ML23310A228

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000498/2023003 and 05000499/2023003, and Notice of Violation
ML23310A228
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 11/13/2023
From: Patricia Vossmar
NRC/RGN-IV/DORS/PBA
To: Gerry Powell
South Texas
References
IR 2023003
Download: ML23310A228 (34)


See also: IR 05000498/2023003

Text

November 13, 2023

EA-23-066

G. T. Powell, President

and CEO

STP Nuclear Operating Company

P.O. Box 289

Wadsworth, TX 77483

SUBJECT: SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION, UNITS 1

AND 2 - INTEGRATED INSPECTION REPORT 05000498/2023003 AND

05000499/2023003, AND NOTICE OF VIOLATION

Dear G. T. Powell:

On September 30, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at South Texas Project Electric Generating Station, Units 1 and 2. On October 11,

2023, the NRC inspectors discussed the results of this inspection with you and other members

of your staff. The results of this inspection are documented in the enclosed report.

The enclosed report discusses a violation associated with a finding of very low safety

significance (Green) for the failure to ensure that conditions adverse to quality involving

essential cooling water expansion joint tolerances, were promptly identified and corrected. The

NRC evaluated this violation in accordance section 2.3.2 of the NRC Enforcement Policy, which

can be found at http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html. The

violation is cited in Enclosure 1, Notice of Violation (Notice). This violation did not meet the

criteria to be treated as a non-cited violation (NCV) because the violation had been previously

identified in 2021 and your corrective actions were inadequately implemented. Expansion joint

tolerances were not restored to their design requirements within a reasonable period of time.

You are required to respond to this letter and should follow the instructions specified in the

enclosed Notice when preparing your response. If you have additional information that you

believe the NRC should consider, you may provide it in your response. The NRCs review of

your response will also determine whether further enforcement action is necessary to ensure

your compliance with regulatory requirements.

Additionally, one finding of very low safety significance (Green) is documented in this report.

This finding involved a violation of NRC requirements. We are treating this violation as an NCV

consistent with Section 2.3.2 of the Enforcement Policy.

A licensee-identified violation which was determined to be of very low safety significance is

documented in this report. We are treating this violation as an NCV consistent with Section 2.3.2

of the Enforcement Policy.

G. Powell 2

If you contest the violations or the significance or severity of the violations documented in this

inspection report, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional

Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector

at South Texas Project Electric Generating Station, Units 1 and 2.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a

response within 30 days of the date of this inspection report, with the basis for your

disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the

NRC Resident Inspector at South Texas Project Electric Generating Station, Units 1 and 2.

This letter, its enclosures, and your response will be made available for public inspection and

copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room

in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections,

Exemptions, Requests for Withholding.

Sincerely,

Signed by Vossmar, Patricia

on 11/13/23

Patricia J. Vossmar, Chief

Reactor Projects Branch A

Division of Operating Reactor Safety

Docket Nos. 05000498, 05000499

License Nos. NPF-76, NPF-80

Enclosures:

1) Notice of Violation

2) Inspection Report 05000498/2023003 and 05000499/2023003

cc w/ encl: Distribution via LISTSERV

ML23310A228

X SUNSI Review X Non-Sensitive X Publicly Available

RLB

Sensitive Non-Publicly Available

OFFICE RI:DORS/A ASRI:DORS/A ASRI:DORS/A SES:ACES

NAME LFlores NBrown SLichvar JKramer

DATE 11/07/23 11/07/23 11/07/23 11/07/23

OFFICE SPE:DORS/A D:DORS BC:DORS/A

NAME RBywater TClark PVossmar

DATE 11/07/23 11/07/23 11/13/23

NOTICE OF VIOLATION

STP Nuclear Operating Company Docket Nos. 05000498, 05000499

South Texas Project, Units 1 and 2 License Nos. NPF-76, NPF-80

During an NRC inspection conducted from July 1 through September 30, 2023, a violation of

NRC requirements was identified. In accordance with the NRC Enforcement Policy, the violation

is listed below:

10 CFR Part 50, Appendix B, Criterion XVI requires, in part, that measures shall be

established to assure that conditions adverse to quality, such as failures, malfunctions,

deficiencies, and nonconformances are promptly identified and corrected.

Contrary to the above, from November 2021 to September 30, 2023, the licensee failed

to assure that conditions adverse to quality, such as failures, malfunctions, and

nonconformances were promptly identified and corrected. Specifically, the licensee

failed to correct a condition adverse to quality associated with the 1B and 2C essential

cooling water expansion joint tolerances. The expansion joint tie rod nut gap settings

were not set to comply with design documentation due to incorrect work instructions.

This violation is associated with a Green significance determination process finding.

Pursuant to 10 CFR 2.201, STP Nuclear Operating Company is hereby required to submit a

written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN: Document

Control Desk, Washington, DC 20555-0001, with a copy to the Regional Administrator,

U.S. Nuclear Regulatory Commission, Region IV, 1600 East Lamar Blvd., Arlington, Texas

76011-4511, and the NRC Resident Inspector at South Texas Project, Units 1 and 2, and email

it to R4Enforcement@nrc.gov within 30 days of the date of the letter transmitting this Notice.

This reply should be clearly marked as a Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/2023003, and should include for the violation: (1) the reason

for the violation, or, if contested, the basis for disputing the violation or severity level; (2) the

corrective steps that have been taken and the results achieved; (3) the corrective steps that will

be taken; and (4) the date when full compliance will be achieved.

Your response may reference or include previous docketed correspondence if the

correspondence adequately addresses the required response. If an adequate reply is not

received within the time specified in this Notice, the NRC may issue an order or a demand for

information requiring you to explain why your license should not be modified, suspended, or

revoked, or why such other action as may be proper should not be taken. Where good cause is

shown, consideration will be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with

your basis for denial, to the Director, Office of Enforcement, U.S. Nuclear Regulatory

Commission, Washington, DC 20555-0001.

Because your response will be made available electronically for public inspection in the NRC

Public Document Room and from the NRCs ADAMS, accessible from the NRC website at

http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not include any

personal privacy or proprietary information so that it can be made available to the public without

redaction.

Enclosure 1

If personal privacy or proprietary information is necessary to provide an acceptable response,

then please provide a bracketed copy of your response that identifies the information that

should be protected and a redacted copy of your response that deletes such information. If you

request that such material is withheld from public disclosure, you must specifically identify the

portions of your response that you seek to have withheld and provide in detail the bases for your

claim (e.g., explain why the disclosure of information will create an unwarranted invasion of

personal privacy or provide the information required by 10 CFR 2.390(b) to support a request for

withholding confidential commercial or financial information).

Dated this 13 day of November 2023

2

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers: 05000498 and 05000499

License Numbers: NPF-76 and NPF-80

Report Numbers: 05000498/2023003 and 05000499/2023003

Enterprise Identifier: I-2023-003-0004

Licensee: STP Nuclear Operating Company

Facility: South Texas Project Electric Generating Station, Units 1 and 2

Location: Wadsworth, TX 77483

Inspection Dates: July 1, 2023, to September 30, 2023

Inspectors: N. Brown, Senior Resident Inspector

L. Flores, Resident Inspector

S. Hedger, Sr Emergency Preparedness Inspector

S. Lichvar, Senior Resident Inspector

J. Rollins, Senior Physical Security Inspector

D. Willis, Team Leader

Approved By: Patricia J. Vossmar, Chief

Reactor Projects Branch A

Division of Operating Reactor Safety

Enclosure 2

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at South Texas Project Electric Generating

Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor

Oversight Process is the NRCs program for overseeing the safe operation of commercial

nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more

information. A licensee-identified non-cited violation is documented in report section: 71114.05.

List of Findings and Violations

Failure to Maintain Design Control of a Pressurizer Power Operated Relief Valve

Cornerstone Significance Cross-Cutting Report

Aspect Section

Mitigating Green [H.7] - 71153

Systems NCV 05000498/2023003-01 Documentation

Open/Closed

EA-23-066

The inspectors identified a Green finding and associated non-cited violation of 10 CFR Part 50

Appendix B, Criterion III, Design Control, for the licensees failure to establish measures to

assure the design basis of the Unit 1 pressurizer power operated relief valve (PORV)

PCV-0656A was correctly translated into drawings, procedures, and instructions. Specifically,

for maintenance on the Unit 1 PORV PCV-0656A performed during refueling outage 1RE23,

the licensee failed to ensure that instructions or procedures assured that a critical tolerance

was within limits before the valve was returned to service, and failed to ensure that the correct

solenoid operator, suitable to the design, was installed during maintenance on the PORV. As

a result, PCV-0656A was inoperable for greater than the technical specification allowed

outage time.

