ML17079A526

From kanterella
Jump to navigation Jump to search
NRC Triennial Fire Protection Inspection Report 05000498/2017007 and 05000499/2017007
ML17079A526
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 03/20/2017
From: Greg Werner
NRC/RGN-IV/DRS/EB-2
To: Gerry Powell
South Texas
Werner G
References
IR 2017007
Download: ML17079A526 (28)


See also: IR 05000498/2017007

Text

March 20, 2017

Mr. G. T. Powell

Executive Vice President and Chief Nuclear Officer

STP Nuclear Operating Company

South Texas Project Electric Generating Station

P.O. Box 289

Wadsworth, TX 77483

SUBJECT: SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION,

UNITS 1 AND 2 - NRC TRIENNIAL FIRE PROTECTION INSPECTION

REPORT 05000498/2017007 AND 05000499/2017007

Dear Mr. Powell:

On February 9, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection

at the South Texas Project Electric Generating Station, Units 1 and 2, and discussed the results

of this inspection with you and other members of your staff. The results of this inspection are

documented in the enclosed report.

The NRC team documented one finding of very low safety significance (Green) in this report.

The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a

of the Enforcement Policy.

If you contest the violation or significance of the violation in this report, you should provide a

written response within 30 days of the date of this inspection report, with the basis for your

denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, DC 20555-0001, with copies to the Regional Administrator, Region IV; the Director,

Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001;

and the NRC resident inspector at the South Texas Project Electric Generating Station, Units 1

and 2.

G. Powell

2

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for

Withholding.

Sincerely,

/RA/

Gregory E. Werner, Chief

Engineering Branch 2

Division of Reactor Safety

Docket Nos. 50-498 and 50-499

License Nos. NPF-76 and NPF-80

Enclosure:

Inspection Report No. 05000498/2017007

and 050000499/2017007

w/ Attachment: Supplemental Information

cc w/ encl: Electronic Distribution

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket:

05000498 and 05000499

License:

NPF-76 and NPF-80

Report:

05000498/2017007 and 05000499/2017007

Licensee:

STP Nuclear Operating Company

Facility:

South Texas Project Electric Generating Station, Units 1 and 2

Location:

FM 521 - 8 miles west of Wadsworth

Wadsworth, Texas 77483

Dates:

January 23 through February 9, 2017

Team Leader:

S. Makor, Acting Senior Reactor Inspector

Inspectors:

S. Alferink, Reactor Inspector

J. Drake, Senior Reactor Inspector

C. Stott, Reactor Inspector

J. Watkins, Reactor Inspector

Approved By:

Gregory E. Werner, Chief

Engineering Branch 2

Division of Reactor Safety

2

SUMMARY

IR 05000498/2017007; 05000499/2017007; 01/23/2017- 02/09/2017; South Texas Project

Electric Generating Station, Units 1 and 2; Fire Protection (Triennial)

The report covers a two-week triennial fire protection team inspection by specialist inspectors

from Region IV. One finding, which was a non-cited violation, was documented. The

significance of inspection findings is indicated by their color (i.e., Green, White, Yellow, or Red)

and determined using Inspection Manual Chapter 0609, Significance Determination Process,

dated April 29, 2015. Cross-cutting aspects are determined using Inspection Manual

Chapter 0310, Aspects within the Cross-Cutting Areas, dated December 4, 2014. All

violations of NRC requirements are dispositioned in accordance with the NRCs Enforcement

Policy, dated November 1, 2016. The NRCs program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,

Revision 6.

A.

NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

Green. The team identified a non-cited violation of License Condition 2.E for the failure

to provide 8-hour emergency lighting in all areas where operators perform manual

actions required during an alternative shutdown. As a compensatory measure, the

licensee added flashlights to the procedure box in the essential cooling water intake

structure. The team noted that operators were also required to carry a flashlight while

on shift. The licensee entered this issue into their corrective action program as

Condition Report 17-1741.

The failure to provide 8-hour emergency lighting in all areas where operators perform

manual actions required during an alternative shutdown was a performance deficiency.

The performance deficiency was more than minor because it was associated with the

protection against external events (fire) attribute of the Mitigating Systems Cornerstone

and it adversely affected the cornerstone objective of ensuring the availability, reliability,

and capability of systems that respond to initiating events to prevent undesirable

consequences. Specifically, the failure to provide 8-hour emergency lighting could

adversely affect the ability of operators to perform the manual actions required for an

alternative shutdown.

The team determined this finding affected the Mitigating Systems Cornerstone. The

team evaluated this finding using Inspection Manual Chapter 0609, Appendix F, Fire

Protection Significance Determination Process, dated September 20, 2013, because it

affected the ability to reach and maintain safe shutdown conditions in case of a fire. The

team determined this finding was of very low safety significance (Green) in Task 1.3.1

because it had a low degradation rating.

The finding did not have a cross-cutting aspect since it was not indicative of present

performance in that the performance deficiency occurred more than three years ago.

Specifically, the team determined that the performance deficiency existed since original

construction. (Section 1R05.08)

3

B.

Licensee-Identified Violations

None

REPORT DETAILS

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R05 Fire Protection (71111.05T)

This report presents the results of a triennial fire protection inspection conducted at

South Texas Project Electric Generating Station, Units 1 and 2 in accordance with NRC

Inspection Procedure 71111.05T, Fire Protection (Triennial), dated January 31, 2013.

The inspection team evaluated the implementation of the approved fire protection

program in selected risk-significant areas with an emphasis on the procedures,

equipment, fire barriers, and systems that ensure the post-fire capability to safely

shutdown the plant.

Inspection Procedure 71111.05T requires the selection of three to five fire areas and one

or more mitigating strategies for review. The inspection team used the fire hazards

analysis section of the South Texas Project Electric Generating Station, Units 1 and 2

Individual Plant Examination of External Events to select the following five risk-significant

fire areas (inspection samples) for review:

Fire Area 20

Non-Radiological Pipe Chase

Fire Area 32

Component Cooling Water Pipe Chase

Fire Area 51

Train D Auxiliary Pump Room

Fire Area 1

Control Room

Fire Area 7

Alternate Shutdown Room

The inspection team evaluated the licensees fire protection program using the

applicable requirements, which included the plant Technical Specifications, Operating

License Condition 2.E, NRC safety evaluations, 10 CFR 50.48, and Branch Technical

Position 9.5-1. The team also reviewed related documents that included the Updated

Final Safety Analysis Report (UFSAR), Section 9.5; the fire hazards analysis; and the

post-fire safe shutdown analysis. Specific documents reviewed by the team are listed in

the attachment.

