(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
|
---|
Category:NOTICE OF DEVIATION/NONCONFORMANCE FROM A REGULATORY
MONTHYEARML20198J2051998-12-17017 December 1998 Notice of Deviation from Insp on 981131-1204.Deviation Noted:Licensee Quality Assurance Dept Conducted Biennial Audits of All Transfer,Packaging & Transport Activities Involving Radioactive Matl ML20247M0531989-07-24024 July 1989 Notice of Deviation from Insp on 890601-30.Deviation Noted: Failure to Properly Support Steam Lines ML20248E2131989-03-31031 March 1989 Notice of Deviation from Insp on 890201-28.Deviations Noted: Failure to Install Water Curtain in Doorway Opening Between Fan Room & Room 81 & Failure to Test Eight fusible-link Valves That Supply Water to Curtains ML20205C8581988-10-19019 October 1988 Notice of Deviation from Insp on 880912-16.Deviations Noted: Failure to Issue Engineering Guide Prepared & Designated as Engineering Manual CEI-6 & Failure of Reradiography of Girth Welds G1 & G2 to Encompass All Repaired Areas ML20151X3731988-04-29029 April 1988 Notice of Deviation from Insp on 880301-31.Deviation Noted: Erection & Use of Scaffolding W/O Safety Review Being Performed ML20151R6341988-04-19019 April 1988 Notice of Deviation from Insp on 880314-18.Deviation Noted: 11 Surveillance Tests Delinquent for Filing ML20236G9181987-07-30030 July 1987 Notice of Deviation from Insp on 870601-0715.Deviation Noted:Failure to Revise Procedure ST-ESF-2 to Reflect Designation of Responsibility for Assuring Equipment Operability to Shift Supervisor Until 870320 ML20214M7991987-05-28028 May 1987 Notice of Deviation from Insp on 870401-30 ML20211Q2441987-02-19019 February 1987 Notice of Deviation from Insp on 870101-31 ML20211R0611986-07-23023 July 1986 Notice of Deviation from Insp on 860601-30 ML20140E0061986-01-29029 January 1986 Notice of Deviation from Insp on 850826-30 ML20137K5281986-01-17017 January 1986 Notice of Deviation from Insp on 851201-31 1998-12-17
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARPNO-IV-99-048, on 991026,Fort Calhoun Station Operators Reported Alert Because 4160 Volt Vital Buses 1A4 Were Deenergized for Approx 2 Minutes.Electrical Maint Personnel Have Inspected Electrical Equipment Inside & Outside Plant1999-10-26026 October 1999 PNO-IV-99-048:on 991026,Fort Calhoun Station Operators Reported Alert Because 4160 Volt Vital Buses 1A4 Were Deenergized for Approx 2 Minutes.Electrical Maint Personnel Have Inspected Electrical Equipment Inside & Outside Plant IR 05000285/19990101999-10-15015 October 1999 Insp Rept 50-285/99-10 on 990913-17.One NCV Noted.Major Areas Inspected:Mitigating Sys,Reactor Safety IR 05000285/19990091999-10-14014 October 1999 Insp Rept 50-285/99-09 on 990913-17.No Violations Noted. Major Areas Inspected:Effective Implementation of Protective Strategy When Required to Respond to Contingency Events ML20211P3441999-09-0707 September 1999 Insp Rept 50-298/99-08 on 990711-0821.No Violations Noted. Major Areas Inspected:Initiating Events,Mitigating Systems & Barrier Integrity IR 05000285/19990061999-09-0303 September 1999 Insp Rept 50-285/99-06 on 990809-12.No Violations Noted. Major Areas Inspected:Cornerstone Area of Reactor Safety, Emergency Preparedness.Insp Included Review of Licensee Program for Problem Identification & Resolution IR 05000285/19990071999-08-13013 August 1999 Insp Rept 50-285/99-07 on 990719-23.No Violations Noted. Major Areas Inspected:Accuracy & Operability of Radiation Monitoring Instrumentation Used for Protection of Occupational Workers IR 05000285/19990051999-07-19019 July 1999 Insp Rept 50-285/99-05 on 990601-0710.No Violations Noted. Major Areas Inspected:Broad Categories of Reactor Safety, Emergency Preparedness & Other Activities ML20195J2591999-06-11011 June 1999 Insp Rept 50-285/99-04 on 990425-0531.Noncited Violations Identified.Major Areas Inspected:Operations,Maint & Plant Support IR 05000285/19990031999-05-18018 May 1999 Insp Rept 50-285/99-03 on 990314-0424.Noncited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support PNO-IV-99-025, on 990513,possible Stop Work in Response to Contract Dispute Occurred.Union Maint Personnel May Participate,But Operators & Security Personnel Will Not Participate.No Press Release Is Planned1999-05-14014 May 1999 PNO-IV-99-025:on 990513,possible Stop Work in Response to Contract Dispute Occurred.Union Maint Personnel May Participate,But Operators & Security Personnel Will Not Participate.No Press Release Is Planned IR 05000285/19990021999-04-0202 April 1999 Insp Rept 50-285/99-02 on 990131-0313.