Area 20 Non-Radiological Pipe Chase
  • Fire Area 32 Component Cooling Water Pipe Chase
  • Fire Area 51 Train D Auxiliary Pump Room
  • Fire Area 1 Control Room
  • Fire Area 7 Alternate Shutdown Room

The inspection team evaluated the licensees fire protection program using the

applicable requirements, which included the plant Technical Specifications, Operating

License Condition 2.E, NRC safety evaluations, 10 CFR 50.48, and Branch Technical

Position 9.5-1. The team also reviewed related documents that included the Updated

Final Safety Analysis Report (UFSAR), Section 9.5; the fire hazards analysis; and the

post-fire safe shutdown analysis. Specific documents reviewed by the team are listed in

the attachment.

Five fire area inspection samples and one mitigating strategy sample were completed.

.01 Protection of Safe Shutdown Capabilities

a. Inspection Scope

The team reviewed the piping and instrumentation diagrams, safe shutdown equipment

list, safe shutdown design basis documents, and the post-fire safe shutdown analysis to

verify that the licensee properly identified the components and systems necessary to

achieve and maintain safe shutdown conditions for fires in the selected fire areas. The

3

team observed walkdowns of the procedures used for achieving and maintaining safe

shutdown in the event of a fire to verify that the procedures properly implemented the

safe shutdown analysis provisions.

For each of the selected fire areas, the team reviewed the separation of redundant safe

shutdown cables, equipment, and components located within the same fire area. The

team also reviewed the licensees method for meeting the requirements of

10 CFR 50.48; Branch Technical Position 9.5-1, Appendix A; and 10 CFR Part 50,

Appendix R,Section III.G. Specifically, the team evaluated whether at least one

post-fire safe shutdown success path remained free of fire damage in the event of a fire.

In addition, the team verified that the licensee met applicable license commitments.

b. Findings

No findings were identified.

.02 Passive Fire Protection

a. Inspection Scope

The team walked down accessible portions of the selected fire areas to observe the

material condition and configuration of the installed fire area boundaries (including walls,

fire doors, and fire dampers) and verify that the electrical raceway fire barriers were

appropriate for the fire hazards in the area. The team compared the installed

configurations to the approved construction details, supporting fire tests, and applicable

license commitments.

The team reviewed installation, repair, and qualification records for a sample of

penetration seals to ensure the fill material possessed an appropriate fire rating and that

the installation met the engineering design. The team also reviewed similar records for

the rated fire wraps to ensure the material possessed an appropriate fire rating and that

the installation met the engineering design.

b. Findings

No findings were identified.

.03 Active Fire Protection

a. Inspection Scope

The team reviewed the design, maintenance, testing, and operation of the fire detection

and suppression systems in the selected fire areas. The team verified the automatic

detection systems and the manual and automatic suppression systems were installed,

tested, and maintained in accordance with the National Fire Protection Association code

of record or approved deviations, and that each suppression system was appropriate for

the hazards in the selected fire areas.

The team performed a walkdown of accessible portions of the detection and suppression

systems in the selected fire areas. The team also performed a walkdown of major

4

system support equipment in other areas (e.g., fire pumps and Halon supply systems) to

assess the material condition of these systems and components.

The team reviewed the electric and diesel fire pumps flow and pressure tests to verify

that the pumps met their design requirements. The team also reviewed the halon

suppression functional tests to verify that the system capability met the design

requirements.

The team assessed the fire brigade capabilities by reviewing training, qualification, and

drill critique records. The team also reviewed pre-fire plans and smoke removal plans

for the selected fire areas to determine if appropriate information was provided to fire

brigade members and plant operators to identify safe shutdown equipment and

instrumentation, and to facilitate suppression of a fire that could impact post-fire safe

shutdown capability. In addition, the team inspected fire brigade equipment to determine

operational readiness for firefighting.

The team observed an unannounced fire drill and subsequent drill critique on

February 8, 2017, using the guidance contained in Inspection Procedure 71111.05AQ,

Fire Protection Annual/Quarterly, dated September 30, 2010. The team observed fire

brigade members fight a simulated fire in the isolation valve cubicle, located outside the

radiological controlled area. The team verified that the licensee identified problems,

openly discussed them in a self-critical manner at the drill debrief, and identified

appropriate corrective actions. Specific attributes evaluated were: (1) proper wearing of

turnout gear and self-contained breathing apparatus; (2) proper use and layout of fire

hoses; (3) employment of appropriate firefighting techniques; (4) sufficient firefighting

equipment was brought to the scene; (5) effectiveness of fire brigade leader

communications, command, and control; (6) search for victims and propagation of the

fire into other areas; (7) smoke removal operations; (8) utilization of pre-planned

strategies; (9) adherence to the pre-planned drill scenario; and (10) drill objectives.

b. Findings

No findings were identified.

.04 Protection from Damage from Fire Suppression Activities

a. Inspection Scope

The team performed plant walkdowns and document reviews to verify that redundant

trains of systems required for hot shutdown, which are located in the same fire area,

would not be subject to damage from fire suppression activities or from the rupture or

inadvertent operation of fire suppression systems. Specifically, the team verified:

  • A fire in one of the selected fire areas would not directly through production of

smoke, heat, or hot gases cause activation of suppression systems that could

potentially damage all redundant safe shutdown trains.

  • A fire in one of the selected fire areas or the inadvertent actuation or rupture of a

fire suppression system would not directly cause damage to all redundant trains

(e.g., sprinkler-caused flooding of other than the locally affected train).

