January 29, 2024

SUBJECT:

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000498/2023004 AND 05000499/2023004

Dear G. T. Powell:

On December 31, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at South Texas Project Electric Generating Station, Units 1 and 2. On January 11, 2024, the NRC inspectors discussed the results of this inspection with Kimberly Harshaw, Executive Vice President and Chief Nuclear Officer, and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555- 0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement ; and the NRC R esident Inspector at South Texas Project Electric Generating Station, Units 1 and 2.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555 -0001; with copies to the Regional Administrator, Region IV ; and the NRC Resident Inspector at South Texas Project Electric Generating Station, Units 1 and 2. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Patricia J. Vossmar, Chief Reactor Projects Branch A Division of Operating Reactor Safety

Docket Nos. 05000498 and 05000499 License Nos. NPF-76 and NPF-80

Enclosure:

As stated

Inspection Report

Docket Numbers: 05000498 and 05000499

License Numbers: NPF-76 and NPF-80

Report Numbers: 05000498/2023004 and 05000499/2023004

Enterprise Identifier: I-2023-004- 0004

Licensee: STP Nuclear Operating Company

Facility: South Texas Project Electric Generating Station, Units 1 and 2

Location: Wadsworth, TX 77483

Inspection Dates: October 1, 2023, to December 31, 2023

Inspectors: N. Brown, Resident Inspector R. Bywater, Senior Project Engineer T. Farina, Senior Operations Engineer L. Flores, Resident Inspector C. Harrington, Operations Engineer S. Lichvar, Technical Assistant J. Melfi, Project Engineer D. You, Operations Engineer

Approved By: Patricia J. Vossmar, Chief Reactor Projects Branch A Division of Operating Reactor Safety

Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at South Texas Project Electric Generating Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Establish Required Compensatory Measures When Equipment Important to Emergency Response was Non-Functional Cornerstone Significance Cross-Cutting Report Aspect Section Emergency Green [H.2] - Field 71111.15 Preparedness NCV 05000498/2023004-01 Presence Open/Closed The inspectors identified a Green, non-cited violation of 10 CFR 50.54(q)(2) which requires that operating nuclear power plant licensees follow and maintain the effectiveness of an emergency plan that meets the requirements in Appendix E of 10 CFR 50, and the planning standards of 10 CFR 50.47(b), including 10 CFR Part 50.47(b)(4), relative to maintaining an emergency classification/action level scheme. Specifically, from July 19, 2023, to July 24, 2023, the licensees response to the loss of the control room area radiation monitor, RT-8066, failed to restore capability to classify emergency action level (EALs) RA3, Radiation Levels that impede access to equipment necessary for normal plant operation, cooldown or shutdown, which would rely on monitoring the control room area radiation monitor consistent with the approved EAL scheme. As a result, the licensees ability to declare an Alert was degraded during this period.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. Unit 1 lowered power to 80 percent power on November 25, 2023, for main turbine steam inlet valve testing and returned to full power on November 26, 2023, and remained there for the inspection period.

Unit 2 began the inspection period at rated thermal power. Unit 2 lowered power to 90 percent power on November 24, 2023, for main turbine steam inlet valve testing and returned to full power on November 25, 2023, and remained there for the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on -site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following systems:

emergency diesel generators the week of December 4, 2023 essential cooling water intake structure and pond the week of December 4, 2023

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather thunderstorms and high winds on November 20-21, 2023.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1, essential cooling water train A valve lineup on October 26, 2023
(2) Unit 1, essential cooling water train C valve lineup on November 2, 2023
(3) Unit 1, essential chilled water trains B and C lineups on December 5, 2023

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples )

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1, isolation valve cubicle, auxiliary feed pump room train A, fire zones Z400 and Z405 on October 25, 2023
(2) Unit 1, electrical auxiliary building power cable vault train A on November 6, 2023
(3) Unit 1, electrical auxiliary building cable spreading/power cable area train C on November 6, 2023

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered from September 27 to November 2, 2023.

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

(1) Biennial Requalification Written Examinations

The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered from November 20 to December 20, 2023.

Annual Requalification Operating Tests

The inspectors evaluated the adequacy of the facility licensees annual requalification operating test.

Administration of an Annual Requalification Operating Test

The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.

Requalification Examination Security

The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.