Failure to Establish Adequate Corrective Actions for Out-of-Tolerance Essential Cooling

Water System Expansion Joints

Cornerstone Significance Cross-Cutting Report

Aspect Section

Mitigating Green [H.8] - 71152A

Systems NOV 05000498,05000499/2023003-02 Procedure

Open Adherence

The inspectors identified a Green finding and associated violation of 10 CFR Part 50

Appendix B, Criterion XVI, Corrective Action, for the licensees failure to promptly identify

and correct a condition adverse to quality. Specifically, the licensee failed to correct essential

cooling water expansion joint configuration in a timely manner to ensure spacing tolerances

complied with design documentation.

2

Additional Tracking Items

Type Issue Number Title Report Section Status

LER 05000498/2023-001-01 Unit 1, Supplement to 71153 Closed

Pressurizer Power Operated

Valve Failed to Open

LER 05000498/2023-001-00 Unit 1, Pressurizer Power 71153 Closed

Operated Relief Valve Failed

to Open

3

PLANT STATUS

Units 1 and 2 began the inspection period at rated thermal power and remained there for the

entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed activities described in IMC 2515,

Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of

IPs. The inspectors reviewed selected procedures and records, observed activities, and

interviewed personnel to assess licensee performance and compliance with Commission rules

and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1) Unit 2, essential cooling water intake structure pump room train A on July 10, 2023

(2) Unit 2, essential cooling water intake structure pump room train C on July 10, 2023

(3) Unit 1, isolation valve cubicle pump room train A valve cubicle penetration area

train A on July 12, 2023

(4) Unit 1, EAB channel one distribution room on August 1, 2023

(5) Unit 1, EAB train A switchgear and battery room fire boundaries on August 23, 2023

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control

room in Units 1 and 2 during I&C surveillances the week of September 25, 2023.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated operator training on September 6, 2023.

4

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the

following planned and emergent work activities to ensure configuration changes and

appropriate work controls were addressed:

(1) Unit 2, EDG train B jacket water leak on July 16, 2023

(2) Unit 2, E2C 'C' ESFAS 4.16kV B-C under voltage on August 14, 2023

(3) Unit 1, planned entry into configuration risk management for train B 125 VDC class

1E battery E1B11 replacement on September 11, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the

following operability determinations and functionality assessments:

(1) Unit 2, EDG train B jacket water leak on July 16, 2023

(2) Unit 2, rod control automatic insertion events on August 10, 18, and September 1,

2023

(3) Unit 1, containment air lock operability on August 28, 2023

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system

operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (8 Samples)

(1) Unit 1, train C essential chiller 12 temperature control module replacement on

June 29, 2023

(2) Unit 2, train B emergency diesel generator on July 27, 2023

(3) Unit 1, 125 VDC battery charger E1A11-1 post maintenance test on August 1, 2023

(4) Unit 2, train A control room envelope HVAC on August 2, 2023

(5) Unit 1, personnel airlock on August 3, 2023

(6) Unit 2, B-C ESFAS under voltage relay on August 14, 2023

(7) diesel fire pump 1 on August 17, 2023

(8) Unit 1, train B 125 VDC Class 1E Battery bank replacement on September 13, 2023

Surveillance Testing (IP Section 03.01) (1 Sample)

(1) Unit 1, RHR pump Train A recirculation line MOV surveillance on July 27, 2023

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) Unit 1, safety injection MOV's inservice testing on August 3, 2023

5

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the licensee's maintenance, testing, and audit program for

the alert and notification system between October 23, 2020, and July 15, 2023.

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the Emergency Preparedness

Organization between October 23, 2020, and July 15, 2023. Inspectors also

evaluated the licensee's ability to staff their emergency response facilities in

accordance with emergency plan commitments.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the 10 CFR 50.54(q) emergency plan change process and

practices between October 23, 2020, and July 15, 2023. The evaluation reviewed

screenings and evaluations documenting implementation of the process. In addition,

the inspectors evaluated changes made to the South Texas Project Electric

Generating Station (STPEGS) Emergency Plan based on NRC notification on May 4,

2022 (ML22124A221). The reviews of the change process documentation or the

emergency plan change do not constitute NRC approval.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program

between October 23, 2020, and July 15, 2023. The evaluation reviewed evidence of

completing various emergency plan commitments, the conduct of drills and exercises,

licensee audits and assessments, and the maintenance of equipment important to

emergency preparedness.

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01)

(1 Sample)

(1) a full site integrated drill that involved a reactor coolant system leak, large break

LOCA, loss of heat sink, radiological release, and a General Emergency on August 2,

2023

6

Drill/Training Evolution Observation (IP Section 03.02) (2 Samples)

The inspectors evaluated:

(1) The licensee's simulator-based licensed operator training evolution that involved a

loss of offsite power and a loss of all but one AC power source resulting in an Alert on

May 23, 2023

(2) the licensee's simulator-based operator training evolution that involved an anticipated

transient without scram, reactor coolant system leak and large break LOCA,

containment breach and a General Emergency on September 13, 2023

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) July 1, 2022, through June 30, 2023

EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13)

(1 Sample)

(1) July 1, 2022, through June 30, 2023

EP03: Alert and Notification System (ANS) Reliability (IP Section 02.14) (1 Sample)

In April 2022, the ANS was changed such that it relies on Integrated Public Alert & Warning

System (IPAWS) as the primary means of public notification. Therefore, the ANS Reliability

PI and associated data is no longer reported by the licensee, and thus is not subject to

further inspection/verification per IP 71151. Evaluation of the licensee's non-siren based

ANS is completed separately per IP 71114.02, Alert and Notification System Evaluation.

71152A - Annual Follow-up Problem Identification and Resolution

Annual Follow-up of Selected Issues (Section 03.03) (3 Samples)

The inspectors reviewed the licensees implementation of its corrective action program

related to the following issues:

(1) essential cooling water pump expansion joint ineffective corrective actions

(2) actions taken to address indications of challenges to the safety conscious work

environment in the security organization

(3) actions to address security material conditions, prioritization of security issues within

the corrective action program, and security equipment reliability.

71152S - Semiannual Trend Problem Identification and Resolution

7

Semiannual Trend Review (Section 03.02) (2 Samples)

(1) The inspectors assessed the effectiveness of licensee's corrective actions to address

indications of challenges within the security organization identified during the 2022

Problem Identification and Resolution (PI&R) inspection completed on June 24, 2022.

(2) The inspectors reviewed the licensee's corrective action program for potential

adverse trends in fire watch compliance within the fire protection program. An

associated observation was documented in NRC inspection report

05000498/2023002 and 05000499/2023002 (ML23208A324).

71153 - Follow Up of Events and Notices of Enforcement Discretion

Event Report (IP section 03.02) (1 Sample)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000498/2023-001-00, "Unit 1, Pressurizer Power Operated Relief Valve Failed

to Open," (ADAMS Accession No. ML23163A248) and LER 05000498/2023-001-01,

"Supplement to Unit 1 Pressurizer Power Operated Relief Valve Failed to Open",

(ADAMS Accession No. ML23207A220). The inspection conclusions associated with

this LER and an associated non-cited violation are documented in this report under

the inspection results section.

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71114.05

This violation of very low safety significance was identified by the licensee and has been

entered into the licensee corrective action program and is being treated as a non-cited

violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Title 10 CFR 50.54(q)(2) requires, in part, that a power reactor licensee follow an

emergency plan which meets the requirements of Appendix E to 10 CFR Part 50 and the

standards of 10 CFR 50.47(b). Title 10 CFR 50.47(b)(14) requires, in part, that the licensee

conduct periodic drills to maintain key skills. South Texas Project Electric Generating Station

(STPEGS) Emergency Plan EP-0001, revision 0, Section N.4.a, says that STPEGS will

conduct an emergency medical drill once per calendar year. Section F.3 says that

communication tests (drills) will be conducted on various frequencies, one of which is

monthly.