Five fire area inspection samples and one mitigating strategy sample were completed.

.01

Protection of Safe Shutdown Capabilities

a. Inspection Scope

The team reviewed the piping and instrumentation diagrams, safe shutdown equipment

list, safe shutdown design basis documents, and the post-fire safe shutdown analysis to

verify that the licensee properly identified the components and systems necessary to

achieve and maintain safe shutdown conditions for fires in the selected fire areas. The

4

team observed walkdowns of the procedures used for achieving and maintaining safe

shutdown in the event of a fire to verify that the procedures properly implemented the

safe shutdown analysis provisions.

For each of the selected fire areas, the team reviewed the separation of redundant safe

shutdown cables, equipment, and components located within the same fire area. The

team also reviewed the licensees method for meeting the requirements of

10 CFR 50.48; Branch Technical Position 9.5-1, Appendix A; and 10 CFR Part 50,

Appendix R,Section III.G. Specifically, the team evaluated whether at least one

post-fire safe shutdown success path remained free of fire damage in the event of a fire.

In addition, the team verified that the licensee met applicable license commitments.

b. Findings

No findings were identified.

.02

Passive Fire Protection

a. Inspection Scope

The team walked down accessible portions of the selected fire areas to observe the

material condition and configuration of the installed fire area boundaries (including walls,

fire doors, and fire dampers) and verify that the electrical raceway fire barriers were

appropriate for the fire hazards in the area. The team compared the installed

configurations to the approved construction details, supporting fire tests, and applicable

license commitments.

The team reviewed installation, repair, and qualification records for a sample of

penetration seals to ensure the fill material possessed an appropriate fire rating and that

the installation met the engineering design. The team also reviewed similar records for

the rated fire wraps to ensure the material possessed an appropriate fire rating and that

the installation met the engineering design.

b. Findings

No findings were identified.

.03

Active Fire Protection

a. Inspection Scope

The team reviewed the design, maintenance, testing, and operation of the fire detection

and suppression systems in the selected fire areas. The team verified the automatic

detection systems and the manual and automatic suppression systems were installed,

tested, and maintained in accordance with the National Fire Protection Association code

of record or approved deviations, and that each suppression system was appropriate for

the hazards in the selected fire areas.

The team performed a walkdown of accessible portions of the detection and suppression

systems in the selected fire areas. The team also performed a walkdown of major

5

system support equipment in other areas (e.g., fire pumps and Halon supply systems) to

assess the material condition of these systems and components.

The team reviewed the electric and diesel fire pumps flow and pressure tests to verify

that the pumps met their design requirements. The team also reviewed the halon

suppression functional tests to verify that the system capability met the design

requirements.

The team assessed the fire brigade capabilities by reviewing training, qualification, and

drill critique records. The team also reviewed pre-fire plans and smoke removal plans

for the selected fire areas to determine if appropriate information was provided to fire

brigade members and plant operators to identify safe shutdown equipment and

instrumentation, and to facilitate suppression of a fire that could impact post-fire safe

shutdown capability. In addition, the team inspected fire brigade equipment to determine

operational readiness for firefighting.

The team observed an unannounced fire drill and subsequent drill critique on

February 8, 2017, using the guidance contained in Inspection Procedure 71111.05AQ,

Fire Protection Annual/Quarterly, dated September 30, 2010. The team observed fire

brigade members fight a simulated fire in the isolation valve cubicle, located outside the

radiological controlled area. The team verified that the licensee identified problems,

openly discussed them in a self-critical manner at the drill debrief, and identified

appropriate corrective actions. Specific attributes evaluated were: (1) proper wearing of

turnout gear and self-contained breathing apparatus; (2) proper use and layout of fire

hoses; (3) employment of appropriate firefighting techniques; (4) sufficient firefighting

equipment was brought to the scene; (5) effectiveness of fire brigade leader

communications, command, and control; (6) search for victims and propagation of the

fire into other areas; (7) smoke removal operations; (8) utilization of pre-planned

strategies; (9) adherence to the pre-planned drill scenario; and (10) drill objectives.

b. Findings

No findings were identified.

.04

Protection from Damage from Fire Suppression Activities

a. Inspection Scope

The team performed plant walkdowns and document reviews to verify that redundant

trains of systems required for hot shutdown, which are located in the same fire area,

would not be subject to damage from fire suppression activities or from the rupture or

inadvertent operation of fire suppression systems. Specifically, the team verified:

A fire in one of the selected fire areas would not directly through production of

smoke, heat, or hot gases cause activation of suppression systems that could

potentially damage all redundant safe shutdown trains.

A fire in one of the selected fire areas or the inadvertent actuation or rupture of a

fire suppression system would not directly cause damage to all redundant trains

(e.g., sprinkler-caused flooding of other than the locally affected train).

6

Adequate drainage was provided in areas protected by water suppression

systems.

b. Findings

No findings were identified.

.05

Alternative Shutdown Capability

a. Inspection Scope

Review of Methodology

The team reviewed the safe shutdown analysis, operating procedures, piping and

instrumentation drawings, electrical drawings, the Updated Final Safety Analysis Report,

and other supporting documents to verify that hot and cold shutdown could be achieved

and maintained from outside the control room for fires that require evacuation of the

control room, with or without offsite power available.

The team conducted plant walkdowns to verify that the plant configuration was

consistent with the description contained in the safe shutdown and fire hazards

analyses. The team focused on ensuring the adequacy of systems selected for

reactivity control, reactor coolant makeup, reactor decay heat removal, process

monitoring instrumentation, and support systems functions.

The team also verified that the systems and components credited for shutdown would

remain free from fire damage. Finally, the team verified that the transfer of control from

the control room to the alternative shutdown location would not be affected by

fire-induced circuit faults (e.g., by the provision of separate fuses and power supplies for

alternative shutdown control circuits).

Review of Operational Implementation

The team verified that licensed and non-licensed operators received training on

alternative shutdown procedures. The team also verified that sufficient personnel to

perform an alternative shutdown were trained and available onsite at all times, exclusive

of those assigned as fire brigade members.

