IR 05000395/2002002

From kanterella
Jump to navigation Jump to search
IR 05000395-02-002 on 03/31/2002 - 06/29/2002, South Carolina Electric & Gas Co., Virgil C. Summer Nuclear Station. Non-Routine Evolution and Events - Reactor Trip
ML022110092
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 07/29/2002
From: Plisco L
Division Reactor Projects II
To: Byrne S
South Carolina Electric & Gas Co
References
EA-02-122 IR-02-002
Download: ML022110092 (45)


Text

July 29, 2002

SUBJECT:

VIRGIL C. SUMMER NUCLEAR STATION - NRC INTEGRATED INSPECTION REPORT NO. 50-395/02-02; EXERCISE OF ENFORCEMENT DISCRETION

Dear Mr. Byrne:

On June 29, 2002, the NRC completed an inspection at your Virgil C. Summer Nuclear Station.

The enclosed report documents the inspection findings which were discussed on July 3, 2002, with Mr. G. Halnon and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection, two findings were identified which were determined to be of very low safety significance (Green). One finding was determined to involve a violation of regulatory requirements. However, because the issue has been entered into your corrective action program, the NRC is treating the issue as a non-cited violation, in accordance with Section VI.A.1 of the NRCs Enforcement Policy. If you deny the non-cited violation, you should provide a response with the basis for your denial, within 30 days of the date of this inspection report, to the United States Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Virgil C. Summer Nuclear Station.

The second finding, involving a failure to establish a fitness for duty procedure consistent with 10 CFR 26.24 requirements, was also a violation of regulatory requirements. Based on your prompt corrective action, the apparent generic nature of the issue, and conflicting NRC guidance regarding the 10 CFR 26.24 requirements, and after consultation with the Director, Office of Enforcement, the NRC has determined that the exercise of enforcement discretion is warranted in accordance with Section VII.B.6 of the "General Statement of Policy and Procedure for NRC Enforcement Actions - May 1, 2000, NUREG-1600, as amended on November 3, 2000 (65 Federal Register 59274), and February 16, 2001 (65 Federal Register 79139) (Enforcement Policy). Accordingly, a Notice of Violation will not be issued.

SCE&G

In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Loren R. Plisco, Division Director Division of Reactor Projects Docket No.: 50-395 License No.: NPF-12

Enclosure:

Integrated Inspection Report No. 50-395/02-02

REGION II==

Docket No.:

50-395 License No.:

NPF-12 Report No.:

50-395/02-02 Licensee:

South Carolina Electric & Gas (SCE&G) Company Facility:

Virgil C. Summer Nuclear Station Location:

P. O. Box 88 Jenkinsville, SC 29065 Dates:

March 31, 2002 through June 29, 2002 Inspectors:

M. Widmann, Senior Resident Inspector

M. King, Resident Inspector

K. Green-Bates, Project Engineer, RII (Sections 1R06 and 1R07)

W. Bearden, Reactor Inspector, RII (Section 1R08.2)

K. Davis, Physical Security Specialist, RII (Sections 3PP1, 3PP2, 4OA1.6, 4OA5.2)

J. Wallo, Physical Security Specialist, RII (Sections 3PP1, 3PP2, 4OA1.6, 4OA5.2)

R. Hamilton, Radiation Specialist, RII (Sections 2OS1, 2OS2, 2PS2, 4OA1.4 and 4OA1.5)

E. Testa, Senior Radiation Specialist, RII (Sections 2OS1, 2OS2, 2PS2, 4OA1.4 and 4OA1.5)

F. Wright, Senior Radiation Specialist, RII (Sections 2OS1, 2OS2, 2PS2, 4OA1.4 and 4OA1.5)

Approved by:

K. Landis, Chief, Reactor Projects Branch 5 Division of Reactor Projects

Attachment:

Supplemental Information

SUMMARY OF FINDINGS IR 05000395/02-02, on 03/31/2002 - 06/29/2002, South Carolina Electric & Gas Co., Virgil C.

Summer Nuclear Station. Non-Routine Evolution and Events - Reactor Trip.

The inspection was conducted by the resident inspectors, a project engineer, three radiation specialists, two physical security specialists, and a reactor inspector. The inspection identified two Green findings involving one non-cited violation and one violation for which the NRC exercised enforcement discretion. The significance of the findings is indicated by its color (Green, White, Yellow, Red) using IMC 0609 Significance Determination Process (SDP).

Findings for which the SDP does not apply are indicated by No Color or by the severity level of the applicable violation. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described at its Reactor Oversight Process website at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

A.

