|
---|
Category:Inspection Plan
MONTHYEARIR 05000395/20240052024-08-22022 August 2024 Updated Inspection Plan for Virgil C. Summer Nuclear Station - Report 05000395/2024005 ML24157A3352024-06-0606 June 2024 – Notification of an NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000395-2024404 and Request for Information ML24022A1202024-01-22022 January 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000395/2024403) IR 05000395/20230052023-08-23023 August 2023 Updated Inspection Plan for Virgil C. Summer Nuclear Station (Report 05000395 2023005) ML23131A1492023-05-10010 May 2023 2023 V.C. Summer Commercial Grade Dedication Inspection Information Request IR 05000395/20220062023-03-0101 March 2023 Annual Assessment Letter for Virgil C. Summer Nuclear Station (Report 05000395/2022006) ML23055A0992023-02-24024 February 2023 Final - Virgil C. Summer - Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000395/20220052022-08-26026 August 2022 Updated Inspection Plan for Virgil C. Summer - Report 05000395/2022005 ML22075A0482022-03-16016 March 2022 V.C. Summer Nuclear Station - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000395/2022401 IR 05000395/20210062022-03-0202 March 2022 Annual Assessment Letter for Virgil C. Summer Unit 1 (Report No 05000395/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections IR 05000395/20200062021-03-0303 March 2021 Annual Assessment Letter for Virgil C. Summer Station, Unit 1 Report 05000395/2020006 ML21050A0012021-02-18018 February 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML21043A1402021-02-11011 February 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20190062020-03-0303 March 2020 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - NRC Report 05000395/2019006 IR 05000395/20190052019-08-28028 August 2019 Updated Inspection Plan for Virgil C. Summer Nuclear Station, Unit 1 - (Report 05000395/2019005) ML19155A2752019-06-0404 June 2019 VC Summer 2019003 Rad Safety Inspection Document Request ML19066A3792019-03-0707 March 2019 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20180062019-03-0404 March 2019 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 Report 05000395/2018006, Report 05000395/2018402, Report 05000395/2018501 ML18240A2122018-08-27027 August 2018 VC Summer Emailed Information Request EB3 RP 2018004 IR 05000395/20180052018-08-23023 August 2018 Updated Inspection Plan for Virgil C. Summer Nuclear Station, Unit 1, (Report 05000395/2018005) IR 05000395/20170062018-02-28028 February 2018 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2017006, Report 05000395/2017402, Report 05000395/2017501 ML17234A2422017-08-21021 August 2017 Updated Inspection Plan ML17150A4552017-05-30030 May 2017 Notification of Virgil C. Summer Design Bases Assurance Inspection - NRC Inspection Report 05000395/2017007 ML17142A1882017-05-19019 May 2017 Virgil C.Summer Emergency Preparedness Inspection and Request for Information Dated: May 19, 2017 IR 05000395/20160062017-03-0101 March 2017 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2016006 IR 05000395/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - NRC Inspection Report 05000395/2016005 ML16130A8192016-05-0404 May 2016 Notification of Inspection and Request for Information IR 05000395/20150052015-09-0101 September 2015 Mid-Cycle Letter for Virgil C. Summer Generating Station Unit 1 - NRC Assessment Report 05000395/2015005 IR 05000395/20140012015-03-0404 March 2015 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2014001 ML14245A2002014-09-0202 September 2014 V.C. Summer Mid-Cycle Ltr 2014 ML14175A5762014-06-24024 June 2014 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20130012014-03-0404 March 2014 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2013001 ML13246A1412013-09-0303 September 2013 Mid Cycle Assessment Letter IR 05000395/20120012013-03-0404 March 2013 Annual Assessment Letter for Summer Nuclear Station, Unit 1, Report 05000395/2012001 ML12248A1172012-09-0404 September 2012 Mid Cycle Assessment Letter Summer 2012 ML1206505962012-03-0505 March 2012 EOC Report 22 ML1124400632011-09-0101 September 2011 Report 22 - Summer ML1106304142011-03-0404 March 2011 V. C. Summer, Inspection/Activity Plan, 03/01/2011 - 06/30/2012, Report 22 ML1024403162010-09-0101 September 2010 Report 22 - 2010 Mid Cycle