5

  • Adequate drainage was provided in areas protected by water suppression

systems.

b. Findings

No findings were identified.

.05 Alternative Shutdown Capability

a. Inspection Scope

Review of Methodology

The team reviewed the safe shutdown analysis, operating procedures, piping and

instrumentation drawings, electrical drawings, the Updated Final Safety Analysis Report,

and other supporting documents to verify that hot and cold shutdown could be achieved

and maintained from outside the control room for fires that require evacuation of the

control room, with or without offsite power available.

The team conducted plant walkdowns to verify that the plant configuration was

consistent with the description contained in the safe shutdown and fire hazards

analyses. The team focused on ensuring the adequacy of systems selected for

reactivity control, reactor coolant makeup, reactor decay heat removal, process

monitoring instrumentation, and support systems functions.

The team also verified that the systems and components credited for shutdown would

remain free from fire damage. Finally, the team verified that the transfer of control from

the control room to the alternative shutdown location would not be affected by

fire-induced circuit faults (e.g., by the provision of separate fuses and power supplies for

alternative shutdown control circuits).

Review of Operational Implementation

The team verified that licensed and non-licensed operators received training on

alternative shutdown procedures. The team also verified that sufficient personnel to

perform an alternative shutdown were trained and available onsite at all times, exclusive

of those assigned as fire brigade members.

The team performed a timed walkdown of the alternative shutdown procedure for Unit 2

with licensed and non-licensed operators to determine the adequacy of the procedure.

The team verified that the operators could reasonably be expected to perform specific

actions within the time required to maintain plant parameters within specified limits.

Time critical actions that were verified included restoring electrical power, establishing

control at the remote shutdown and local shutdown panels, establishing reactor coolant

makeup, and establishing decay heat removal.

The team also reviewed the periodic testing of the alternative shutdown transfer

capability and instrumentation and control functions to verify that the tests were

adequate to demonstrate the functionality of the alternative shutdown capability.

6

b. Findings

No findings were identified.

.06 Circuit Analysis

a. Inspection Scope

The team reviewed the post-fire safe shutdown analysis to verify that the licensee

identified the circuits that may impact the ability to achieve and maintain safe shutdown.

The team verified, on a sample basis, that the licensee properly identified the cables for

equipment required to achieve and maintain hot shutdown conditions in the event of a

fire in the selected fire areas. The team verified that these cables were either

adequately protected from the potentially adverse effects of fire damage or were

analyzed to show that fire induced circuit faults (e.g., hot shorts, open circuits, and

shorts to ground) would not prevent safe shutdown.

The teams evaluation focused on the cables of selected components from the

emergency diesel generator, component cooling water, auxiliary feedwater, high head

safety injection, low head safety injection, pressurizer power operated relief valves

(PORVs), PORV block valves, alternative shutdown control room isolation and transfer

switches, and chemical volume and control system. For the sample of components

selected, the team reviewed electrical elementary and block diagrams, and identified

power, control, and instrument cables necessary to support their operation. In addition,

the team reviewed cable routing information to verify that fire protection features were in

place as needed to satisfy the separation requirements specified in the fire protection

license basis. Specific components reviewed by the team are listed in the attachment.

b. Findings

No findings were identified.

.07 Communications

a. Inspection Scope

The team inspected the contents of designated emergency storage lockers and

reviewed the alternative shutdown procedure to verify that portable radio

communications and fixed emergency communications systems were available,

operable, and adequate for the performance of designated activities. The team verified

the capability of the communication systems to support the operators in the conduct and

coordination of their required actions. The team also verified that the design and

location of communications equipment such as repeaters and transmitters would not

cause a loss of communications during a fire. The team discussed system design,

testing, and maintenance with the system engineer.

b. Findings

No findings were identified.

7

.08 Emergency Lighting

a. Inspection Scope

The team reviewed the portion of the emergency lighting system required for alternative

shutdown to verify that it was adequate to support the performance of manual actions

required to achieve and maintain hot shutdown conditions, and to illuminate access and

egress routes to the areas where manual actions would be required. The team

evaluated the locations and positioning of the emergency lights during a walkdown of the

alternative shutdown procedure.

The team verified that the licensee installed emergency lights with an 8-hour capacity,

maintained the emergency light batteries in accordance with manufacturer

recommendations, and tested and performed maintenance in accordance with plant

procedures and industry practices.

b. Findings

Introduction. The team identified a Green non-cited violation of License Condition 2.E

for the failure to provide 8-hour emergency lighting in all areas where operators perform

manual actions required during an alternative shutdown.

Description. During a walkdown of the alternative shutdown procedure, the team

identified four areas where the 8-hour emergency lighting was not sufficient for operators

to perform manual actions required during an alternative shutdown. The four areas,

manual actions, and associated procedure sections are provided in the table below.

Area Manual Action (Procedure Step)

Electrical Auxiliary Building Penetration De-energize valve 2-CC-MOV-0339

Space (train A) (Addendum 20)

Electrical Auxiliary Building Penetration De-energize valve 2-CC-MOV-0356

Space (train B) (Addendum 21)

Essential Cooling Water Intake Structure De-energize dampers HZ-FV-9895/9895A

(train B) (Addendum 5, Step 2.0)

Essential Cooling Water Intake Structure De-energize dampers HZ-FV-9896/9896A

(train C) (Addendum 5, Step 2.0)

In response to the teams request, the licensee conducted a blackout test to evaluate the

adequacy of the 8-hour emergency lighting in the essential cooling water intake structure

(train B). This blackout test confirmed the teams determination that the 8-hour

emergency lighting in the room was not sufficient for operators to de-energize dampers

HZ-FV-9895/9895A.