Inspector Identified Finding Cornerstone: Mitigating Systems

Green. The inspectors identified one non-cited violation evaluated as having very low safety significance (Green) for inadequate design control of the main feedwater pumps recirculation flow control valves logic. The licensee failed to implement proper design control through adequate testing of the digital control logic modification in order to fully understand the operation of the system. The design change to the circuit logic prevented the control room operators from having manual control of the valves which resulted in an automatic reactor trip. Post-modification testing did not identify the logic flaw in the recirculation valve controls.

The safety significance of the finding was very low because the reactor trip response and emergency feedwater system availability were unaffected by the design flaw in the circuit logic. (Section 1R14)

Enforcement Discretion. The inspectors identified a violation for failure to establish a fitness for duty procedure consistent with 10 CFR 26.24 requirements. Based on prompt corrective action, the apparent generic nature of the issue, and conflicting NRC guidance regarding the 10 CFR 26.24 requirements, the NRC has determined that the exercise of enforcement discretion is warranted in a

Inspection Report

ISI

Inservice Inspection

kV

kilovolt

LCO

Limiting Conditions for Operations

LER

Licensee Event Report

LOCA

Loss of Coolant Accident

LOR

Licensed Operator Requalification

MWe

Megawatt - electric

Attachment

MDEFW

Motor Driven Emergency Feedwater

MFW

Main Feedwater

MR

Maintenance Rule

MSIP

Mechanical Stress Improvement Process

MWR

Maintenance Work Request

NCN

Nonconformance Notice

NCV

Non-Cited Violation

NDE

Nondestructive Examination

NI

Nuclear Instrumentation

NPF

Nuclear Power Facility [Type of license]

NRC

Nuclear Regulatory Commission

NRR

Office of Nuclear Reactor Regulation

NSSS

Nuclear Steam Supply System

NUREG

NRC Technical Report Designation

OS

Occupational Safety

PAP

Personnel Access Portal

PI

Performance Indicator

PMT

Post Maintenance Testing

PTP

Preventive Test Procedure

PS

Public Safety

PWSCC

Primary Water Stress-Corrosion Cracking

QSP

Quality Systems Procedure

RB

Reactor Building

RBCU

Reactor Building Cooling Unit

RCA

Radiation Control Area

RCS

Reactor Coolant System

RF

Refueling Outage

RII

Region II [NRC]

RPV

Reactor Pressure Vessel

RWP

Radiation Work Permit

SCE&G

South Carolina Electric and Gas

SDP

Significance Determination Process

SG

Steam Generator

SOP

System Operating Procedure

SSCs

Structures, Systems or Components

STP

Surveillance Test Procedure

SW

Service Water

Tavg

Temperature - average

TB

Turbine Building

TI

Temporary Instruction

TS

Technical Specification

TWR

Technical Work Record

URI

Unresolved Item

UT

Ultrasonic

VHRA

Very High Radiation Area

WO

Work Order

Attachment

List of Documents Reviewed

Section 1R04 - Equipment Alignment (71111.04)

Procedures

SOP-211, Emergency Feedwater System

SOP-306, Emergency Diesel Generator

SOP-307, Diesel Generator Fuel Oil System

SOP-505, Control Building Ventilation System

FSAR Sections 6.4.1, 8.3.1, 9.5.4, and 10.4.9

TS Sections 3.7.1.2, 3.7.6, and 3.8.1

D-302-085, Emergency Feedwater (Nuclear)

D-302-351, Diesel Generator - Fuel Oil

D-302-353, Diesel Generator - Miscellaneous Services

D-302-842, Chilled Water - To Cooling Coils

D-912-140, Control Room Normal and Emergency Air Handling System

Section 1R06 Flood Protection Measures (71111.06)

Corrective Action Reports

CERs 0-C-00-0875, 00-1386, 00-1825, 01-0936, 01-1332, 01-1914, 02-0567, 02-0568, 02-

0611, 02-0788, 02-0916, 02-1110, 02-1111, 02-1417, 02-0949, 02-1154, 02-1329, 02-1359,

and 02-1741.