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000285/19990011999-03-11011 March 1999 Insp Rept 50-285/99-01 on 990208-26.One Noncited Violation Was Identified.Major Areas Inspected:Evaluation of Cumulative Effect of Operator Workarounds at Plant Reactor Facility IR 05000285/19980191999-01-0808 January 1999 Insp Rept 50-285/98-19 on 981005-23 & 1211.Violations Noted. Major Areas Inspected:Corrective Action Program in Identifying Evaluation,Correcting & Preventing Problems That Affect Safe Operation of Facility ML20206R1601999-01-0808 January 1999 Notice of Violation from Insp on 981005-23 & 1211.Violations noted:licensee-established Measures Failed to Assure Prompt Identification & Effective Corrective Action to Address Potential for Core Reactivity Change IR 05000285/19980231999-01-0707 January 1999 Insp Rept 50-285/98-23 on 981108-1219.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000285/19980251998-12-30030 December 1998 Insp Rept 50-285/98-25 on 981130-1204.No Violations Noted. Major Areas Inspected:Licensee Emergency Preparedness Program IR 05000285/19980261998-12-17017 December 1998 Insp Rept 50-285/98-26 on 981131-1204.Deviations Noted. Major Areas Inspected:Plant Support Activities ML20198J2051998-12-17017 December 1998 Notice of Deviation from Insp on 981131-1204.Deviation Noted:Licensee Quality Assurance Dept Conducted Biennial Audits of All Transfer,Packaging & Transport Activities Involving Radioactive Matl IR 05000285/19980131998-12-16016 December 1998 Insp Rept 50-285/98-13 on 981130-1204.No Violations Noted. Major Areas Inspected:Review Implementation of Liquid & Gaseous Radwaste Effluent Mgt Program IR 05000285/19980241998-11-20020 November 1998 Insp Rept 50-285/98-24 on 981102-06.Violations Noted.Major Areas Inspected:Plant Support ML20195H8021998-11-20020 November 1998 Notice of Violation from Insp on 981102-06.Violation Noted: from 4:45 to 11:45 Am on 980423,room 13 on Elevation 989 Ft of Auxiliary Building Not Posted as Airborne Radioactivity Area When Sample Results Showed Excess Radioactivity IR 05000285/19980211998-11-13013 November 1998 Insp Rept 50-285/98-21 on 980927-1107.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000285/19980171998-10-28028 October 1998 Insp Rept 50-285/98-17 on 980928-1002.No Violations Noted. Major Areas Inspected:Licensee Operator Requalification Program to Determine Whether Program Incorporated Appropriate Requirements IR 05000285/19980181998-10-0808 October 1998 Insp Rept 50-285/98-18 on 980831-0902.No Violations Noted. Major Areas Inspected:Changes to Fort Calhoun Station Radiological Emergency Action Levels IR 05000285/19980201998-10-0505 October 1998 Insp Rept 50-285/98-20 on 980816-0926.No Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000285/19980221998-09-29029 September 1998 Insp Rept 50-285/98-22 on 980914-18.No Violations Noted. Major Areas Inspected:Routine,Announced Insp Reviewed Implementation of Radiological Environ & Meteorological Monitoring Programs IR 05000285/19980141998-08-28028 August 1998 Insp Rept 50-285/98-14 on 980705-0815.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000285/19980121998-08-17017 August 1998 Insp Rept 50-285/98-12 on 980601-05 (on Site) & 980811 (in Ofc).One Noncited Violation Noted.Major Areas Inspected: Operations,Maint & Engineering.Root Cause Assessment, Performed as Result of 980527 Pump FW-10 Occurrence IR 05000285/19980151998-08-0606 August 1998 Insp Rept 50-285/98-15 on 980727-31.No Violations Noted. Major Areas Inspected:Testing & Maint,Protected Area Barrier & Detection Aids,Vital Area Barriers & Detection Aids, Security Event Logs & Security Training & Qualifications IR 05000285/19980161998-07-29029 July 1998 Insp Rept 50-285/98-16 on 980706-10.Violations Noted.Major Areas Inpected:Solid Radwaste Mgt & Radioactive Matls Transportations,Associated Training Activities & QA Oversight ML20236W2931998-07-29029 July 1998 Notice of Violation from Insp on 980606-10.Violation Noted: Licensee Did Not Take Dry Active Samples Annually.Dry Active Waste Stream Samples Were Collected in June 1995 & Aug 1997 IR 05000285/19980101998-07-21021 July 1998 Insp Rept 50-285/98-10 on 970524-0704.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20236M7531998-07-0808 July 1998 Notice of Violation from Insp on 980521-0605.Violation Noted:On 980520,licensee Personnel Did Not Write Maint Work Document to Document Deficiency W/Valve FP-230 Following Manipulation of Valve ML20236M7581998-07-0808 July 1998 Insp Rept 50-285/98-11 on 980521-0605.