The team performed a timed walkdown of the alternative shutdown procedure for Unit 2

with licensed and non-licensed operators to determine the adequacy of the procedure.

The team verified that the operators could reasonably be expected to perform specific

actions within the time required to maintain plant parameters within specified limits.

Time critical actions that were verified included restoring electrical power, establishing

control at the remote shutdown and local shutdown panels, establishing reactor coolant

makeup, and establishing decay heat removal.

The team also reviewed the periodic testing of the alternative shutdown transfer

capability and instrumentation and control functions to verify that the tests were

adequate to demonstrate the functionality of the alternative shutdown capability.

7

b. Findings

No findings were identified.

.06

Circuit Analysis

a. Inspection Scope

The team reviewed the post-fire safe shutdown analysis to verify that the licensee

identified the circuits that may impact the ability to achieve and maintain safe shutdown.

The team verified, on a sample basis, that the licensee properly identified the cables for

equipment required to achieve and maintain hot shutdown conditions in the event of a

fire in the selected fire areas. The team verified that these cables were either

adequately protected from the potentially adverse effects of fire damage or were

analyzed to show that fire induced circuit faults (e.g., hot shorts, open circuits, and

shorts to ground) would not prevent safe shutdown.

The teams evaluation focused on the cables of selected components from the

emergency diesel generator, component cooling water, auxiliary feedwater, high head

safety injection, low head safety injection, pressurizer power operated relief valves

(PORVs), PORV block valves, alternative shutdown control room isolation and transfer

switches, and chemical volume and control system. For the sample of components

selected, the team reviewed electrical elementary and block diagrams, and identified

power, control, and instrument cables necessary to support their operation. In addition,

the team reviewed cable routing information to verify that fire protection features were in

place as needed to satisfy the separation requirements specified in the fire protection

license basis. Specific components reviewed by the team are listed in the attachment.

b. Findings

No findings were identified.

.07

Communications

a. Inspection Scope

The team inspected the contents of designated emergency storage lockers and

reviewed the alternative shutdown procedure to verify that portable radio

communications and fixed emergency communications systems were available,

operable, and adequate for the performance of designated activities. The team verified

the capability of the communication systems to support the operators in the conduct and

coordination of their required actions. The team also verified that the design and

location of communications equipment such as repeaters and transmitters would not

cause a loss of communications during a fire. The team discussed system design,

testing, and maintenance with the system engineer.

b. Findings

No findings were identified.

8

.08

Emergency Lighting

a. Inspection Scope

The team reviewed the portion of the emergency lighting system required for alternative

shutdown to verify that it was adequate to support the performance of manual actions

required to achieve and maintain hot shutdown conditions, and to illuminate access and

egress routes to the areas where manual actions would be required. The team

evaluated the locations and positioning of the emergency lights during a walkdown of the

alternative shutdown procedure.

The team verified that the licensee installed emergency lights with an 8-hour capacity,

maintained the emergency light batteries in accordance with manufacturer

recommendations, and tested and performed maintenance in accordance with plant

procedures and industry practices.

b. Findings

Introduction. The team identified a Green non-cited violation of License Condition 2.E

for the failure to provide 8-hour emergency lighting in all areas where operators perform

manual actions required during an alternative shutdown.

Description. During a walkdown of the alternative shutdown procedure, the team

identified four areas where the 8-hour emergency lighting was not sufficient for operators

to perform manual actions required during an alternative shutdown. The four areas,

manual actions, and associated procedure sections are provided in the table below.

Area

Manual Action (Procedure Step)

Electrical Auxiliary Building Penetration

Space (train A)

De-energize valve 2-CC-MOV-0339

(Addendum 20)

Electrical Auxiliary Building Penetration

Space (train B)

De-energize valve 2-CC-MOV-0356

(Addendum 21)

Essential Cooling Water Intake Structure

(train B)

De-energize dampers HZ-FV-9895/9895A

(Addendum 5, Step 2.0)

Essential Cooling Water Intake Structure

(train C)

De-energize dampers HZ-FV-9896/9896A

(Addendum 5, Step 2.0)

In response to the teams request, the licensee conducted a blackout test to evaluate the

adequacy of the 8-hour emergency lighting in the essential cooling water intake structure

(train B). This blackout test confirmed the teams determination that the 8-hour

emergency lighting in the room was not sufficient for operators to de-energize dampers

HZ-FV-9895/9895A.

9

As a compensatory measure, the licensee added flashlights to the procedure box in the

Essential Cooling Water Intake Structure. The team noted that operators were also

required to carry a flashlight while on shift.

Analysis. The failure to provide 8-hour emergency lighting in all areas where operators

perform manual actions required during an alternative shutdown was a performance

deficiency. The performance deficiency was more than minor because it was associated

with the protection against external events (fire) attribute of the Mitigating Systems

Cornerstone and it adversely affected the cornerstone objective of ensuring the

availability, reliability, and capability of systems that respond to initiating events to

prevent undesirable consequences. Specifically, the failure to provide 8-hour

emergency lighting could adversely affect the ability of operators to perform the manual

actions required for an alternative shutdown.

The team determined this finding affected the Mitigating Systems Cornerstone. The

team evaluated this finding using Inspection Manual Chapter 0609, Appendix F, Fire

Protection Significance Determination Process, dated September 20, 2013, because it

affected the ability to reach and maintain safe shutdown conditions in case of a fire. The

team assigned the finding to the post-fire safe shutdown category since it impacted the

remote shutdown and control room abandonment element. Using Inspection Manual

Chapter 0609, Appendix F, Attachment 2, Degradation Rating Guidance Specific to

Various Fire Protection Program Elements, dated February 28, 2005, the team

assigned the finding a low degradation rating since the ability to reach and maintain safe

shutdown conditions in the event of a control room fire would be minimally impacted by

the failure to provide 8-hour emergency lighting in the four areas. Specifically, the team

determined that operators were required to carry flashlights while on shift and these

flashlights would be sufficient for operators to perform the required manual actions.

Because this finding had a low degradation rating, it screened as having very low safety

significance (Green) in Task 1.3.1.

The finding did not have a cross-cutting aspect since it was not indicative of present

performance in that the performance deficiency occurred more than three years ago.

Specifically, the team determined that the performance deficiency existed since original

construction.

