Interim Deficiency Rept DER 83-42 Re Thermowells in Rcs. Initially Reported on 830629.Investigation,testing & Evaluation Continuing.Next Rept Delayed Until 840815 Due to Extensive Investigation
ML20092G213
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 06/11/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-29714-TDS, DER-83-42, NUDOCS 8406250079
Download: ML20092G213 (2)


Text

.

.+

"Ep'[a Arizona Public Service Company m, i a i j: .,

1: 7 :~

9 '

June 11, 1984 ANPP-29714-TDS/TRB U..S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention: Mr. T. W. Bishop, Director Division of Resident Reactor Projects and Engineering Programs

Subject:

Time Extension For Report - DER 83-42 A 50.55(e) Potentially Reportable Deficiency Relating To Thermowells In The Reactor Coolant System File: 84-019-026; D.4.33.2

Reference:

(A) Telephone conversation between P.. Johnson and J. Roedel on June 29, 1983 (B) ANPP-27398, dated July 25, 1983 (Interim Report)

(C) ANPP-27852, dated September 21, 1983 (Time Extension)

(D) ANPP-28320, dated November 30, 1983 (Time Extension)

(E) ANPP-28575, dated January 9,1984 (Time Extension)

(F) ANPP-28733, dated January 27, 1984 (Interim Report, Revision 1)-

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Reference (A), Interim Reports were transmitted by Reference (B) and (F),

and Time Extensions were requestied by References (C), (D) and-(E). At-that time, it was estimated that a Final Report would be available by June 15, 1984~.

Due to the extensive investigation, testing and evaluation required, it is now expected.that this information will be finalized by August 15, 1984, 'at which time a complete report will be submitted. _.

1 1

There is no new information or change to the Interim Report at this time.

Very trul yours -

)

(- ---- --

.C- Q.-c cu.t wt m E. E. Van. Brunt, Jr.

APS-Vice President Nuclear Production ANPP Project Director.

EEVB/TRB:db 1

cc: - See Page Two 8406a50079 840611 PDR ADOCK OS000Sa8

.IE-A7-

'S

_ PDR.

g. -

i s

'Mr. '.T W. Bishop DER 83-42 Page Two ec: Richard DeYoung, Director '

Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. G. Woods, Jr.

D. B. Karner W. E. Ide D. B. Easnacht A. C. Rogers L. A. Souza D.'E. Fowler l T. D. Shriver C. N. Russo J. Vorees J. R. Bynum J. M. Allen J. A. - Brand A. C. Gehr W. J. Stubblefield

) W. G. Bingham R. L. Patterson R. W. Welcher H. D. Foster D. R. Hawkinson L. E. Vorderbrueggen G. A. Fiorelli S. R. Frost J. Self D. Canady i ' Records Center .

' Institute of Nuclear Power Operations . '