MONTHYEARIR 05000395/20240052024-08-22022 August 2024 Updated Inspection Plan for Virgil C. Summer Nuclear Station - Report 05000395/2024005 ML24157A3352024-06-0606 June 2024 – Notification of an NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000395-2024404 and Request for Information ML24022A1202024-01-22022 January 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000395/2024403) IR 05000395/20230052023-08-23023 August 2023 Updated Inspection Plan for Virgil C. Summer Nuclear Station (Report 05000395 2023005) ML23131A1492023-05-10010 May 2023 2023 V.C. Summer Commercial Grade Dedication Inspection Information Request IR 05000395/20220062023-03-0101 March 2023 Annual Assessment Letter for Virgil C. Summer Nuclear Station (Report 05000395/2022006) ML23055A0992023-02-24024 February 2023 Final - Virgil C. Summer - Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000395/20220052022-08-26026 August 2022 Updated Inspection Plan for Virgil C. Summer - Report 05000395/2022005 ML22075A0482022-03-16016 March 2022 V.C. Summer Nuclear Station - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000395/2022401 IR 05000395/20210062022-03-0202 March 2022 Annual Assessment Letter for Virgil C. Summer Unit 1 (Report No 05000395/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections IR 05000395/20200062021-03-0303 March 2021 Annual Assessment Letter for Virgil C. Summer Station, Unit 1 Report 05000395/2020006 ML21050A0012021-02-18018 February 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML21043A1402021-02-11011 February 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20190062020-03-0303 March 2020 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - NRC Report 05000395/2019006 IR 05000395/20190052019-08-28028 August 2019 Updated Inspection Plan for Virgil C. Summer Nuclear Station, Unit 1 - (Report 05000395/2019005) ML19155A2752019-06-0404 June 2019 VC Summer 2019003 Rad Safety Inspection Document Request ML19066A3792019-03-0707 March 2019 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20180062019-03-0404 March 2019 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 Report 05000395/2018006, Report 05000395/2018402, Report 05000395/2018501 ML18240A2122018-08-27027 August 2018 VC Summer Emailed Information Request EB3 RP 2018004 IR 05000395/20180052018-08-23023 August 2018 Updated Inspection Plan for Virgil C. Summer Nuclear Station, Unit 1, (Report 05000395/2018005) IR 05000395/20170062018-02-28028 February 2018 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2017006, Report 05000395/2017402, Report 05000395/2017501 ML17234A2422017-08-21021 August 2017 Updated Inspection Plan ML17150A4552017-05-30030 May 2017 Notification of Virgil C. Summer Design Bases Assurance Inspection - NRC Inspection Report 05000395/2017007 ML17142A1882017-05-19019 May 2017 Virgil C.Summer Emergency Preparedness Inspection and Request for Information Dated: May 19, 2017 IR 05000395/20160062017-03-0101 March 2017 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2016006 IR 05000395/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - NRC Inspection Report 05000395/2016005 ML16130A8192016-05-0404 May 2016 Notification of Inspection and Request for Information IR 05000395/20150052015-09-0101 September 2015 Mid-Cycle Letter for Virgil C. Summer Generating Station Unit 1 - NRC Assessment Report 05000395/2015005 IR 05000395/20140012015-03-0404 March 2015 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2014001 ML14245A2002014-09-0202 September 2014 V.C. Summer Mid-Cycle Ltr 2014 ML14175A5762014-06-24024 June 2014 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20130012014-03-0404 March 2014 Annual Assessment Letter for Virgil C. Summer Nuclear Station, Unit 1 - Report 05000395/2013001 ML13246A1412013-09-0303 September 2013 Mid Cycle Assessment Letter IR 05000395/20120012013-03-0404 March 2013 Annual Assessment Letter for Summer Nuclear Station, Unit 1, Report 05000395/2012001 ML12248A1172012-09-0404 September 2012 Mid Cycle Assessment Letter Summer 2012 ML1206505962012-03-0505 March 2012 EOC Report 22 ML1124400632011-09-0101 September 2011 Report 22 - Summer ML1106304142011-03-0404 March 2011 V. C. Summer, Inspection/Activity Plan, 03/01/2011 - 06/30/2012, Report 22 ML1024403162010-09-0101 September 2010 Report 22 - 2010 Mid Cycle Inspection/Activity Plan ML1006208862010-03-0303 March 2010 Report 22 - 2010001, Inspection/Activity Plan ML0924403682009-09-0101 September 2009 Inspection/Activity Plan, 09/01/2009 - 12/31/2010 ML0906304762009-03-0404 March 2009 Enclosure - Summer Inspection / Activity Plan (03/01/2009 - 06/30/2010) ML0824609582008-09-0202 September 2008 Inspection Activity Plan - 09/02/2008 - 12/31/2009 IR 05000395/20080012008-03-0303 March 2008 Annual Assessment Letter (IR 05000395-08-001) ML0724802462007-08-31031 August 2007 Inspection / Activity Plan 09/01/2007 - 03/31/2009, Report 22 ML0706003462007-03-0101 March 2007 Inspection / Activity Plan for 03/01/2007 - 09/30/2007 RC-07-0021, Inspection and Mitigation Plan/Schedule of Alloy 82/182 Pressurizer Butt Welds (C-04-1719)2007-01-31031 January 2007 Inspection and Mitigation Plan/Schedule of Alloy 82/182 Pressurizer Butt Welds (C-04-1719) ML0624303732006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan, 09/01/06 - 03/31/08 ML0606104122006-03-0202 March 2006 Inspection / Activity Plan, 03/01/2006 - 09/30/2007 2024-08-22
