Letter Sequence Other |
|---|
TAC:MD6398, Increase Flexibility in Mode Restraints, Addition of LCO 3.0.8, Inoperability of Snubbers, Deletion of E BAR Definition and Revision to RCS Specific Activity Tech Spec, Changes to Reflect Revision of 10 CFR 50.55A, Limit Inservice Testing Program SR 3.0.2 Application to Frequencies of 2 Years or Less, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO, Correct Example 1.4-1, Containment Structural Integrity, TSTF-28, Correct LCO 3.0.6 Bases, Add Restriction for Lowest LOOP Tave During Mode 2 Physics Testing (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement
Results
Other: L-08-161, Copy of Applicable Portions of the NRC and Davis-Besse Improved Technical Specifications Conversion Website - Sections 3.0, 3.1, 3.2, 3.4, and 3.6 and Chapter 4.0, L-08-241, Attachment 1, Applicable Portions of the U.S. Nuclear Regulatory Commission (NRC) and Davis-Besse Nuclear Power Station (DBNPS) Improved. Technical Specification (ITS) Conversion Website, Section 3.5 RAIs, L-08-338, Copy of Improved Technical Specifications (ITS), L-08-378, Implementation of Improved Technical Specification Amendment No. 279, ML073531253, ML080140025, ML081350505, ML082000451, ML082600577, ML082840099, ML082900630, ML082900683, ML082900780, ML082900882, ML082910112, ML082910125
|
MONTHYEARML0725600462007-09-11011 September 2007 9/11/2007-Meeting to Discuss Davis-Besse License Amendment Request for Conversion to Improved Technical Specifications (ITS) - 9/11/2007 NRC Meeting Slides Project stage: Meeting ML0725600562007-09-12012 September 2007 9/12/2007 Meeting to Discuss Davis-Besse License Amendment Request for Conversion to Improved Technical Specifications (ITS) 9/12/2007 NRC Meeting Slides Project stage: Meeting ML0729001172007-11-0707 November 2007 Meeting Summary with Fenco to Discuss Licensees ITS Conversion License Amendment Request for Davis-Besse Project stage: Meeting ML0735312532008-02-0404 February 2008 Improved Technical Specification Conversion Project stage: Other ML0814804652008-05-16016 May 2008 Improved Technical Specification Conversion License Amendment Request, Volume 5, (Revision 1), Section 3.0 - LCO and SR Applicability Project stage: Request ML0814804712008-05-16016 May 2008 Improved Technical Specification Conversion License Amendment Request, Volume 15, (Revision 1), Chapter 4.0 - Design Features Project stage: Request ML0814804692008-05-16016 May 2008 Improved Technical Specification Conversion License Amendment Request, Volume 11, (Revision 1), Section 3.6 - Containment Systems Project stage: Request ML0814804682008-05-16016 May 2008 Improved Technical Specification Conversion License Amendment Request, Volume 9, (Revision 1), Section 3.4 - Reactor Coolant System (RCS) Project stage: Request ML0814804672008-05-16016 May 2008 Improved Technical Specification Conversion License Amendment Request, Volume 7, (Revision 1), Section 3.2 - Power Distribution Limits Project stage: Request ML0814804662008-05-16016 May 2008 Improved Technical Specification Conversion License Amendment Request, Volume 6, (Revision 1), Section 3.1 - Reactivity Control Systems Project stage: Request L-08-159, Supplement to License Amendment Request: Conversion of Current Technical Specifications (CTS) to Improved Technical Specifications (ITS) - Volumes 5, 6, 7, 9, 11, and 15, TAC No. MD63982008-05-16016 May 2008 Supplement to License Amendment Request: Conversion of Current Technical Specifications (CTS) to Improved Technical Specifications (ITS) - Volumes 5, 6, 7, 9, 11, and 15, TAC No. MD6398 Project stage: Supplement L-08-161, Copy of Applicable Portions of the NRC and Davis-Besse Improved Technical Specifications Conversion Website - Sections 3.0, 3.1, 3.2, 3.4, and 3.6 and Chapter 4.02008-05-16016 May 2008 Copy of Applicable Portions of the NRC and Davis-Besse Improved Technical Specifications Conversion Website - Sections 3.0, 3.1, 3.2, 3.4, and 3.6 and Chapter 4.0 Project stage: Other ML0801400252008-05-16016 May 2008 Notice of Consideration of Issuance of Amendments to Facility Operating Licenses and Opportunity for a Hearing (Tac Nos. MD6319-MD3622, MD6324-MD6333, MD6398-MD6403, MD6644-MD6649, and