IR 05000275/2017007

From kanterella
Revision as of 05:03, 6 July 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
DCPP - Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/ Multi Unit Dose Assessment Plans - Inspection Report (05000275/2017007 and 050003
ML18025A000
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 01/24/2018
From: Haire M S
NRC/RGN-IV/DRP/RPB-A
To: Welsch J M
Pacific Gas & Electric Co
Haire M S
References
IR 2017007
Download: ML18025A000 (18)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD

. ARLINGTON, TX 76011

-4511 January 24, 2018 Mr. James M. Welsch, Vice President, Nuclear Generation and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424

SUBJECT: DIABLO CANYON POWER PLANT, UNITS 1 AND 2

- INSPECTION OF THE IMPLEMENTATION OF MITIGATION STRATEGIES AND SPENT FUEL POOL INSTRUMENTATION ORDERS AND EMERGENCY PREPAREDNESS COMMUNICATION/STAFFING/ MULTI

-UNIT DOSE ASSESSMENT PLANS

- INSPECTION REPORT (05000275/2017007 AND 05000323/2017007

)

Dear Mr. Welsch:

On December 27

, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Diablo Canyon Power Plant, Units 1 and 2.

On December 27, 2017 , t he NRC inspectors discussed the results of this inspection with Mr. C. Murry , Acting Station Director, and other members of your staff. Inspectors documented the results of this inspection in the enclosed inspection report. The inspection examined activities conducted under your license as they relate to the implementation of mitigation strategies and spent fuel pool instrumentation orders (EA-12-049 and EA-12-051) and Emergency Preparedness Communication, Staffing, and Multi-Unit Dose Assessment Plans, your compliance with the Commission's rules and regulations, and with the conditions of your operating license. Within these areas, the inspection involved examination of selected procedures and records, observation of activities, and interviews with station personnel.

Based on the results of this inspection, no findings of significance were identified.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding,"

a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Sincerely,/RA/ Mark S. Haire

, Chief, Project Branch A Division of Reactor Projects Docket Nos. 50-275 and 50

-323 License Nos. DPR-80 and DPR-82

Enclosure:

Inspection Report 05000 275/201700 7 and 5000323/2017007 w/

Attachment:

Supplemental Information cc w/encl: Electronic Distribution

Enclosure U.S. NUCLEAR REGULATORY COMMISSION REGION IV Docket: 50-275 and 50

-323 License: DPR-80 and DPR

-82 Report: 05000275/2017007 and 05000323/2017007 Licensee: Pacific Gas and Electric Company Facility: Diablo Canyon Power Plant, Units 1 and 2 Location: P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424 Dates: November 13 through December 27, 2017 Inspectors:

J. Mateychick

, Senior Reactor Inspector (Team Leader) C. Newport, Senior Resident Inspector R. Alexander, Senior Project Engineer E. Uribe, Project Engineer Approved By: Mark S. Haire Chief, Project Branch A Division of Reactor Projects 2

SUMMARY

IR 05000275/2017007

05000323/2017007
11/13/2017 - 12/27/2017
Diablo Canyon Power Plant, Units 1 and 2
Temporary Instruction 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans , issued December 23, 2015. The inspection covered a one week inspection onsite by three inspectors from the Region IV office and one of the assigned resident inspectors.

No findings of significance were identified.

The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 5.

A. NRC-Identified and Self-Revealing Findings

None

B. Licensee-Identified Violations

None 3

REPORT DETAILS

4. Other Activities

4OA5 Other Activities

(TI 2515/191) The objective of Temporary Instruction (TI) 2015/191 "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi

-Unit Dose Assessment Plans" is to verify that licensees have adequately implemented the mitigation strategies as described in the licensee's Final Integrated Plan (ADAMS Accession No. ML16221A390

) and the NRC's plant safety evaluation (ADAMS Accession No. ML16349A386

) and to verify that the licensee installed reliable water-level measurement instrumentation in their spent fuel pools. The purpose of this TI is also to verify the licensees have implemented Emergency Preparedness (EP) enhancements as described in their site

