IR 05000354/2020005

From kanterella
Revision as of 06:07, 17 February 2021 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Updated Inspection Plan (Inspection Report 05000354/2020005)
ML20238C057
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 08/31/2020
From: Brice Bickett
Reactor Projects Branch 3
To: Carr E
Public Service Enterprise Group
References
IR 2020005
Download: ML20238C057 (7)


Text

August 31, 2020

SUBJECT:

HOPE CREEK NUCLEAR GENERATING STATION - UPDATED INSPECTION PLAN (INSPECTION REPORT 05000354/2020005)

Dear Mr. Carr:

The enclosed inspection plan lists the inspections scheduled through June 30, 2022, for Hope Creek Nuclear Generating Station. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP),

including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the May 28, 2020, memo, Inspection Guidance During Transition From COVID-19 Mandatory Telework (ML20141L766). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:

https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling. Additionally, during this period the NRC will schedule an additional inspection per a revised version of Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerability in Electrical Power Systems (NRC Bulletin 2012-01) for any sites who elect to implement the guidance of the Industry Initiative on Open Phase Condition, Revision 3 (ML19163A176), which included an option for relying on annunciation and operator manual actions instead of automatic protective features to isolate a power supply affected by an open phase condition. Licensees will be individually notified when the NRC schedules these inspections.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 610-337-5312 with any questions you have regarding this letter.

Sincerely, X /RA/

Signed by: NRC-PIV Brice A. Bickett, Chief Reactor Projects Branch 3 Division of Reactor Projects Docket No. 05000354 License No. NPF-57 Enclosure:

Hope Creek Inspection Plan cc: Distribution via ListServ

ML20238C057 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME PFinney Bickett DATE 8/27/2020 8/31/2020

IP 22 Inspection Activity Plan Report Hope Creek 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count EP EXERCISE INSPECTION - HOPE CREEK 4 1 05/18/2020 12/31/2020 IP 71114.01 000716 Exercise Evaluation 1 05/18/2020 12/31/2020 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 05/18/2020 12/31/2020 IP 71151 001397 Performance Indicator Verification Access Control, Equip Perf, Training-HC 3 1 07/06/2020 07/08/2020 IP 71130.02 000734 Access Control 1 07/06/2020 07/08/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1 07/06/2020 07/08/2020 IP 71130.07 000739 Security Training 1 07/06/2020 07/08/2020 IP 71130.09 001656 Security Plan Changes 1 07/06/2020 07/08/2020 IP 71151 001338 Performance Indicator Verification RP Rad Hazards Control / Radiation Monitoring Instrumentation 71124.01 / 71124.05 (REMOTE AND ON-SITE) 1 1 07/20/2020 08/31/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 07/20/2020 08/31/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation RP Rad Hazard Controls / In-Plant Airborne / Occupational Dose Assessment 71124.01 / 71124.03 / 71124.04 (REMOTE) 1 1 08/10/2020 08/14/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1 08/10/2020 08/14/2020 IP 71124.04 000728 Occupational Dose Assessment Material Control and Accountability - Hope Creek Unit 1 1 1 09/14/2020 09/18/2020 IP 71130.11 000742 Material Control and Accounting (MC&A)

EP PROGRAM INSPECTION - HOPE CREEK 1 1 09/28/2020 10/02/2020 IP 71114.02 000717 Alert and Notification System Testing 1 09/28/2020 10/02/2020 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1 09/28/2020 10/02/2020 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 09/28/2020 10/02/2020 IP 71114.05 000720 Maintenance of Emergency Preparedness 1 09/28/2020 10/02/2020 IP 71151 001397 Performance Indicator Verification Hope Creek Requal Inspection with P/F Results 2 1 10/04/2020 10/10/2020 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance 1 10/04/2020 10/10/2020 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance TRIENNIAL HEAT SINK 1 1 10/05/2020 10/09/2020 IP 71111.07T 000700 Heat Sink Performance This report does not include INPO and OUTAGE activities. Page 1 of 4 This report shows only on-site and announced inspection procedures.

