9/11/2007-Meeting to Discuss Davis-Besse License Amendment Request for Conversion to Improved Technical Specifications (ITS) - 9/11/2007 NRC Meeting Slides
ML072560046
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 09/11/2007
From: Thomas Wengert
NRC/NRR/ADRO/DORL/LPLIII-2
To:
Wengert, Thomas J, NRR/DORL, 415-4037
Shared Package
ML072560043 List:
References
LAR 06-0003
Download: ML072560046 (19)


Text

FirstEnergy Nuclear Operating Co. (FENOC)

Meeting to Discuss Davis-Besse License Amendment Request for Conversion to Improved Technical Specifications (ITS)

(LAR No. 06-0003; August 3, 2007)

September 11 - 12, 2007 9:00 AM ,," 4:00 PM U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Room O-04B6 Rockville, Maryland

NRC Introductions (1 of 3)

Division of Operating Reactor Licensing (DORL)

- Thomas Wengert - Davis-Besse Project Mgr.

Russell Gibbs - Chief, Plant Licensing Branch 111-2 Technical Specifications Branch (ITSB)

- Ross Tel, - Davis-Besse ITS Cony. Mgr.

- Timothy Kobetz - Chief, ITSB 9/11/2007 7:24 AM 2

NRC Introductions (2 of 3)

ITS Conversion Section Lead Reviewers

- Bill Cartwright 3.6 Containment Systems 3.7 Plant Systems 3.9 Refueling Operations

- Robert Clark 3.8 Electrical Power System

- Timothy Kolb 3.4 Reactor Cooling System

- Aron Lewin 3.3 Instrumentation

- Carl Schulten 1.0 Use & Application 2.0 Safety Limits 3.0 LCO & SR Applicability

- Ross Telson 3.5 Emergency Core Cooling

- Gerald Waig 3.1 Reactivity Control Systems 3.2 Power Distribution Limits 4.0 Design Features 5.0 Administrative Controls 9/11/2007 7:24 AM 3

NRC Introductions (3 of 3)

.V. Current Identified BSI (Beyond-Scope Issue), ESI (Emerging Staff Is sue), ar ld other non-ITSB Tech. Support Leads:

George Wilson, Jr. - Chief, Electrical Engineering Branch (EEEB)

Gregory Cranston - Chief, Reactor Systems Branch (SRXB)

-. William Kemper - Chief, Instrumentation &

Controls Branch (EICB)

Michelle Hart - Chief, Accident Dose Branch (AADB) 9/11/2007 7:24 AM 4

FENOC Davis-Besse Introductions

.O-William Bentley - FENOC Davis-Besse ITS Conversion Project Mgr.

(per FENOC/Davis-Besse) 9/11/2007 7:24 AM 5

Review &Approve Agenda (Day 1 of 2)

  • ODay 1

- Introductions

- Project Overview (proposed agenda addition)

Review/resolve pending application acceptance review items Discussion of informal vs. Official Agency Records

- Review conversion "beyond-scope"' items

- status Ratify project plan (schedule milestones, meetings, etc.)

- Discussion of project plan revision process

- Opportunity for public comment 9/11/2007 7:24 AM 6

Review & Approve Agenda (Day 2 of 2)

,.V Day 2

- Just-in-time training & issuance of passwords for NRC staff to submit questions to on-line Q&A database to facilitate accelerated review

- Review select portions of draft NRC office instruction LIC-601 ("Technical Specification Conversion Accelerated Review") guidance

- Continuation of topics scheduled, but not completed, from Day 1 agenda

- Other emergent discussion topics, as needed

- Opportunity for public comment

- Adjourn 9/11/2007 7:24 AM 7

Project Overview (1 of 2)

(Proposed Agenda Addition)

Scope

- LAR 06-0003 is 3,528 pages (including cover letter & 17 volumes; excluding two pending LARs and anticipated future supplements)

,CTS Markup NUREG Markup (Proposed ITS)

Discussion of Changes (DOCs)

Justification for Deviations (JFDs)

- Staff review is currently estimated at:

1 year and " 2,500 staff-hours (excluding BSIs)

Support & coordination of " 6 NRR branches An Issuance Package rv 700-800 pages including Safety Evaluation, ITS, DOCs, Final estimates are pending; updates are not uncommon as BSI's surface throughout the review...