Enforcement. License Condition 2.E states, in part, that the licensee shall implement

and maintain in effect all provisions of the approved fire protection program as described

in the Updated Final Safety Analysis Report through Amendment Number 55 for Unit 1,

the Updated Final Safety Analysis Report through Amendment Number 62 for Unit 2,

and the Fire Hazards Analysis Report through Amendment Number 23. Section 4.1 of

the Fire Hazards Analysis Report contains a comparison of the licensees fire protection

program to the requirements in 10 CFR Part 50, Appendix R. The Fire Hazards Analysis

Report states that fixed self-contained emergency lighting, consisting of sealed-beam

units with individual 8-hour minimum battery supply, will be provided in areas needed for

operation of hot standby/hot shutdown equipment, and in access and egress routes

thereto.

Contrary to the above, prior to February 9, 2017, the licensee failed to implement and

maintain in effect all provisions of the approved fire protection program. Specifically, the

licensee failed to provide 8-hour emergency lighting in all areas needed for operation of

hot standby/hot shutdown equipment.

10

The licensee entered this issue into their corrective action program as Condition

Report CR 17-1741. In addition to ensuring operators carried flashlights while on

shift, the licensee also implemented a compensatory measure of adding flashlights to

the procedure box in the essential cooling water intake Structure. Because this violation

was of very low safety significance and has been entered into the corrective action

program, this violation is being treated as a non-cited violation, consistent with

Section 2.3.2.a of the NRC Enforcement Policy: NCV 05000498/2017007-01; 05000499/2017007-01, Failure to Provide 8-hour Emergency Lighting for All Alternative

Shutdown Manual Actions.

.09

Cold Shutdown Repairs

a. Inspection Scope

South Texas Project Electric Generating Station has three trains of redundant

equipment in each unit and, therefore, does not credit any cold shutdown repairs.

b. Findings

No findings were identified.

.10

Compensatory Measures

a. Inspection Scope

The team verified that compensatory measures were implemented for out-of-service,

degraded, or inoperable fire protection and post-fire safe shutdown equipment, systems,

or features (e.g., detection and suppression systems and equipment; passive fire

barriers; or pumps, valves, or electrical devices providing safe shutdown functions). The

team also verified that the short-term compensatory measures compensated for the

degraded function or feature until appropriate corrective action could be taken, and that

the licensee was effective in returning the equipment to service in a reasonable period of

time.

The team reviewed operator manual actions credited for achieving hot shutdown for fires

that do not require an alternative shutdown. The team verified that operators could

reasonably be expected to perform the actions within the applicable shutdown time

requirements. The team reviewed these operator manual actions using the guidance

contained in NUREG-1852, Demonstrating the Feasibility and Reliability of Operator

Manual Actions in Response to Fire, dated October 2007.

For the train of systems necessary to achieve and maintain hot shutdown conditions, the

team verified that the licensee treated these manual actions as compensatory measures

while appropriate corrective actions are implemented or while preparations are made by

the licensee to submit exemptions or deviations. For components important to safe

shutdown that could adversely affect the safe shutdown capability, the team verified that

operators could reasonably be expected to perform the actions within the applicable

shutdown time requirements.

11

b. Findings

No findings were identified.

.11

Review and Documentation of Fire Protection Program Changes

a. Inspection Scope

The team reviewed changes made to the approved fire protection program since

September 25, 2014. The team verified that the changes did not constitute an adverse

effect on the ability to safely shutdown.

b. Findings

No findings were identified.

.12

Control of Transient Combustibles and Ignition Sources

a. Inspection Scope

The team reviewed the licensees approved fire protection program, implementing

procedures, and programs for the control of ignition sources and transient combustibles.

The team assessed the licensees effectiveness in preventing fires and in controlling

combustible loading within limits established in the fire hazards analysis. The team

performed plant walkdowns to independently verify that transient combustibles and

ignition sources were being properly controlled in accordance with the administrative

controls.

b. Findings

No findings were identified.

.13

Alternative Mitigation Strategy Inspection Activities

a. Inspection Scope

The team reviewed the licensees implementation of guidance and strategies intended to

maintain or restore core, containment, and spent fuel pool cooling capabilities under the

circumstances associated with the potential loss of large areas of the plant due to

explosions or fire as required by 10 CFR 50.54(hh)(2).

The team verified that the licensee implemented and maintained adequate procedures,

maintained and tested equipment necessary to properly implement the strategies, and

ensured station personnel were knowledgeable and capable of implementing the

procedures. The team performed a visual inspection of portable equipment used to

implement the strategy to ensure the availability and material readiness of the

equipment, including the adequacy of portable pump trailer hitch attachments, and verify

the availability of on-site vehicles capable of towing the portable pump. The team

assessed the off-site ability to obtain fuel for the portable pump and foam used for

firefighting efforts. The strategy and procedure selected for this inspection sample

included:

12

Procedure 0POP10-FP-0001, Alternate Fire Protection System Operation,

Revision 4

One mitigating strategy sample was completed.

b. Findings

No findings were identified.

4.

OTHER ACTIVITIES [OA]

4OA2 Problem Identification and Resolution (71152)

Corrective Actions for Fire Protection Deficiencies

a. Inspection Scope

The team selected a sample of condition reports associated with the licensee's fire

protection program to verify that the licensee had an appropriate threshold for identifying

deficiencies. The team reviewed the corrective actions proposed and implemented to

verify that they were effective in correcting identified deficiencies. The team evaluated

the quality of recent engineering evaluations through a review of condition reports,

calculations, and other documents during the inspection.

b. Findings

No findings were identified.

4OA6 Meetings, Including Exit

Exit Meeting Summary

On February 9, 2017, the team presented the inspection results to Mr. G. Powell, Executive

Vice President and Chief Nuclear Officer, and other members of the licensee staff. The

licensee acknowledged the findings presented.

The team verified that no proprietary information was retained by the team members or

documented in this report.