MD6684) Project stage: Other ML0826005772008-05-30030 May 2008 Attachment 1, Applicable Portions of the U.S. Nuclear Regulatory Commission (NRC) and Davis-Besse Nuclear Power Station (DBNPS) Improved. Technical Specification (ITS) Conversion Website Project stage: Other ML0813505052008-06-17017 June 2008 Improved Technical Specifications Conversion Milestone Schedule Project stage: Other ML0815705882008-06-18018 June 2008 Request for Additional Information Related to Improved Technical Specifications Conversion Project stage: RAI ML0816503642008-06-20020 June 2008 RAI Related to Improved Technical Specifications Conversion Project stage: RAI L-08-221, Response to Request for Additional Information Related to Improved Technical Specifications Conversion2008-07-23023 July 2008 Response to Request for Additional Information Related to Improved Technical Specifications Conversion Project stage: Response to RAI ML0822706612008-08-0707 August 2008 Improved Technical Specification Conversion License Amendment Request, Volume 1, Revision 1, Application of Selection Criteria to the DBNPS Technical Specifications Project stage: Request L-08-240, Improved Technical Specification Conversion License Amendment Request, Volume 14, Revision 1, ITS Section 3.9, Refueling Operations2008-08-0707 August 2008 Improved Technical Specification Conversion License Amendment Request, Volume 14, Revision 1, ITS Section 3.9, Refueling Operations Project stage: Request ML0822706622008-08-0707 August 2008 Improved Technical Specification Conversion License Amendment Request, Volume 2, Revision 1, Generic Determination of No Significant Hazards Consideration and Environmental Assessment Project stage: Request ML0822706672008-08-0707 August 2008 Improved Technical Specification Conversion License Amendment Request, Volume 16, Revision 1, ITS Chapter 5.0, Administrative Controls Project stage: Request ML0822706692008-08-0707 August 2008 Improved Technical Specification Conversion License Amendment Request, Volume 12, Revision 1, ITS Section 3.7, Plant Systems Project stage: Request ML0822706662008-08-0707 August 2008 Improved Technical Specification Conversion License Amendment Request, Volume 10, Revision 1, ITS Section 3.5, Emergency Core Cooling Systems Project stage: Request ML0822706702008-08-0707 August 2008 Improved Technical Specification Conversion License Amendment Request, Volume 13, Revision 1, ITS Section 3.8, Electrical Power Systems Project stage: Request ML0822706652008-08-0707 August 2008 Improved Technical Specification Conversion License Amendment Request, Volume 8, Revision 1, Section 3.3 - Instrumentation Project stage: Request ML0822706582008-08-0707 August 2008 Supplement to License Amendment Request: Conversion of Current Technical Specifications to Improved Technical Specifications - Volumes 1, 2, 3, 4, 8, 10, 12, 13, 14, and 16 Project stage: Supplement ML0822706632008-08-0707 August 2008 Improved Technical Specification Conversion License Amendment Request Volume 3, Revision 1, ITS Chapter 1.0, Use and Application Project stage: Request ML0822706642008-08-0707 August 2008 Improved Technical Specification Conversion License Amendment Request, Volume 4, Revision 1, ITS Chapter 2.0, Safety Limits Project stage: Request ML0826005762008-08-26026 August 2008 Copy of Applicable Portions of the NRC & Davis-Besse Improved Technical Specifications Conversion Website - Chapters 1.0, 2.0 and 5.0 & Sections 3.3, 3.5, 3.7, 3.8, & 3.9 & Response to Request for Additional Information Related to Update to Project stage: Response to RAI L-08-241, Attachment 1, Applicable Portions of the U.S. Nuclear Regulatory Commission (NRC) and Davis-Besse Nuclear Power Station (DBNPS) Improved. Technical Specification (ITS) Conversion Website, Section 3.5 RAIs2008-08-26026 August 2008 Attachment 1, Applicable Portions of the U.S. Nuclear Regulatory Commission (NRC) and Davis-Besse Nuclear Power Station (DBNPS) Improved. Technical Specification (ITS) Conversion Website, Section 3.5 RAIs Project stage: Other L-08-224, Response to Request for Additional Information License Amendment Request to Convert Current Technical