[Table view] Category:Letter
MONTHYEARML24256A2322024-10-22022 October 2024 Relief Request RR-5-P1 Charging/Safety Injection Pumps ML24255A3152024-10-22022 October 2024 Relief Request RR-5-V2 Regarding Pressure Isolation Valves ML24250A0782024-10-22022 October 2024 Relief Request RR-5-V1 Regarding Service Water Return Header Check Valves 05000395/LER-2024-002, Loss of Control Room Emergency Filtration System2024-10-15015 October 2024 Loss of Control Room Emergency Filtration System ML24290A1052024-10-0707 October 2024 Core Operating Limits Report VCSNS Unit 1 Cycle 29, Revision 0 ML24274A1942024-09-26026 September 2024 (Vcsns), Unit 1 Subsequent License Renewal Application (SLRA) First 10 CFR 54.21(b) Annual Amendment IR 05000395/20244042024-09-26026 September 2024 Cyber Security Inspection Report 05000395-2024404 - Public ML24267A0552024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24221A2112024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0592024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0642024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0542024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) IR 05000395/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000395/2024402 IR 05000395/20240052024-08-22022 August 2024 Updated Inspection Plan for Virgil C. Summer Nuclear Station - Report 05000395/2024005 ML24190A4012024-08-19019 August 2024 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application - Dominion Energy Letter Dated May 30, 2024 IR 05000395/20240022024-08-12012 August 2024 Integrated Inspection Report 05000395/2024002 ML24180A0062024-08-0505 August 2024 Issuance of Amendment No. 227 to Modify Technical Specification 3.8.3.1 to Increase Completion Time for 120-Volt A.C. Vital Busses ML24218A3002024-08-0101 August 2024 Environmental Review Response to NRC Requests for Additional Information and Response to NRC Requests for Confirmation of Information Set 1 ML24158A3882024-07-31031 July 2024 Issuance of Amendment No. 226 to Change Emergency Plan Staff Augmentation Times and Relocate Emergency Operations Facility ML24162A3292024-07-0505 July 2024 Letter to E Carr - V.C. Summer Unit 1 - Summary of the May 2024 Audit Regarding the Environmental Review of the Subsequent License Renewal Application IR 05000395/20240112024-06-26026 June 2024 – Comprehensive Engineering Team Inspection Report 05000395/2024011 ML24178A1192024-06-25025 June 2024 Update to License Amendment Request- Inverter Allowed Outage Time (AOT) Extension ML24177A1382024-06-25025 June 2024 Aging Management Audit Report- VC Summer, Unit 1 - Subsequent License Renewal Application ML24185A1902024-06-25025 June 2024 Submittal of Updated Final Safety Analysis Report, Revision 24 ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24171A0152024-06-17017 June 2024 Update to Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Set 2 Safety Review ML24157A3352024-06-0606 June 2024 – Notification of an NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000395-2024404 and Request for Information ML24155A2042024-05-31031 May 2024 Proposed Alternative Request RR-24-123, Containment Unbonded Post-Tensioning System Inservice Inspection Requirements ML24155A1462024-05-30030 May 2024 Update to Subsequent License Renewal Application (SLRA) -Response to NRC Request for Additional Information Set 1 Response to NRC Request for Confirmation of Information Set 1 and Supplement 3 ML24143A1792024-05-22022 May 2024 Special Report 2024-001-01 for Virgil C. Summer Nuclear Station (Vcsns), Unit 1, Waste Gas System Inoperability ML24141A2822024-05-20020 May 2024 (Vcsns), Unit 1 - License Amendment Request - Emergency Response Organization (ERO) Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes IR 05000395/20240012024-05-10010 May 2024 Integrated Inspection Report 05000395/2024001 ML24129A2002024-05-0606 May 2024 Update to Subsequent License Renewal Application, Supplement 2 IR 05000395/20240402024-05-0101 May 2024 95001 Supplemental Inspection Report 05000395/2024040 and Follow-Up Assessment Letter ML24121A1002024-04-29029 April 2024 Response to Request for Additional Information Regarding Alternative Request RR-5-V2 