Request for Additional Information No. 270, Revision 0 Power Uprate to 2568 Mwt (Tac No. MB5289)
ML022550154
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 09/18/2002
From: Mozafari B
NRC/NRR/DLPM/LPD2
To: Young D
Florida Power Corp
mozafari B, NRR/DLPM, 415-2020
References
TAC MB5289
Download: ML022550154 (5)


Text

September 18, 2002 Mr. Dale E. Young, Vice President Crystal River Nuclear Plant (NA1B)

ATTN: Supervisor, Licensing and Regulatory Programs 15760 W. Power Line Street Crystal River, Florida 34428-6708

SUBJECT:

CRYSTAL RIVER UNIT 3 REQUEST FOR ADDITIONAL INFORMATION RE: PROPOSED LICENSE AMENDMENT REQUEST ON POWER UPRATE TO 2568 MWT (TAC NO. MB5289)

Dear Mr. Young:

By letter dated June 5, 2002, you submitted an amendment application to revise the Crystal River Unit 3 (CR-3) Improved Technical Specifications Section 1.1 and License Condition 2.C.(1) to allow operation up to 2568 MWt. The enclosed Request for Additional Information (RAI) was previously discussed with your staff on September 10, 2002.

For the staff to complete its review on schedule, your response to this RAI is requested no later than October 11, 2002. This date was mutually agreed upon in a telephone conversation with Paul Infanger on September 10, 2002. If you need to revise the target date, please call me at the earliest opportunity at 301-415-2020.

Sincerely,

/RA/

Brenda L. Mozafari, Senior Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-302

Enclosure:

As stated cc w/encl: See next page

REQUEST FOR ADDITIONAL INFORMATION POWER UPRATE TO 2568 MWT CRYSTAL RIVER UNIT 3

1) Section 4.7.2.4 of Attachment A to the amendment request indicates the RTPTS value at end of license (EOL) for the limiting beltline material, upper shell longitudinal welds WF-18 and WF-8, is 206.0 oF. The attachment also indicates that neutron embrittlement analyses were performed using a 7-percent increase in neutron fluence and the chemical composition reported in Reference 7, BAW-2325, Revision 1, Response to Request for Additional Information (RAI) Regarding Reactor Pressure Vessel Integrity, January 1999. This report identifies the EOL RTPTS value for the upper shell longitudinal weld as 215.7 oF, which is greater than the value reported in this amendment. Since the neutron fluence was assumed to increase in this evaluation, the RTPTS should have increased.

Explain this discrepancy and provide the following information:

a) the neutron fluence at the clad-base metal interface for the upper shell longitudinal weld at EOL, b) the amounts of copper and nickel for the upper shell longitudinal weld, c) the unirradiated reference temperature for the upper shell longitudinal weld, and d) the margin value utilized in the RTPTS evaluation for the upper shell longitudinal weld.

2) In order to satisfy the reactor vessel Charpy upper-shelf energy requirements of Appendix G, 10 CFR Part 50, Florida Power Corporation has performed equivalent margins analyses for the beltline welds. What is the impact of the power uprate on the equivalent margins analyses? Provide the neutron fluence at the 1/4 thickness at EOL for the beltline welds and describe the impact of this neutron fluence on the equivalent margins analyses.

ENCLOSURE

September 18, 2002 Mr. Dale E. Young, Vice President Crystal River Nuclear Plant (NA1B)

ATTN: Supervisor, Licensing and Regulatory Programs 15760 W. Power Line Street Crystal River, Florida 34428-6708

SUBJECT:

CRYSTAL RIVER UNIT 3 REQUEST FOR ADDITIONAL INFORMATION RE: PROPOSED LICENSE AMENDMENT REQUEST ON POWER UPRATE TO 2568 MWT (TAC NO. MB5289)

Dear Mr. Young:

By letter dated June 5, 2002, you submitted an amendment application to revise the Crystal River Unit 3 (CR-3) Improved Technical Specifications Section 1.1 and License Condition 2.C.(1) to allow operation up to 2568 MWt. The enclosed Request for Additional Information (RAI) was previously discussed with your staff on September 10, 2002.

For the staff to complete its review on schedule, your response to this RAI is requested no later than October 11, 2002. This date was mutually agreed upon in a telephone conversation with Paul Infanger on September 10, 2002. If you need to revise the target date, please call me at the earliest opportunity at 301-415-2020.

Sincerely,

/RA/

Brenda L. Mozafari, Senior Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-302

Enclosure:

As stated cc w/encl: See next page DISTRIBUTION:

PUBLIC L. Wert OGC PDII-2 Reading K. Jabbour ACRS B. Elliot (email) E. Dunnington (Hardcopy) S. Coffin (email)

A. Howe (email) B. Mozafari ADAMS ACCESSION NO. ML022550154 OFFICE PDII-2/PM PDII-2/LA PDII-2/Acting SC NAME BMozafari EDunnington KJabbour DATE 9/17/02 9/16/02 9/17/02 OFFICIAL RECORD COPY

Mr. Dale E. Young CRYSTAL RIVER UNIT NO. 3 Florida Power Corporation cc:

Mr. R. Alexander Glenn Chairman Associate General Counsel (MAC-BT15A) Board of County Commissioners Florida Power Corporation Citrus County P.O. Box 14042 110 North Apopka Avenue St. Petersburg, Florida 33733-4042 Inverness, Florida 34450-4245 Mr. Jon A. Franke Ms. Sherry L. Bernhoft Plant General Manager Manager Regulatory Affairs Crystal River Nuclear Plant (NA2C) Crystal River Nuclear Plant (NA2H) 15760 W. Power Line Street 15760 W. Power Line Street Crystal River, Florida 34428-6708 Crystal River, Florida 34428-6708 Mr. Michael A. Schoppman Mr. Daniel L. Roderick Framatome ANP Director Site Operations 1911 North Ft. Myer Drive, Suite 705 Crystal River Nuclear Plant (NA2C)

Rosslyn, Virginia 22209 15760 W. Power Line Street Crystal River, Florida 34428-6708 Mr. William A. Passetti, Chief Department of Health Senior Resident Inspector Bureau of Radiation Control Crystal River Unit 3 2020 Capital Circle, SE, Bin #C21 U.S. Nuclear Regulatory Commission Tallahassee, Florida 32399-1741 6745 N. Tallahassee Road Crystal River, Florida 34428 Attorney General Department of Legal Affairs Mr. Richard L. Warden The Capitol Manager Nuclear Assessment Tallahassee, Florida 32304 Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Mr. Craig Fugate, Director Crystal River, Florida 34428-6708 Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100