Specifications (CTS) to Improved Technical Specifications (Its), and Copy of Two Questions from NRC and Davis-Besse Its2008-09-0303 September 2008 Response to Request for Additional Information License Amendment Request to Convert Current Technical Specifications (CTS) to Improved Technical Specifications (Its), and Copy of Two Questions from NRC and Davis-Besse Its Project stage: Response to RAI ML0824902952008-10-0202 October 2008 ITSB Draft M, to Davis-Besse Amendment Conversion Improved Technical Specifications with Beyond Scope Issues Project stage: Draft Other ML0824902892008-10-0202 October 2008 ITSB Draft L, to Davis-Besse Amendment Conversion Improved Technical Specifications with Beyond Scope Issues Project stage: Draft Other ML0824902802008-10-0202 October 2008 ITSB Draft La, to Davis Besse Amendment Conversion Improved Technical Specifications with Beyond Scope Issues Project stage: Draft Other ML0824902752008-10-0202 October 2008 Draft a, Attachment to Davis Besse Amendment Conversion Improved Technical Specifications with Beyond Scope Issues Project stage: Draft Other ML0824902712008-10-0202 October 2008 List of Acronyms to Davis Besse Draft Amend. ITS Conversion Project stage: Draft Other ML0824902622008-10-0202 October 2008 Draft Safety Evaluation for Conversion to ITS with Beyond Scope Issues, (TAC MD Project stage: Draft Approval ML0824903002008-10-0202 October 2008 ITSB Draft R, to Davis-Besse Amendment Conversion Improved Technical Specifications with Beyond Scope Issues Project stage: Draft Other ML0820004512008-10-0808 October 2008 Environmental Assessment and Finding of No Significant Impact for the Proposed Conversion to the Improved Technical Specifications Project stage: Other ML0828400992008-10-0808 October 2008 Assessment -Davis-Besse Nuclear Power Station, Unit No. 1 - Environmental Assessment and Finding of No Significant Impact for the Proposed Conversion to the Improved Technical Specifications (TAC 6398) Project stage: Other L-08-338, Copy of Improved Technical Specifications (ITS)2008-10-21021 October 2008 Copy of Improved Technical Specifications (ITS) Project stage: Other ML0829006302008-11-20020 November 2008 List of Acronyms to Davis-Besse Amend. Re; ITS with Beyond Scope Issues Project stage: Other ML0829006832008-11-20020 November 2008 Table A-DOC Attachment - Administrative Changes - to Davis-Besse Amend. ITS with Beyond Scope Issues Project stage: Other ML0829007802008-11-20020 November 2008 ITSB L-Less Restrictive Changes - Attachment to Davis-Besse Amendment Beyond Scope Issues Project stage: Other ML0829008822008-11-20020 November 2008 ITSB LA-Removed Details - Attachment to Davis-Besse Beyond Scope Issues Project stage: Other ML0829101252008-11-20020 November 2008 ITSB R-Relocated Specifications - to Davis Besse Amendment Beyond Scope Issues Project stage: Other ML0829101122008-11-20020 November 2008 ITSB M - More Restrictive Changes - to Davis Besse Amendment Beyond Scope Issues Project stage: Other ML0829006002008-11-20020 November 2008 Issuance of Amendment 279 for the Conversion to the Improved TSs with Beyond Scope Issues Project stage: Approval L-08-378, Implementation of Improved Technical Specification Amendment No. 2792008-12-16016 December 2008 Implementation of Improved Technical Specification Amendment No. 279 Project stage: Other 2008-02-04
[Table View] |
Text
June 17, 2008 Mr. Barry S. Allen Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1 - IMPROVED TECHNICAL SPECIFICATIONS CONVERSION MILESTONE SCHEDULE (TAC NO. MD6398)
Dear Mr. Allen:
By letter to the Nuclear Regulatory Commission (NRC) dated August 3, 2007, FirstEnergy Nuclear Operating Company (FENOC) submitted an application requesting to amend the operating license for the Davis-Besse Nuclear Power Station, Unit No. 1 (DBNPS). FENOC has proposed to revise the current technical specifications to the improved technical specifications (ITS) consistent with improved standard technical specifications as described in "Standard Technical Specifications Babcock and Wilcox Plants," Revision 3.1 (STS). STS Revision 3.1 is the December, 2005, update to NUREG-1430, which was published June 2004.