9/11/2007 7:24 AM 8

Project Overview (2 of 2)

(Proposed Agenda Addition)

",-20Currently-Identified Out-of-Scope Issues or "OSIs" (issues that warrantnon-ITSB Technical Branch input) were identified either by D-B or Staff during acceptance review:

- "17 are Beyond-Scope Issues or"BSIs"

"-,13are licensee-ID'd (LB); ",4are staff-ID'd (SB)

BSI's are ITS elements that are neither congruent with CTS nor STS (NUREG) AND can not be promptly justified by ITSB staff as acceptable due to a unique site-specific CLB.-related condition

- "'2 of the OSI's are Emerging Staff Issues or "ESIs" (SE)

ESI's involve non-ITSB Tech Branch concerns or staff positions that diverge from a proposed ITS which is otherwise congruent with either CTS or STS (or which might have otherwise been justified as acceptable by LR's due to a unique site-specific CLB-related condition) 9/11/2007 7:24 AM 9

Review/Resolve Pending Application Acceptance Review Items staff have identified no items that would prevent acceptance of your application for review However, a number of items were identified which, we recommend for your consideration to promote a more efficient, effective, and timely review Unlike acceptance issues, your address of these items is voluntary. Presently, none of these items have been determined essential to the disposition of your application (though that will likely change during the course of the review) 9/11/2007 7:24 AM 10 1

Recommended Application Items (Recommendations- not requirements)

Official submittal of items Supplement addressing in the compact disk shared issues identified during with staff (preferably in Acceptance Review:

acceptable electronic format): - Staff- and Licensee-Identified BSI's

- Clean ITS & Bases - DOC's and JFD's which

- CTS & Bases are not fully effective in

- D-B UFSAR describing changes

- Ops Schematics - Other identified corrections being

- DOC Tables consolidated for our BSI's acceptance letter 9/11/2007 7:24 AM 11

Discussion of Informal vs.

OFFICIAL Agency Records NRR Office Instruction COM-203 "Informal Interfacing and Exchange of Information with Licensees and Applicants:"

Regulations require that all license applications, requests for amendments and associated correspondence be submitted in writing or by authorized electronic submission (Electronic Information Exchange (EIE) or CD-ROM)

It is NRC policy to make all correspondence used to support decision making an official agency record and to make it publicly available by placing a copy into ADAMS, unless exempted ...

Information informally exchanged with licensees or applicants, and used in decision making, must be properly documented to ensure public disclosure and allow public participation in the decision making process.

9/11/2007 7:24 AM 12

Review ITS Conversion Beyond-scope" Items BSI's Are...

BSI's are ITS elements in the application that are neither congruent with CTS nor STS (NUREG) AND can

.not be promptly justified by ITSB staff as acceptable due to a unique site-specific CLB-related condition 17 Currently-Identified BSI's (14 TACs):

- 5 BSI's itemized in your application (5 TACs)

- 3 of 4 BSI's from 8/29 WJBentley email (3 TACs)

- 5 BSI's regarding 2 LARs (2 TACs)

- 4 staff-identified BSIs (4 TACs) 9/11/2007 7:24 AM 13

Current Summary of BSI's I *ý 1 B MD6399 Lewin EEEB 3.3.8 BSI-1 SFAS SR Requirements (EDG Degraded Voltage & Loss of Voltage Channel Checks) 2 MD6400 Lewin EICB 3.3.11 BSI-2 Steam & Feedwater Rupture Control Sys. Trip Setpoints B SRXB 3 L MD6401 Kolb SRXB 3.4.1 BSI-3 DNB Margin B (for reactor pressure)

L 4 BSI-4 RCS Loop, Modes 1&2 Change of CTS B K(Reactor Coolant Loops and Coolant Circulation)

LSRXB LCO 5 MD6403 Telson BSI-5 ECCS-Core Flooding Tanks B EICB 3.5.1...