Inspection/Activity Plan ML1006208862010-03-0303 March 2010 Report 22 - 2010001, Inspection/Activity Plan ML0924403682009-09-0101 September 2009 Inspection/Activity Plan, 09/01/2009 - 12/31/2010 ML0906304762009-03-0404 March 2009 Enclosure - Summer Inspection / Activity Plan (03/01/2009 - 06/30/2010) ML0824609582008-09-0202 September 2008 Inspection Activity Plan - 09/02/2008 - 12/31/2009 IR 05000395/20080012008-03-0303 March 2008 Annual Assessment Letter (IR 05000395-08-001) ML0724802462007-08-31031 August 2007 Inspection / Activity Plan 09/01/2007 - 03/31/2009, Report 22 ML0706003462007-03-0101 March 2007 Inspection / Activity Plan for 03/01/2007 - 09/30/2007 RC-07-0021, Inspection and Mitigation Plan/Schedule of Alloy 82/182 Pressurizer Butt Welds (C-04-1719)2007-01-31031 January 2007 Inspection and Mitigation Plan/Schedule of Alloy 82/182 Pressurizer Butt Welds (C-04-1719) ML0624303732006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan, 09/01/06 - 03/31/08 ML0606104122006-03-0202 March 2006 Inspection / Activity Plan, 03/01/2006 - 09/30/2007 2024-08-22
[Table view] Category:Letter
MONTHYEARML24256A2322024-10-22022 October 2024 Relief Request RR-5-P1 Charging/Safety Injection Pumps ML24255A3152024-10-22022 October 2024 Relief Request RR-5-V2 Regarding Pressure Isolation Valves ML24250A0782024-10-22022 October 2024 Relief Request RR-5-V1 Regarding Service Water Return Header Check Valves 05000395/LER-2024-002, Loss of Control Room Emergency Filtration System2024-10-15015 October 2024 Loss of Control Room Emergency Filtration System ML24290A1052024-10-0707 October 2024 Core Operating Limits Report VCSNS Unit 1 Cycle 29, Revision 0 ML24274A1942024-09-26026 September 2024 (Vcsns), Unit 1 Subsequent License Renewal Application (SLRA) First 10 CFR 54.21(b) Annual Amendment IR 05000395/20244042024-09-26026 September 2024 Cyber Security Inspection Report 05000395-2024404 - Public ML24267A0552024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24221A2112024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0592024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0642024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0542024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) IR 05000395/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000395/2024402 IR 05000395/20240052024-08-22022 August 2024 Updated Inspection Plan for Virgil C. Summer Nuclear Station - Report 05000395/2024005 ML24190A4012024-08-19019 August 2024 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application - Dominion Energy Letter Dated May 30, 2024 IR 05000395/20240022024-08-12012 August 2024 Integrated Inspection Report 05000395/2024002 ML24180A0062024-08-0505 August 2024 Issuance of Amendment No. 227 to Modify Technical Specification 3.8.3.1 to Increase Completion Time for 120-Volt A.C. Vital Busses ML24218A3002024-08-0101 August 2024 Environmental Review Response to NRC Requests for Additional Information and Response to NRC Requests for Confirmation of Information Set 1 ML24158A3882024-07-31031 July 2024 Issuance of Amendment No. 226 to Change Emergency Plan Staff Augmentation Times and Relocate Emergency Operations Facility ML24162A3292024-07-0505 July 2024 Letter to E Carr - V.C. Summer Unit 1 - Summary of the May 2024 Audit Regarding the Environmental Review of the Subsequent License Renewal Application IR 05000395/20240112024-06-26026 June 2024 – Comprehensive Engineering Team Inspection Report 05000395/2024011 ML24178A1192024-06-25025 June 2024 Update to License Amendment Request- Inverter Allowed Outage Time (AOT) Extension ML24177A1382024-06-25025 June 2024 Aging Management Audit Report- VC Summer, Unit 1 - Subsequent License Renewal Application ML24185A1902024-06-25025 June 2024 Submittal of Updated Final Safety Analysis Report, Revision 24 ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24171A0152024-06-17017 June 2024 Update to Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Set 2 Safety Review ML24157A3352024-06-0606 June 2024 – Notification of an NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000395-2024404 and Request for Information ML24155A2042024-05-31031 May 2024 Proposed Alternative Request RR-24-123, Containment Unbonded Post-Tensioning System Inservice Inspection Requirements ML24155A1462024-05-30030 May 2024 Update to