Procedures

V. C. Summer Station Administrative Procedure SAP-107; 10CFR50.59 Review

Process, dated 5/8/01

V. C. Summer Emergency Operating Procedure EOP 17.1; Response to Reactor

Building Flooding, dated 11/17/94

V. C. Summer Engineering Services Procedure ES-425; Cumulative Effects Program,

dated 6/18/01

V. C. Summer Engineering Services Procedure ES-416; Design Modification Change

Process and Control, Revision 0

V. C. Summer Engineering Guideline EC-01; Design Input Development, dated 3/2/01

Other Documents

V. C. Summer Flood Calculation DC03290-002; Flooding Evaluation for all Areas not

Affected by the FW System, Revision 6

V. C. Summer Evaluation Request 21007, Service Water System Pressure, dated

2/14/86

Attachment

V. C. Summer TS 6.8.1, Procedures and Programs, Regulatory Guide 1.33," dated

4/11/02

V. C. Summer 50.59 Design Package Implementation MRF 31738 dated 11/14/84

Section 1R07 Heat Sink Performance (71111.07)

Corrective Action Reports

CERs 0-C-01-0788, 01-0144, 01-1788, and 02-2087.

Other Documents

V. C. Summer Calculation PGT-2001-1711, Evaluation of the V.C. Summer Reactor

Building Cooling Units Thermal Performance Test Tube Side Turbulent Flow

Requirements, Revision 0

V. C. Summer Calculation PGT-2002-1003, Evaluation of the V.C. Summer Reactor

Building Cooling Unit Cooling Water Flow Instrument Bias Uncertainty, Revision 0

V. C. Summer Preventive Test Procedure PTP-213.002; Service Water System Heat

Exchanger Data Collection, Revision 0

V. C. Summer Station Administrative Procedure SAP-1255; Service Watr System

Reliability Optimization Program, Revision 0

Sections 1R08.1 and 1RO8.2 - Inservice Inspection Activities (71111.08)

Procedures

Westinghouse Procedure MRS-SSP-1300, Field Service Procedure for Application of

the Mechanical Stress Improvement Process (MSIP)

Procedure, SCEG-UT-89-4, Ultrasonic Straight Beam Examination, Revision 2

Procedure, SCEG-UT-89-9, Manual Ultrasonic Examination of Vessel Welds Less Than

or Equal to 2 Inches, Revision 2

Procedure, SCEG-UT-89-10, Ultrasonic Examination of Class 1 and 2 Vessel Welds

Over 2 Inches Thick, Revision 2

Procedure, SCEG-UT-89-11, Manual Ultrasonic Examination of Ferritic Piping Welds,

Revision 0

Procedure, SCEG-UT-89-1, Manual Ultrasonic Examination of Austenitic Piping Welds,

Revision 0

Westinghouse Procedure, CGE-ISI-208, Remote Eddy Current Examination of Reactor

Vessel Nozzle to Pipe Welds Inside Surface for Virgil C. Summer, Revision 1

Westinghouse Procedure, CGE-ISI-254, Remote Ultrasonic Examination of Reactor

Vessel for Virgil C. Summer, Revision 2

Other Documents

Virgil C. Summer letter dated April 17, 2002, Inspection/MSIP Plan for VCSNS Hot Leg

Welds

Attachment

AEA Technology Engineering Services, MSIP Parameters for B and C Hot Leg Nozzles,

January 2002

Virgil C. Summer Special Report SPR 2000-005, Steam Generator Tube inspection

during Refueling Outage 12, dated November 8, 2000

Condition Evaluation Report (CER) 0-C-02-1067, Snubber functional test results within

degraded acceptance criteria

CER 0-C-02-1073, Excessive inspection failures on component cooling supports

requiring inspection scope expansion

CER 0-C-02-1078, Snubber piping attachment gap exceeded acceptance criteria

CER 0-C-02-1108, Rigid pipe support found misaligned

CER 0-C-02-1110, Rust and blistered paint identified during containment inspection

CER 0-C-02-1111, Elastomer cover over moisture barrier not properly adhering

CER 0-C-02-1181, Flow accelerated corrosion components turned over to QC without

proper preparation to allow inspection

CER 0-C-02-1267, As-found support hot measurement exceeded acceptance criteria

CER 0-C-02-1268, Drawing deficiency identified during snubber inspection

CER 0-C-02-1272, Snubber functional test results within degraded acceptance criteria

CER 0-C-02-1294, SG Blowdown piping snubber functional test results failed

acceptance criteria

CER 0-C-02-1296, Weld on component cooling heat exchanger did not meet

requirements

CER 0-C-02-1301, Weld on component cooling heat exchanger ready for QC fit up

inspection without proper preparation to allow inspection

CER 0-C-02-1308, Flaw identified in B hot leg nozzle weld during pre-MSIP WESDYNE