ML24120A2072024-04-29029 April 2024 Submittal of Annual Radiological Environmental Operating Report ML24116A2052024-04-23023 April 2024 Annual Radioactive Effluent Release Report ML24109A1792024-04-19019 April 2024 Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML24108A0392024-04-18018 April 2024 Letter to E Carr-V.C. Summer Unit 1- Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application 05000395/LER-2024-001, (Vcsns), Unit 1, Automatic Actuation of B Emergency Diesel Generator2024-04-17017 April 2024 (Vcsns), Unit 1, Automatic Actuation of B Emergency Diesel Generator ML24108A0672024-04-17017 April 2024 Submittal of Summary for Condition of the Service Water Intake Structure Provided in Accordance with License Condition 2.C.5.d ML24100A7312024-04-0909 April 2024 Personnel Exposure and Monitoring Annual Report ML24095A2072024-04-0101 April 2024 Update to Subsequent License Renewal Application (SLRA) Supplement 1 ML24087A2182024-03-26026 March 2024 (Vcsns), Unit 1 - License Amendment Request - Emergency Response Organization (ERO) Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes - Response to Request. ML24087A2262024-03-26026 March 2024 License Amendment Request - Inverter Allowed Outage Time Extension Response to Request for Additional Information ML24088A2062024-03-26026 March 2024 Annual Operating Report 2024-09-26
[Table view] |
Inspection Report - Summer - 2017006 |
---|
|
|
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION ary 28, 2018
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR VIRGIL C. SUMMER NUCLEAR STATION, UNIT 1 - REPORT 05000395/2017006, REPORT 05000395/2017402, REPORT 05000395/2017501
Dear Mr. Lippard:
The Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance assessment of Virgil C. Summer Nuclear Station, Unit 1, reviewing performance indicators (PIs),
inspection results, and enforcement actions from January 1, 2017 through December 31, 2017.
This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.
The NRC determined the performance at Virgil C. Summer Nuclear Station, Unit 1, during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2019. This updated inspection plan now includes planned security inspections which were formerly transmitted under separate correspondence. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
The NRC will perform Temporary Instruction (TI) 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 404-997-4603 with any questions you have regarding this letter.
Sincerely,
/RA/
Randall A. Musser, Chief Reactor Projects Branch 3 Division of Reactor Projects Docket Nos.: 50-395 License Nos.: NPF-12 Enclosure:
Summer Inspection/Activity Plan (03/01/2018 - 12/31/2019)
cc Distribution via ListServ SUBJECT: ANNUAL ASSESSMENT LETTER FOR VIRGIL C. SUMMER NUCLEAR STATION, UNIT 1 - REPORT 05000395/2017006, REPORT 05000395/2017402, REPORT 05000395/2017501 February 28, 2018 DISTRIBUTION:
M. Kowal, RII K. Sloan, RII OE MAIL RIDSNRRDIRS PUBLIC RidsNrrPMSummer Resource ROPassessment.Resource ROPreports Resource Institute of Nuclear Power Operations (INPO)
ADAMS Accession No. ML18059A203 OFFICE RII:DRP RII:DRP NAME LPressley RMusser DATA 2/21/2018 2/22/2018 OFFICAL RECORD COPY
IP 22 Inspection Activity Plan Report Summer 03/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count MITIGATING STRATEGIES 4 1 03/05/2018 03/09/2018 TI 2515/191 000509 Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 SECURITY BASELINE INSPECTION 3 1 05/06/2018 05/11/2018 IP 71130.02 000734 Access Control 1 05/06/2018 05/11/2018 IP 71130.05 000737 Protective Strategy Evaluation 1 05/06/2018 05/11/2018 IP 71151 001338 Performance Indicator Verification SUMMER INITIAL LICENSE EXAM 3 1 05/07/2018 05/11/2018 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1 06/04/2018 06/08/2018 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
TARGET SET 1 1 06/18/2018 06/22/2018 IP 71130.14 000743 Review of Power Reactor Target Sets EP PROGRAM INSPECTION 2 1 08/27/2018 08/31/2018 IP 71114.02 000717 Alert and Notification System Testing 1 08/27/2018 08/31/2018 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1 08/27/2018 08/31/2018 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 08/27/2018 08/31/2018 IP 71114.05 000720 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 08/27/2018 08/31/2018 IP 71151 001397 Performance Indicator Verification UNIT 1 IN-SERVICE INSPECTION 1 1 10/15/2018 10/19/2018 IP 71111.08P 000702 Inservice Inspection Activities - PWR UNIT 1 SG IN-SERVICE INSPECTION 1 1 10/15/2018 10/19/2018 IP 71111.08P 000702 Inservice Inspection Activities - PWR CYBER SECURITY 5 1 10/22/2018 10/26/2018 IP 71130.10P 000741 Cyber Security 1 11/05/2018 11/09/2018 IP 71130.10P 000741 Cyber Security This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures.