8

As a compensatory measure, the licensee added flashlights to the procedure box in the

Essential Cooling Water Intake Structure. The team noted that operators were also

required to carry a flashlight while on shift.

Analysis. The failure to provide 8-hour emergency lighting in all areas where operators

perform manual actions required during an alternative shutdown was a performance

deficiency. The performance deficiency was more than minor because it was associated

with the protection against external events (fire) attribute of the Mitigating Systems

Cornerstone and it adversely affected the cornerstone objective of ensuring the

availability, reliability, and capability of systems that respond to initiating events to

prevent undesirable consequences. Specifically, the failure to provide 8-hour

emergency lighting could adversely affect the ability of operators to perform the manual

actions required for an alternative shutdown.

The team determined this finding affected the Mitigating Systems Cornerstone. The

team evaluated this finding using Inspection Manual Chapter 0609, Appendix F, Fire

Protection Significance Determination Process, dated September 20, 2013, because it

affected the ability to reach and maintain safe shutdown conditions in case of a fire. The

team assigned the finding to the post-fire safe shutdown category since it impacted the

remote shutdown and control room abandonment element. Using Inspection Manual

Chapter 0609, Appendix F, Attachment 2, Degradation Rating Guidance Specific to

Various Fire Protection Program Elements, dated February 28, 2005, the team

assigned the finding a low degradation rating since the ability to reach and maintain safe

shutdown conditions in the event of a control room fire would be minimally impacted by

the failure to provide 8-hour emergency lighting in the four areas. Specifically, the team

determined that operators were required to carry flashlights while on shift and these

flashlights would be sufficient for operators to perform the required manual actions.

Because this finding had a low degradation rating, it screened as having very low safety

significance (Green) in Task 1.3.1.

The finding did not have a cross-cutting aspect since it was not indicative of present

performance in that the performance deficiency occurred more than three years ago.

Specifically, the team determined that the performance deficiency existed since original

construction.

Enforcement. License Condition 2.E states, in part, that the licensee shall implement

and maintain in effect all provisions of the approved fire protection program as described

in the Updated Final Safety Analysis Report through Amendment Number 55 for Unit 1,

the Updated Final Safety Analysis Report through Amendment Number 62 for Unit 2,

and the Fire Hazards Analysis Report through Amendment Number 23. Section 4.1 of

the Fire Hazards Analysis Report contains a comparison of the licensees fire protection

program to the requirements in 10 CFR Part 50, Appendix R. The Fire Hazards Analysis

Report states that fixed self-contained emergency lighting, consisting of sealed-beam

units with individual 8-hour minimum battery supply, will be provided in areas needed for

operation of hot standby/hot shutdown equipment, and in access and egress routes

thereto.

Contrary to the above, prior to February 9, 2017, the licensee failed to implement and

maintain in effect all provisions of the approved fire protection program. Specifically, the

licensee failed to provide 8-hour emergency lighting in all areas needed for operation of

hot standby/hot shutdown equipment.

9

The licensee entered this issue into their corrective action program as Condition

Report CR 17-1741. In addition to ensuring operators carried flashlights while on

shift, the licensee also implemented a compensatory measure of adding flashlights to

the procedure box in the essential cooling water intake Structure. Because this violation

was of very low safety significance and has been entered into the corrective action

program, this violation is being treated as a non-cited violation, consistent with

Section 2.3.2.a of the NRC Enforcement Policy: NCV 05000498/2017007-01;

05000499/2017007-01, Failure to Provide 8-hour Emergency Lighting for All Alternative

Shutdown Manual Actions.

.09 Cold Shutdown Repairs

a. Inspection Scope

South Texas Project Electric Generating Station has three trains of redundant

equipment in each unit and, therefore, does not credit any cold shutdown repairs.

b. Findings

No findings were identified.

.10 Compensatory Measures

a. Inspection Scope

The team verified that compensatory measures were implemented for out-of-service,

degraded, or inoperable fire protection and post-fire safe shutdown equipment, systems,

or features (e.g., detection and suppression systems and equipment; passive fire

barriers; or pumps, valves, or electrical devices providing safe shutdown functions). The

team also verified that the short-term compensatory measures compensated for the

degraded function or feature until appropriate corrective action could be taken, and that

the licensee was effective in returning the equipment to service in a reasonable period of

time.

The team reviewed operator manual actions credited for achieving hot shutdown for fires

that do not require an alternative shutdown. The team verified that operators could

reasonably be expected to perform the actions within the applicable shutdown time

requirements. The team reviewed these operator manual actions using the guidance

contained in NUREG-1852, Demonstrating the Feasibility and Reliability of Operator

Manual Actions in Response to Fire, dated October 2007.

For the train of systems necessary to achieve and maintain hot shutdown conditions, the

team verified that the licensee treated these manual actions as compensatory measures

while appropriate corrective actions are implemented or while preparations are made by

the licensee to submit exemptions or deviations. For components important to safe

shutdown that could adversely affect the safe shutdown capability, the team verified that

operators could reasonably be expected to perform the actions within the applicable

shutdown time requirements.

10

b. Findings

No findings were identified.

.11 Review and Documentation of Fire Protection Program Changes

a. Inspection Scope

The team reviewed changes made to the approved fire protection program since

September 25, 2014. The team verified that the changes did not constitute an adverse

effect on the ability to safely shutdown.

b. Findings

No findings were identified.