Attachment

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

J. Alston, Systems Engineering Department Supervisor

M. Berg, Manager, Design Engineering

J. Berrio, Manager, Operations-Production Support and Programs

A. Capristo, Chief Administrative Officer

F. Cox, Design Engineering Department Safe Shutdown

G. Ferrigno, Radiation Protection GS

K. Frazier, Systems Engineering Department, Elect/IMS Section Supervisor

C. Gann, Manager, Employee Concerns Program

C. Georgeson, Supervisor, Design Engineering

D. Gore, Supervisor, Reactor Analysis

D. Hubenak, Radiation Protection GS

D. Janak, Performance Improvement Coordinator

D. Jenkins, Operations Support-Procedures

W. Jordan, Plant Operator

R. Kersey, Supervisor, Design

D. Koehl, President and Chief Executive Officer

R. Krupa, Senior Staff Specialist, Quality

R. Lacey, Design Engineering Department Electrical

B. Lane, Manager, Operations Division - Integrated Work Mgmt. & Outage

G. Lamberth, Operations Support-Procedures

H. Leon, Design Engineering Department, Electrical Engineer

J. Lovejoy, Manager Assistant, Maintenance

N. Mayer, Manager, Major Projects

M. Murray, Manager, Regulatory Affairs/Licensing

C. Pence, Manager, Chemistry

B. Powell, Staff Operations Specialist

G. Powell, Executive Vice President and Chief Nuclear Officer

D. Rohan, Operations Support-Procedures

R. Scarborough, Manager NOS

M. Schaefer, Plant General Manager

G. Schinzel, Supervising Engineer

C. Stinson, Manager, Maintenance & Technology Training

R. Stastny, Manager, Maintenance

D. Wiegand, Fire Protection Engineering

D. Whiddon, Supervisor, Quality

R. Gonzales, Engineer Staff

NRC Personnel

F. Sanchez, Senior Resident Inspector

N. Hernandez, Resident Inspector

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

None

2

LIST OF DOCUMENTS REVIEWED

Cable Routing Data Components

A2AF01C1WB

A2RC13C1LAA

B2CV31C2WA

B2SP17CDSA

A2AF01C1WC

A2RC13C1LB

B2CV31C2WC

B2SP17CHSB

A2AF01C1WD

A2RC13C1LC

B2CVAEC1LA

B2SP17CHSE

A2AF01C1WE

A2RC13C1WA

B2MB04C1SK

B2SP17CHSF

A2AF01C1WF

A2RC13C1WB

B2MB04C1SU

C2CV26C1WA

A2AF01C1WG

A2RC13C1WC

B2MB04C1SV

C2CV26C1WB

A2AM14C1SA

A2RC13C1WD

B2MB04C1SW

C2CV26C1WC

A2CV26C1WA

A2RC13C1WE

B2RC05C2WA

C2CV26C1WD

A2CV26C1WB

A2RC13C1WF

B2RC05C2WB

C2CV26C1WE

A2CV26C1WC

A2RCAAC1WA

B2RC05C2WC

C2CV31C1SB

A2CV26C1WD

A2RCABC1LA

B2RC05C2WD

C2CV31C1WA

A2CV26C1WE

A2RCABC1LB

B2RC05C2WE

C2CV31C1WC

A2CVAAC1GA

A2RCABC1LC

B2RC13C2LB

C2CVACC1GA

A2MB01C1SB

A2SI05C1SA

B2RC13C2LC

C2CVAHC1LA

A2MB01C1SJ

A2SI05CSSB

B2RC13C2LD

C2MB04C1SB

A2MB01C2SN

A2SI06C1SA

B2RC13C2LE

C2MB04C1SL

A2MB04C1SB

A2SI06C1SB

B2RC13C2WA

C2SP17CFSA

A2MB04C1SS

A2SIAAC1EA

B2RC13C2WB

N2AM11C3SA

A2MB04C1ST

A2SIAAC1EB

B2RC13C2WC

N2IC14C1XD

A2MB04C1SU

A2SP17CHSB

B2RC13C2WD

N2IC14C1XD1

A2RC05C1WA

A2SP17CHSE

B2RC13C2WE

N2IC14C3XD

A2RC05C1WB

A2SP17CHSF

B2RC13C2WF

N2IC14C3XD1

A2RC05C1WC

A2SP22CASG

B2RCACC1WA

A2RC05C1WD

A2SP22CMSD

B2RCADC1LA

A2RC05C1WE

A2SP27CASE

B2RCADC1LB

A2RC13C1LA

B2CV31C2SB

B2RCADC1LC

Calculations

Number

Title

Revision/Date

EC6053 Sheet 187

4.16 kV Switchgear Transfer Switch Schemes

Figure 8.5 Fuse Curves for 15 Amp Type A4J15 fuse,

KWN15A fuse, and ITE Class J 30 Amp A4J30 fuse

December 24,

1987

3

Calculations

Number

Title

Revision/Date

MC06023

Appendix R Evaluation

13

MC-5557

IVC Flooding Analysis

9

NC-0709

Fire Hazards Analysis

6

NC-9703

Flooding Analysis: MAB

2

Condition Reports

11-10905 15-864

17-1020*

13-11633

16-1036-1

17-1022*

14-10845

16-12666

17-1026

14-16243

16-13030

17-1029*

14-17206

16-13587

17-1042*

14-17681

16-13588

17-1102*

14-17098

16-13821

17-1110*

14-4215-4

16-13941

17-1113*

15-10544

16-13993

17-1141*

15-10698

16-14060

17-1473*

15-16087

16-14207

17-1661*

15-17634

16-14210

17-1677*

15-18016

16-14274

17-1741*

15-20739

16-1488

17-1776*

15-22156

16-15937

17-1777*

15-22736-2

16-15951

17-1790*

15-23704

16-16045

15-23705

16-1832

15-23793

16-3841

15-23796

16-4633

15-23859

16-4905

15-24143

16-6501

15-24188

16-8427

15-24734 16-903

15-25399

17-1016*

15-26129

17-1019

  • Issued as a result of inspection activities.

