MONTHYEARML24022A1202024-01-22022 January 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000395/2024403) IR 05000395/20230052023-08-23023 August 2023 Updated Inspection Plan for Virgil C. Summer Nuclear Station (Report 05000395 2023005) ML23131A1492023-05-10010 May 2023 2023 V.C. Summer Commercial Grade Dedication Inspection Information Request IR 05000395/20220062023-03-0101 March 2023 Annual Assessment Letter for Virgil C. Summer Nuclear Station (Report 05000395/2022006) ML23055A0992023-02-24024 February 2023 Final - Virgil C. Summer - Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000395/20220052022-08-26026 August 2022 Updated Inspection Plan for Virgil C. Summer - Report 05000395/2022005 ML22075A0482022-03-16016 March 2022 V.C. Summer Nuclear Station - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000395/2022401 IR 05000395/20210062022-03-0202 March 2022 Annual Assessment Letter for Virgil C. Summer Unit 1 (Report No 05000395/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections IR 05000395/20200062021-03-0303 March 2021 Annual Assessment Letter for Virgil C. Summer Station, Unit 1 Report 05000395/2020006 ML21050A0012021-02-18018 February 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML21043A1402021-02-11011 February 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20190062020-03-0303 March 2020 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - NRC Report 05000395/2019006 IR 05000395/20190052019-08-28028 August 2019 Updated Inspection Plan for Virgil C. Summer Nuclear Station, Unit 1 - (Report 05000395/2019005) ML19155A2752019-06-0404 June 2019 VC Summer 2019003 Rad Safety Inspection Document Request ML19066A3792019-03-0707 March 2019 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20180062019-03-0404 March 2019 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 Report 05000395/2018006, Report 05000395/2018402, Report 05000395/2018501 ML18240A2122018-08-27027 August 2018 VC Summer Emailed Information Request EB3 RP 2018004 IR 05000395/20180052018-08-23023 August 2018 Updated Inspection Plan for Virgil C. Summer Nuclear Station, Unit 1, (Report 05000395/2018005) IR 05000395/20170062018-02-28028 February 2018 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2017006, Report 05000395/2017402, Report 05000395/2017501 ML17234A2422017-08-21021 August 2017 Updated Inspection Plan ML17150A4552017-05-30030 May 2017 Notification of Virgil C. Summer Design Bases Assurance Inspection - NRC Inspection Report 05000395/2017007 ML17142A1882017-05-19019 May 2017 Virgil C.Summer Emergency Preparedness Inspection and Request for Information Dated: May 19, 2017 IR 05000395/20160062017-03-0101 March 2017 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2016006 IR 05000395/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - NRC Inspection Report 05000395/2016005 ML16130A8192016-05-0404 May 2016 Notification of Inspection and Request for Information IR 05000395/20150052015-09-0101 September 2015 Mid-Cycle Letter for Virgil C. Summer Generating Station Unit 1 - NRC Assessment Report 05000395/2015005 IR 05000395/20140012015-03-0404 March 2015 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2014001 ML14245A2002014-09-0202 September 2014 V.C. Summer Mid-Cycle Ltr 2014 ML14175A5762014-06-24024 June 2014 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20130012014-03-0404 March 2014 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2013001 ML13246A1412013-09-0303 September 2013 Mid Cycle Assessment Letter IR 05000395/20120012013-03-0404 March 2013 Annual Assessment Letter for Summer Nuclear Station, Unit 1, Report 05000395/2012001 ML12248A1172012-09-0404 September 2012 Mid Cycle Assessment Letter Summer 2012 ML1206505962012-03-0505 March 2012 EOC Report 22 ML1124400632011-09-0101 September 2011 Report 22 - Summer ML1106304142011-03-0404 March 2011 V. C. Summer, Inspection/Activity Plan, 03/01/2011 - 06/30/2012, Report 22 ML1024403162010-09-0101 September 2010 Report 22 - 2010 Mid Cycle Inspection/Activity Plan ML1006208862010-03-0303 March 2010 Report 22 - 2010001, Inspection/Activity Plan ML0924403682009-09-0101 September 2009 Inspection/Activity Plan, 09/01/2009 - 12/31/2010 ML0906304762009-03-0404 