NDE activities

CER 0-C-02-1321, Welds turned over to QC without proper preparation to allow

inspection

CER 0-C-02-1328, Incorrect velocity slope line identified during snubber activation test

Section 2OS1 Access Controls to Radiologically Significant Areas (71121.01)

Procedures, Instructions, and Manuals

Health Physics Procedure (HPP), 157, Personnel Monitoring for Contamination,

Revision 9, 03/08/02

HPP-158, Contamination Control for Equipment and Materials, Revision 10, 12/18/01

HPP-160, Control and Posting of Radioactive Control Zones, Revision 10, 03/21/02

HPP-163, Qualification for the Use of Respiratory Protection Equipment, Revision 9,

01/09/01

HPP-302, Radiation and Contamination Survey Techniques, Revision 9, 06/23/98

HPP-401, Issuance, Termination and Use of RWPs and Standing RWPs, Revision14,

09/25/01

HPP-402, Radiological Survey Requirements and Controls for Reactor Building and

Incore Pit Entries, Revision 10, 06/20/00

HPP-403, Radiological Control for Nuclear Work Activities, Revision 8, 03/21/02

Attachment

HPP-405, Personnel Decontamination and Skin Dose Determination, Revision 14,

06/20/00

HPP-408, Fuel Movement Control, Revision 8, 08/09/99

HPP-410, Health Physics Routine Survey, Revision 8, 09/25/01

HPP-419, Electronic Dosimeter Alarm Setpoint, Revision 0, 10/31/01

Station Administrative Procedure (SAP) SAP-500 Health Physics Manual, Revision 11,

02/08/02

SAP-1167, NRC Performance Indicators, Revision 0

Radiation Work Permits (RWPs) reviewed and pre-job briefings attended

RWP 02-00045/001, Perform ISI to Include All Support Work (Insulation, Scaffold, Weld

Prep, Etc.)

RWP 02-00049/001, All Work Associated With Seal Table Thimble Cleaning to Include

Retracting Thimbles

RWP 02-00059/001, All Test Unit Activities Including STPs 215.008, 230.006A,B,C,D, &

E, All 250 Series, and Fire Service Testing

RWP 02-00063/001, All Work in the Pressurizer Cubicle to Include Manway

Removal/Replacement, PZR Safety, and Misc. Valve Work

RWP 02-00070/001, Reactor Head Work to Support Refueling

RWP 02-00071/001, RVLIS, CRDM Ductwork, NOZZLE Covers, NI Covers, Cavity Seal

Plate, Missile Shields, Detension, Tension Studs

RWP 02-00090/001, All Work Associated With Steam Generator Secondary Side

Inspections and Maintenance

Condition Evaluation Reports (CERs)

CER 0-C-02-1007, Individual was found to have trace amounts of radioactivity on his

pants and belt when he in-processed through dosimetry

CER 0-C-02-1010, During in-processing through Dosimetry, trace amounts of Co-60

and Co-58 on the lanyard

CER 0-C-02-1077, Low level radioactive material found on individuals lanyards when

in-processing through dosimetry

CER 0-C-02-1418, Low level radioactive material found at security portal

CER 0-C-02-1146, Low level radioactive material found upon exit count at the Whole

Body Count Room

Section 2OS2 As Low As Is Reasonably Achievable (71121.02)

Procedures, Instructions, and Manuals

Chemistry Procedure (CP), CP-614, Reactor Coolant Chemistry Control, Revision 11

CP-625, Degasification And Oxygenation of The Reactor Coolant System, Revision 8

HPP-150, Requirement For Issuance And Use of Personnel Dosimetry, Revision 8,

10/17/01

Attachment

HPP-151, Use of The Radiation Work Permit and Standing Radiation Work Permit,

Revision 8, 07/24/00

HPP-152, Radiation Control Area Access Control, Revision 8, 11/06/01

HPP-413, Diving Operations, Revision 2

HPP-719, Authorization and Control for Resin Transfer, Revision 4, 01/06/99

HPP-819, Temporary Shielding Evaluation, Installation, and Removal, Revision 11,

02/02/02

SAP-500, Health Physics Manual, Revision 11, 02/08/02

ALARA Packages /RWPs

02-0045, ISI-UT,PT, ETC. (MSIP not included)

02-0050, All Snubber Inspection

02-0053, MSIP (B&C Nozzle w / Spider Assembly Also) (Actual work not observed on

this RWP)

02-0059, All Test Group Work Except LLRT

02-0071, RVLIS, CRDM, Detension/Tension, Nozzle Covers Etc.