Enclosure
IP 22 Inspection Activity Plan Report RP OCCUPATIONAL WEEK 1 3 1 10/22/2018 10/26/2018 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 10/22/2018 10/26/2018 IP 71124.02 000726 Occupational ALARA Planning and Controls 1 10/22/2018 10/26/2018 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1 10/22/2018 10/26/2018 IP 71124.04 000728 Occupational Dose Assessment 1 10/22/2018 10/26/2018 IP 71124.05 000729 Radiation Monitoring Instrumentation 1 10/22/2018 10/26/2018 IP 71151 000746 Performance Indicator Verification RP OCCUPATIONAL WEEK 2 2 1 11/05/2018 11/09/2018 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 11/05/2018 11/09/2018 IP 71124.02 000726 Occupational ALARA Planning and Controls 1 11/05/2018 11/09/2018 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1 11/05/2018 11/09/2018 IP 71124.04 000728 Occupational Dose Assessment 1 11/05/2018 11/09/2018 IP 71124.05 000729 Radiation Monitoring Instrumentation 1 11/05/2018 11/09/2018 IP 71151 000746 Performance Indicator Verification EP EXERCISE INSPECTION 1 1 03/25/2019 03/29/2019 IP 71114.01 000716 Exercise Evaluation 1 03/25/2019 03/29/2019 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 03/25/2019 03/29/2019 IP 71114.08 000723 Exercise Evaluation Scenario Review 1 03/25/2019 03/29/2019 IP 71151 001397 Performance Indicator Verification PROBLEM IDENTIFICATION AND RESOLUTION 4 1 05/06/2019 05/10/2019 IP 71152B 000747 Problem Identification and Resolution 1 05/20/2019 05/24/2019 IP 71152B 000747 Problem Identification and Resolution TRIENNIAL HEAT SINK PERFORMANCE 1 1 06/24/2019 06/28/2019 IP 71111.07T 000700 Heat Sink Performance -Triennial SUMMER REQUAL INSPECTION 2 1 08/05/2019 08/09/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance -
Biennial SECURITY BASELINE INSPECTION 1 1 08/12/2019 08/16/2019 IP 71130.02 000734 Access Control 1 08/12/2019 08/16/2019 IP 71151 001338 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.
Enclosure
IP 22 Inspection Activity Plan Report RP RADHAZARD & PUBLIC 4 1 08/19/2019 08/23/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 08/19/2019 08/23/2019 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1 08/19/2019 08/23/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program 1 08/19/2019 08/23/2019 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1 08/19/2019 08/23/2019 IP 71151 000746 Performance Indicator Verification NFPA 805 TFPI 1 1 08/26/2019 08/30/2019 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial)
1 09/09/2019 09/13/2019 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial)
SUMMER INITIAL LICENSE EXAM 3 1 09/30/2019 10/04/2019 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1 11/04/2019 11/08/2019 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
EVALUATIONS OF CHANGES, TESTS AND EXPERIMENTS 3 1 11/04/2019 11/08/2019 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments SECURITY BASELINE INSPECTION 2 1 11/18/2019 11/22/2019 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1 11/18/2019 11/22/2019 IP 71130.07 000739 Security Training This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.
Enclosure