March 2009 Enclosure - Summer Inspection / Activity Plan (03/01/2009 - 06/30/2010) ML0824609582008-09-0202 September 2008 Inspection Activity Plan - 09/02/2008 - 12/31/2009 IR 05000395/20080012008-03-0303 March 2008 Annual Assessment Letter (IR 05000395-08-001) ML0724802462007-08-31031 August 2007 Inspection / Activity Plan 09/01/2007 - 03/31/2009, Report 22 ML0706003462007-03-0101 March 2007 Inspection / Activity Plan for 03/01/2007 - 09/30/2007 RC-07-0021, Inspection and Mitigation Plan/Schedule of Alloy 82/182 Pressurizer Butt Welds (C-04-1719)2007-01-31031 January 2007 Inspection and Mitigation Plan/Schedule of Alloy 82/182 Pressurizer Butt Welds (C-04-1719) ML0624303732006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan, 09/01/06 - 03/31/08 ML0606104122006-03-0202 March 2006 Inspection / Activity Plan, 03/01/2006 - 09/30/2007 ML0524205142005-08-29029 August 2005 Inspection/Activity Plan - Summer - 09/01/05 - 03/31/07 ML0506107552005-03-0303 March 2005 Inspection / Activity Plan, 03/01/2005 - 09/30/2006 2024-01-22
[Table view] Category:Letter
MONTHYEARML24038A0322024-02-0707 February 2024 (Vcsns), Unit 1, 10 CFR 21 Report - Emergency Diesel Generator Flash Contactor Relay IR 05000395/20230042024-01-31031 January 2024 Integrated Inspection Report 05000395/2023004 ML24022A1582024-01-22022 January 2024 (Vcsns), Unit 1 - Reply to a Notice of Violation: EA-23-093 ML24022A1202024-01-22022 January 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000395/2024403) ML24018A0112024-01-18018 January 2024 CFR 21 Report Emergency Diesel Generator Fuel Oil Piping IR 05000395/20240112024-01-17017 January 2024 Notification of VC Summer Station Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000395/2024011 ML23361A1042023-12-21021 December 2023 Inservice Testing Program for Pumps and Valves Fifth Interval Update and Associated Relief and Alternative Requests IR 05000395/20230912023-12-21021 December 2023 Final Significance Determination of a White Finding and Notice of Violation and Assessment Followup Letternrc Inspection Report 05000395/2023091 ML23354A1802023-12-20020 December 2023 301 Examination Report with Cover Letter ML23347A0492023-12-12012 December 2023 Technical Specification Bases Changes Updated Through November 2023 ML23334A2462023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23334A2372023-11-30030 November 2023 (Vvsns), Unit 1 - Annual Commitment Change Summary Report ML23332A1942023-11-28028 November 2023 (Vcsns), Unit 1, Correction of Typographical Error in License Amendment Request - Inverter Allowed Outage Time (AOT) Extension ML23317A2242023-11-0909 November 2023 (Vcsns), Unit 1 - License Amendment Request - Inverter Allowed Outage Time (AOT) Extension ML23289A1172023-11-0303 November 2023 Tribal Request for Scoping Comments Concerning the Environmental Review of the V.C. Summer SLRA ML23289A1152023-11-0303 November 2023 Ltr to R. Nelson - Request for Scoping Comments Concerning the Environmental Review of the V.C. Summer SLRA ML23289A1162023-11-0303 November 2023 Ltr to W. Emerson - Request for Scoping Comments Concerning the Environmental Review of the V.C. Summer SLRA IR 05000395/20234032023-11-0101 November 2023 Material Control and Accounting Program Inspection Report 05000395/2023403 Cover IR 05000395/20230032023-11-0101 November 2023 Integrated Inspection Report 05000395/2023003 ML23284A1792023-10-16016 October 2023 Subsequent License Renewal Application Online Reference Portal ML23275A0142023-10-11011 October 2023 SLRA - Acceptance and Opportunity for Hearing - Letter ML23284A1662023-10-10010 October 2023 (Vcsns), Unit 1 - Request for Regulatory Conference; (EA-23-093) IR 05000395/20230902023-10-0404 October 2023 NRC Inspection Report 05000395/2023090 and Preliminary Yellow Finding and Apparent Violation IR 05000395/20230112023-09-27027 September 2023 Focused Engineering Inspection Report 05000395/2023011 ML23250A3112023-09-20020 September 2023 Request to Revise Reactor Vessel Material Surveillance Capsule Withdrawal Schedules ML23244A2352023-09-18018 September 2023 Request to Use a Subsequent Edition of the ASME Code, Section XI ML23230A0012023-09-15015 September 2023 Request to Use a Provision of a