Contrary to the above, from January 1, 2022, to April 1, 2023, the licensee failed to follow an

emergency plan which met the requirements of Appendix E and the standards of

10 CFR 50.47(b). Specifically, in 2022, the licensee failed to conduct the annual emergency

medical drill. In addition, in March 2023, the licensee failed to conduct the monthly

communication test.

8

Significance/Severity: Green. The inspectors assessed the significance of the finding using

IMC 0609 Appendix B, Emergency Preparedness SDP. Using this, the performance

deficiency was determined to have very low safety significance (Green) because it was a

failure to comply with NRC requirements, was not a loss of planning standard function, and

was not a degraded risk significant planning standard function. The planning standard

function was not lost because the licensee did conduct drills and training that addressed

portions of the related emergency plan commitments.

Corrective Action References: Condition Reports 2023-638, 2023-4788 and 2023-7230

Failure to Maintain Design Control of a Pressurizer Power Operated Relief Valve

Cornerstone Significance Cross-Cutting Report

Aspect Section

Mitigating Green [H.7] - 71153

Systems NCV 05000498/2023003-01 Documentation

Open/Closed

EA-23-066

The inspectors identified a Green finding and associated non-cited violation of

10 CFR Part 50 Appendix B, Criterion III, Design Control, for the licensees failure to

establish measures to assure the design basis of the Unit 1 pressurizer power operated relief

valve (PORV) PCV-0656A was correctly translated into drawings, procedures, and

instructions. Specifically, for maintenance on the Unit 1 PORV PCV-0656A performed during

refueling outage 1RE23, the licensee failed to ensure that instructions or procedures assured

that a critical tolerance was within limits before the valve was returned to service, and failed

to ensure that the correct solenoid operator, suitable to the design, was installed during

maintenance on the PORV. As a result, PCV-0656A was inoperable for greater than the

technical specification allowed outage time.

9

Description:

During refueling outage 1RE23 in October of 2021, the licensee performed maintenance on a

leaking Unit 1 pressurizer PORV PCV-0656A. This valve is one of two safety-related valves

used to relieve primary pressure during a primary feed and bleed event scenario. The

licensee contracted with a vendor to perform assessment in accordance with the work orders.

After maintenance activities were completed on the valve during the Unit 1 outage 1RE23,

Unit 1 was returned to full power operation in November 2021. Shortly after startup, PCV-

0656A experienced excessive leakage and its block valve was shut in accordance with

technical specification 3.4.4. The unit continued operation for the rest the cycle in this

condition.

When Unit 1 entered refueling outage 1RE24 in 2023, PCV-0656A failed to open in Mode 4

during the stroke testing surveillance 0PSP03-RC-0010, Pressurizer Power Operated Relief

Valve Operability Test, revision 17, on March 18, 2023. PCV-0656A was declared inoperable

for cold overpressure mitigation and Unit 1 entered technical specification 3.4.9.3, Action C.

About two hours were allowed for equilibrium of temperatures across the valve, and then the

valve was successfully opened during reperformance of 0PSP03-RC-0010.

PORV PCV-0656A was disassembled for corrective maintenance during refueling outage

1RE24. As-found measurements showed the lower portion of the valve cage had minor bore

internal diameters that were out of tolerance resulting in an insufficient gap between the plug

and cage, which could lead to thermal binding. The licensee performed a preliminary Prevent

Recurring Equipment Problems (PREP) evaluation. The PREP evaluation identified that it

was readily apparent that thermal binding caused the failure of PCV-0656A to open when

tested. Inspectors reviewed the maintenance records and determined that during PORV

installation in 2021, the licensee had failed to measure critical dimensions of the valve

internals prior to reassembling the valve and returning it to service. This resulted in a failure

to meet the cage to plug required tolerance of 0.004-0.006 inches.

In addition, after the valves failure to open was investigated, the licensee found that the

incorrect replacement solenoid operator had been installed in 2021. The solenoid operator

included an opening orifice that had been removed through a previous design modification in

1997. Design change package (DCP) 97-02406, June 10, 1997, revised the vendor drawing

to remove the opening orifice from the solenoid operator to allow the valve to meet its stroke

time requirement. When the modification to remove the opening orifice in the solenoid for the

PORV was approved in 1997, the licensee failed to establish a new vendor part number and

purge the existing stock of solenoids to ensure configuration was maintained. As a result,

solenoids had been in stock since 1998 and were never confirmed to be the correct

configuration prior to one being installed in PORV PCV-0656A in 2021.

The licensee performed a root cause evaluation for this issue.

Corrective Actions: The licensee rebuilt pressurizer PORV 656A in 1RE24 and returned the

valve to operable within its required design and proper configuration.

Corrective Action References: CR 2023-2765

10

Performance Assessment:

Performance Deficiency: The licensees failure to adequately maintain the design of Unit 1

pressurizer PORV was a performance deficiency. Specifically, for maintenance on the Unit 1

PORV PCV-0656A performed during 1RE23, the licensee failed to ensure that instructions or

procedures assured that a critical tolerance was within limits before the valve was returned to

service, and that the correct solenoid operator, suitable to the design, was installed during

maintenance on the PORV.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Design Control attribute of the Mitigating Systems

cornerstone and adversely affected the cornerstone objective to ensure the availability,

reliability, and capability of systems that respond to initiating events to prevent undesirable

consequences. Specifically, this design control issue led to a PORV being inoperable for the

entire operating cycle, a condition prohibited by technical specifications.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using

Inspection Manual Chapter 0609 App A, exhibit 2, the inspectors determined that the finding

required a detailed risk evaluation because the degraded condition represented a loss of the

PRA function of one train of a multi-train technical specifications system for greater than its

technical specifications allowed outage time. A senior reactor analyst performed a detailed

risk evaluation.

The analyst conducted a detailed risk evaluation in accordance with IMC 0609 appendix A.

The South Texas Project SPAR Model version 8.80 along with SAPHIRE software

version 8.2.8 were used for the evaluation. The analyst assumed that the performance

deficiency resulted in the Unit 1 pressurizer PORV PCV-0656A being in a condition where it

would have been unable to perform its required function of opening on demand. Based on the

nature and cause of the condition and the timeline of events described above, the analyst

assumed that PORV PCV-0656A was in this condition throughout the operating cycle from

November 2021 to March 2023. Therefore, the analyst determined that an exposure time of

1 year would be appropriate for the analysis. The analyst determined that this condition would

be most appropriately modeled by setting the basic event PPR-PORV-CC-PCV656 (PORV

PCV-656 FAILS TO OPEN ON DEMAND) to TRUE in the Events and Conditions

Assessment (ECA) workspace for an exposure time of 1 year.

The analyst noted that one of the PRA safety functions impacted by this condition was the

ability to perform decay heat removal by a feed-and-bleed approach in which a high-

pressure injection source is aligned to the reactor coolant system (RCS) to provide a source

of coolant inventory while the pressurizer PORVs are opened to provide a pathway for

coolant to flow from the RCS. The analyst noted that the SPAR model included success

criteria in which both (i.e., 2-out-of-2) PORVs were required to be available to perform this

safety function. Through discussions with the licensee, the analyst became aware that the

licensee had an analysis to support the conclusion that this safety function could be

successfully implemented with one PORV instead of two (i.e., a 1-out-of-2 success criteria).

The analyst determined that this information would be consistent with the NRCs guidance to

include consideration of best available information for SDP evaluations. After review of the

licensees analysis regarding this safety function, including facility operating procedures that

existed at the time of the failed condition, the NRC concluded that the success criteria for this

feed-and-bleed safety function would be most appropriately modeled using a 1-out-of-2

11

success criteria with respect to the opening of either of the pressurizer PORVs on demand.

Therefore, a modeling change was implemented in the SPAR model to reflect the revised

failure logic associated with this safety function.