-specific submittals and NRC safety assessments, including multi-unit dose assessment capability and enhancements t o ensure that staffing is sufficient and communications can be maintained during such an event. The inspection verifies that plans for complying with NRC Orders EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond- Design-Basis External Events (ADAMS Accession No. ML12229A174)and EA-12-051, Order Modifying Licenses With Regard to Reliable Spent Fuel Pool Instrumentation (ADAMS Accession No. ML12056A044)are in place and are being implemented by the licensee. Additionally, the inspection verifies implementation of staffing and communications information provided in response to the March 12, 2012 , request for information letter and multiunit dose assessment information provided per COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for Japan Lessons Learned, dated March 27, 2013 (ADAMS Accession No. ML12339A262).

The team discussed the plans and strategies with plant staff, reviewed documentation, and where appropriate, performed plant walkdowns to verify that the strategies could be implemented as stated in the licensee's submittals and the NRC staff prepared safety evaluation.

For most strategies, this included verification that the strategy was feasible, procedures and/or guidance had been developed, training had been provided to plant staff, and required equipment had been identified and staged. Specific details of the team's inspection activities are described in the following sections. 1. Mitigation Strategies for Beyond-Design-Basis External Events

a. Inspection Scope

The team examined the licensee's established guidelines and implementing procedures for the beyond-design-basis mitigation strategies.

The team assessed how the licensee coordinated and documented the interface/transition between existing off-normal and Emergency Operating Procedures with the newly developed mitigation strategies.

The team selected a number of mitigation strategies , conducted plant walkdowns with licensed operators and responsible plant staff , to assess the adequacy and completeness of the procedures; familiarity of operators with the procedure objectives and specific guidance; staging and compatibility of equipment ,

and the practicality of the operator actions prescribed by the procedures, consistent with the postulated scenarios.

The team verified that a preventive maintenance program had been established for the FLEX portable equipment and that periodic equipment inventories were in place and being conducted.

Additionally, the team examined the introductory and planned periodic/refresher training provided to the Operations and Fire Protection staffs most likely to be tasked with implementation of the FLEX mitigation strategies.

The team also reviewed the introductory and planned periodic training provided to the Emergency Response Organization personnel.

Documents reviewed are listed in the attachment.

b. Assessment Based on samples selected for review, the inspectors verified that the licensee satisfactorily implemented appropriate elements of the FLEX strategy as described in the plant specific submittals and the associated safety evaluation and determined that the licensee is generally in compliance with NRC Order EA-12-049. The inspectors verified that the licensee satisfactorily:

Developed and issued FLEX Support Guidelines (FSG s) to implement the FLEX strategies for postulated external events; Integrated their FSGs into their existing plant procedures such that entry into and departure from the FSGs are clear when using existing plant procedures; Protected FLEX equipment from site-specific hazards; Developed and implemented adequate testing and maintenance of FLEX equipment to ensure their availability and capability; Trained their staff to assure personnel proficiency in the mitigation of beyond-design-basis events; and Developed means to ensure that the necessary off-site FLEX equipment will be available from off-site locations.

The inspectors verified that non-compliances with current licensing requirements, and other issues identified during the inspection were entered into the licensee's corrective action program.

c. Findings

No findings identified.

2. Spent Fuel Pool (SFP) Instrumentation

a. Inspection Scope

The team examined the licensee's newly installed spent fuel pool instrumentation. Specifically, the inspectors verified the sensors were installed as described in the plant specific submittals and the associated safety evaluation and that the cabling for the power supplies and the indications for each channel are physically and electrically separated.

Additionally, environmental conditions and accessibility of the instruments were evaluated.

Documents reviewed are listed in the attachment.

b. Assessment Based on samples selected for review, the inspectors determined that the licensee satisfactorily installed and established control of the spent fuel pool instrumentation as described in the plant specific submittals and the associated safety evaluation and determined that the licensee is generally in compliance with NRC Order EA-12-051. The inspectors verified that the licensee satisfactorily:

Installed the SFP instrumentation sensors, cabling , and power supplies to provide physical and electrical separation as described in the plant specific submittal and safety evaluation; Installed the SFP instrumentation display in the location, environmental conditions

, and accessibility as described in the plant specific submittals; and Trained their staff to assure personnel proficiency with the maintenance, testing, and use of the SFP instrumentation.