4

Design Change Notices

0601177

0601176

0701838

Drawings

Number

Title

Revision/Date

5S139F00063#2

Piping & Instrumentation Diagram Feedwater

36

5S109F00016#2

Piping & Instrumentation Diagram Main Steam

34

5S142F00024

Piping & Instrumentation Diagram Auxiliary

Feedwater

12

5R209F05017#2

Piping and Instrumentation Diagram Component

Cooling Water System

20

E0AAAA Sht. 1

Single line Diagram Main one Line Diagram Unit

Number 1 and 2

28

9E0AAAB#1 Sht. 1

Single Line Diagram Class 1E 125V DC and 120V

Vital AC Non-Class 1E 48V, 125V, 250V, DC and

120V Vital AC Non-Class 1E Inverter power for

Computer 208V/120V AC Regulated Power

27

C012-000937F

Detail M-1A Silicone Elastomer Typical Mechanical

Penetration Seals (walls and Floors)

November 9,

1999

9E0DG04#2 Sht. 1

Elementary diagram Standby Diesel Generator

Number 21 Emergency Control and Instrumentation

20

9E0DG04#2 Sht. 2

Elementary diagram Standby Diesel Generator

Number 21, 22, and 23 Emergency Control and

Instrumentation

16

5Z109Z42117#2

Instrumentation ESF Load Sequencer Actuation

Train A Logic Diagram System SP

12

804101197CE

STP Log Number Cooper Bessemer G5-553-137

Control Schematic (Starting Sequence Control)

0

9-E-MB03-01#2

Elementary Diagram Master Block Diagram ESF

Main Control Board ZCP003

6

9E0PK03#2

Elementary Diagram ESF Transformer and 4.16kV

Bus E1A, E1B, and E1C Protection and Metering

Circuit

9

9E0PK04#2 Sht. 1

Elementary Diagram ESF Transformer and 4.16kV

Bus E2A, E2B, and E2C Protection and Metering

Circuit

14

5

Drawings

Number

Title

Revision/Date

9E0DG01#2 Sht.1

Elementary Diagram Standby Diesel Generator

DG21 4.16kV Feeder Breaker

16

9E0PK01#2 Sht. 1

Elementary Diagram 4.16kV ESF Bus E1A, E1B,

and E1C Supply Breaker Control

10

9E0PK01#2

Elementary Diagram 4.16kV ESF Bus E1A, E1B,

and E1C Supply Breaker Control

7

9-E-RC1 3-01

Elementary Diagram Reactor Coolant Pressurizer

Power Relief Valves PCV-655A and PCV-656A

9

9E0SI05#2 Sht. 1

Elementary Diagram High Head Safety Injection

Pumps PA201A, PA201B, and PA201C

8

9E0SI06#2 Sht. 1

Elementary Diagram Low Head Safety Injection

Pumps PA202A, PA202B, and PA202C

9

9E0CH11#2 Sht. 1

Elementary Diagram E.A.B. HVAC Essential Chilled

Water Chiller Units CH004, CH005, and CH006

10

9-E-CH11-03#2

Elementary Diagram E.A.B. HVAC Essential Chilled

Water Chiller Units CH004, CH005, and CH006

5

9-E-PKAA-01 #2

Single Line Diagram 4.16kV Class 1E

Switchgear E2A

10

9E0PKAB#2 Sht. 1

Single Line Diagram 4.16kV Class 1E

Switchgear E2B

10

9E0PKAC-01#2

Single Line Diagram 4.16kV Class 1E

Switchgear E2C

9

9E0EW01#2 Sht. 1

Elementary Diagram Essential Cooling Water

Pumps Number 2A, 2B, and 2C

20

9E0AF01#2 Sht. 1

Elementary Diagram Auxiliary Feedwater Pumps

Number 21, 21, and 23

10

9E-AF01-02 #2

Elementary Diagram Auxiliary Feedwater Pumps

Number 11, 12, and 13

3

9E0CV26#2 Sht. 1

Elementary Diagram Centrifugal Charging Pumps

Number 2A and 2B (PA201A and PA201B)

12

9E0CV26#2 Sht. 2

Elementary Diagram Centrifugal Charging Pumps

Number 2A and 2B (PA201A and PA201B)

12

6

Drawings

Number

Title

Revision/Date

9E0CC01#2 Sht. 1

Elementary Diagram Component Cooling Water

PA201A, PA201B, and PA201C

16

9E0CC01#2 Sht. 2

Elementary Diagram Component Cooling Water

PA201A, PA201B and PA201C

20

9-E-CC10-01 #2

Elementary Diagram Master Cable Block Diagram

Component Cooling Water System

13

9E0CV05#2 Sht. 1

Elementary Diagram CVCS VCT Outlet Isolation

MOV-0112B and MOV-0113A

12

9E0CV31#1 Sht. 1

Elementary Diagram CVCS RWST to Charging

Pump MOV-0112C AND MOV-0113B

14

9E0SI12#2 Sht. 1

Elementary Diagram SI RWST Outlet MPVs 0001A,

0001B, and 0001C

11

9E0RC05#1 Sht. 1

Elementary Diagram Reactor Coolant Pressurizer

Relief Block Valve MOV0001A and MOV0001B

17

9E0RC05#2 Sht. 1

Elementary Diagram Reactor Coolant Pressurizer

Relief Block Valve MOV0001A and MOV0001B

15

5-R-14-9-Z-42155#1

Reactor Coolant Pressurizer Relief Block Valves

logic Diagram System

11

9E0AF13#2 Sht. 1

Elementary Diagram AFW to Steam Generator 2D

Regulating Valve FV-7526

16

9E0CV09#2 Sht. 1

Elementary Diagram CVCS Excess Letdown Line

Isolation MOV-0083 and MOV-0082

11

9E0RH05#2 Sht. 1

Elementary Diagram Residual Heat Removal

Pumps 2A, 2B, and 2C (PA201A, PA201B, and

PA201C)