Remedial Training and Re-examinations The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions

The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.

Control Room Simulator

The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during Unit 2 testing and surveillances for risk significant systems on November 16 and 21, 2023.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated operator training on November 28, 2023.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 2, emergent work on E2D11 battery maintenance on October 30, 2023
(2) Unit 2, yellow risk due to maintenance during the week of November 6, 2023
(3) Unit 1, unplanned entry into comprehensive risk management program for trains B and C essential chiller inoperability on November 10, 2023
(4) Unit 2, unplanned entry into comprehensive risk management program for train B essential cooling water on November 12, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 2 control rod shutdown bank "C" incomplete movement during performance of control rod operability testing on October 18, 2023
(2) Unit 1, RE-8066 control room radiation monitor functionality on July 24, 2023
(3) Unit 2, train B emergency diesel generator sequencer trouble alarm on November 11, 2023
(4) Unit 2, train B essential cooling water screen wash flow for traveling screen on November 17, 2023
(5) Unit 1, essential chiller train C chilled water leakage on November 19, 2023

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (5 Samples)

(1) Unit 2, control rod operability testing of shutdown bank C on October 18, 2023
(2) Unit 1, ESF load sequencer cabinet C replacement of power supplies 1 and 2 on October 19, 2023
(3) Unit 2, train B diesel generator 6-year maintenance on November 18, 2023
(4) Unit 2, train C essential chiller on November 19, 2023
(5) Unit 1, train C essential chiller on November 20, 2023

Surveillance Testing (IP Section 03.01) (3 Samples)

(1) Unit 1, train C emergency diesel generator on October 19, 2023
(2) Unit 2, train C emergency diesel generator on November 21, 2023
(3) Unit 2, train D auxiliary feedwater train D quarterly test on November 30,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 1 (July 1, 2022, through September 30, 2023)
(2) Unit 2 (July 1, 2022, through September 30, 2023)

MS07: High Pressure Injection Systems (IP Section 02.06) (2 Samples)

(1) Unit 1 (July 1, 2022, through September 30, 2023)
(2) Unit 2 (July 1, 2022, through September 30, 2023)

MS08: Heat Removal Systems (IP Section 02.07) (2 Samples)

(1) Unit 1 (July 1, 2022, through September 30, 2023)
(2) Unit 2 (July 1, 2022, through September 30, 2023)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (October 1, 2022, through September 30, 2023)
(2) Unit 2 (October 1, 2022, through September 30, 2023)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (October 1, 2022, through September 30, 2023)
(2) Unit 2 (October 1, 2022, through September 30, 2023)

INSPECTION RESULTS

Failure to Establish Required Compensatory Measures When Equipment Important to Emergency Response was Non-Functional Cornerstone Significance Cross-Cutting Report Aspect Section Emergency Green [H.2] - Field 71111.15 Preparedness NCV 05000498/2023004 -01 Presence Open/Closed The inspectors identified a Green, non-cited violation of 10 CFR 50.54(q)(2) which requires that operating nuclear power plant licensees follow and maintain the effectiveness of an emergency plan that meets the requirements in Appendix E of 10 CFR 50, and the planning standards of 10 CFR 50.47(b), including 10 CFR Part 50.47(b)(4), relative to maintaining an emergency classification/action level scheme. Specifically, from July 19, 2023, to July 24, 2023, the licensees response to the loss of the control room area radiation monitor, RT-8066, failed to restore capability to classify emergency action level (EALs) RA3, Radiation Levels that impede access to equipment necessary for normal plant operation, cooldown or shutdown, whic h would rely on monitoring the control room area radiation monitor consistent with the approved EAL scheme. As a result, the licensees ability to declare an Alert was degraded during this period.

Description:

On June 18, 2023, the licensee performed work authorization number (WAN)653108 to change the air filter in containment atmosphere radiation monitors, RT-8010A and RT-8011. The licensee completed the filter change, performed post maintenance channel chec ks, and returned the radiation monitors to service.

On July 19, 2023, shortly after maintenance was completed, the primary and alternate communication ports from RT8011 that provide input into RM -11, Radiation Monitoring -

Computer Program, and RM -23, Control Room Radiation Monitoring Panel, failed. This caused indications on RM-11 and RM-23 to freeze. The licensee began troubleshooting RT-8011 under WAN 692724. During troubleshooting activities, the affected radiation monitor loop lost communication, subsequently causing the licensee to declare approximately 23 radiation monitors non-functional, including the control room area radiation monitor, RT-8066.