.12 Control of Transient Combustibles and Ignition Sources

a. Inspection Scope

The team reviewed the licensees approved fire protection program, implementing

procedures, and programs for the control of ignition sources and transient combustibles.

The team assessed the licensees effectiveness in preventing fires and in controlling

combustible loading within limits established in the fire hazards analysis. The team

performed plant walkdowns to independently verify that transient combustibles and

ignition sources were being properly controlled in accordance with the administrative

controls.

b. Findings

No findings were identified.

.13 Alternative Mitigation Strategy Inspection Activities

a. Inspection Scope

The team reviewed the licensees implementation of guidance and strategies intended to

maintain or restore core, containment, and spent fuel pool cooling capabilities under the

circumstances associated with the potential loss of large areas of the plant due to

explosions or fire as required by 10 CFR 50.54(hh)(2).

The team verified that the licensee implemented and maintained adequate procedures,

maintained and tested equipment necessary to properly implement the strategies, and

ensured station personnel were knowledgeable and capable of implementing the

procedures. The team performed a visual inspection of portable equipment used to

implement the strategy to ensure the availability and material readiness of the

equipment, including the adequacy of portable pump trailer hitch attachments, and verify

the availability of on-site vehicles capable of towing the portable pump. The team

assessed the off-site ability to obtain fuel for the portable pump and foam used for

firefighting efforts. The strategy and procedure selected for this inspection sample

included:

11

Revision 4

One mitigating strategy sample was completed.

b. Findings

No findings were identified.

4. OTHER ACTIVITIES [OA]

4OA2 Problem Identification and Resolution (71152)

Corrective Actions for Fire Protection Deficiencies

a. Inspection Scope

The team selected a sample of condition reports associated with the licensee's fire

protection program to verify that the licensee had an appropriate threshold for identifying

deficiencies. The team reviewed the corrective actions proposed and implemented to

verify that they were effective in correcting identified deficiencies. The team evaluated

the quality of recent engineering evaluations through a review of condition reports,

calculations, and other documents during the inspection.

b. Findings

No findings were identified.

4OA6 Meetings, Including Exit

Exit Meeting Summary

On February 9, 2017, the team presented the inspection results to Mr. G. Powell, Executive

Vice President and Chief Nuclear Officer, and other members of the licensee staff. The

licensee acknowledged the findings presented.

The team verified that no proprietary information was retained by the team members or

documented in this report.