The inspectors verified that non-compliances with current licensing requirements, and other issues identified during the inspection were entered into the licensee's corrective action program.

c. Findings

No findings identified.

3. Staffing and Communication Request for Information

a. Inspection Scope

Through discussions with plant staff, review of documentation

, and plant walkdowns the team verified that the licensee has implemented required changes to staffing, communications equipment , and facilities to support an Extended Loss of All AC Power (ELAP) scenario as described in the licensee's staffing assessment and the NRC safety assessment.

The team also verified that the licensee has implemented dose assessment (including releases from spent fuel pools) capability using the licensee's site-specific dose assessment software and approach as described in the licensee's dose assessment submittal.

Documents reviewed are listed in the attachment.

b. Assessment The inspectors reviewed information provided in the licensee's multi-unit dose submittal and in response to the NRC's March 12, 2012, request for information letter and verified that the licensee satisfactorily implemented enhancements pertaining to Near-Term Task Force Recommendation 9.3 response to a large scale natural emergency event that results in an extended loss of all ac power to the site and impedes access to the site. The inspectors verified the following:

Licensee satisfactorily implemented required staffing change(s)to support an ELAP scenario; Emergency preparedness communications equipment and facilities are sufficient for dealing with an ELAP scenario; and Implemented dose assessment capabilities (including releases from spent fuel pools) using the licensee's site-specific dose assessment software and approach. The inspectors verified that non-compliances with current licensing requirements, and other issues identified during the inspection were entered into the licensee's corrective action program.

c. Findings

No findings identified.

4OA6 Meetings, Including Exit

Exit Meeting Summary

On November 16

, 2017, the inspectors presented the on-site inspection results in a management debrief to Mr. H. Hamzehee, Manager Regulatory Services

, and other members of the site staff. The inspectors completed an exit meeting with Mr. C. Murry , Acting Station Director, and other members of the site staff, via telephone on December 27

, 201 7 , who acknowledged the final results of the inspection.

The inspectors confirmed that proprietary information was not provided or examined during the inspection.

=SUPPLEMENTAL

INFORMATION=

KEY POINTS OF CONTACT

Licensee Personnel

B. Ashbrook, Security and Emergency Services Manager
M. Baker, Engineering Supervisor
T. Baldwin, Business Initiatives Chief
R. B aradar an, Acting Manager, Regulatory Services
J. Brancheau, Operations Shift Forman
K. Bych, Manager, Engineering
A. Chitwood, Operations

Shift Manager

C. Christensen, Emergency Preparedness
W. Conklin, FLEX Engineer
D. Esminger, Chief, Fire Department
M. Frauenheim, Process Improvement Manager
F. Gaber, FLEX Program Owner, Arizona Public Service
S. Guess, Manager, Operations
H. Hamzehee, Manager, Regulatory Services
J. Harker, Manager, Maintenance and Technical Training
S. Kirvin, Manager, Security
S. Leke, Nuclear Operator
D. Madson, Acting Compliance Supervisor
S. Maze, Fukushima Program Supervisor
M. McCoy, NRC Interface, Regulatory Services
J. Morris, Regulatory Services Supervisor
C. Murry, Acting Station Director
A. Peck, Engineering Director
D. Phillips, Security Operations Support
G. Reed, Beyond Design Basis Project Manager
B. Simpson, Manager, Operations Training
A. Sorensen, Regulatory Services Engineer
D. Spaulding, Strategic Projects Contractor
D. Ven tr es ca, Security Operations supervisor
R. Waltos, Assistant engineering Director
A. Warwick, Supervisor, Emergency Planning
T. Wernet, Assistant Chief, Fire Department
D. Yoder, FLEX Engineer

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Closed

2515/191 TI Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/ Multi-Unit Dose Assessment Plans