Licensed operators followed 0POP04-RA-0001, revision 44, Radiation Monitoring System Alarm Response, and notified the Emergency Response Organization via email of the non-functional radiation monitors.

Through continued troubleshooting, the licensee was able to restore RT-8011, and most of the radiation monitors impacted by the failure of the radiation monitor loop, to a functional status. RT-8066 was not successfully restored and remained in a non-functional status.

On July 24, 2023, the inspectors identified that RT-8066 was listed in Procedure 0EPM01-IP-0004, revision 0, Equipment Important to Emergency Response, as requiring the implementation of compensatory measures if it was non-functional. Required compensatory measures for the failure of RT-8066 included actions to monitor other functional radiation monitors in the building. The inspectors queried the licensee to verify if they had implemented the required compensatory measures and found that they had not been implemented since July 19, 2023. This resulted in the licensees degraded ability to declare EAL Alert RA3, Radiation Levels that impede access to equipment necessary for normal plant operation, cooldown or shutdown. The licensee immediately implemented the required compensatory measures, thereby restoring their EAL scheme, and declared RT-8066 non-functional in their Operability Assessment System (OAS).

The licensee determined that the u nit supervisor recognized RT-8066 as equipment important to emergency response when it became non-functional on July 19, 2023, but the crew did not make an entry into the OAS at that time. With the OAS not being updated to reflect the correct nonfunctional status of RT-8066, subsequent watch teams remained unaware of RT-8066s non-functional condition. Consequently, the required compensatory measures were not implemented from July 19 to 24, 2023.

Corrective Action References: The licensee entered these issues into the corrective action program with condition report CR-2023-7042.

Performance Assessment:

Performance Deficiency: The licensees failure to implement required compensatory measures for the failed control room area radiation monitor in accordance with the emergency plan was a performance deficiency.

Screening: The inspectors determined that the performance deficiency was more than minor because it was associated with the Emergency Response Organization Performance attribute of the Emergency Preparedness Cornerstone and adversely affected the cornerstone objective of ensuring the licensee is capable of implementing adequate measures to protect the health and safety of the public in the event of a radiological emergency.

Specifically, compensatory measures were not established upon the loss of the control room area radiation monitor resulting in degraded ability to declare an Alert.

Significance: The inspectors assessed the significance of the finding using NRC Inspection Manual Chapter 0609, Appendix B, "Emergency Preparedness Significance Determination Process," dated September 22, 2015. The inspectors determined the finding to be of very low safety significance (Green), consistent with Figure 5.4-1, because it would have resulted in an Alert being declared in a degraded manner.

Cross-Cutting Aspect: H.2 - Field Presence: Leaders are commonly seen in the work areas of the plant observing, coaching, and reinforcing standards and expectations. Deviations from standards and expectations are corrected promptly. Senior managers ensure supervisory and management oversight of work activities, including contractors and supplemental personnel.

Specifically, licensee shift management did not ensure the Operability Assessment System remained current per procedure 0POP01-ZO-0011, Operability, Functionality, and Reportability Guidance, revision 18, which states, the Shift Manager/Unit Supervisor is responsible for ensuring the Operability Assessment System remains current. This led to inadequate shift turnover and continued failure to implement required compensatory measures.

Enforcement:

Violation: Title 10 CFR 50.54(q)(2) requires that a holder of a nuclear power plant operating license follow and maintain the effectiveness of an emergency plan that meets the requirements of Appendix E of this part and the planning standards of 10 CFR 50.47(b).

Furthermore, 10 CFR Part 50.47(b)(4), requires that a standard emergency classification and action level scheme, the bases of which include facility system and effluent parameters, is in use by the nuclear facility licensee.