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000285/19980091998-06-25025 June 1998 Errata to Insp Rept 50-285/98-09.Correction Due to Errrors on Pages 5 & 13 ML20249A6181998-06-15015 June 1998 Insp Rept 50-285/98-09 on 980412-0523.Violations Noted:Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20249A6171998-06-15015 June 1998 Notice of Violation from Insp on 980412-0523.Violation Noted:On 980402,licensee Did Not Have Adequate Procedure for Performing Activity That Affected Quality PNO-IV-98-021A, on 980526,update to Loss of Offsite Power Made.Components Have Been Replaced & Sys Functioning Properly.Correction Should Be Made to Info in Original Pn. Nonvital Buses 1A1 & 1A2 Continuously Energized1998-05-26026 May 1998 PNO-IV-98-021A:on 980526,update to Loss of Offsite Power Made.Components Have Been Replaced & Sys Functioning Properly.Correction Should Be Made to Info in Original Pn. Nonvital Buses 1A1 & 1A2 Continuously Energized ML20249C1431998-05-24024 May 1998 Notice of Violation from Insp on 980415-24.Violation Noted: Inspectors Identified That Licensee Had Not Submitted in 1984 & 1994 Relief Requests for Code Class Welds That Did Not Receive Full Exam Coverage During 10-yr ISI Intervals IR 05000285/19980071998-05-24024 May 1998 Insp Rept 50-285/98-07 on 980415-24.Violations Noted.Major Areas Inspected:Operations & Maint PNO-IV-98-021, on 980520,loss of Offsite Power Occurred as Result of Fault on Transformer T1A-3,161 Kv to 4 Kv Transformer Which Supplies Power to One of Two Vital Electrical Buses.Special Followup Initiated on 9805211998-05-21021 May 1998 PNO-IV-98-021:on 980520,loss of Offsite Power Occurred as Result of Fault on Transformer T1A-3,161 Kv to 4 Kv Transformer Which Supplies Power to One of Two Vital Electrical Buses.Special Followup Initiated on 980521 ML20217N0991998-04-30030 April 1998 Insp Rept 50-285/98-06 on 980406-10.Violations Noted.Major Areas Inspected:Plant Support ML20217N0931998-04-30030 April 1998 Notice of Violation from Insp on 980406-10.Violation Noted: on 980407,individual Working in Accordance W/Radiation Work Permit 98-0011 Entered Restricted High Radiation Area in Steam Generator Bay B W/O Radiation Protection Coverage IR 05000285/19980051998-04-22022 April 1998 Insp Rept 50-285/98-05 on 980301-0411.Violations Noted. Major Areas Inspected:Operation,Maint,Engineering & Plant Support ML20217E0061998-04-22022 April 1998 Notice of Violation from Insp on 980301-0411.Violation Noted:Inspectors Identified That Licensee Did Not Have Procedure for Performing an Activity That Affected Quality ML20217Q9251998-04-0606 April 1998 Insp Rept 50-285/98-01 on 980120-23 & 26-0306.No Violations Noted.Major Areas Inspected:Plant Support,Including Fire Protection Program IR 05000285/19980031998-03-27027 March 1998 Insp Rept 50-285/98-03 on 980223-27 & 0311-18.No Violations Identified.Major Areas Inspected:Licensee Physical Security Program,Access Authorization,Alarm Stations,Communications, Access Control of Event Logs & Mgt Support ML20217D4471998-03-25025 March 1998 Notice of Violation from Insp on 980209-13 W/In Ofc Insp Until 980302.Violation Noted:Since Aug 1994 QA Lead Auditor Had Not Satisfied or Completed QA Qualification Manual Requirements Prior to Conducting Lead Auditor Functions IR 05000285/19980021998-03-25025 March 1998 Insp Rept 50-285/98-02 on 980209-13 W/In Ofc Insp Until 980302.Violations Noted.Major Areas Inspected:Operations & Engineering IR 05000285/19980041998-03-12012 March 1998 Insp Rept 50-285/98-04 on 980118-0228.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support 1999-09-07
[Table view] |
Text
.
APPENDIX A NOTICE OF DEVIATION Omaha Public Power District Docket: 50-285/86-18
' Fort Calhoun Station License: DPR-40 Based on the results of an NRC inspection conducted on June 1-30, 1986, a deviation from your commitments made to the NRC was identified. The deviation consisted of the failure to provide certain parameters on the safety parameter
~
display system. In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1985), the
. deviation is listed below:
-In a letter to the NRC dated October 28, 1983, the licensee committed to
- implementation of a safety parameter display system (SPDS) for monitoring selected safety system parameters.
In deviation from the above, the licensee failed to include all of the parameters on the SPDS specified in the letter. The parameters that were not monitored are reactor coolant system average temperature, boronometer reading, and the temperature of the containment. (285/8618-01)
Omaha Public Power District is hereby requested to submit to this office, within 30 days of the date of the letter transmitting this Notice, a written statement or explanation in reply, including for each deviation: (1)-the reason for the deviation if admitted, (2) the corrective steps which have been taken and the results achieved, (3) the corrective steps which will be taken to avoid further deviations, and (4) the date when full compliance will be achieved. Where good cause is shown, consideration will be given to extending the response time.
Dated at Arlington, Texas, this sta dday offi V aet 1986 I) 1 8607280088 860723 PDR ADOCK 05000285 G PDR