LIST OF DOCUMENTS REVIEWED

Calculations

Number Title Revision
STA-294 Fukushima Emergency Pump Sizing

Drawings

Number Title Revision 8920 Model 500F Globe Valve Union Bonnet
AA 347139 Emergency Operations Facility
900004146, Sheet
FSG 99 Posting
OP1.DC23 Control
6/29/2016
900004146, Sheet
FSG 99 Posting
OP1.DC23 Control
6/29/2016

Miscellaneous Documents

Number Title Revision DCM T-45 Diverse and Flexible Coping Strategies (FLEX) 1 DCM T-45, Appendix A
Strategy S

-9, Communications Strategy

DN 50813278
FLEX PMCR: EAFW Pumps
10/21/2015
EDT 4*1278
Security Fence NMOD: FLEX RWR Strategy (NMOD
68038941) 7/24/2015 PG&E Letter
DCL-15-117 Response to March 12, 2012,
NRC 10 CFR
50.54(f) Request for Information Regarding Recommendation 9.3, Resubmittal of Phase 2 Staffing Assessment
10/28/2015
PG&E Letter DCL

-16-003 Pacific Gas and Electric Company's Notification of Full Compliance with Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond

-Design-Basis External Events (Order Number

EA-12-049) for Diablo Canyon Power Plant Unit 1
01/05/2016
PG&E Letter DCL

-16-077 Pacific Gas and Electric Company's Notification of

Full Compliance with Commission Order Modifying Licenses with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (Order Number
EA-12-049) for Diablo Canyon Power Plant Units 1 and 2
7/28/2016

Miscellaneous Documents

Number Title Revision
NEI 12-06 Diverse and Flexible Coping Strategies (FLEX)
Implementation Guide
NRC Letter ML16349A386
Diablo Canyon Power Plant, Unit Nos. 1 and 2

- Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA

-12-049 and EA

-12-051 (CAC Nos. MF0958, MF0959, MF0963, and

MF0964) 12/28/2016
Diablo Canyon Power Plant Beyond Design Basis Validation of the FLEX Time Sensitive Actions Units 1

and 2 4

Diablo Canyon Power Plant Emergency Plan

- Section 5, Organizational Control of Emergencies

4.18
FLEX Maintenance Plan Frequency Spreadsheet

{None}

FLEX Equipment Status Board (per
FS1.ID4), various dates 6/02/2016 10/05/2017
10/16/2017
10/19/2017
11/14/2017
MIDAS Demonstration Report: Combined Accident Runs (DRILL)
11/16/2017
SAFER Response Plan for Diablo Canyon Power Plant Operation and Maintenance Manual

- STARS Alliance PG&E Fukushima

- 150kW

Operation and Maintenance Manual

- STARS Alliance PG&E Fukushima

- 275kW

SIMPLEX Infinity 200kW Portable Load Bank
EATON Doub le-Throw Safety Switch Spent Fuel Pool Instrumentation System Westinghouse Standard Product Technical Manual Spent Fuel Pool Instrumentation System Configuration

- Unit 1

Installation Instructions for Westinghouse Spent Fuel Pool Instrumentation System Equipment Mounting & Termination Installation Instructions for Westinghouse Spent Fuel Pool Instrumentation System Power

-Up & Acceptance

Miscellaneous Documents

Number Title Revision Testing
Spent Fuel Pool Instrumentation System Westinghouse Torque Specification Spent Fuel Pool Instrumentation System Westinghouse Specialty Tools List Spent Fuel Pool Instrumentation System Westinghouse Standard Product Integrated Function Test Procedure Spent Fuel Pool Instrumentation System Westinghouse Calibration Procedure

Notifications

(Corrective Action Program Documents)

50950327*
50950367*
50950415*
50950417*
50950447*
50950592*
50950613*
50950615*
50950624*
50950628*
50950634*
50950673*
50950674*
50950536*
50950575*
50950576*
50950619*
50950675*
50950677*
50937019
50946852
50646319
50880784
50904294
50950628*
Preventative Maintenance Activities Number Title Revision WO 64175685