Miscellaneous Documents

Corporate ALARA Plan, Revision 10

FSAR Chapter 12 (Radiation Protection), Amendment 00-01, Dated 12/2000

Virgil C. Summer Nuclear Station, Health Physics and Radwaste Services, RF-12,

Outage Report

Attachment I, RF-12 Health Physics ALARA Report, A RCS Hot Leg Piping Inspection

and Repair

Virgil C. Summer Nuclear Station, RF-13 Outage, ALARA Plan, Issued 3/20/2002

QA-CHP-02-001, 2001 Annual ALARA Appraisal, February 7, 2002

Health Physics Field Operations, Self-Assessment Summary Report, QA-CHP-01-002,

Assessment Period, February 26 - March 2, 2001

VIRGIL C. SUMMER ALARA Action Plan, 4/01/2002

ALARA Committee Meeting Minutes, 1st QUARTER 2002, 02/05.02

ALARA Committee Job Review (pre-job), RWP 02-090, 05/7/02

Plan of the day schedule 05/06/02 (Outage Schedule)

Dose Printout by individual for Health Physics, Mechanical Maintenance, and Master-

Lee, 05/07/02

Condition Evaluation Reports (CERs)

CER 0-C-01-1901, Identified enhancements for ALARA program and ALARA Committee

CER 0-C-02-1169, CER written to formalize policy for ensuring ED alarms are

recognized when hearing protection is utilized consistent with the radiological hazards

that may be present

CER 0-C-02-1187, Electronic Dosimeter dose rate alarm-ED# 207401

CER 0-C-02-1241, Divers back pocket chamber was offscale when he exited the RCA

(Dose of less than 20 mrem estimated)

Attachment

CER 0-C-02-1273, Individual received electronic dosimeter dose rate alarm

CER 0-C-02-1315, Did not estimate man-rem for decon activity to support MSIP for

RWP 02-00043

CER 0-C-02-1388, Unnecessary exposure expended on attempts to repack XVG08085

CER 0-C-02-1416, Trace amounts of Co-58 on an exit count were not investigated in

accordance with guidance initiated for RF-13, but no procedure violation occurred

Section 2PS2 Radioactive Material Processing and Transportation (71122.02)

Procedures, Instructions, and Manuals

Engineering Services (ES) Procedure, ES-362, Radioactive Material Shipping

Inspection, Revision 7, 09/01/00

System Operating Procedure (SOP), SOP-108, Liquid Waste Processing System,

Revision 10, 03/12/99

HPP-703, Shipping Radioactive Material, Revision 13, 12/05/01

HPP-712, Classification of Radioactive Materials, Revision 9, 11/19/01

HPP-716.028, Transfer and De-watering Ion Exchange Resin and or Activated Charcoal

Filter Media Using the Scientific Ecology Group (SEG) Rapid De-watering System,

Revision 0, 12/09/99

HPP-716.029, 10-160B Cask Handling, Revision 0, 11/19/01

HPP-717, Sample Collection, Preparation and Analysis Techniques For Assuring

Compliance with 10 CFR Part 61, Revision 6, 12/09/99

SEG S.D.-P-03-046, Transfer and De-watering Ion Exchange Resin and or Activated

Charcoal Filter Media Using the SEG Rapid De-watering System, Revision 2, 11/22/93

Process Control Program-001, Process Control Program for Processing Wet Waste,

Revision 10, 03/12/99

Drawings

DURATEK Corporation Vendor Drawing DT-61, Radwaste Demineralizer Package

P&ID, Revision 2, 5/23/93

FSAR Figure 10.4-17, D302-362, Liquid Effluents from Nuclear Plant to Fairfield

Penstock, Revision 9, 08/01/96

FSAR Figure 11.2-2, Sheet 1, E-302-735, System Flow Diagram Waste Processing,

Revision 14, 01/19/01

FSAR Figure 11.2-2, Sheet 2, E-302-736, System Flow Diagram Waste Processing,

Revision 13, 09/13/97

FSAR Figure 11.2-2, Sheet 3, E-302-737, System Flow Diagram Waste Processing,

Revision 11, 10/11/01

FSAR Figure 11.2-2, Sheet 4, E-302-738, System Flow Diagram Waste Processing,

Revision 10, 12/19/01

FSAR Figure 11.2-2, Sheet 5, E-302-734, System Flow Diagram Waste Processing,

Revision 13, 03/05/01

Radioactive Shipment Documentation

Attachment

Virgil C. Summer 01-60, Radioactive Material, n.o.s, 7, UN2982,10-160 Poly HIC

Containing De-watered Bead Resin in 10 -160B Cask USA/9204/B(U)-85, 07/31/01

Virgil C. Summer 01-62, Radioactive Material, Type B(U) Package, Fissile Excepted, 7