12

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

J. Alston, Systems Engineering Department Supervisor

M. Berg, Manager, Design Engineering

J. Berrio, Manager, Operations-Production Support and Programs

A. Capristo, Chief Administrative Officer

F. Cox, Design Engineering Department Safe Shutdown

G. Ferrigno, Radiation Protection GS

K. Frazier, Systems Engineering Department, Elect/IMS Section Supervisor

C. Gann, Manager, Employee Concerns Program

C. Georgeson, Supervisor, Design Engineering

D. Gore, Supervisor, Reactor Analysis

D. Hubenak, Radiation Protection GS

D. Janak, Performance Improvement Coordinator

D. Jenkins, Operations Support-Procedures

W. Jordan, Plant Operator

R. Kersey, Supervisor, Design

D. Koehl, President and Chief Executive Officer

R. Krupa, Senior Staff Specialist, Quality

R. Lacey, Design Engineering Department Electrical

B. Lane, Manager, Operations Division - Integrated Work Mgmt. & Outage

G. Lamberth, Operations Support-Procedures

H. Leon, Design Engineering Department, Electrical Engineer

J. Lovejoy, Manager Assistant, Maintenance

N. Mayer, Manager, Major Projects

M. Murray, Manager, Regulatory Affairs/Licensing

C. Pence, Manager, Chemistry

B. Powell, Staff Operations Specialist

G. Powell, Executive Vice President and Chief Nuclear Officer

D. Rohan, Operations Support-Procedures

R. Scarborough, Manager NOS

M. Schaefer, Plant General Manager

G. Schinzel, Supervising Engineer

C. Stinson, Manager, Maintenance & Technology Training

R. Stastny, Manager, Maintenance

D. Wiegand, Fire Protection Engineering

D. Whiddon, Supervisor, Quality

R. Gonzales, Engineer Staff

NRC Personnel

F. Sanchez, Senior Resident Inspector

N. Hernandez, Resident Inspector

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

None

Attachment

LIST OF DOCUMENTS REVIEWED

Cable Routing Data Components

A2AF01C1WB A2RC13C1LAA B2CV31C2WA B2SP17CDSA

A2AF01C1WC A2RC13C1LB B2CV31C2WC B2SP17CHSB

A2AF01C1WD A2RC13C1LC B2CVAEC1LA B2SP17CHSE

A2AF01C1WE A2RC13C1WA B2MB04C1SK B2SP17CHSF

A2AF01C1WF A2RC13C1WB B2MB04C1SU C2CV26C1WA

A2AF01C1WG A2RC13C1WC B2MB04C1SV C2CV26C1WB

A2AM14C1SA A2RC13C1WD B2MB04C1SW C2CV26C1WC

A2CV26C1WA A2RC13C1WE B2RC05C2WA C2CV26C1WD

A2CV26C1WB A2RC13C1WF B2RC05C2WB C2CV26C1WE

A2CV26C1WC A2RCAAC1WA B2RC05C2WC C2CV31C1SB

A2CV26C1WD A2RCABC1LA B2RC05C2WD C2CV31C1WA

A2CV26C1WE A2RCABC1LB B2RC05C2WE C2CV31C1WC

A2CVAAC1GA A2RCABC1LC B2RC13C2LB C2CVACC1GA

A2MB01C1SB A2SI05C1SA B2RC13C2LC C2CVAHC1LA

A2MB01C1SJ A2SI05CSSB B2RC13C2LD C2MB04C1SB

A2MB01C2SN A2SI06C1SA B2RC13C2LE C2MB04C1SL

A2MB04C1SB A2SI06C1SB B2RC13C2WA C2SP17CFSA

A2MB04C1SS A2SIAAC1EA B2RC13C2WB N2AM11C3SA

A2MB04C1ST A2SIAAC1EB B2RC13C2WC N2IC14C1XD

A2MB04C1SU A2SP17CHSB B2RC13C2WD N2IC14C1XD1

A2RC05C1WA A2SP17CHSE B2RC13C2WE N2IC14C3XD

A2RC05C1WB A2SP17CHSF B2RC13C2WF N2IC14C3XD1

A2RC05C1WC A2SP22CASG B2RCACC1WA

A2RC05C1WD A2SP22CMSD B2RCADC1LA

A2RC05C1WE A2SP27CASE B2RCADC1LB

A2RC13C1LA B2CV31C2SB B2RCADC1LC

Calculations

Number Title Revision/Date

EC6053 Sheet 187 4.16 kV Switchgear Transfer Switch Schemes December 24,

Figure 8.5 Fuse Curves for 15 Amp Type A4J15 fuse, 1987

KWN15A fuse, and ITE Class J 30 Amp A4J30 fuse

2

Calculations

Number Title Revision/Date

MC06023 Appendix R Evaluation 13

MC-5557 IVC Flooding Analysis 9

NC-0709 Fire Hazards Analysis 6

NC-9703 Flooding Analysis: MAB 2

Condition Reports

11-10905 15-864 17-1020*

13-11633 16-1036-1 17-1022*

14-10845 16-12666 17-1026

14-16243 16-13030 17-1029*

14-17206 16-13587 17-1042*

14-17681 16-13588 17-1102*

14-17098 16-13821 17-1110*

14-4215-4 16-13941 17-1113*

15-10544 16-13993 17-1141*

15-10698 16-14060 17-1473*

15-16087 16-14207 17-1661*

15-17634 16-14210 17-1677*

15-18016 16-14274 17-1741*

15-20739 16-1488 17-1776*

15-22156 16-15937 17-1777*

15-22736-2 16-15951 17-1790*

15-23704 16-16045

15-23705 16-1832

15-23793 16-3841

15-23796 16-4633

15-23859 16-4905

15-24143 16-6501

15-24188 16-8427

15-24734 16-903

15-25399 17-1016*

15-26129 17-1019

  • Issued as a result of inspection activities.

3

Design Change Notices

0601177 0601176 0701838

Drawings

Number Title Revision/Date

5S139F00063#2 Piping & Instrumentation Diagram Feedwater 36

5S109F00016#2 Piping & Instrumentation Diagram Main Steam 34

5S142F00024 Piping & Instrumentation Diagram Auxiliary 12

Feedwater

5R209F05017#2 Piping and Instrumentation Diagram Component 20

Cooling Water System

E0AAAA Sht. 1 Single line Diagram Main one Line Diagram Unit 28

Number 1 and 2

9E0AAAB#1 Sht. 1 Single Line Diagram Class 1E 125V DC and 120V 27

Vital AC Non-Class 1E 48V, 125V, 250V, DC and

120V Vital AC Non-Class 1E Inverter power for

Computer 208V/120V AC Regulated Power

C012-000937F Detail M-1A Silicone Elastomer Typical Mechanical November 9,

Penetration Seals (walls and Floors) 1999

9E0DG04#2 Sht. 1 Elementary diagram Standby Diesel Generator 20

Number 21 Emergency Control and Instrumentation

9E0DG04#2 Sht. 2 Elementary diagram Standby Diesel Generator 16

Number 21, 22, and 23 Emergency Control and

Instrumentation

5Z109Z42117#2 Instrumentation ESF Load Sequencer Actuation 12

Train A Logic Diagram System SP

804101197CE STP Log Number Cooper Bessemer G5-553-137 0

Control Schematic (Starting Sequence Control)