-0010 Annual Inspection/Test of Emergency AFW Pump 1

10/13/2017
WO 64175685

-0010 Annual Inspection/Test of Emergency AFW Pump 1 10/13/2017

WO 64175685

-0020 Annual Inspection/Test of Emergency ASW Pump 1

10/13/2017
WO 64175685

-0040 Annual Inspection/Test of Raw Water Pump 1

10/13/2017
Preventative Maintenance Activities Number Title Revision WO 64175685

-0050 Annual Inspection/Test of FLEX 480V Safety Function Support (Distribution Panel) 1

10/12/2017
WO 64175685

-0060 Annual Inspection/Test of FLEX 480V Safety Function Support (Distribution Panel) 4

10/12/2017
WO 64175685

-0070 Annual Inspection/Test of 275KW FLEX 480V Diesel Generator 1

10/12/2017
WO 64175685

-0080 Annual Inspection/Test of 20KW FLEX 120/240V Diesel Driven Generator FDEG5

10/12/2017
WO 64177475

-0010 Quarterly Inspection/Test of 275KW FLEX 480V Diesel Generator 2

11/10/2017
WO 64177475

-0020 Quarterly Inspection/Test of 150KW FLEX 480V Diesel Generator

11/10/2017
WO 64177475

-0030 Quarterly Inspection/Test of 20KW FLEX 120/240V Diesel Driven Generator FDEG6

11/09/2017
WO 64177475

-0050 Quarterly Inspection/Test of Emergency ASW Pump 2

11/10/2017
WO 64177475

-0060 Quarterly Inspection/Test of Raw Water Reservoir Pump 0-2

11/09/2017
WO 64177475

-0070 Quarterly Inspection/Test of Emergency AFW Pump

0-2
11/09/2017
WO 64177475

-0090 Quarterly Inspection/Test of Portable Diesel Fuel Oil Caddy 0-2

11/06/2017
WO 641810 91-0100 6 Month Inspection/Test of Emergency RCS Makeup Pump 0-1 4/20/2017 WO 64181091

-0200 6 Month Inspection/Test of Emergency RCS Makeup Pump 0-2 4/20/2017 WO 64181091

-0300 6 Month Inspection/Test of Emergency RCS Makeup Pump 0-3 3/13/2017

Procedures

Number Title Revision
AD4.ID4 Temporary Storage Process
EOP
ECA-0.0 Loss of All Vital AC Power (Unit 1)
EOP
ECA-0.0 Loss of All Vital AC Power (Unit 2)
EP R-2 Release of Airborne Radioactive Materials Initial Assessment
EP
RB-16 Operating Instructions for the EARS Computer Program 14 FS1 FLEX and SFP Instrumentation Program
FS1.ID1 FLEX Strategy Management

Procedures

Number Title Revision
FS1.ID2 Spent Fuel Pool Level Instrumentation Management
FS1.ID4 FLEX Equipment Status and Availability
FLEX Support Guideline 01
Long Term RCS Inventory Control
FLEX Support Guideline 02
Alternate AFW Suction Source
FLEX Support Guideline 03 (Unit 1)
Alternate Low Pressure Feedwater
FLEX Support Guideline 03 (Unit 2)
Alternate Low Pressure Feedwater
FLEX Support Guideline 04

(Unit 1) ELAP DC Bus Load Shed and Management

FLEX Support Guideline 04

(Unit 2) ELAP DC Bus Load Shed and Management

FLEX Support Guideline 05
Initial Assessment and FLEX Equipment Staging
1A FLEX Support Guideline 08
Alternate RCS Boration
FLEX Support Guideline 09
Low Decay Heat Temperature Control
FLEX Support Guideline 10 (Unit 1)
Accumulator Isolation
FLEX Support Guideline 10 (Unit 2)
Accumulator Isolation
FLEX Support Guideline 11
Alternate SFP Makeup and Cooling 1A FLEX Support Guideline 12
Alternate Containment Cooling
FLEX Support Guideline 14 (Unit 1)
Shutdown RCS Makeup