12

9E0RH05#2 Sht. 2

Elementary Diagram Residual Heat Removal

Pumps 2A, 2B, and 2C

1

9E0PLAA#2 Sht. 1

Single Line Diagram 480V Class-1E Center E2A

19

9E0PLAB#2 Sht. 1

Single Line Diagram 480V Class-1E Center E2B

16

9E0PLAC#2 Sht. 1

Single Line Diagram 480V Class-1E Center E2C

17

9E0PMAA#2 Sht. 1

Single Line Diagram 480V Class-1E Motor Control

Center E2A1

26

7

Drawings

Number

Title

Revision/Date

9E0PMAA#2 Sht. 2

Single Line Diagram 480V Class-1E Motor Control

Center E2A1

21

9E0PMAB#2 Sht. 1

Single Line Diagram 480V Class-1E Motor Control

Center E2A2

27

9E0PMAC#2 Sht. 1

Single Line Diagram 480V Class-1E Motor Control

Center E2A3 ECW Building

14

9E0PMAD#2 Sht. 1

Single Line Diagram 480V Class-1E Motor Control

Center E2B1

25

9E0PMAD#2 Sht. 2

Single Line Diagram 480V Class-1E Motor Control

Center E2B1

22

9E0PMAE#2 Sht. 1

Single Line Diagram 480V Class-1E Motor Control

Center E2B2

17

9E0PMAF#2 Sht. 1

Single Line Diagram 480V Class-1E Motor Control

Center E2B3 ECW Building

15

9E0PMAG#2 Sht. 1

Single Line Diagram 480V Class-1E Motor Control

Center E2C1

21

9E0PMAG#2 Sht. 2

Single Line Diagram 480V Class-1E Motor Control

Center E2C1

17

9E0PMAH#2 Sht. 1

Single Line Diagram 480V Class-1E Motor Control

Center E2C2

21

9E0PMAJ#2 Sht. 1

Single Line Diagram 480V Class-1E Motor Control

Center E2C3 ECW Building

14

9E0PMAK#2 Sht. 1

Single Line Diagram 480V Class-1E Motor Control

Center E2A4

22

9E0PMAL#2 Sht. 1

Single Line Diagram 480V Class-1E Motor Control

Center E2B4

22

9E0PMAM#2 Sht. 1

Single Line Diagram 480V Class-1E Motor Control

Center E2C4 Center

20

9E0PCAA#2 Sht. 1

Single Line Diagram 13.8 kV Switchgear 2F

17

9E0PCAB#2 Sht. 1

Single Line Diagram 13.8 kV Switchgear 2G

17

9E0PCAC#2 Sht. 1

Single line Diagram 13.8 kV Switchgear 2H

16

8

Drawings

Number

Title

Revision/Date

9E0VAAA#2 Sht. 1

Single Line Diagram Vital 120V AC Distribution

Panels DP001, DP1201 Channel I

27

5R209F05017

Piping and Instrumentation Component Cooling

Water System

20

86-534801 Sht. 1

Liquid Level Controller FR72LL - Remote

Electronics

A

86-534801 Sht. 2

Liquid Level Controller FR72LL - Remote

Electronics

A

9-W-01-9-E-50102

Electrical-Communications Maintenance Jack

Station One Line Diagram

5

9E569E03765

Electrical - Electrical Auxiliary Bldg. Lighting &

Communications Plan Elevation 35-0

11

9E569E03751

Electrical - Electrical Auxiliary Bldg. Lighting &

Communications Plan Elevation 10-0

15

9E569E03753

Electrical - Electrical Auxiliary Bldg. Lighting &

Communications Plan Elevation 10-0

20

9E569E03767#2

Electrical - Electrical Auxiliary Bldg. Lighting Plan

Elevation 35-0

21

9E560E03001

Electrical Elementary Diagram - Lighting Fixture

Schedule Units 1 & 2

30

0-E-0102 SH. 5

Electrical Lighting Notes & Details Lighting Symbols

9

7E569E03046

Appendix R Light Locations

3

9E560E0102 SH. 23

Electrical Lighting Notes And Details Wall Mount

Emergency LTGS.