8/27/2020 2:18:00 PM

IP 22 Inspection Activity Plan Report Hope Creek 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count RP Performance Indicator Verification 1 1 11/16/2020 11/16/2020 IP 71151 000746 Performance Indicator Verification 50.59 Inspection 3 1 12/13/2020 12/19/2020 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments FORCE-ON-FORCE PLANNING AND LIMITED SCOPE TACTICAL RESPONSE DRILLS- HC 6 1 12/14/2020 12/18/2020 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1 12/14/2020 12/18/2020 IP 92707 001711 Security Inspection of Facilities Impacted by a Local, State, or Federal Emergency Where the NRCs Ability to Conduct Triennial Force On-Force Exercises is Limited FY21 HOPE CREEK Initial Exam 4 1 01/10/2021 01/16/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1 02/14/2021 02/27/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

Access Auth, Fitness for Duty, Access Control, SPR, PI 3 1 02/01/2021 02/05/2021 IP 71130.01 000733 Access Authorization 1 02/01/2021 02/05/2021 IP 71130.02 000734 Access Control 1 02/01/2021 02/05/2021 IP 71130.08 000740 Fitness For Duty Program 1 02/01/2021 02/05/2021 IP 71130.09 001656 Security Plan Changes 1 02/01/2021 02/05/2021 IP 71151 001338 Performance Indicator Verification EP Program Inspection - Salem/Hope Creek 1 1 02/22/2021 04/26/2021 IP 71151 001397 Performance Indicator Verification 1 03/22/2021 03/26/2021 IP 71114.02 000717 Alert and Notification System Testing 1 03/22/2021 03/26/2021 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1 03/22/2021 03/26/2021 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 03/22/2021 03/26/2021 IP 71114.05 000720 Maintenance of Emergency Preparedness INSERVICE INSPECTION 1 1 04/18/2021 04/24/2021 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

RP Rad Hazard Assess and Control; Occupational ALARA Plan & Control 71124.01/.02 1 1 04/19/2021 04/23/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 04/19/2021 04/23/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls This report does not include INPO and OUTAGE activities. Page 2 of 4 This report shows only on-site and announced inspection procedures.

8/27/2020 2:18:00 PM

IP 22 Inspection Activity Plan Report Hope Creek 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count RP Rad Hazard; ALARA; In-Plant Airborne; Dose Assess 71124.01/.02/.03/.04 1 1 05/17/2021 05/21/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 05/17/2021 05/21/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1 05/17/2021 05/21/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1 05/17/2021 05/21/2021 IP 71124.04 000728 Occupational Dose Assessment RP Rad Waste Processing and Transportation 71124.08 1 1 06/14/2021 06/18/2021 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation DESIGN BASIS ASSURANCE INSPECTION - TEAMS 6 1 08/01/2021 08/07/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

1 08/15/2021 08/21/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

RP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 1 1 08/09/2021 08/13/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment PI&R BIENNIAL - HC 4 1 10/18/2021 10/22/2021 IP 71152B 000747 Problem Identification and Resolution 1 11/01/2021 11/05/2021 IP 71152B 000747 Problem Identification and Resolution RP Performance Indicator Verification 71151 (REMOTE) 1 1 11/15/2021 11/16/2021 IP 71151 000746 Performance Indicator Verification RP Rad Hazard Assessment 71124.01 1 1 02/07/2022 02/11/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls Fire Protection - Hope Creek 3 1 03/14/2022 03/18/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

1 03/28/2022 04/01/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

EP EXERCISE INSPECTION - HOPE CREEK 4 1 05/23/2022 05/27/2022 IP 71114.01 000716 Exercise Evaluation 1 05/23/2022 05/27/2022 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1 05/23/2022 05/27/2022 IP 71151 001397 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 3 of 4 This report shows only on-site and announced inspection procedures.

8/27/2020 2:18:00 PM

IP 22 Inspection Activity Plan Report Hope Creek 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count RP Rad Instrumentation 71124.05 1 1 05/23/2022 05/27/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation Access Control, Protective Strat, TSR, SPR, PI- HC 4 1 06/06/2022 06/10/2022 IP 71130.02 000734 Access Control 1 06/06/2022 06/10/2022 IP 71130.05 000737 Protective Strategy Evaluation 1 06/06/2022 06/10/2022 IP 71130.09 001656 Security Plan Changes 1 06/06/2022 06/10/2022 IP 71130.14 000743 Review of Power Reactor Target Sets 1 06/06/2022 06/10/2022 IP 71151 001338 Performance Indicator Verification FY22 Hope Creek Initial Licensing Examination 4 1 06/26/2022 07/01/2022 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

This report does not include INPO and OUTAGE activities. Page 4 of 4 This report shows only on-site and announced inspection procedures.

8/27/2020 2:18:00 PM