Procedures

Number Title Revision FLEX Support Guideline 14 (Unit 2)
Shutdown RCS Makeup
FLEX Support Guideline 40
Component Cooling Water Alignment for ELAP
FLEX Support Guideline 41
Refill Fire Water Storage Tank with FLEX Equipment
FLEX Support Guideline 42
Establishing the FLEX Suction Header Water Supply
FLEX Support Guideline 43
Staging FLEX Equipment
FLEX Support Guideline 44
Site Debris Removal 1 FLEX Support Guideline 45 (Unit 1)
Supplying Power to SI Accumulator and RHR Valves
FLEX Support Guideline 45 (Unit 2)
Supplying Power to SI Accumulator and RHR Valves
FLEX Support Guideline 47
Operation of FLEX Communications Equipment
FLEX Support Guideline 49 (Unit1)
Align RCS Injection for Inventory / Boration
FLEX Support Guideline 49 (Unit2)
Align RCS Injection for Inventory / Boration
FLEX Support Guideline 50 (Unit 1)
Align Injection to Normal Charging During Reflux
FLEX Support Guideline 50 (Unit 2)
Align Injection to Normal Charging During Reflux
FLEX Support Guideline 51
Pacing Emergency ASW Pumps in Service
FLEX Support Guideline 54

(Unit 1) Placing 480V Loads in Service

FLEX Support Guideline 54

(Unit 2) Placing 480V Loads in Service

Procedures

Number Title Revision FLEX Support Guideline 56
Supply FLEX 480V Power to Telecommunications Equipment 1 FLEX Support Guideline 57
Fueling FLEX Equipment
FLEX Support Guideline 58

(Unit 1) Preparing 4kV Bus for Service

FLEX Support Guideline 58

(Unit 2) Preparing 4kV Bus for Service

FLEX Support Guideline 59

(Unit 1) Placing 4kV Bus in Service

FLEX Support Guideline 59

(Unit 2) Placing 4kV Bus in Service

FLEX Support Guideline 60
Local Manual Operation of 10% Steam Dumps
FLEX Support Guideline 61
Restarting Turbine Driven AFW Pump After Overspeed Trip 0 FLEX Support Guideline 62
Local Closing of MSIVs
FLEX Support Guideline 63
Establishing Forced FLEX Guidelines
FLEX Support Guideline 98
FLEX ERO Guidance for BDB Event Response Draft - 0 FLEX Support Guideline 99
FLEX Equipment Operating Guides
MA1.ID27 Preventive Maintenance Program
MP T-BDB-001 BDB Communications Equipment Inventory
OP AP
SD-1 Loss of AC Power
TS3.ID2 Licensing Basis Impact Evaluations
Training Documents Number Title Revision
Enrollment and Completion Report for EQIP

-0022 November 13, 2017

Fire Training FLEX Presentation

{None} ECTP 1702 ERO Requalification Training on FSGs for ERO

-TSC, EOF Leaders, ERO

-TSC Engineers, and Emergency Response Unit

2017
EDP 912 FLEX Support Guidelines

{None}

EQIP-0022 Wheel Loader Participant's Guide

{None} ESP 4Q2012

2012 ESP Continuing Training

- Fukushima Project 0 JITTOP 1608

FLEX Equipment Status
0A MDCT 1502E
Electrical Maintenance Continuing Training 2015
2015 MSCT 1401 Fukushima Design Changes Overview
2014 R151C3 FLEX - The First 24 Hours
0A R156C6 Licensed Operator Continuing Training

- In-Plant Walkdown Package (FLEX)

2015 R161C11 Oasis FLEX Dynamic Learning Activity
TU 1443 2014 ESP Continuing Training

- Introduction to FLEX Systems

2014
ML18025A000
SUNSI Review:
ADAMS:
Non-Publicly Available
Non-Sensitive
Keyword:
NRC-002 By:
JMM/rdr
Yes
No
Publicly Available
Sensitive
OFFICE SRI:EB2 S PE: PBA PE:IPAT SRI: PBA BC: PBA
NAME JMateychick
RAlexander
EUribe CNewport MHaire
SIGNATURE /RA/ /RA-E/ /RA/ /RA-E/ /RA/
DATE 1/22/18 1/17/2018 1/24/18 1/22/18 1/24/18