Subsequent License Renewal Application (SLRA) -Response to NRC Request for Additional Information Set 1 Response to NRC Request for Confirmation of Information Set 1 and Supplement 3 ML24143A1792024-05-22022 May 2024 Special Report 2024-001-01 for Virgil C. Summer Nuclear Station (Vcsns), Unit 1, Waste Gas System Inoperability ML24141A2822024-05-20020 May 2024 (Vcsns), Unit 1 - License Amendment Request - Emergency Response Organization (ERO) Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes IR 05000395/20240012024-05-10010 May 2024 Integrated Inspection Report 05000395/2024001 ML24129A2002024-05-0606 May 2024 Update to Subsequent License Renewal Application, Supplement 2 IR 05000395/20240402024-05-0101 May 2024 95001 Supplemental Inspection Report 05000395/2024040 and Follow-Up Assessment Letter ML24121A1002024-04-29029 April 2024 Response to Request for Additional Information Regarding Alternative Request RR-5-V2 ML24120A2072024-04-29029 April 2024 Submittal of Annual Radiological Environmental Operating Report ML24116A2052024-04-23023 April 2024 Annual Radioactive Effluent Release Report ML24109A1792024-04-19019 April 2024 Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML24108A0392024-04-18018 April 2024 Letter to E Carr-V.C. Summer Unit 1- Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application 05000395/LER-2024-001, (Vcsns), Unit 1, Automatic Actuation of B Emergency Diesel Generator2024-04-17017 April 2024 (Vcsns), Unit 1, Automatic Actuation of B Emergency Diesel Generator ML24108A0672024-04-17017 April 2024 Submittal of Summary for Condition of the Service Water Intake Structure Provided in Accordance with License Condition 2.C.5.d ML24100A7312024-04-0909 April 2024 Personnel Exposure and Monitoring Annual Report ML24095A2072024-04-0101 April 2024 Update to Subsequent License Renewal Application (SLRA) Supplement 1 ML24087A2182024-03-26026 March 2024 (Vcsns), Unit 1 - License Amendment Request - Emergency Response Organization (ERO) Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes - Response to Request. ML24087A2262024-03-26026 March 2024 License Amendment Request - Inverter Allowed Outage Time Extension Response to Request for Additional Information ML24088A2062024-03-26026 March 2024 Annual Operating Report 2024-09-26
[Table view] |
Inspection Report - Summer - 2020006 |
---|
|
|
Text
March 3, 2021
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR VIRGIL C. SUMMER NUCLEAR STATION, UNIT 1 - REPORT 05000395/2020006
Dear Mr. Stoddard:
The Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance assessment of Virgil C. Summer Nuclear Station, Unit 1, reviewing performance indicators (PIs),
inspection results, and enforcement actions from January 1, 2020 through December 31, 2020.
This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.
The NRC determined the performance at Virgil C. Summer Nuclear Station, Unit 1, during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2022.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the February 1, 2021 memo, Calendar Year 2021 Inspection Guidance During COVID-19 Telework Restrictions (ML21027A274).
For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 301-415-2934 with any questions you have regarding this letter.
Sincerely,
/RA/
Booma Venkataraman, Acting Chief Reactor Projects Branch 3 Division of Reactor Projects Docket Nos.: 50-395 License Nos.: NPF-12 Enclosure:
Summer Inspection/Activity Plan (03/01/2022 - 12/31/2022)
cc Distribution via ListServ 2 SUBJECT: ANNUAL ASSESSMENT LETTER FOR VIRGIL C. SUMMER NUCLEAR STATION, UNIT 1 - REPORT 05000395/2020006 DATED: March 3, 2021 DISTRIBUTION:
M. Kowal, RII L. Gibson, RII S. Price, RII OE MAIL RIDSNRRDROS PUBLIC RidsNrrPMSummer Resource ROPassessment Resource ROPreports Resource ADAMS Accession No. ML21061A245 OFFICE RII: DRP RII: DRP RII: DRP NAME J. Hamman A/ Wilson B. Venkataraman DATA 2/24/21 2/24/21 3/3/21 OFFICAL RECORD COPY