9-E-MB03-01#2 Elementary Diagram Master Block Diagram ESF 6

Main Control Board ZCP003

9E0PK03#2 Elementary Diagram ESF Transformer and 4.16kV 9

Bus E1A, E1B, and E1C Protection and Metering

Circuit

9E0PK04#2 Sht. 1 Elementary Diagram ESF Transformer and 4.16kV 14

Bus E2A, E2B, and E2C Protection and Metering

Circuit

4

Drawings

Number Title Revision/Date

9E0DG01#2 Sht.1 Elementary Diagram Standby Diesel Generator 16

DG21 4.16kV Feeder Breaker

9E0PK01#2 Sht. 1 Elementary Diagram 4.16kV ESF Bus E1A, E1B, 10

and E1C Supply Breaker Control

9E0PK01#2 Elementary Diagram 4.16kV ESF Bus E1A, E1B, 7

and E1C Supply Breaker Control

9-E-RC1 3-01 Elementary Diagram Reactor Coolant Pressurizer 9

Power Relief Valves PCV-655A and PCV-656A

9E0SI05#2 Sht. 1 Elementary Diagram High Head Safety Injection 8

Pumps PA201A, PA201B, and PA201C

9E0SI06#2 Sht. 1 Elementary Diagram Low Head Safety Injection 9

Pumps PA202A, PA202B, and PA202C

9E0CH11#2 Sht. 1 Elementary Diagram E.A.B. HVAC Essential Chilled 10

Water Chiller Units CH004, CH005, and CH006

9-E-CH11-03#2 Elementary Diagram E.A.B. HVAC Essential Chilled 5

Water Chiller Units CH004, CH005, and CH006

9-E-PKAA-01 #2 Single Line Diagram 4.16kV Class 1E 10

Switchgear E2A

9E0PKAB#2 Sht. 1 Single Line Diagram 4.16kV Class 1E 10

Switchgear E2B

9E0PKAC-01#2 Single Line Diagram 4.16kV Class 1E 9

Switchgear E2C

9E0EW01#2 Sht. 1 Elementary Diagram Essential Cooling Water 20

Pumps Number 2A, 2B, and 2C

9E0AF01#2 Sht. 1 Elementary Diagram Auxiliary Feedwater Pumps 10

Number 21, 21, and 23

9E-AF01-02 #2 Elementary Diagram Auxiliary Feedwater Pumps 3

Number 11, 12, and 13

9E0CV26#2 Sht. 1 Elementary Diagram Centrifugal Charging Pumps 12

Number 2A and 2B (PA201A and PA201B)

9E0CV26#2 Sht. 2 Elementary Diagram Centrifugal Charging Pumps 12

Number 2A and 2B (PA201A and PA201B)

5

Drawings

Number Title Revision/Date

9E0CC01#2 Sht. 1 Elementary Diagram Component Cooling Water 16

PA201A, PA201B, and PA201C

9E0CC01#2 Sht. 2 Elementary Diagram Component Cooling Water 20

PA201A, PA201B and PA201C

9-E-CC10-01 #2 Elementary Diagram Master Cable Block Diagram 13

Component Cooling Water System

9E0CV05#2 Sht. 1 Elementary Diagram CVCS VCT Outlet Isolation 12

MOV-0112B and MOV-0113A

9E0CV31#1 Sht. 1 Elementary Diagram CVCS RWST to Charging 14

Pump MOV-0112C AND MOV-0113B

9E0SI12#2 Sht. 1 Elementary Diagram SI RWST Outlet MPVs 0001A, 11

0001B, and 0001C

9E0RC05#1 Sht. 1 Elementary Diagram Reactor Coolant Pressurizer 17

Relief Block Valve MOV0001A and MOV0001B

9E0RC05#2 Sht. 1 Elementary Diagram Reactor Coolant Pressurizer 15

Relief Block Valve MOV0001A and MOV0001B

5-R-14-9-Z-42155#1 Reactor Coolant Pressurizer Relief Block Valves 11

logic Diagram System

9E0AF13#2 Sht. 1 Elementary Diagram AFW to Steam Generator 2D 16

Regulating Valve FV-7526

9E0CV09#2 Sht. 1 Elementary Diagram CVCS Excess Letdown Line 11

Isolation MOV-0083 and MOV-0082

9E0RH05#2 Sht. 1 Elementary Diagram Residual Heat Removal 12

Pumps 2A, 2B, and 2C (PA201A, PA201B, and

PA201C)