6L Administrative Control of Penetrations during Refueling SI C Ih T (Pending LAR No. 06-0002; Feb 12, 2007) 7D14L I SRXB 1.0 Measurement Uncertainty Recapture Power Uprate (MU) 7 MD5240 Schulten EICB (Pending LAR No. 05-0007; April 12, 2007).

B AADB L SRXB L MD 4 LB Measurement Uncertainty Recapture Power Uprate (MU) 8 AADB 3.3.1 (Pending LAR No. 05-0007; April 12, 2007)

L SRXB Measurement Uncertainty Recapture Power Uprate (MU) 9 MD5240 Cartwright EICB 3.7.6 (Pending LAR No. 05-0007; April 12, 2007)

B MADB 9/11/2007 7:24 AM 14

Current Summary of BSI 'S SRXB 1 L 5.6.3c Measurement Uncertainty Recapture Power Uprate (MU)

MD5240 Waig EICB (Pending LAR No. 05-0007; April 12, 2007) 0 B AADB 1 MD6644 Kolb SRXB SR 3.4.1 BSI-6 M1 RCS Flow Surveillance 1 B ID64 Ki Desal 1 S MD6645 Clark EEEB SR 3.8.1.13 BSI-7 (OS1-12) Diesel Generator Endurance Run 2 B Wilson 1 S Wag EEEB 5 B MD6646 & Wilson ITS 5.5.16 BSI-8 (OS1-15) Battery Monitoring & Maintenance Program ITS 5.5.16 1 Clark 6 B MD6647 Waig SRXB1 LCO 3.2.5 BSI-9 (OS1-16) Power Distr Limit ITS LCO 3.2.5 A.

6 B IAction A.2 7 B MD6648 Waig SRXB 3.1.9 BSI-10 (OSI-17) Incorporation of TSTF-467T ITS 3.1.9 MD6684 Waig SRXB 3.2.1 BSI-12 (OS1-18) Rod Insertion Limits ITS 3.2.1 Action A.2 8 B I Action A.2.

1 L EEEB BSI-11 (OS1-19) Diesel Generator 9 B M Wilson Load Rejection Surveillance ITS SR 3.8.1.10 9/11/2007 7:24 AM 15

Ratify Project Plan (Schedule Milestones, Status Meetings, Etc.)

D-B / FENOC Submits-ITS Conversion Req. (LAR 06-0003) 8/312007 n/a LAR in ADAMS and ITS Conversion In-scope Review TACS Issued 8/6/2007 8/13/2007 Lead Reviewers (LRs) In-Scope Enhanced Acceptance Review 8/14/2007 9/4/2007 LR & Tech Branch OSI Detailed Review & Q&A / RAI Period 8/31/2007 2/1412008 Licensee Q&A Responses & Formal Closeout Submittals 9/25/2007 3/14/2008 NRC Issues Acceptance & Schedule Confirmation Letter Milestone 10/112007 Tech Branch OSI SE Inputs to ITSB LR's Milestone 3/27/2008 LR's Verify Formal Closeout Submittals 1/10/2008 4/21/2008 DRAFT SE to Licensee For Factual Information Verification Milestone 5/12/2008 Licensee Provides Comments on DRAFT SE to NRC 5/12/2008 5/27/2008 OGC Review of DRAFT SE/LAR 6/10/2008 7/9/2008 NRC Issues FINAL SE/LAR Milestone 7/30/2008 9/11/2007 7:24 AM 16

Project Plan Revision Process Anticipated or Actual Schedule Delay

- causing party should promptly inform the other party and coordinate and publish an appropriately revised schedule. The cause of the schedule delay should be documented along with the agreed-upon revised schedule.

Changes that don't delay projected LAR issuance date

- may be accomplished informally with the mutual concurrence of the impacted stakeholders.

SEarly completion of any activity

-will not necessitate schedule revision; however, NRC staff will endeavor to accommodate early completions by completing subsequent tasks early.

9/11/2007 7:24 AM 1 17

Any Further Discussion or Questions from Staff?

From Licensee?

Public Comment?