IP 22 Inspection Activity Plan Report Summer 03/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count SECURITY BASELINE INSPECTION 1 1 02/28/2021 03/05/2021 IP 71130.02 000734 Access Control 1 02/28/2021 03/05/2021 IP 71130.05 000737 Protective Strategy Evaluation 1 02/28/2021 03/05/2021 IP 71130.09 001656 Security Plan Changes 1 02/28/2021 03/05/2021 IP 71151 001338 Performance Indicator Verification EMERGENCY PREPAREDNESS EXERCISE 5 1 03/01/2021 03/05/2021 IP 71114.01 000716 Exercise Evaluation 1 03/01/2021 03/05/2021 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 03/01/2021 03/05/2021 IP 71151 001397 Performance Indicator Verification PROBLEM IDENTIFICATION & RESOLUTION 4 1 04/26/2021 04/30/2021 IP 71152B 000747 Problem Identification and Resolution 1 05/10/2021 05/14/2021 IP 71152B 000747 Problem Identification and Resolution TARGET SET INSPECTION 2 1 06/01/2021 06/04/2021 IP 71130.14 000743 Review of Power Reactor Target Sets DESIGN BASES ASSURANCE INSPECTION (PROGRAMS) 3 1 06/07/2021 06/11/2021 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements 1 06/21/2021 06/25/2021 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements SECURITY BASELINE INSPECTION 2 1 07/12/2021 07/16/2021 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1 07/12/2021 07/16/2021 IP 71130.07 000739 Security Training SUMMER REQUAL INSPECTION 2 1 07/19/2021 07/23/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance RP PUBLIC RAD SAFETY AND TRANSPORTATION BASELINE INSPECTION 2 1 08/02/2021 08/06/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1 08/02/2021 08/06/2021 IP 71124.07 000731 Radiological Environmental Monitoring Program 1 08/02/2021 08/06/2021 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &
Transportation 1 08/02/2021 08/06/2021 IP 71151 000746 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report Summer 03/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count SUMMER INITIAL LICENSE EXAM 3 1 08/02/2021 08/06/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1 09/06/2021 09/17/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
UNIT 1 IN-SERVICE INSPECTION 1 1 10/11/2021 10/15/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
UNIT 1 POST-APPROVAL LICENSE RENEWAL PHASE 1 1 1 10/18/2021 10/22/2021 IP 71003 000687 Post-Approval Site Inspection for License Renewal RP OCCUPATIONAL BASELINE INSPECTION 2 1 10/18/2021 10/22/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 10/18/2021 10/22/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1 10/18/2021 10/22/2021 IP 71151 000746 Performance Indicator Verification POST-APPROVAL LICENSE RENEWAL PHASE 2 5 1 01/31/2022 02/04/2022 IP 71003 000687 Post-Approval Site Inspection for License Renewal 1 02/14/2022 02/18/2022 IP 71003 000687 Post-Approval Site Inspection for License Renewal SECURITY BASELINE INSPECTION 1 1 02/07/2022 02/11/2022 IP 71130.02 000734 Access Control 1 02/07/2022 02/11/2022 IP 71130.09 001656 Security Plan Changes 1 02/07/2022 02/11/2022 IP 71151 001338 Performance Indicator Verification EMERGENCY PREPAREDNESS PROGRAM INSPECTION 2 1 04/11/2022 04/15/2022 IP 71114.02 000717 Alert and Notification System Testing 1 04/11/2022 04/15/2022 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1 04/11/2022 04/15/2022 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 04/11/2022 04/15/2022 IP 71114.05 000720 Maintenance of Emergency Preparedness 1 04/11/2022 04/15/2022 IP 71151 001397 Performance Indicator Verification RP OCCUPATIONAL AND PUBLIC RAD SAFETY INSPECTION 4 1 06/20/2022 06/24/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 06/20/2022 06/24/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation 1 06/20/2022 06/24/2022 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1 06/20/2022 06/24/2022 IP 71124.07 000731 Radiological Environmental Monitoring Program This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report Summer 03/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count RP OCCUPATIONAL AND PUBLIC RAD SAFETY INSPECTION 4 1 06/20/2022 06/24/2022 IP 71151 000746 Performance Indicator Verification TRIENNIAL HEAT SINK PERFORMANCE 1 1 07/11/2022 07/15/2022 IP 71111.07T 000700 Heat Sink Performance SUMMER INITIAL LICENSE EXAM 4 1 08/08/2022 08/12/2022 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1 09/12/2022 09/23/2022 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
NFPA 805 TRIENNIAL FIRE PROTECTION INSPECTION 4 1 08/15/2022 08/19/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
1 08/29/2022 09/02/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
EVALUATIONS OF CHANGES, TESTS AND EXPERIMENTS 3 1 10/24/2022 10/28/2022 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.