ML20248E213
| ML20248E213 | |
| Person / Time | |
|---|---|
| Site: | Fort Calhoun |
| Issue date: | 03/31/1989 |
| From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | |
| Shared Package | |
| ML20248E105 | List: |
| References | |
| 50-285-89-09, 50-285-89-9, NUDOCS 8904120162 | |
| Download: ML20248E213 (1) | |
Text
____
1 l
L
. APPENDIX B NOTICE OF DEVIA ION 0maha Public Power District Docket:
50-285 Fort Calhoun Station License:
OPR-40 r
' Based on the results of an NRC inspection conducted on February 1-28, 1989,'a
' deviation of your commitments made tolthe NRC was identified.
The deviation 1
consisted of the? failure to install and' test portions of the fire water 3
sprinkler system.
In accordance with the." General Statement of Policy and a
. Procedure for NRC Enforcement Actions," 10 CFR Part 2., Appendix C (1988), the j
tdeviation is listed below:
Failure to Install and Test Portions of the Fire Water Sprinkler System-(1)' Section 9.11.3 of the Updated Safety Analysis Report'(USAR) states, in part,.that a safe shutdown analysis has been performed on an 1
area-by-area basis to satisfy the provision of Appendix R to 10 CFR Part 50.
Evaluation of fire protection for safe shutdown is
. contained in the Safety Evaluation Report (SER), " Fort Calhoun Power Station Unit 1,"
dated August 23, 1978.
Section 4;9 of the SER states, in part, that water curtains will be installed to reinforce' protection by 3-hour fire doors at doorway openings betwee'n the' turbine and the auxiliary buildings.
1
,In deviation from the above, the licensee did not install a water-curtain at.the doorway opening between the fan room (in the turbine building) and Room 81 (in the auxiliary building).
(2) Section 9.11.4 of the USAR states in part that testing is performed and verified by inspection and audit to demonstrate conformance with subsequent design and system readiness requirements.
In deviation from the above, the licensee failed to test the eight' fusible-link valves that supply the water curtains.
Omaha Public Power District is hereby requested to submit a written statement or explanation to this office within 30 days of the date of the letter transmitting this-Notice.
This reply should be clearly marked as a " Reply to a 4
Notice of Deviation" and should include a written statement or explanation for each deviation:.(1) the reason for the deviation if admitted, (2) the corrective steps which have been taken and the results achieved, (3) the i
corrective steps which will be taken to avoid further deviations, and-(4) the j
date when full compliance will be achieved.
Where good cause is shown,
. consideration will be given to extending the response time.
Dated at-Arlington, 4,1989 Texas this 3)# day of 71 8904120162 890331 PDR ADOCK 05000285 o
_ _ _ _ _ - _ _ _ - - _ _ - _ _ - _ _