9

9W019E00466 #2

Mech. And Elect. Aux. Bldg. Fire Detection

Plan El. 21-0 & 29-0

7

9W019E00467 #2

Mech. And Elect. Aux. Bldg. Fire Detection

Plan El. 35-0 & 41-0

9

9W019E00468 #2

Mechanical and Electrical Aux. Bldg. Fire Detection

Plan El. 60-0

7

9-W-01-9-E-50471 #2 Mechanical & Electrical Auxiliary Building Fire

Detection Partial Plans for Miscellaneous Areas

4

9

Drawings

Number

Title

Revision/Date

9-W-01-9-E-50474 #2 Isolation Valves Cubicle Fire Detection

Plan El. 10-0 & 21-2

4

9-W-01-9-E-50475 #2 Isolation Valves Cubicle Fire Detection

Plan El. 58-6

3

7M149M24514 #2

Fire Areas Mechanical & Electrical Building Plan at

El. 21-0, 23-0, 29-0, & 32-0

10

7M149M24515 #2

Fire Areas Mechanical & Electrical Auxiliary Building

Plan at El. 35-0, 41-0 & 51-0

14

7M149M24516 #2

Fire Areas Mechanical & Electrical Auxiliary Building

Plan at El. 60-0

11

7M-14-9M-24534 #2

Fire Areas Isolation Valves Cubicle Plan at El. 10-0

& 21-2

4

7M-14-9M-24535 #2

Fire Areas Isolation Valves Cubicle Plan at El. 34-0

& 44-0

4

7M-14-9M-24536 #2

Fire Areas Isolation Valves Cubicle Plan El. 51-6

4

7M-14-9M-24537 #2

Fire Areas Isolation Valves Cubicle Plan at El. 59-6

4

7M-14-9M-24538 #2

Fire Areas Isolation Valves Cubicle Sections A-A &

B-B

4

7M149M24513 #1

Fire Areas Mechanical & Electrical Auxiliary Building

Plan at El, 10-0

10

7M149M24515 #1

Fire Areas Mechanical & Electrical Auxiliary Building

Plan at EL. 35-0, 41-0 &51-6

19

7M149M24514 #1

Fire Areas Mechanical & Electrical Building Plan at

EL. 21-0, 23-0 & 330-0

10

7M149M24516 #1

Fire Areas Mechanical & Electrical Building Plan at

EL. 60-0

11

7M-14-9M-24534 #1

Fire Areas Mechanical & Electrical Building Plan at

EL. 10-0 & 21-2

4

00000E0AAAA

Single Line Diagram Main One Line Diagram Unit

No. 1 & 2

28

00009E0AAAB #1

Single Line Diagram Class 1E 125V DC & 120V Vital

AC Non-Class 1E 48V, 125V, 250, DC, & 120V Vital

AC Non-Class 1E Inverter Power for Computer

27

10

Drawings

Number

Title

Revision/Date

208V/120V AC Regulated Power

AC Non-Class 1E Inverter Power for Computer

208V/120V AC Regulated Power

7M149M24513,

Sheet 1

Mechanical & Electrical Auxiliary Building, Plan at

El. 10-0

10

7M149M24514,

Sheet 1

Mechanical & Electrical Auxiliary Building, Plan at

El. 21-0, 23-0, 29-0, and 30-0

10

7M149M24515,

Sheet 1

Mechanical & Electrical Auxiliary Building, Plan at

El. 35-0, 41-0, and 51-6

19

7M149M24516,

Sheet 1

Mechanical & Electrical Auxiliary Building, Plan at

El. 60-0

11

7M149M24534,

Sheet 1

Isolation Valves Cubicle, Plan at El. 10-0 and 21-2

4

9-E-56-9-E-3608,

Sheet 2

Electrical - Mechanical Auxiliary Building, Lighting

and Communications Plan, Elevation 29-0

13

9-E-NI02-091,

Sheet 2

Elementary Diagram, Master Block Diagram,

Neutron Flux Monitoring System, QDPS Interface

4

Miscellaneous Documents

Number

Title

Revision/Date

Westinghouse Type EB, EHB, MARK 75 Type

HFBFuse Curves for 15 Amp circuit breaker

December 11,

1985

Littelfuse Incorporated Time-Current Characteristics

334 and 336 Series Indicating Fuses Fuse Curves

September 25,

1986

STP Users Guide for Maintenance Jack and

Fueling/Refueling Jack Systems

September

1987

07-457-70

Evaluation for Adding 500 GPM of Demineralized

Water to the Spent Fuel Pool Using the Temporary

Fire Water Pump Through the Fire Water Header

December 9,

2008

1200006

Design Change Notice

March 7, 2012

1200360

Design Change Notice

March 13,

2012

9703446

Document Change Notice

October 8,

1997

11

Miscellaneous Documents

Number

Title

Revision/Date

ED-1020

Document Change Notice

January 2,

1991

204608A

PCF Amendment Form

February 14,

1994

204641A

PCF Amendment Form

January 31,

1994

CR 08-14399

STP Multiple Spurious Operation Report

1

STP MSO Generic List

1

15-06 (FP)

STP Nuclear Operating Company Fire Protection

Quality Audit Report

August 31,

2015

16-07 (FP)

STP Nuclear Operating Company Fire Protection

Quality Audit Report

August 17,

2016

Active Fire Protection Impairment Permits

January 26,

2017

U2 Open Fire Watches

January 26,

2017

17-01-03

Unannounced Fire Drill (0PGP03-ZF-0011, STEGS

Fire Brigade, Rev. 16)

February 8,

2017

NCR 89-2-025

Appendix R Emergency DC Lighting, ECWIS

Rooms 101, 102, 103

January 26,

1989

5A019MFP001

Post-Fire Operator Actions and Equipment

Protection Requirements

16

Fire Hazards Analysis Report

23

Modifications

Number

Title

Date

1401401

13-11489-1, Revise Drawing as Shown on Page 3

June 16, 2014

1400495

13-11489-1, Change Page 2 of

Calculation 0238-0201005SQ

May 19, 2014

12

Procedures

Number

Title

Revision

0PSP03-CV-0011

Chemical and Volume Control System Valve

Operability Test (Cold Shutdown)

28

0PSP03-RC-0010

Pressurizer Power Operated Relief Valve Operability

Test

13

0PSP03-ZG-0005

Remote Shutdown System Operability Test (Cold

Shutdown)

16

1PSP03-ZG-0007A

Train A Remote Shutdown System Operability Test

9

1PSP03-ZG-0007B

Train B Remote Shutdown System Operability Test

9

1PSP03-ZG-0007C

Train C Remote Shutdown System Operability Test

9

2PSP03-ZG-0007A

Train A Remote Shutdown System Operability Test

4

2PSP03-ZG-0007B

Train A Remote Shutdown System Operability Test

5

2PSP03-ZG-0007C

Train A Remote Shutdown System Operability Test

5

1PSP03-ZG-0007C

Train C Remote Shutdown System Operability Test

9

2PSP03-ZG-0007C

Train C Remote Shutdown System Operability Test

5

0PGP03-ZF-0011

STPEGS Fire Brigade

16

0POP10-FP-0001

Alternate Fire Protection System Operation

4

0PRP06-ZR-0013

Respirator Fit Testing

8

0POP01-ZA-0001

Plant Operations Department Administrative Guidelines 49

0PTP03-FP-0106

Fire Protection Water System Functional Test

15

0POP10-FP-0001

Alternate Fire Protection System Operation

4

0POP10-ZO-EDMG

Extensive Damage Mitigation Guideline

5

0PGP03-ZF-0018

Fire Protection System Functionality Requirements

19

0POP04-ZO-0009

Safe Shutdown Fire Response

15

13

Procedures

Number

Title

Revision

0PGP05-ZV-0014

Emergency Response Activities

15

PMI-EM-EL-0001

Emergency Light Testing

0

0PGP03-ZF-0001A

Hot Work Program

3

0PGP03-ZF-0019

Control of Transient Fire Loads and Use of

Combustible and Flammable Liquids and Gases

15

0PGP03-ZF-0018

Fire Protection System Functionality Requirements

19

0PGP03-ZT-0131

Fire Protection Training and Qualification Program

11

0POP04-ZO-0009

Safe Shutdown Fire Response

14

0POP04-ZO-0008

Fire/Explosion

25

0PGP04-ZA-0002

Condition Report Engineering Evaluation

24

0POP04-ZO-0001

Control Room Evacuation

42

2TOP07-LB-0001

Unit 2 ECWIS Emergency DC Lighting Test

0

Vendor Document

Number

Title

Revision

VTD-M568-0004

Holophane M-19 12 volt DC power pack for automatic

emergency lighting - Installation and maintenance

instructions

3

Work Orders

553365

476850

509206

469672

498017

476853

509205

439418

516337

525424

503414

455441

482275

525364

497337

489640

499679

486919

479338

525362

507880

470941

476848

484809

502929

96006291

ML17079A526

SUNSI Review: ADAMS:

Non-Publicly Available Non-Sensitive Keyword: NRC-002

By: STM Yes No Publicly Available

Sensitive

OFFICE

ASRI:EB2

RI:EB2

SRI:EB2

RI:EB1

RI:EB2

C:EB2

C:PBB

C:EB2

NAME

SMakor

SAlferink

JDrake

CStott

JWatkins

GWerner

NTaylor

GWerner

SIGNATURE

/RA/

/RA/

/RA/

/RA/

/RA/

/RA/

/RA/DLP

for

/RA/

DATE

03/08/17

03/03/17

03/06/17

03/06/17

03/16/17

03/10/2017

03/20/17

03/20/17