The analyst also noted that another PRA safety function that is dependent on the functioning

of the pressurizer PORVs is present in event sequences involving an anticipated transient

without scram (ATWS) in which the pressurizer PORVs are relied on to provide a function to

open on demand to limit peak pressure in the RCS during the event. The analyst noted that

the existing default success criteria for this RCS pressure limiting safety function in the SPAR

model was a 5-out-of-5 criteria for both pressurizer PORVs and all three pressurizer safety

valves to open on demand. The analyst also noted that alternative success criteria associated

with this safety function was also present (but not activated/effective by default) in the SPAR

model, which reflected that the opening of less than five of these five valves would be

necessary to achieve the required function. The analyst reviewed multiple sources of design

basis information, accident analyses, and operating parameters for the facility and

determined that the most appropriate success criteria for this safety function would be to

require the opening of either: 1) all three pressurizer safety valves, or 2) 2-out-of-3 safety

valves plus both PORVs. The analyst adjusted the logic structure of the existing SPAR model

basic events to reflect this best available information associated with this safety function.

The analyst also noted that another PRA safety function that is typically credited in several

event sequences in SPAR models for Westinghouse pressurized water reactor (PWR)

facilities involves the operation of steam dump valves as part of a decay heat removal

strategy in which steam from the steam generator(s) is routed from the main steam system

header to the main condenser. The analyst noted that this function was not reflected in the

SPAR model for South Texas Project. The analyst reviewed the modeling of this function in a

sampling of other Westinghouse PWR facility models and determined that this function was

consistently modeled at other Westinghouse PWR facilities that are similar in design and

operation to South Texas Project. The analyst reviewed available documentation and

reference sources, as well as engaged personnel involved with SPAR model development, to

determine whether a basis existed for excluding the crediting of this function for South Texas

Project. The analyst reviewed facility design basis information and operating procedures and

determined that including credit for this safety function in the South Texas Project model

would be appropriate. Therefore, a surrogate basic event was incorporated in the SPAR

model fault tree SG-PORVS as an equivalent means of providing credit for this safety

function as compared to the typical modeling approach for the same function at other PWR

facilities. Consistent with the operational and design characteristics of South Texas Project as

compared to other similarly designed and operated PWR facilities, the analyst assumed an

overall failure probability of 5E-3 for this credited function.

With the assumptions and modeling changes described above, using the updated test and

limited use (TLU) SPAR model STP Steam Dump Addition dated June 19, 2023, the analyst

obtained a result of 2.47E-7/year for an increase in average annual core damage frequency

(delta-CDF) associated with internal events. Therefore, the increase in risk associated with

external events was also evaluated. The analyst obtained a result of 3.06E-7/year for a delta-

CDF associated with the external events of hurricane, straight line high winds, tornado, and

seismic events. Since the SPAR model did not include modeling of fire events, the analyst

determined that best available information associated with the risk attributable to fire events

would be obtained from the licensees fire PRA model. The analyst obtained and reviewed

12

the results of the licensees fire PRA modeling of the impact of this condition and concluded

that the increase in risk for this condition associated with fire events was best estimated to be

a delta-CDF of 2.3E-7/year. The dominant sequences involved hurricane and high wind

events with failures of offsite power, auxiliary feedwater, and feed-and-bleed functions; as

well as loss of main feedwater and loss of condenser heat sink events with failures of feed-

and-bleed and either auxiliary feedwater or steam generator PORV functions. One additional

dominant sequence involved a steam generator tube rupture event with a failure of the

secondary side cooldown function.

The risk significance of the finding was also evaluated for impact on large early release

frequency (LERF). The analyst evaluated the increase in LERF using Inspection Manual

Chapter 0609, appendix H, Containment Integrity Significance Determination Process. The

finding was treated as a Type A finding because it could influence the likelihood of accidents

leading to core damage as well as being a contributor to LERF. The analyst reviewed all

sequences contributing to CDF for any elements affecting LERF and screened out all

sequences except those associated with a steam generator tube rupture (SGTR) event. For

the SGTR sequence, the analyst applied the applicable assessment factor from Table 6.2,

Phase 2 Assessment Factors - Type A Findings at Power. This resulted in an increase in

LERF from internal and external events (minus fire events) of 5.0E-8/year. From the

licensees fire risk analysis, the analyst determined the best estimate of increase in LERF due

to fire events was 1.0E-8/year.

The analyst performed an uncertainty analysis using the Monte Carlo method with 3,800 runs

on the internal and external events (minus fire events) results in SAPHIRE. The mean value

result was 5.56E-7/year, and the 5th and 95th percentile results were 8.8E-8/year and 1.7-

6/year, respectively, with 97.3 percent of the results falling within the range of less than 1.0E-

6/year. The analyst considered that the uncertainty distribution associated with the

overall/total result (i.e., with the addition of the fire event results of 2.3E-7/year) would be

shifted upward with a dominant portion of the results remaining below the 1.0E-6/year

threshold.

The analyst determined that the crediting of Diverse and Flexible Coping (FLEX) Strategies

had no impact on the results of this analysis. The analyst also determined that the application

of a 5E-3 failure probability associated with the steam dump safety function was an

appropriately conservative assumption, based on being slightly higher than the failure

probabilities reflected in the modeling of this same function at other similarly designed and

operated facilities. The analyst conducted a sensitivity analysis on this parameter by setting it

to a higher failure probability of 1E-2 and concluded that the corresponding increase in the

resulting total delta-CDF for the analysis was relatively minimal (at approximately 1.1E-

8/year).

The licensees risk significance evaluation yielded results of 1.69E-7/year and 1.06E-9/year

for internal events for delta-CDF and delta-LERF, respectively, as well as results of 2.3E-

7/year and 1.0E-8/year for fire events for delta-CDF and delta-LERF, respectively.

The analyst concluded that the overall risk significance of the finding was determined to be

very low safety significance (Green), based on best estimates of 7.8E-7/year for total

delta-CDF and 6.0E-8/year for total delta-LERF.

Cross-Cutting Aspect: H.7 - Documentation: The organization creates and maintains

complete, accurate and up-to-date documentation. Specifically, the licensee failed to create

and maintain complete, accurate, and up-to-date documentation for PCV-0656A.

13

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires, in part, that

measures shall be established to assure that applicable regulatory requirements and the

design basis are correctly translated into specifications, drawings, procedures, and

instructions. These measures shall include provisions to assure that appropriate quality

standards are specified and included in design documents and that deviations from such

standards are controlled. Measures shall also be established for the selection and review for

suitability of application of materials, parts, equipment, and processes that are essential to

the safety-related functions of the structures, systems and components.

Technical specification 3.4.4, Relief Valves, requires, in part, that both PORVs and their

associated block valves shall be operable in Modes 1, 2, and 3. Technical specification 3.4.4

action statement (b) requires, in part, that with one PORV inoperable due to causes other

than excessive seat leakage, within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> either restore the PORV to operable status or

close the associated block valve and remove power from the block valve; within the following

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> restore the PORV to operable status or be in hot standby within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />

and in hot shutdown within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

Contrary to the above, from October 2021, the licensee failed to establish measures to

assure that applicable regulatory requirements and the design basis were correctly translated

into specifications, drawings, procedures, and instructions, and failed to establish measures

for the selection and review for suitability of application of materials, parts, equipment, and

processes that are essential to the safety-related functions of the structures, systems and

components. Specifically, for maintenance on the Unit 1, PORV PCV-0656A performed

during 1RE23, the licensee failed to ensure that instructions or procedures assured that a

critical tolerance was within limits before the valve was returned to service, and that the

correct solenoid operator, suitable to the design, was installed during maintenance on the

PORV. As a result, from November 3, 2021, to March 18, 2023, during operating cycle 24,

PORV PCV-0656A was inoperable for greater than the allowed outage time permitted by

technical specification 3.4.4 action (b) for one PORV inoperable due to causes other than

excessive seat leakage, and the unit was not placed in hot standby within the following 6

hours.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Failure to Establish Adequate Corrective Actions for Out-of-Tolerance Essential Cooling

Water System Expansion Joints

Cornerstone Significance Cross-Cutting Report

Aspect Section

Mitigating Green [H.8] - 71152A

Systems NOV 05000498,05000499/2023003-02 Procedure

Open Adherence

The inspectors identified a Green finding and associated violation of 10 CFR Part 50

Appendix B, Criterion XVI, Corrective Action, for the licensees failure to promptly identify

and correct a condition adverse to quality. Specifically, the licensee failed to correct essential

cooling water expansion joint configuration in a timely manner to ensure spacing tolerances

complied with design documentation.