9E0RH05#2 Sht. 2 Elementary Diagram Residual Heat Removal 1

Pumps 2A, 2B, and 2C

9E0PLAA#2 Sht. 1 Single Line Diagram 480V Class-1E Center E2A 19

9E0PLAB#2 Sht. 1 Single Line Diagram 480V Class-1E Center E2B 16

9E0PLAC#2 Sht. 1 Single Line Diagram 480V Class-1E Center E2C 17

9E0PMAA#2 Sht. 1 Single Line Diagram 480V Class-1E Motor Control 26

Center E2A1

6

Drawings

Number Title Revision/Date

9E0PMAA#2 Sht. 2 Single Line Diagram 480V Class-1E Motor Control 21

Center E2A1

9E0PMAB#2 Sht. 1 Single Line Diagram 480V Class-1E Motor Control 27

Center E2A2

9E0PMAC#2 Sht. 1 Single Line Diagram 480V Class-1E Motor Control 14

Center E2A3 ECW Building

9E0PMAD#2 Sht. 1 Single Line Diagram 480V Class-1E Motor Control 25

Center E2B1

9E0PMAD#2 Sht. 2 Single Line Diagram 480V Class-1E Motor Control 22

Center E2B1

9E0PMAE#2 Sht. 1 Single Line Diagram 480V Class-1E Motor Control 17

Center E2B2

9E0PMAF#2 Sht. 1 Single Line Diagram 480V Class-1E Motor Control 15

Center E2B3 ECW Building

9E0PMAG#2 Sht. 1 Single Line Diagram 480V Class-1E Motor Control 21

Center E2C1

9E0PMAG#2 Sht. 2 Single Line Diagram 480V Class-1E Motor Control 17

Center E2C1

9E0PMAH#2 Sht. 1 Single Line Diagram 480V Class-1E Motor Control 21

Center E2C2

9E0PMAJ#2 Sht. 1 Single Line Diagram 480V Class-1E Motor Control 14

Center E2C3 ECW Building

9E0PMAK#2 Sht. 1 Single Line Diagram 480V Class-1E Motor Control 22

Center E2A4

9E0PMAL#2 Sht. 1 Single Line Diagram 480V Class-1E Motor Control 22

Center E2B4

9E0PMAM#2 Sht. 1 Single Line Diagram 480V Class-1E Motor Control 20

Center E2C4 Center

9E0PCAA#2 Sht. 1 Single Line Diagram 13.8 kV Switchgear 2F 17

9E0PCAB#2 Sht. 1 Single Line Diagram 13.8 kV Switchgear 2G 17

9E0PCAC#2 Sht. 1 Single line Diagram 13.8 kV Switchgear 2H 16

7

Drawings

Number Title Revision/Date

9E0VAAA#2 Sht. 1 Single Line Diagram Vital 120V AC Distribution 27

Panels DP001, DP1201 Channel I

5R209F05017 Piping and Instrumentation Component Cooling 20

Water System

86-534801 Sht. 1 Liquid Level Controller FR72LL - Remote A

Electronics

86-534801 Sht. 2 Liquid Level Controller FR72LL - Remote A

Electronics

9-W-01-9-E-50102 Electrical-Communications Maintenance Jack 5

Station One Line Diagram

9E569E03765 Electrical - Electrical Auxiliary Bldg. Lighting & 11

Communications Plan Elevation 35-0

9E569E03751 Electrical - Electrical Auxiliary Bldg. Lighting & 15

Communications Plan Elevation 10-0

9E569E03753 Electrical - Electrical Auxiliary Bldg. Lighting & 20

Communications Plan Elevation 10-0

9E569E03767#2 Electrical - Electrical Auxiliary Bldg. Lighting Plan 21

Elevation 35-0

9E560E03001 Electrical Elementary Diagram - Lighting Fixture 30

Schedule Units 1 & 2

0-E-0102 SH. 5 Electrical Lighting Notes & Details Lighting Symbols 9

7E569E03046 Appendix R Light Locations 3

9E560E0102 SH. 23 Electrical Lighting Notes And Details Wall Mount 9

Emergency LTGS.

