Fire Protection Inspection Report 05000498/2023010 and 05000499/2023010
ML23074A192
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 03/27/2023
From: Nick Taylor
NRC/RGN-IV/DORS/EB2
To: Gerry Powell
South Texas
References
IR 2023010
Download: ML23074A192 (9)


Text

March 24, 2023

SUBJECT:

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION - FIRE PROTECTION INSPECTION REPORT 05000498/2023010 AND 05000499/2023010

Dear G. T. Powell:

On February 16, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at South Texas Project Electric Generating Station. On February 16, 2023, the NRC inspectors discussed the results of this inspection with K. Harshaw and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Signed by Taylor, Nicholas on 03/24/23 Nicholas H. Taylor, Chief Engineering Branch 2 Division of Operating Reactor Safety Docket Nos. 05000498, 05000499 License Nos. NPF-76, NPF-80

Enclosure:

As stated

Inspection Report

Docket Numbers: 05000498 and 05000499 License Numbers: NPF-76 and NPF-80 Report Numbers: 05000498/2023010 and 05000499/2023010 Enterprise Identifier: I-2023-010-0007 Licensee: STP Nuclear Operating Company Facility: South Texas Project Electric Generating Station Location: Wadsworth, TX Inspection Dates: January 30, 2023 to February 17, 2023 Inspectors: M. Chisolm, Reactor Inspector S. Makor, Reactor Inspector J. Drake, Senior Reactor Inspector Approved By: Nicholas H. Taylor, Chief Engineering Branch 2 Division of Operating Reactor Safety Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a fire protection inspection at South Texas Project Electric Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.05 - Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)

The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).

(1) Cable spreading room, train A
(2) Auxiliary shutdown area
(3) Relay cabinet area of control room

Fire Protection Program Administrative Controls (IP Section 03.02) (2 Samples)

The inspectors verified that the selected controls are implemented in accordance with the licensees current licensing basis and have adequate implementing procedures.

(1) Fire brigade training program and qualifications Observed a fire brigade drill on February 28, 2023
(2) Administrative controls for control of fire impairments and compensatory measures

Fire Protection Program Changes/Modifications (IP Section 03.03) (3 Samples)

The inspectors evaluated the licensee's procedures controlling modifications and procedure revisions for adequacy in reviewing potential impacts to the fire protection program.

(1) Procedure revisions to Procedure 0PTP03-FP-0103, Fire Protection System Flush, revision 11
(2) Condition report engineering evaluation (CREE) 21-12326-4, supplement 1, deviation to NFPA 20-1974/1976 and NFPA 22-1976 regarding the requirement of frost-proof casings for suction piping for the fire water storage tanks within South Texas Project Fire Hazard Analysis Report
(3) Procedure revisions to procedure 0PGP03-ZF-0018, Fire Protection System Functionality Requirements, revision

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On February 16, 2023, the inspectors presented the fire protection team inspection results to K. Harshaw, Executive Vice President and Chief Nuclear Officer and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.21N.05 Corrective Action Condition 2016-1381, 2018-1230, 2020-1243, 2020-2006, 2020-

Documents Reports 6916, 2020-7172, 2020-10868, 2020-10874, 2020-10892,

20-10933, 2020-10939, 2020-10940, 20-10945, 2020-

11608, 2021-5234, 2021-12326, 2022-477, 2022-3169,

22-5568, 2022-5730, 2022-6644, 2021-9005, 2022-

9108, 2022-9644, 2022-10077, 2022-10098, 2022-10513,

22-10748, 2022-10966, 2022-11450, 2022-12749,23-288, 2023-786, 2023-592, 2023-1133, 2023-12326

71111.21N.05 Corrective Action Condition 2023-413, 2023-414, 2023-427, 2023-1089, 2023-1090,

Documents Reports 2023-1094, 2023-1098, 2023-1100, 2023-1102, 2023-

Resulting from 1103, 2023-1136, 2023-1151, 2023-1153, 2023-1158,

Inspection 2023-1161, 2023-1162, 2023-1198, 2023-1204, 2023-

26, 2023-1230, 2023-1231, 2023-1297, 2023-1305,

23-1310, 2023-1326, 2023-1328, 2023-1329, 2023-

1330, 2023-1332, 2023-1333, 2023-1334, 2023-1335,

23-1337, 2023-1338, 2023-1339, 2023-1341, 2023-

1343, 2023-1346, 2023-1349, 2023-1350, 2023-1494,

23-1646, 2023-1661

71111.21N.05 Engineering Condition Report Gap Analysis Of OPGP03-ZF-0018 And DRAFT Revision 08/14/2018

Evaluations Engineering 5 NUREG-0452

Evaluation 2017-

24176

71111.21N.05 Engineering Condition Report Change To Compensatory Actions Required For Fire 02/19/2019

Evaluations Engineering detector Functionality Exceptions

Evaluation 2018-

201

71111.21N.05 Engineering Condition Report STP is proposing a deviation from NFPA 20-1974 (Diesel 05/12/2022

Evaluations Engineering Fire Pump 1), NFPA 20-1976 (Diesel Fire Pump 2 &3),

Evaluation 21- and NFPA 22-1976

2326-4 Supp. 2

71111.21N.05 Engineering Condition Report Seismic evaluation of tables in relay rooms 02/11/2016

Evaluations Engineering

Inspection Type Designation Description or Title Revision or

Procedure Date

Evaluation

34303270

71111.21N.05 Miscellaneous South Texas Project Nuclear Operating Company Active 01/30/2023

Fire Protection Impairment Permits

71111.21N.05 Miscellaneous FP-0-17000180 Fire Protection System Flush 04/26/2022

71111.21N.05 Miscellaneous NOC-AE- Attachment 1, STP Fire Hazards Analysis Report 03/30/2021

21003792 Amendment 26 Summary of Changes

71111.21N.05 Miscellaneous PRA-NB-03 South Texas Project Electric Generating Station 10

Probabilistic Risk Assessment Initiating Events

71111.21N.05 Miscellaneous PRA-NB-23 South Texas Project Electric Generating Station 10

Probabilistic Risk Assessment Fire Protection System

71111.21N.05 Procedures 0PGP03-ZA- Controlled System or Barrier Impairment 20

0514

71111.21N.05 Procedures 0PGP03-ZF-0016 Fire Protection Alternative Compensatory Measures 0

71111.21N.05 Procedures 0PGP03-ZO- Operator Time Critical Action Program 5

0057

71111.21N.05 Procedures 0PGP05-ZN- Change to Licensing Basis Documents and Amendments 31

0004 to the Operating License

71111.21N.05 Procedures 0POP02-FA- Fire Detection System 16

0001

71111.21N.05 Procedures 0POP04-ZO- Control Room Evacuation 50

0001

71111.21N.05 Procedures 0POP04-ZO- Fire/Explosion 30

0008

71111.21N.05 Procedures 0POP11-CW- Condenser Waterbox Online Isolation and Restoration Rev 30

0001

71111.21N.05 Procedures 0PTP03-FP-0103 Fire Protection System Flush 11

71111.21N.05 Procedures 0PTP03-FP-0120 Fire Hose Hydrostatic Test 13

71111.21N.05 Procedures OPGP04-ZA- Engineering and Vendor Document Processing 16

28

71111.21N.05 Work Orders 583296 WAN# 682, Diesel Fire Pump tripped on water temp 01/26/2023

above safe level

71111.21N.05 Work Orders PMWO WAN Sequential start of diesel fire pumps 1,2,3 02/04/2020

617838

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.21N.05 Work Orders PMWO WAN Sequential start of diesel fire pumps 1,2,3 09/17/2021

24865

7