14

Description: On August 11, 2022, the NRC issued a Green, non-cited violation 0500498/2022002-02 and 0500499/2022002-02, of 10 CFR Part 50, Appendix B,

Criterion XVI, Corrective Action, for the failure to Identify Conditions Adverse to Quality

Within Essential Cooling Water System (ML22215A226). One of the conditions adverse to

quality identified in this finding was out of tolerance expansion joints located at the essential

cooling water pump discharges identified by the NRC on November 10, and 17, 2021 in

condition reports (CR) 2021-12089 and 2021-12337, respectively. To address the condition,

the licensee planned to adjust a total of five expansion joints in upcoming train work outages

under CR 2021-12048.

The essential cooling water expansion joints are designed to absorb longitudinal deformation

of the essential cooling water piping due to thermal expansion and contraction. The tie rods

connecting the flanges of the expansion joint at each end allow longitudinal movement of the

expansion joint within the defined range of expansion and contraction.

On June 22, 2023, during system walkdowns in the essential cooling water intake structure

building, the inspectors noted that the 1B and 2C essential cooling water discharge

expansion joint tie rod nuts appeared to be loose and questioned their configuration. The

licensee conducted walkdowns of all trains of essential cooling water and documented that

that the expansion joint tie rod nut gap settings were not set per the design specification as

shown in vendor drawing 8113-00030TF, 24 inch Expansion Joint Assembly, revision 5.

The inspectors reviewed the corrective actions associated with CR 2021-12048 and noted

that the 1B essential cooling water expansion joint tie rod nut tolerance was corrected under

work authorization number (WAN) 662730 on May 10, 2022, and the 2C essential cooling

water expansion joint tie rod nut tolerance was corrected under WAN 662291 on

November 25, 2021. Step 3.2 of WANs 662730 and 662291 directs resetting the expansion

joint tie rod nut gap settings per vendor drawing 8113-00030TF. The gap settings were

correctly shown on drawing 8113-00030TF and required only a 0.25 gap on both sides of the

outlet side tie plate; however, step 3.2.2 of both WANs also incorrectly stated, in part, to

ensure that the compression stop nuts (inlet side) are set at 0.025 gap.

On September 11, 2014, CR 2014-16257 was initiated when the NRC identified that the

essential cooling water pump expansion joint tie rod nut dimensions were not configured

according to the vendor drawing. The licensee performed a stress analysis to verify

operability and documented this in Condition Report Engineering Evaluation (CREE)

14-16257-1. WANs 502648-502653 were created using WCG-0003, Planners Guide,

revision 35, to disposition CREE 14-16257-1 and adjust the gap settings on all six trains of

essential cooling water to restore compliance with vendor drawing 8113-00030TF. These

work orders contained the same incorrect instructions as those contained in WANs 662730

and 662291 that were written to correct the conditions noted in CR 2021-12048. WCG-0003,

step 5.5.1.3.1 states, in part, that Work Packages SHALL be reviewed by Engineering if the

work instructions involve the disposition of a CREE. Contrary to this step, WANs 502648-

502653 were not reviewed by engineering.

WANs 662730 and 662291 were also prepared using WCG-0003, Planners Guide,

revision 41. Step 5.7.3.14 of WCG-003 states, in part, that the planner SHALL review past

performance work instructions for technical accuracy when preparing work packages. During

the work package development for WANs 662730 and 662291 for 1B and 2C essential

cooling water expansion joint tie rod nut gap setting correction, the planner, during their

review of the previously performed WANs associated with CR 2014-16257, did not identify

15

that the expansion joint tie rod nut gap settings were incorrect in those instructions, resulting

in the error being carried forward into WANs 662730 and 662291.

Corrective Actions: The licensee has initiated CR 2023-6947 to document and correct the

erroneous step in the work instructions.

Corrective Action References: Condition Reports (CR) 2022-6950, 2023-6230, 2023-6231,

2023-6238, 2023-6240, 2023-6241, 2023-6243, 2023-6244. 2014-16257, 2021-12048,

2021-12089, 2021-12337

Performance Assessment:

Performance Deficiency: The licensees failure to correct a condition adverse to quality is a

performance deficiency. Specifically, the licensee failed to correct essential cooling water

expansion joint tolerances due to inadequate implementation of corrective actions to restore

compliance with design documentation.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Equipment Performance attribute of the Mitigating

Systems cornerstone and adversely affected the cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences. Specifically, incorrect expansion joint gap settings can induce

additional stresses into connected piping, thereby challenging the systems reliability.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The

inspectors determined that this finding is of very low safety significance (Green), because the

nonconformance of essential cooling water system expansion joints with design

documentation did not result in inoperability or PRA non-functionality of the essential cooling

water system.

Cross-Cutting Aspect: H.8 - Procedure Adherence: Individuals follow processes, procedures,

and work instructions. Specifically, the failure to follow appropriate steps in WCG-0003,

Planners Guide, resulted in erroneous work instructions initiated in 2014 to be implemented

on the 1B and 2C essential cooling water discharge expansion joints in 2021 and 2022,

respectively, that were inadequate to correct the conditions adverse to quality associated with

out-of-tolerance essential cooling water expansion joints.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion XVI requires, in part, that measures

shall be established to assure that conditions adverse to quality, such as failures,

malfunctions, deficiencies, and nonconformance's are promptly identified and corrected.

Contrary to the above, from November 2021 to September 30, 2023, the licensee failed to

assure that conditions adverse to quality, such as failures, malfunctions, and

nonconformance's were promptly identified and corrected. Specifically, the licensee failed to

correct a condition adverse to quality associated with the 1B and 2C essential cooling water

expansion joint tolerances. The expansion joint tie rod nut gap settings were not set to

comply with design documentation due to incorrect work instructions.

16

Enforcement Action: This violation is being cited because the licensee failed to restore

compliance within a reasonable period after the violation was identified consistent with

Section 2.3.2 of the Enforcement Policy.

Assessment 71152S

Assessment

From July 31, 2023, to August 2, 2023, inspectors completed an onsite inspection at the

South Texas Project Electric Generating Station (STP) to assess the effectiveness of the

licensees corrective actions to address indications of challenges to the safety conscious work

environment (SCWE) in its security organization. These SCWE challenges were first

identified by the NRC during a problem identification and resolution (PI&R) inspection

completed on June 24, 2022, and documented in NRC inspection report 05000498/2022010

and 05000499/2022010 (ML22220A045). In addition to the SCWE challenges identified

during the PI&R inspection, the NRC also identified a notable increase in security-related

allegations from onsite sources at STP in 2022 and documented this increase in the NRCs

2022 Allegation Program Annual Trend Report (ML23110A294). Based on these insights, the

NRC determined that additional SCWE focused inspection activity would be performed to

determine whether the licensees corrective actions to address the security work environment

concerns have been effective.

During this follow-up inspection, NRC inspectors preformed the following activities:

  • Obtained a description of the licensees corrective actions and verified the

implementation of these actions during the onsite inspection.

  • Reviewed relevant documentation and records such as employee concern program

concerns and corrective action program documents regarding SCWE-related issues in

the security organization, as well as recent safety culture surveys completed by

personnel in the security organization.

  • Conducted focus group interviews with approximately 48 randomly selected security

officers and 9 security supervisors across all security shifts.

  • Conducted individual interviews with key personnel such as licensee and contractor

employee concerns program managers and security managers, and members of the

licensees security executive oversight committee.

The team noted that the licensee had taken several corrective actions to address the causes

of the challenges to SCWE in the security organization, including measures to promptly

address security material conditions such as dedicating engineering resources to security

systems, revising its corrective action program procedures to ensure security issues are

properly prioritized and promptly addressed, and developing a security equipment reliability

and life cycle management plan. The licensee also took several actions to improve its

security staffing to significantly decrease the amount of overtime that was contributing to low

security force morale at the time of the PI&R inspection in 2022.