UN2916, Ir-192 Radiography Source, 08/16/01

Virgil C. Summer 02-14, Radioactive Material, Type B(U) Package, 7, UN2916, Special

Form Ir-192, 03/06/02

Virgil C. Summer 02-20, Radioactive Material, Low Specific Activity (LSA), n.o.s., 7

UN2912, C-van Containing Dry Active Waste and One Liner of Charcoal Media,

03/26/02

Virgil C. Summer 02-31, Radioactive Material, Low Specific Activity, LSA, n.o.s, 7

UN9212, Contaminated Laundry and 2 boxes on Non Rad Modesty Clothing, 04/24/02

Virgil C. Summer 02-41, Radioactive Material, Surface Contaminated Object, SCO 7,

UN2913, Contaminated Equipment, 05/07/02

Miscellaneous Documents

Virgil C. Summer 1, FSAR, § 11, Radioactive Waste Management

Virgil C. Summer 10 CFR Part 61 Waste Stream Analysis Reports: (Primary Resin,

sampled 10/12/01; Nuclear Blow-down Resin, sampled 06/21/00; Reactor Coolant

Sample Filter, sampled 02/09/02; Seal Water Injection Filter, sampled 02/17/02; Spent

Fuel Pool Filter, sampled 02/20/02; Waste Water Charcoal Media, sampled 02/01/02;

Dry Active Waste, sampled 02/13/02; and Waste Water Resin, sampled 02/01/02)

Radioactive Shipment Record Log 2001 and 2002

Certificate of Compliance 9269, USA/9269/B(U)-85, Revision 3, Docket Number 71-

9269

Certificate of Compliance 9204, USA/9204/B(U)-85, Revision 7, Docket Number 71-

9204

Condition Evaluation Reports (CERs)

CER 0-C-01-2183, Unitech laundry truck arrived with tires unsuitable for radioactive

material transport, 11/27/01

CER 0-C-02-0281, Approximately 2000 gallons of Floor Drain Tank water was

inadvertently transferred to the Decon Pit Collection Tank, 02/07/02

CER 0-C-02-0570, Radiography source received in excess of site radiography license

limit, 03/08/02.

CER 0-C-02-1027, XDM-0040D vessel failure identified during resin reload, 04/19/02

CER 0-C-02-1030, XDM-0040A potential vessel failure identified during vessel reload,

04/18/02

CER 0-C-02-1213, Depleted demineralizers allowed chromated water to break through

to the floor drain while draining component cooling water in the Intermediate Building,

04/27/02

CER 0-C-02-1234, Chromated water observed being drained directly to floor drain

without being processed, 04/29/02

CER 0-C-02-1427, NRC inspectors identified need to procedurally control radioactive

shipment emergency and exclusive use instructions, 05/06/02

Attachment

CER 0-C-02-1423, Health physics did not adequately verify drivers qualification for

hauling hazardous material, 05/07/02

Sections 3PP1, 3PP2 - Access Authorization and Access Control (71130.01 and 71130.02)

Procedures

SAP-1005, Unescorted Access Authorization Program, Revision 7

SPP-210, Security Lock & Key Control, Revision 9

SPP-211, Security Key Card Control, Revision 7

SPP-224, Operational Testing of Security Access Control & Intrusion Detection System

Revision 4

SPP-228, Search Equipment Operational Test Procedure, Revision 4

SPP-213, Security Identification Badge Fabrication I Control, Revision 14

Fitness For Duty Procedure FFD-100, Revision 5, For Cause Testing Following

Accidents Involving Failures In Individual Performance Resulting In Personal Injury.

FFD-100, Revision 5, Attachment 1, Statement of Alcohol Consumption - Call In

FFD-100, Revision 5, Attachment 2, Change D, Emergency Recall Positive Result Form

FFD-100, Revision 5, Attachment 3, Change D, Request to Administer Drug/Alcohol

Test For Cause

Other Documents

Virgil C. Summer Physical Security Plan, Amendment 45

Virgil C. Summer Contingency Plan, Revision 10

Key and Lock Daily and Annual Inventory Logs

Semi-Annual Fitness for Duty Report, July - December, 2001