Contrary to the above, from July 19, 2023, to July 24, 2023, upon loss of the control room area radiation monitor, RT-8066, the licensee failed to ensure that the standard emergency classification and action level scheme, as approved by the NRC for use by the licensee, was in use and maintained the effectiveness of the emergency plan. Specifically, the licensee failed to implement compensatory measures for the failed radiation monitor, which degraded the licensees ability to declare emergency action level off-normal event RA3, Radiation Levels that impede access to equipment necessary for normal plant operation, cooldown or shutdown.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 26, 2023, the inspectors presented the STP 2023 BRQ technical debrief inspection results to Bobby Simpson, Manager, Organizational Effectiveness, and other members of the licensee staff.
  • On December 20, 2023, the inspectors presented the STP 2023 BRQ exit meeting inspection results to Bobby Simpson, Manager, Organizational Effectiveness, and other members of the licensee staff.
  • On January 11, 2024, the inspectors presented the integrated inspection results to Kimberly Harshaw, Executive Vice President and Chief Nuclear Officer, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.01 Corrective Action CR-YYYY-NNNN 2022-30; 2022-100; 2022-4832; 2023-8846

Documents

71111.01 Miscellaneous 5R289MB01006 Essential Cooling Water Operations Design Basis Document 9

71111.01 Miscellaneous 5Q159MB1023 Standby Diesel Generator System 4

71111.01 Miscellaneous Listing Listing of Condition reports for 1 year related to adverse

weather.

71111.01 Procedures 0PGP03-ZV-0001 Severe Weather Plan 25

71111.01 Procedures 0PGP03-ZV-0004 Winter Readiness Program 13

71111.01 Procedures 0POP01-ZO-0004 Extreme Cold Weather Guideline 44

71111.04 Drawings 3V111V01054 Piping and instrumentation Diagram Refrigeration Chiller 14

3V111VCH006 Chilled Water System Train "C"

71111.04 Miscellaneous 5R289MB01006 Essential Cooling Water Operations Design Basis Document 9

71111.04 Procedures 0POP02-CH-0001 Essential Chilled Water System 59

71111.04 Procedures 0POP02-EW-Essential Cooling Water Operations 85

0001

71111.05 Procedures 0-EAB02-FP-Fire Preplan Electrical Auxiliary Building, Power Cable Vault 3

0010 Train A

71111.05 Procedures 0-EAB65-FP-Fire Preplan Electrical Auxiliary Building, Cable 2

0057 Spreading/Power Cable Area, Train C

71111.05 Procedures 0-IVC50-FP-0401 Fire Preplan Isolation Valve Cubicle, Pump Room Train A 2

71111.11B Corrective Action CR-YYYY-NNNN 2023-11293, 2021-12263, 2022-6984, 2022-9303,

Documents 2023-2443, 2023-2483, 2023-4259, 2023-4608, 2023-4842,

23-4842, 2023-5276, 2023-5463, 2023-6173, 2023-9926

71111.11B Miscellaneous STP Simulator Core Reload Acceptance Test Cycle 24 05/11/2022

71111.11B Miscellaneous 2022 Annual Simulator Exam Sample Plan

71111.11B Miscellaneous 2023 Annual Simulator Exam Sample Plan

71111.11B Miscellaneous 2023 Annual JPM Exam Sample Plan

71111.11B Miscellaneous Transient Test 1 04/25/2022

71111.11B Miscellaneous Transient Test 5 04/25/2022

71111.11B Miscellaneous Transient Test 10 05/09/2022

71111.11B Miscellaneous STP Simulator Deficiency Reports 2022-2023

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.11B Miscellaneous Various Operator Medical Records

71111.11B Miscellaneous Annual Performance Test #24

71111.11B Miscellaneous Annual Performance Test #25

71111.11B Miscellaneous Annual Performance Test #22

71111.11B Miscellaneous Annual Performance Test #31

71111.11B Miscellaneous Job Performance Measure #2.03

71111.11B Miscellaneous Job Performance Measure #3.03

71111.11B Miscellaneous Job Performance Measure #62.02a

71111.11B Miscellaneous Job Performance Measure #152.01

71111.11B Miscellaneous Job Performance Measure #01.01a

71111.11B Miscellaneous Job Performance Measure #18.01

71111.11B Miscellaneous Job Performance Measure #5.01

71111.11B Miscellaneous Job Performance Measure #12.01

71111.11B Miscellaneous Job Performance Measure #38.01a

71111.11B Miscellaneous Job Performance Measure #144.01

71111.11B Miscellaneous 2023 STP Biennial Exam RO and SRO Week 3

71111.11B Miscellaneous 0POP01-ZA-0014 Active License Maintenance - Crew C Q2/Q3 2023 2