Despite these corrective actions, the inspection team found that there are still safety culture

challenges in the security organization under the safety culture traits of environment for

raising concerns, respectful work environment, work processes, and effective safety

communication. During interviews, security officers expressed several negative perceptions in

these areas that, if left unaddressed, may further degrade the level of trust in the security

organization and affect the officers willingness to raise concerns in the future. A full

description of these safety culture traits, including attributes and examples, can be found in

17

NUREG-2165, Safety Culture Common Language (ML14083A200). Applicable examples

found in NUREG-2165 are referenced in the teams findings below.

The safety culture trait of environment for raising concerns (RC) is defined as a safety-

conscious work environment where personnel feel free to raise safety concerns without fear

of retaliation, intimidation, harassment, or discrimination. The inspectors noted that while

most of the officers interviewed stated that they would raise nuclear safety and security

concerns through multiple avenues, some officers did report that they felt that they could be

targeted by security management after they raised the concern [RC 1.1]. While officers were

not able to provide specific examples of discrimination, this perception could cause officers to

hesitate to report when they identify a concern in the future. In addition, most of the officers

stated that while they would continue to raise concerns, they did not believe that

management would address their concerns in a timely or comprehensive manner [RC 1.1,

RC 2.6]. Officers provided several examples of security equipment issues that they felt were

not being corrected in a timely manner or were closed without corrective action.

The safety culture trait of respectful work environment (WE) is defined as a work environment

where trust and respect permeate the organization. The inspectors noted that most officers

interviewed stated that when individual performance issues are identified, management

implements broad corrective actions that apply to all and, as such, are seen as punitive.

Many officers interviewed felt that leaders are not addressing negative performance directly

with individuals [WE 3.5]. Some officers also stated that they do not feel that they are treated

with respect. For example, officers reported multiple interactions with members of

management that were perceived as defensive and dismissive in response to concerns that

were raised [WE 1.2, WE 3.2].

The safety culture trait of work processes (WP) is achieved when the process of planning and

controlling work activities is implemented so that safety is maintained. The inspectors noted

that, in addition to the lack of responsiveness to concerns raised, some officers shared the

perception that security work planning is lacking leading to security material deficiencies or

compensatory measures that could have been prevented. Examples provided by the officers

included preventative maintenance of vehicles, posting of unattended openings created

during outages, and ensuring placement of officer environmental shelters for planned work

[WP 1.1].

The safety culture trait of effective safety communication (CO) is achieved when

communication maintains a focus on safety. The inspectors noted that most security officers

stated that they do not receive feedback on the resolution of concerns in a timely manner, to

include the basis for why decisions are made. Specifically, the majority of security officers

expressed the concern that they did not understand why corrective actions to address

security equipment deficiencies, including equipment issues presenting industrial safety

concerns, take so long to correct [CO 2.5].

The inspectors concluded that while the licensee had taken several corrective actions, more

attention is needed in the areas described above in order to assure that sustainable

improvement would be achieved. The licensee acknowledged the inspection teams

observations and entered them into its corrective action program as CR 23-7389. The NRC

plans to continue to monitor the licensees progress in addressing these challenges to safety

culture in its security organization.

18

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

inspection results to K. Harshaw, Executive Vice President and Chief Nuclear Officer,

and other members of the licensee staff.

  • On October 11, 2023, the inspectors presented the integrated inspection results to

G. T. Powell, President and CEO, and other members of the licensee staff.

19

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.05 Procedures 0EAB02-FP-0003 Fire Preplan for Electrical Auxiliary Building Channel One 4

Distribution Room

71111.05 Procedures 0EAB02-FP-0004 Fire Preplan for Electrical Auxiliary Building ESF Switchgear 4

Room Train A

71111.05 Procedures 0EAB02-FP-0084 Fire Preplan for Electrical Auxiliary Building Channel I 3

Battery Room

71111.05 Procedures 0IVC50-FP-0401 Fire Preplan Isolation Valve Cubicle Pump Room, Train A 3

71111.05 Procedures 0IVC50-FP-0408 Fire Preplan Isolation Valve Cubicle Penetration Area Train 3

A

71111.05 Procedures 0IVC51-FP-0405 Fire Preplan Isolation Valve Cubicle Pump Room 2

71111.05 Procedures 2ECW56-FP- Fire Preplan Essential Cooling Water Intake Structure Pump 5

0603 Room Train C

71111.05 Procedures 2ECW58-FP- Fire Preplan Essential Cooling Water Intake Structure Pump 5

0605 Room Train A

71111.13 Corrective Action CR-YYYY-NNNN 2023-6833, 2023-7059, 2023-7626

Documents

71111.13 Procedures 0PGP02-ZA-0003 Comprehensive Risk Management Program 16

71111.13 Procedures 0PGP03-ZO-0055 Protected Components 18

71111.13 Procedures 0POP01-ZO-0006 Risk Management Actions (RMA's) 28

71111.13 Procedures 0POP11-DJ-0002 Online Class 1E 125VDC Battery and Inverter Removal from 20

Service and Restoration

71111.13 Work Orders Work 644467

Authorization

Number

71111.15 Corrective Action CR-YYYY-NNNN 2023-6985, 2023-7042, 2023-8019, 2023-8034, 2023-7149,

Documents 2023-6833, 2023-7059, 2017-22703, 2023-8182, 2007-5177,

2023-7577. 2023-7847

71111.15 Engineering CREE 23-7847-7

Evaluations

71111.15 Miscellaneous VTD-T905-0001 Instruction Manual for Personnel Airlock 4

71111.15 Miscellaneous VTD-W120-0653 7300 Lead/Lag Amplifier Instruction Bulletin 0

71111.15 Procedures 0EPM01-IP-0004 Equipment Important to Emergency Response 0

20

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.15 Procedures 0PMP04-ZG- Personnel Airlock Inspection and Maintenance, RCB End 4

0013A Door

71111.15 Procedures 0POP01-ZO-0011 Operability, Functionality and Reportability Guidance 18

71111.15 Procedures EP-0003-000 Emergency Action Levels Technical Basis Manual 0

71111.15 Work Orders Work 665510, 667076, 687594, 448682

Authorization

Number

71111.24 Corrective Action CR-YYYY-NNNN 2023-6338, 2023-7307, 2023-7149, 2023-8019, 2023-8033,

Documents 2023-7626

71111.24 Miscellaneous Station Unit 1 Logs 07/27/2023

71111.24 Miscellaneous VTD-B350-0001 Operation and Maintenance Manual Electro-hydraulic Rotary 3

Damper Actuator Assembly

71111.24 Miscellaneous VTD-G185-0018 Installation and Operating Instructions Lead-Antimony Types, 2

Lead-Calcium Types

71111.24 Miscellaneous VTD-G185-0021 Nuclear Class-1E GNB Flooded Batteries Type NCN-17S 0

Lead Calcium

71111.24 Procedures 0PGP03-ZM- Post-Maintenance Testing Implementation 7

0025A

71111.24 Procedures 0PMP08-ZI-0136 Borg Warner Electro-Hydraulic Rotary Damper Actuator 10

71111.24 Procedures 0PSP03-DG-0002 Standby Diesel 12(22) Operability Test 67

71111.24 Procedures 0PSP03-RH-0009 Residual Heat Removal System Valve Operability Test 17

71111.24 Procedures 0PSP03-SI-0020 safety injection system miscellaneous and train 1A(2A) valve 23

operability test

71111.24 Procedures 0PSP06-DJ-0003 125 Class 1E Battery Intercell Connection Resistance 21

Surveillance Test

71111.24 Procedures 0PSP06-DJ-0006 Battery Charger 8 Hour Load Verification 31

71111.24 Work Orders Work 691745, 660020, 693431, 633532, 623717, 628964, 636059,

Authorization 637670. 667076, 687594, 665510, 68689, 693869, 644467,

Number 627199, 692507

71114.02 Corrective Action CR-YYYY-NNNN 2023-7167

Documents

Resulting from

Inspection

71114.02 Miscellaneous Form 1 - Siren Test - Quarterly Growl - Date of Test: 12/9/20 01/05/2021

21

Inspection Type Designation Description or Title Revision or

Procedure Date

71114.02 Miscellaneous Form 1 - Siren Test - Bi-Weekly Silent - Date of Test: 11/16/2020

10/14/20

71114.02 Miscellaneous Form 1 - Siren Test - Bi-Weekly Silent - Date of Test: 6/23/21 06/30/2021

71114.02 Miscellaneous Form 1 - Siren Test - Quarterly Growl - Date of Test: 9/22/21 10/06/2021

71114.02 Miscellaneous Form 1 - Siren Test - Quarterly Growl - Date of Test: 3/23/22 03/23/2022

71114.02 Miscellaneous Form 1 - Siren Test - Bi-Weekly Silent - Date of Test: 2/2/22 02/07/2022

71114.02 Miscellaneous Form 1 - Siren Test - Complete Cycle Test - Date of Test: 07/25/2021

6/23/21

71114.02 Miscellaneous RE: Testing Your Alert Radio, Batteries for Alert Radios, and 01/27/2021

Alert Radio Test Schedule

71114.02 Miscellaneous EP-00006 Prompt Notification System Design Report 4

71114.02 Miscellaneous Integrated Public Attachment 7, IPAWS Quality Checklist 03/28/2023

Alert and Warning

System (IPAWS)