Previous Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for Non-Destructive Examinations ML23235A0432023-09-0505 September 2023 Receipt and Availability of the Subsequent License Renewal Application IR 05000395/20234012023-08-30030 August 2023 Security Baseline Inspection Report 05000395/2023401 ML23242A1192023-08-29029 August 2023 (Vcsns), Unit 1 - Inservice Inspection (ISI) Owner'S Activity Report (OAR) for Refueling Outage 27 ML23243B0362023-08-25025 August 2023 Request for FEMA Consultation on the Dominion Energy Proposal to Consolidate the Emergency Operations Facility for the Virgil C. Summer Nuclear Station Unit 1 IR 05000395/20230052023-08-23023 August 2023 Updated Inspection Plan for Virgil C. Summer Nuclear Station (Report 05000395 2023005) ML23233A1752023-08-17017 August 2023 Application for Subsequent Renewed Operating License IR 05000395/20230022023-08-14014 August 2023 Integrated Inspection Report - Integrated Inspection Report 05000395/2023002 and Apparent Violation IR 05000395/20230102023-08-12012 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000395/2023010 ML23207A1102023-07-26026 July 2023 NRC Regulatory Issues Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations IR 05000395/20234412023-07-17017 July 2023 95001 Supplemental Inspection Report 05000395/2023441 and Follow Up Assessment Letter ML23190A0012023-07-0909 July 2023 Special Report 2023-003 Inoperable Radiation Monitoring Instrumentation Channel ML23187A5092023-07-0606 July 2023 Request for Federal Emergency Management Agency Consultation on the Dominion Energy Proposal to Consolidate the Emergency Operations Facility for the Virgil C. Summer Nuclear Station Unit 1 ML23178A1682023-06-26026 June 2023 2022 Annual Report of Emergency Core Cooling System (ECCS) Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML23173A1052023-06-22022 June 2023 Special Report 2023-002 Inoperable Loose-Part Monitoring System Channel ML23163A2352023-06-12012 June 2023 Request to Use a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for the SPS Sixth Inservice Inspection (Isi) Intervals and VCSNS Fifth ISI Interval ML23159A2332023-06-0808 June 2023 License Amendment Request - Emergency Response Organization Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes ML23156A3092023-06-0505 June 2023 Requalification Program Inspection Virgil C. Summer Nuclear Station Unit 1 - 05000395/2023003 2024-02-07
[Table view] |
Inspection Report - Summer - 2008001 |
---|
|
|
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION II
rch 3, 2008
SUBJECT:
ANNUAL ASSESSMENT LETTER - VIRGIL C. SUMMER NUCLEAR STATION (NRC INSPECTION REPORT 05000395/2008001)
Dear Mr. Archie:
On February 6, 2008, the NRC staff completed its performance review of the Virgil C. Summer Nuclear Station. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2007. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only--Security Related Information" will include the security cornerstone review and resultant inspection plan.
Overall, Virgil C. Summer Nuclear Station operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRC=s Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. We also plan on conducting non-ROP inspections which include: TI 2515/171, Verification of Site Specific Implementation of B.5.b Phase 2 & 3 Mitigating Strategies; and TI 2515/172, Reactor Coolant System Dissimilar Metal Butt Welds.
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through June 30, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
SCE&G 2 In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (404) 562-4662 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Eugene Guthrie, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket No.: 50-395 License No.: NPF-12 Enclosure: Summer Inspection/Activity Plan (03/01/08 - 06/30/09)
cc w/encl.: (See page 3)
_________________________
OFFICE RII:DRP RII:DRP RII:DRP RII:DRP SIGNATURE /RA/ /RA/ /RA/ /RA/
NAME JDodson DArnertt LGarner EGuthrie DATE 2/28/08 2/27/08 3/3/08 3/3/08 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO
SCE&G 3 cc w/encl.:
Kathryn M. Sutton, Esq.
Morgan, Lewis & Bockius LLP Electronic Mail Distribution Henry J. Porter Assistant Director Division of Radioactive Waste Mgmt.