Form 2

71111.11B Procedures 0PGP03-ZA-0065 Qualification of Plant Staff Personnel 15

71111.11B Procedures 0PGP03-ZA-Medical Examinations - NRC Regulated 4

28A

71111.11B Procedures 0PGP03-ZT-0132 Licensed Operator Requalification 14

71111.11B Procedures 0PNT01-TQ-1001 Exam Security 10

71111.11B Procedures 0PNT01-ZA-0037 Simulator Configuration Control 15

71111.11B Procedures 0PNT01-ZT-0300 LOR Training Program 1

71111.11B Procedures 0PNT01-ZT-0301 LOR Annual and Biennial Evaluation 4

71111.11B Procedures 0PNT01-ZT-0301 Simulator Scenario / Set Review Checklist 2023 2

Add. 2

71111.11B Procedures 0PNT01-ZT-0304 LOR Conduct of Simulator Training 1

71111.11B Procedures 0POP01-ZA-0014 Initial Operator License and Licensed Operator Programs 34

71111.11B Procedures JA-LOR-02 Simulator Critique Job Aid 3

71111.11Q Miscellaneous RST223.19 Lesson Plan: Reactor Startup/Turbine Startup 0

71111.11Q Procedures 0OPP03-ZG-0005 Plant Startup to 100% 123

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.11Q Procedures 0POP03-ZG-0004 Reactor Startup 52

71111.13 Corrective Action CR-YYYY-NNNN 2023-9972, 2023-10345, 2023-10352, 2023-10288,

Documents 2023-10254, 2023-10362, 2023-10369

71111.13 Procedures 0POP01-ZO-Risk Management Actions (RMA's) 28

0006

71111.13 Procedures 0PGP02-ZA-0003 Comprehensive Risk Management Program 16

71111.15 Calculations MC06118 ECW Screen Wash Minimum Flow, Unit 2 12/12/1988

71111.15 Corrective Action CR-YYYY-NNNN 2023-9682, 2023-6985, 2023-7042, 2023-10363,

Documents 2023-10482, 2023-10352, 2023-10577, 2023-10571,

23-9850

71111.15 Engineering 20-7996-6 Replacement ECW Traveling Screen 2B 08/17/2023

Changes

71111.15 Miscellaneous VTD-S637-0009 ESF Load Sequencer for South Texas Project Electric 1

Generating Station

71111.15 Miscellaneous VTD-Y018-0001 Open Turbopak Centrifugal Liquid Chilling Units Instructions 3

Operating and Maintenance Models OT A1 A3 thru OT K3

E3 90-650 Tons

71111.15 Procedures 0EPM01-IP-0004 Equipment Important to Emergency Response 0

71111.15 Procedures 0POP01-ZO-0011 Operability Functionality, and Reportability Guidance 18

71111.15 Procedures 0POP09-AN-Annunciator Lampbox 3M03 Response Instructions 37

03M3

71111.15 Procedures 0PSP03-RS-0001 Control Rod Operability 39

71111.15 Procedures EP-0003.000 Emergency Action Levels Technical Basis Manual 0

71111.15 Work Orders Work 698806, 697100

Authorization

Number

71111.24 Corrective Action CR-YYYY-NNNN 2023-9682, 2023-10538, 2023-10352, 2023-10577,

Documents 2023-10571, 2023-10568

71111.24 Procedures 0PSP03-AF-0007 Auxiliary Feedwater Pump 14(24) Inservice Test 64

71111.24 Procedures 0PSP03-DG-0003 Standby Diesel 13(23) Operability Test 66

71111.24 Procedures 0PSP03-RS-0001 Control Rod Operability 39

71111.24 Work Orders Work 594859, 598078, 648958, 661040, 670903, 672054,

Authorization 697100, 697363, 698376, 698758, 698806, 698983

Number

Inspection Type Designation Description or Title Revision or

Procedure Date

71151 Procedures MSPI Bases Document 27

71151 Procedures 0PGP05-ZN-0007 Preparation and Submittal of NRC Performance Indicators 10

71151 Procedures RMG1020 MSPI User's Manual 2

71151 Procedures SEG-0007 Mitigating System Performance Indicator Collection, 11

Processing and Maintenance of Data

13