9W019E00466 #2 Mech. And Elect. Aux. Bldg. Fire Detection 7

Plan El. 21-0 & 29-0

9W019E00467 #2 Mech. And Elect. Aux. Bldg. Fire Detection 9

Plan El. 35-0 & 41-0

9W019E00468 #2 Mechanical and Electrical Aux. Bldg. Fire Detection 7

Plan El. 60-0

9-W-01-9-E-50471 #2 Mechanical & Electrical Auxiliary Building Fire 4

Detection Partial Plans for Miscellaneous Areas

8

Drawings

Number Title Revision/Date

9-W-01-9-E-50474 #2 Isolation Valves Cubicle Fire Detection 4

Plan El. 10-0 & 21-2

9-W-01-9-E-50475 #2 Isolation Valves Cubicle Fire Detection 3

Plan El. 58-6

7M149M24514 #2 Fire Areas Mechanical & Electrical Building Plan at 10

El. 21-0, 23-0, 29-0, & 32-0

7M149M24515 #2 Fire Areas Mechanical & Electrical Auxiliary Building 14

Plan at El. 35-0, 41-0 & 51-0

7M149M24516 #2 Fire Areas Mechanical & Electrical Auxiliary Building 11

Plan at El. 60-0

7M-14-9M-24534 #2 Fire Areas Isolation Valves Cubicle Plan at El. 10-0 4

& 21-2

7M-14-9M-24535 #2 Fire Areas Isolation Valves Cubicle Plan at El. 34-0 4

& 44-0

7M-14-9M-24536 #2 Fire Areas Isolation Valves Cubicle Plan El. 51-6 4

7M-14-9M-24537 #2 Fire Areas Isolation Valves Cubicle Plan at El. 59-6 4

7M-14-9M-24538 #2 Fire Areas Isolation Valves Cubicle Sections A-A & 4

B-B

7M149M24513 #1 Fire Areas Mechanical & Electrical Auxiliary Building 10

Plan at El, 10-0

7M149M24515 #1 Fire Areas Mechanical & Electrical Auxiliary Building 19

Plan at EL. 35-0, 41-0 &51-6

7M149M24514 #1 Fire Areas Mechanical & Electrical Building Plan at 10

EL. 21-0, 23-0 & 330-0

7M149M24516 #1 Fire Areas Mechanical & Electrical Building Plan at 11

EL. 60-0

7M-14-9M-24534 #1 Fire Areas Mechanical & Electrical Building Plan at 4

EL. 10-0 & 21-2

00000E0AAAA Single Line Diagram Main One Line Diagram Unit 28

No. 1 & 2

00009E0AAAB #1 Single Line Diagram Class 1E 125V DC & 120V Vital 27

AC Non-Class 1E 48V, 125V, 250, DC, & 120V Vital

AC Non-Class 1E Inverter Power for Computer

9

Drawings

Number Title Revision/Date

208V/120V AC Regulated Power

AC Non-Class 1E Inverter Power for Computer

208V/120V AC Regulated Power

7M149M24513, Mechanical & Electrical Auxiliary Building, Plan at 10

Sheet 1 El. 10-0

7M149M24514, Mechanical & Electrical Auxiliary Building, Plan at 10

Sheet 1 El. 21-0, 23-0, 29-0, and 30-0

7M149M24515, Mechanical & Electrical Auxiliary Building, Plan at 19

Sheet 1 El. 35-0, 41-0, and 51-6

7M149M24516, Mechanical & Electrical Auxiliary Building, Plan at 11

Sheet 1 El. 60-0

7M149M24534, Isolation Valves Cubicle, Plan at El. 10-0 and 21-2 4

Sheet 1

9-E-56-9-E-3608, Electrical - Mechanical Auxiliary Building, Lighting 13

Sheet 2 and Communications Plan, Elevation 29-0

9-E-NI02-091, Elementary Diagram, Master Block Diagram, 4

Sheet 2 Neutron Flux Monitoring System, QDPS Interface

Miscellaneous Documents

Number Title Revision/Date

Westinghouse Type EB, EHB, MARK 75 Type December 11,

HFBFuse Curves for 15 Amp circuit breaker 1985

Littelfuse Incorporated Time-Current Characteristics September 25,

334 and 336 Series Indicating Fuses Fuse Curves 1986

STP Users Guide for Maintenance Jack and September

Fueling/Refueling Jack Systems 1987

07-457-70 Evaluation for Adding 500 GPM of Demineralized December 9,

Water to the Spent Fuel Pool Using the Temporary 2008

Fire Water Pump Through the Fire Water Header

1200006 Design Change Notice March 7, 2012

1200360 Design Change Notice March 13,

2012

9703446 Document Change Notice October 8,

1997

10

Miscellaneous Documents

Number Title Revision/Date

ED-1020 Document Change Notice January 2,

1991

204608A PCF Amendment Form February 14,

1994

204641A PCF Amendment Form January 31,

1994

CR 08-14399 STP Multiple Spurious Operation Report 1

STP MSO Generic List 1

15-06 (FP) STP Nuclear Operating Company Fire Protection August 31,

Quality Audit Report 2015

16-07 (FP) STP Nuclear Operating Company Fire Protection August 17,

Quality Audit Report 2016

Active Fire Protection Impairment Permits January 26,

2017

U2 Open Fire Watches January 26,

2017

17-01-03 Unannounced Fire Drill (0PGP03-ZF-0011, STEGS February 8,

Fire Brigade, Rev. 16) 2017

NCR 89-2-025 Appendix R Emergency DC Lighting, ECWIS January 26,

Rooms 101, 102, 103 1989

5A019MFP001 Post-Fire Operator Actions and Equipment 16

Protection Requirements

Fire Hazards Analysis Report 23

Modifications

Number Title Date

1401401 13-11489-1, Revise Drawing as Shown on Page 3 June 16, 2014

1400495 13-11489-1, Change Page 2 of May 19, 2014

Calculation 0238-0201005SQ

11

Procedures

Number Title Revision

0PSP03-CV-0011 Chemical and Volume Control System Valve 28

Operability Test (Cold Shutdown)

0PSP03-RC-0010 Pressurizer Power Operated Relief Valve Operability 13

Test

0PSP03-ZG-0005 Remote Shutdown System Operability Test (Cold 16

Shutdown)

1PSP03-ZG-0007A Train A Remote Shutdown System Operability Test 9

1PSP03-ZG-0007B Train B Remote Shutdown System Operability Test 9

1PSP03-ZG-0007C Train C Remote Shutdown System Operability Test 9

2PSP03-ZG-0007A Train A Remote Shutdown System Operability Test 4

2PSP03-ZG-0007B Train A Remote Shutdown System Operability Test 5

2PSP03-ZG-0007C Train A Remote Shutdown System Operability Test 5

1PSP03-ZG-0007C Train C Remote Shutdown System Operability Test 9

2PSP03-ZG-0007C Train C Remote Shutdown System Operability Test 5

0PGP03-ZF-0011 STPEGS Fire Brigade 16

0POP10-FP-0001 Alternate Fire Protection System Operation 4

0PRP06-ZR-0013 Respirator Fit Testing 8

0POP01-ZA-0001 Plant Operations Department Administrative Guidelines 49

0PTP03-FP-0106 Fire Protection Water System Functional Test 15

0POP10-FP-0001 Alternate Fire Protection System Operation 4

0POP10-ZO-EDMG Extensive Damage Mitigation Guideline 5

0PGP03-ZF-0018 Fire Protection System Functionality Requirements 19

0POP04-ZO-0009 Safe Shutdown Fire Response 15

12

Procedures

Number Title Revision

0PGP05-ZV-0014 Emergency Response Activities 15

PMI-EM-EL-0001 Emergency Light Testing 0

0PGP03-ZF-0001A Hot Work Program 3

0PGP03-ZF-0019 Control of Transient Fire Loads and Use of 15

Combustible and Flammable Liquids and Gases

0PGP03-ZF-0018 Fire Protection System Functionality Requirements 19

0PGP03-ZT-0131 Fire Protection Training and Qualification Program 11

0POP04-ZO-0009 Safe Shutdown Fire Response 14

0POP04-ZO-0008 Fire/Explosion 25

0PGP04-ZA-0002 Condition Report Engineering Evaluation 24

0POP04-ZO-0001 Control Room Evacuation 42

2TOP07-LB-0001 Unit 2 ECWIS Emergency DC Lighting Test 0

Vendor Document

Number Title Revision

VTD-M568-0004 Holophane M-19 12 volt DC power pack for automatic 3

emergency lighting - Installation and maintenance

instructions

Work Orders

553365 476850 509206 469672

498017 476853 509205 439418

516337 525424 503414 455441

482275 525364 497337 489640

499679 486919 479338 525362

507880 470941 476848 484809

502929 96006291

13

ML17079A526

SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002

By: STM Yes No Publicly Available Sensitive

OFFICE ASRI:EB2 RI:EB2 SRI:EB2 RI:EB1 RI:EB2 C:EB2 C:PBB C:EB2

NAME SMakor SAlferink JDrake CStott JWatkins GWerner NTaylor GWerner

SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/ /RA/ /RA/DLP /RA/

for

DATE 03/08/17 03/03/17 03/06/17 03/06/17 03/16/17 03/10/2017 03/20/17 03/20/17