S.C. Department of Health and Environmental Control Electronic Mail Distribution Bruce L. Thompson Manager Nuclear Licensing (Mail Code 830)
South Carolina Electric & Gas Company Electronic Mail Distribution Thomas D. Gatlin General Manager Nuclear Plant Operations (Mail Code 303)
South Carolina Electric & Gas Company Electronic Mail Distribution
SCE&G 4 Letter to Jeffrey from Eugene F. Guthrie dated March 3, 2008 SUBJECT: ANNUAL ASSESSMENT LETTER - VIRGIL C. SUMMER NUCLEAR STATION NRC INSPECTION REPORT 05000395/2008001 Distribution w/encl.:
C. Evans, RII EICS (Part 72 Only)
L. Slack, RII EICS OE Mail (email address if applicable)
R. Martin, NRR RIDSNRRDIRS PUBLIC
Page 1 of 2 Summer 03/03/2008 08:12:34 Inspection / Activity Plan Report 22 03/01/2008 - 06/30/2009 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 5 1 IP 71152B Identification and Resolution of Problems 03/10/2008 03/14/2008 Baseline Inspections 1 IP 71152B Identification and Resolution of Problems 03/24/2008 03/28/2008 Baseline Inspections PSB1-RP - RADIATION PROTECTION PREINSPECTION VISIT 1 1 IP 7112101 Access Control to Radiologically Significant Areas 03/24/2008 03/26/2008 Baseline Inspections PSB1-RP - RADIATION PROTECTION OCCUPATIONAL WK1 3 1 IP 7112101 Access Control to Radiologically Significant Areas 04/28/2008 05/02/2008 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 04/28/2008 05/02/2008 Baseline Inspections 1 IP 7112202 Radioactive Material Processing and Transportation 04/28/2008 05/02/2008 Baseline Inspections 1 IP 71151-OR01 Occupational Exposure Control Effectiveness 04/28/2008 05/02/2008 Baseline Inspections 1 IP 71151-PR01 RETS/ODCM Radiological Effluent 04/28/2008 05/02/2008 Baseline Inspections EB3-ISI - SUMMER - ISI 1 1 IP 7111108P Inservice Inspection Activities - PWR 05/05/2008 05/09/2008 Baseline Inspections PSB1-RP - RADIATION PROTECTION OCCUPATIONAL WK2 3 1 IP 7112101 Access Control to Radiologically Significant Areas 05/05/2008 05/09/2008 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 05/05/2008 05/09/2008 Baseline Inspections 1 IP 7112202 Radioactive Material Processing and Transportation 05/05/2008 05/09/2008 Baseline Inspections 1 IP 71151-OR01 Occupational Exposure Control Effectiveness 05/05/2008 05/09/2008 Baseline Inspections 1 IP 71151-PR01 RETS/ODCM Radiological Effluent 05/05/2008 05/09/2008 Baseline Inspections TI-171 - B.5.B PHASE 2&3 4 1 IP 2515/171 Verification of Site Specific Implementation Of B.5.b Phase 2 & 3 Mitigating Strategies 06/23/2008 06/27/2008 Generic Safety Inspection EB3TI172 - TI-172 1 1 IP 2515/172 Reactor Coolant System Dissimiliar Metal Butt Welds 07/07/2008 07/11/2008 Generic Safety Inspection EB1-CDBI - COMPONENT DESIGN BASIS INSPECTION 10 1 IP 7111121 Component Design Bases Inspection 07/28/2008 08/01/2008 Baseline Inspections 1 IP 7111121 Component Design Bases Inspection 08/11/2008 08/15/2008 Baseline Inspections 1 IP 7111121 Component Design Bases Inspection 08/25/2008 08/29/2008 Baseline Inspections 1 IP 7111121 Component Design Bases Inspection 09/08/2008 09/12/2008 Baseline Inspections OL RQ - REQUAL INSPECTION 2 1 IP 7111111B Licensed Operator Requalification Program 08/11/2008 08/15/2008 Baseline Inspections PSB1-EP - EP INSP 1 1 IP 7111402 Alert and Notification System Testing 09/22/2008 09/26/2008 EP Baseline Inspection 1 IP 7111403 Emergency Response Organization Augmentation Testing 09/22/2008 09/26/2008 EP Baseline Inspection 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 09/22/2008 09/26/2008 EP Baseline Inspection 1 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 09/22/2008 09/26/2008 EP Baseline Inspection This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Summer 03/03/2008 08:12:34 Inspection / Activity Plan Report 22 03/01/2008 - 06/30/2009 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PSB1-EP - EP INSP 1 1 IP 71151-EP01 Drill/Exercise Performance 09/22/2008 09/26/2008 Baseline Inspections 1 IP 71151-EP02 ERO Drill Participation 09/22/2008 09/26/2008 Baseline Inspections 1 IP 71151-EP03 Alert & Notification System 09/22/2008 09/26/2008 Baseline Inspections OL EXAM - INITIAL EXAM PREP 3 1 V23297 SUMMER/JANUARY 2009 EXAM AT POWER FACILITIES 01/05/2009 01/09/2009 Not Applicable OL EXAM - INITIAL EXAM - WEEK 1 3 1 V23297 SUMMER/JANUARY 2009 EXAM AT POWER FACILITIES 02/02/2009 02/06/2009 Not Applicable OL EXAM - INITIAL EXAM - WEEK 2 3 1 V23297 SUMMER/JANUARY 2009 EXAM AT POWER FACILITIES 02/09/2009 02/13/2009 Not Applicable PSB1EP - EP EXERCISE 3 1 IP 7111401 Exercise Evaluation 03/30/2009 04/03/2009 EP Baseline Inspection 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 03/30/2009 04/03/2009 EP Baseline Inspection 1 IP 71151-EP01 Drill/Exercise Performance 03/30/2009 04/03/2009 Baseline Inspections 1 IP 71151-EP02 ERO Drill Participation 03/30/2009 04/03/2009 Baseline Inspections 1 IP 71151-EP03 Alert & Notification System 03/30/2009 04/03/2009 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.