Procedure 66

71114.02 Procedures 0PGP05-ZV-0007 Prompt Notification System 13

71114.03 Miscellaneous Form 19 - ENRS Test - Quarterly - Test Date: 12/1/20 12/07/2020

71114.03 Miscellaneous Form 19 - ENRS Test - Quarterly - Test Date: 11/11/21 12/13/2021

71114.03 Miscellaneous Emergency Notification and Response System (ENRS) Tests 10/19/2022

- Quarterly - Test Date: 9/13/22

71114.03 Miscellaneous Emergency Notification and Response System (ENRS) Tests 02/28/2023

- Quarterly - Test Date: 2/22/23

71114.03 Miscellaneous Emergency Notification and Response System (ENRS) Tests 06/22/2023

- Quarterly - Test Date: 6/20/23

71114.03 Miscellaneous Form 19 - ENRS Test - Quarterly - Test Date: 3/1/22 03/09/2022

71114.03 Procedures 0EPR04-UA-0002 ENRS Operation 1

71114.03 Procedures 0ERP01-ZV-IN03 Emergency Response Organization Notification 19

71114.03 Procedures 0PGP05-ZV-0003 Emergency Response Organization 22

71114.04 Corrective Action Condition Reports 23-7171

Documents

Resulting from

Inspection

71114.04 Miscellaneous 0EPR03-FM- Protective Action Recommendation Decision Flowcharts 0

ALL06

22

Inspection Type Designation Description or Title Revision or

Procedure Date

71114.04 Miscellaneous 0EPR03-FM- Classification Public Address Announcements 0, 1

ALL14

71114.04 Miscellaneous 0EPR04-UA-0019 Site Evacuation Routes 0, 1

71114.04 Miscellaneous 0EPR04-UA-0020 STAMPEDE User's Manual 0, 1

71114.04 Miscellaneous 50.54(q) Update to EP0005.000, Protective Action Recommendation 11/18/2021

Effectiveness Basis Document

Evaluation,

Evaluation CR

Tracking Number:

21-8929-2

71114.04 Miscellaneous 50.54(q) EP-0002.000, On-Shift Staffing Analysis (OSA) 09/29/2021

Effectiveness

Evaluation,

Evaluation CR

Tracking Number:

21-8929-3

71114.04 Miscellaneous 50.54(q) Replacement of ARINC Security Computer System Software 04/04/2023

Effectiveness (Condition Report 21-6686)

Evaluation,

Evaluation CR

Tracking Number:

23-78-4

71114.04 Miscellaneous 50.54(q) 0EPR04-UA-0019, Site Evacuation Routes, Revision 1 03/31/2022

Effectiveness

Evaluation,

Evaluation CR

Tracking Number:

CR #20-2575-155

71114.04 Miscellaneous 50.54(q) Screen 0EPR04-UA-0020, STAMPEDE User's Manual, Rev. 1 03/16/2022

Evaluation,

Evaluation CR

Tracking Number:

20-2575-150

71114.04 Miscellaneous 50.54(q) Screen 0EPR02-CK-EOF06, EOF RP Coordinator Checklist, Rev. 1 03/17/2022

23

Inspection Type Designation Description or Title Revision or

Procedure Date

Evaluation,

Evaluation CR

Tracking Number:

20-2575-150

71114.04 Miscellaneous 50.54(q) Screen 0EPM03-FM-ADM11, Quarterly EP Performance Indicator 03/17/2022

Evaluation, Report, Rev. 1

Evaluation CR

Tracking Number:

20-2575-150

71114.04 Miscellaneous 50.54(q) Screen 0EPM03-FM-FAE06, Quarterly Field Monitoring Team Kit 3/17/2022

Evaluation, Inventory, Rev. 1

Evaluation CR

Tracking Number:

20-2575-150

71114.04 Miscellaneous 50.54(q) Screen 0EPR03-FM-ALL14, Classification Public Address 03/29/2022

Evaluation, Announcement, Rev. 1

Evaluation CR

Tracking Number:

20-2575-153

71114.04 Miscellaneous 50.54(q) Screen 0PGP05-ZV-0018, Beyond Design Basis Event Emergency 03/30/2022

Evaluation, Response Organization Activation, Rev. 1

Evaluation CR

Tracking Number:

20-2575-169

71114.04 Miscellaneous 50.54(q) Screen 0EPM01-IP-0006, Emergency Preparedness Drills and 11/18/2021

Evaluation, Exercises, Rev. 0

Evaluation CR

Tracking Number:

21-4440-6

71114.04 Miscellaneous 50.54(q) Screen Offsite Dose Calculation Manual (ODCM), Revision 23 12/06/2022

Evaluation,

Evaluation CR

Tracking Number:

22-5917-18

24

Inspection Type Designation Description or Title Revision or

Procedure Date

71114.04 Miscellaneous NOC-AE- South Texas Project, Units 1 and 2,; Docket Nos. STN 50- 05/04/2022

22003890 498; STN 50-499; 72-1041; Change to South Texas Project

Electric Generating Station (STPEGS) Emergency Plan

71114.04 Procedures 0ERP01-ZV-IN07 Offsite Protective Action Recommendations 19

71114.04 Procedures 0PGP05-ZV-0010 Emergency Plan Change 19, 20

71114.05 Corrective Action CR-YYYY-NNNN 2020-11164, 2020-11806, 2021-4027, 2021-6619,

Documents 2021-9291, 2021-9430, 2021-9436, 2021-10299, 2022-997,

2022-1985, 2022-3555, 2022-4020, 2022-4756, 2022-4857,

2022-5557, 2022-6188, 2022-6303, 2022-7177, 2022-7011,

22-9178, 2022-11207, 2022-12137, 2023-369, 2023-638,

202023-745, 2023-1118, 2023-1581, 2023-1734, 2023-1969,

2023-1978, 2023-4788, 2023-4886, 2023-5773, 2023-6135,

23-6141, 2023-6767, 23-6771, 23-6985

71114.05 Corrective Action CR-YYYY-NNNN 2023-7090, 2023-7168, 2023-7170, 2023-7172, 2023-7174,

Documents 2023-7230

Resulting from

Inspection

71114.05 Miscellaneous 0EPM03-FM-FAE13 - Quarterly Computer Functional Test - 01/31/2023

1st Quarter 2023

71114.05 Miscellaneous Form 18 - Quarterly Computer Functional Test - 1st Quarter 01/31/2022

2022

71114.05 Miscellaneous South Texas Project Electric Generating Station, 10 CFR 04/26/2022

50.155 Evaluation Report, White Team - December 1, 2021

71114.05 Miscellaneous South Texas Project Electric Generating Station; Blue Team 04/5/2022

Tabletop Evaluation Report, February 12th, 2020

71114.05 Miscellaneous South Texas Project Electric Generating Station; New EPlan 04/05/2022

Validation Drill Evaluation Report, White Team - February

9th, 2022

71114.05 Miscellaneous South Texas Project Electric Generating Station; Dress 10/21/2021

Rehearsal Evaluation Report, Red Team - June 16, 2021

71114.05 Miscellaneous Environmental Sampling Drill, Final Report, December 1, 1/20/2022

2021

71114.05 Miscellaneous South Texas Project Electric Generating Station; Exercise 10/21/2021

Evaluation Report, Red Team - July 28 and 29, 2021

25

Inspection Type Designation Description or Title Revision or

Procedure Date

71114.05 Miscellaneous 2021 Health Physics Drill, Final Report, August 17, 2021 10/19/2021

71114.05 Miscellaneous South Texas Project Electric Generating Station; Blue Team 12/29/2022

Combined Functional Drill, November 30, 2022, Evaluation

Report

71114.05 Miscellaneous South Texas Project Electric Generating Station; 2022 07/11/2022

Exercise Dress Rehearsal Evaluation Report, White Team -

June 8th, 2022

71114.05 Miscellaneous South Texas Project Electric Generating Station; 2022 08/17/2022

Exercise Evaluation Report, White Team - July 20, 2022

71114.05 Miscellaneous Environmental Monitoring Drill, Final Report, December 7, 01/19/2023

2022

71114.05 Miscellaneous STP 2022 KeROP Drill 2nd Quarter, EPlan Scenarios 07/06/2022

Evaluation Report, June 16, 2022

71114.05 Miscellaneous STP 2022 KeROP Drill 3rd Quarter, EPlan Scenarios 02/09/2023

Evaluation Report, July 1 - September 30, 2022

71114.05 Miscellaneous South Texas Project Electric Generating Station, 2022 Red 10/21/2022

Team Combined Functional Drill, September 21st, 2022,

Evaluation Report

71114.05 Miscellaneous STP 2022 Shift Manager Up Relief Drills, EPlan Scenarios 07/06/2022

Evaluation Report, February 3 - March 31, 2022

71114.05 Miscellaneous STP 2022 State & County Drills 2nd Quarter, EPlan 07/06/2022

Scenarios Evaluation Report, April 1 - June 20, 2022

71114.05 Miscellaneous STP 2023 State & County Drills 1st Quarter, EPlan 04/26/2023

Scenarios Evaluation Report, January 1 - March 31

71114.05 Miscellaneous STP 2022 KeROP Drill 1st Quarter, EPlan Scenarios 07/06/2022

Evaluation Report, March 30, 2022

71114.05 Miscellaneous STP 2021 Licensed Operator Requal Cycle 212, EPlan 04/20/2022

Scenarios Evaluation Report, May 4 - June 21, 2021

71114.05 Miscellaneous STP 2021 Licensed Operator Requal Cycle 213, EPlan 06/28/2022

Scenarios Evaluation Report, August 10 - September 7,

2021

71114.05 Miscellaneous STP 2022 Licensed Operator Requal Cycle 223, EPlan 07/6/2022

Scenarios Evaluation Report, May 23 - June 20, 2022

71114.05 Miscellaneous STP 2022 Licensed Operator Requal Cycle 225, EPlan 01/19/2023

26

Inspection Type Designation Description or Title Revision or

Procedure Date

Scenarios Evaluation Report, November 13 - December 15,

2022

71114.05 Miscellaneous STP 2023 Licensed Operator Requal Cycle 231, EPlan 05/08/2023

Scenarios Evaluation Report, January 31 - February 28,

2023

71114.05 Miscellaneous South Texas Project Electric Generating Station; 2023 07/10/2023

Onsite Medical Response Capabilities Demonstration May

24th, 2023

71114.05 Miscellaneous Audit Report STP Nuclear Operating Company, Emergency Preparedness 03/03/2020

Number 20-01 Quality Audit Report

(EP)

71114.05 Miscellaneous Audit Report STP Nuclear Operating Company; Emergency Preparedness 03/11/2021

Number 21-01 Quality Audit Report

(EP)

71114.05 Miscellaneous Audit Report STP Nuclear Operating Company; Emergency Preparedness 03/15/2022

Number 22-01 Quality Audit Report

(EP)

71114.05 Miscellaneous Audit Report STP Nuclear Operating Company; Emergency Preparedness 03/23/2023

Number 23-01 Quality Audit Report

(EP)

71114.05 Miscellaneous EP-0004 Evacuation Time Estimate 2012 Revision 0 09/06/2021

71114.05 Miscellaneous KLD TR-1244 South Texas Project Electric Generating Station, 07/29/2022

Development of Evacuation Time Estimates

71114.05 Procedures 0EPM01-IP-0001 Emergency Preparedness Program Administration 0

71114.05 Procedures 0EPM01-IP-0003 Emergency Preparedness Facilities/Equipment Inventories 0

and Surveillances

71114.05 Procedures 0EPM01-IP-0004 Equipment Important to Emergency Response 0

71114.05 Procedures 0EPM01-IP-0005 Emergency Preparedness Training & Qualification 0

71114.05 Procedures 0EPM01-IP-0006 Emergency Preparedness Drills and Exercises 1

71114.05 Procedures 0EPR01-IP-0002 Emergency Notifications 1

71114.05 Procedures 0EPR01-IP-0003 Site Evacuation 0

71114.05 Procedures 0EPR01-IP-0004 Emergency Exposure Controls 0

71114.05 Procedures 0EPR01-IP-0005 Termination and Recovery 0

71114.05 Procedures 0PGP03-ZV-0005 Equipment Important to Emergency Response 7

27

Inspection Type Designation Description or Title Revision or

Procedure Date

71114.05 Procedures 0PGP03-ZX-0002 Condition Reporting Process 53

71114.05 Procedures 0PGP03-ZX- CAQ Resolution Process 16

0002A

71114.05 Procedures 0PGP03-ZX- Station Cause Analysis Program 14

0002B

71114.05 Procedures 0PQP01-ZA-0001 Internal Audits 24

71114.05 Procedures 0PQP01-ZA-0001 Internal Audits 24

71114.05 Procedures 0PQP01-ZA-0015 Oversight Planning and Scheduling Process 37

71114.05 Procedures EP-0003 South Texas Project Electric Generating Station (STPEGS) 0

Emergency Action Level Technical Bases Manual

71114.05 Procedures EP-0005 Protective Action Recommendation (PAR) Strategies 11/19/2021

71114.06 Procedures 0EPR01-IP-0002 Emergency Notifications 1

71114.06 Procedures 0POP05-EO- Reactor Trip or Safety Injection 27

EO00

71151 Corrective Action CR-YYYY-NNNN 2021-8961, 2022-1207, 2022-1983, 2022-1984, 2022-12059,

Documents 2022-12060

71151 Miscellaneous South Texas Project Electric Generating Station, 2022 Red 10/21/2022

Team Combined Functional Drill, September 21st, 2022,

Evaluation Report

71151 Miscellaneous STP 2022 Licensed Operator Requal Cycle 225, EPlan 01/19/2023

Scenarios Evaluation Report, November 13 - December 15,

2022

71151 Miscellaneous STP 2022 Licensed Operator Requal Cycle 231, EPlan 05/08/2023

Scenarios Evaluation Report, January 31 - February 28,

2023

71151 Procedures 0EPM04-UA-0003 EP Performance Indicator Evaluation and Tracking 0

71152A Corrective Action CR-YYYY-NNNN 2021-12048, 2023-6230, 2023-6231, 2023-6244, 2022-6950,

Documents 2022-6238, 2022-6240, 2023-6241, 2023-6243, 2023-6947,

2014-16257, 2021-12089, 2021-12337

71152A Drawings DWG-8113- 24 Expansion Joint Ass'y 5

00030TF

71152A Engineering CREE 21-12048-1, 14-16257-1

Evaluations

71152A Procedures WCG-0003 Planner's Guide 35

28

Inspection Type Designation Description or Title Revision or

Procedure Date

71152A Procedures WCG-0003 Planner's Guide 41

71152A Work Orders Work 662730, 662291

Authorization

Number

71153 Miscellaneous LER Unit 1, Pressurizer Power Operated Relief Valve Failed To 06/12/2023

05000498/2023- Open

001-00

71153 Miscellaneous LER Unit 1, Supplement to Pressurizer Power Operated Valve 07/26/2023

05000498/2023- Failed to Open

001-01

29