ML082460958

From kanterella
Jump to navigation Jump to search
Inspection Activity Plan - 09/02/2008 - 12/31/2009
ML082460958
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 09/02/2008
From:
NRC/RGN-II/DRP/RPB5
To:
References
Download: ML082460958 (2)


Text

Summer Inspection / Activity Plan 09/02/2008 - 12/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 09/02/2008 09:19:23 Report 22 10 EB1-CDBI

- COMPONENT DESIGN BASIS INSPECTION Baseline Inspections Component Design Bases Inspection 09/08/2008 09/12/2008 1

7111121 IP 1

PSB1-EP

- EMERGENCY PREPAREDNESS INSPECTION Baseline Inspections Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 10/27/2008 10/31/2008 1

2515/175 IP EP Baseline Inspection Alert and Notification System Testing 10/27/2008 10/31/2008 1

7111402 IP EP Baseline Inspection Emergency Response Organization Augmentation Testing 10/27/2008 10/31/2008 1

7111403 IP EP Baseline Inspection Emergency Action Level and Emergency Plan Changes 10/27/2008 10/31/2008 1

7111404 IP EP Baseline Inspection Correction of Emergency Preparedness Weaknesses and Deficiencies 10/27/2008 10/31/2008 1

7111405 IP Baseline Inspections Drill/Exercise Performance 10/27/2008 10/31/2008 1

71151-EP01 IP Baseline Inspections ERO Drill Participation 10/27/2008 10/31/2008 1

71151-EP02 IP Baseline Inspections Alert & Notification System 10/27/2008 10/31/2008 1

71151-EP03 IP 3

OL EXAM

- INITIAL EXAM PREP Not Applicable SUMMER/JANUARY 2009 EXAM AT POWER FACILITIES 01/05/2009 01/09/2009 1

V23297 3

OL EXAM

- INITIAL EXAM - WEEK 1 Not Applicable SUMMER/JANUARY 2009 EXAM AT POWER FACILITIES 02/02/2009 02/06/2009 1

V23297 3

OL EXAM

- INITIAL EXAM - WEEK 2 Not Applicable SUMMER/JANUARY 2009 EXAM AT POWER FACILITIES 02/09/2009 02/13/2009 1

V23297 3

PSB1EP

- EMERGENCY PREPAREDNESS EXERCISE EP Baseline Inspection Exercise Evaluation 03/30/2009 04/03/2009 1

7111401 IP EP Baseline Inspection Emergency Action Level and Emergency Plan Changes 03/30/2009 04/03/2009 1

7111404 IP Baseline Inspections Drill/Exercise Performance 03/30/2009 04/03/2009 1

71151-EP01 IP Baseline Inspections ERO Drill Participation 03/30/2009 04/03/2009 1

71151-EP02 IP Baseline Inspections Alert & Notification System 03/30/2009 04/03/2009 1

71151-EP03 IP 1

PSB1-RP

- TI 2515/173 GROUND WATER Generic Safety Inspection Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 04/27/2009 05/01/2009 1

2515/173 IP 3

PSB1-RP

- RADIATION PROTECTION PUBLIC INSPECTION Baseline Inspections Radiation Monitoring Instrumentation and Protective Equipment 05/18/2009 05/22/2009 1

7112103 IP Baseline Inspections Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 05/18/2009 05/22/2009 1

7112201 IP Baseline Inspections Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 05/18/2009 05/22/2009 1

7112203 IP Baseline Inspections Occupational Exposure Control Effectiveness 05/18/2009 05/22/2009 1

71151-OR01 IP Baseline Inspections RETS/ODCM Radiological Effluent 05/18/2009 05/22/2009 1

71151-PR01 IP 1

EB3ISI

- INSERVICE INSPECTION Baseline Inspections Inservice Inspection Activities - PWR 10/26/2009 10/30/2009 1

7111108P IP 1

EB3TI172

- TI-172 RCS DM BUTT WELDS Generic Safety Inspection Reactor Coolant System Dissimiliar Metal Butt Welds 10/26/2009 10/30/2009 1

2515/172 IP This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Summer Inspection / Activity Plan 09/02/2008 - 12/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 09/02/2008 09:19:23 Report 22 1

PSB1-RP

- RP ACCESS CONTROLS INSPECTION ( OUTAGE)

Baseline Inspections Access Control to Radiologically Significant Areas 11/02/2009 11/06/2009 1

7112101 IP This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.