Enclosed is a copy of the revised milestone schedule for the ITS for DBNPS. The milestone date for the NRC issuance of the final ITS and safety evaluation is November 15, 2008.
This revised schedule will supersede the schedule which was previously sent to you by our letter dated February 4, 2008, on the same subject. We have already discussed this revised schedule with members of your staff, and we will continue to conduct weekly status calls between FENOC and NRC staffs to facilitate completion of the review.
If you have any questions regarding this letter, please contact me at 301-415-4037.
Sincerely,
/RA/
Thomas J. Wengert, Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346
Enclosure:
Milestone Schedule cc w/encls: See next page
Mr. Barry S. Allen June 17, 2008 Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1 - IMPROVED TECHNICAL SPECIFICATIONS CONVERSION MILESTONE SCHEDULE (TAC NO. MD6398)
Dear Mr. Allen:
By letter to the Nuclear Regulatory Commission (NRC) dated August 3, 2007, FirstEnergy Nuclear Operating Company (FENOC) submitted an application requesting to amend the operating license for the Davis-Besse Nuclear Power Station, Unit No. 1 (DBNPS). FENOC has proposed to revise the current technical specifications to the improved technical specifications (ITS) consistent with improved standard technical specifications as described in "Standard Technical Specifications Babcock and Wilcox Plants," Revision 3.1 (STS). STS Revision 3.1 is the December, 2005, update to NUREG-1430, which was published June 2004.
Enclosed is a copy of the revised milestone schedule for the ITS for DBNPS. The milestone date for the NRC issuance of the final ITS and safety evaluation is November 15, 2008.
This revised schedule will supersede the schedule which was previously sent to you by our letter dated February 4, 2008, on the same subject. We have already discussed this revised schedule with members of your staff, and we will continue to conduct weekly status calls between FENOC and NRC staffs to facilitate completion of the review.
If you have any questions regarding this letter, please contact me at 301-415-4037.
Sincerely,
/RA/
Thomas J. Wengert, Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346
Enclosure:
Milestone Schedule cc w/encls: See next page DISTRIBUTION:
PUBLIC LPL3-2 R/F RidsNrrPMTWengert RidsNrrDirsItsb RidsOgcRp RidsRgn3MailCenter RidsNrrLAEWhitt RidsAcrsAcnw&mMailCenter ALewin, NRR RidsNrrDorlLpl3-2 RidsNrrDorlDpr Accession Number: ML081350505 NRR-106 OFFICE LPL3-2/PM LPL3-2/LA DIRS/ITSB/BC LPL3-2/BC NAME TWengert:sp EWhitt RElliott RGibbs DATE 06 /16/08 06/16/08 05/27/08 06/17/08 OFFICIAL RECORD COPY
IMPROVED TECHNICAL SPECIFICATION (ITS) CONVERSION MILESTONE SCHEDULE DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1 DOCKET NO. 50-346 Milestone Tasks Milestone as of 9/11/07 Milestone as of 2/04/08 Milestone as of 6/16/08 1
Submittal of ITS Conversion Request 8/3/2007 8/3/2007 8/3/2007 2
NRC Issues Schedule Confirmation Letter 10/1/2007 2/4/2008 2/4/2008 3
NRC Staff Completed Initial Detailed Review &
Posting of all Initial Questions 2/14/2008 2/26/2008 4/2/20081 5/30/20082 4
NRC Staff and FENOC Resolution of Open Q&As
& Pending RAIs N/A 3/27/2008 4/2/20081 6/30/20082 5
Final FENOC Q&A Responses and License Amendment Request Supplements Due 3/14/2008 4/24/2008 5/16/20083 7/30/20084 6
Draft Safety Evaluation (SE) and ITS to FENOC for Factual Information Verification 5/12/2008 7/17/2008 9/18/2008 7
FENOC Submits Comments on Draft SE and ITS to NRC 5/27/2008 7/31/2008 10/2/2008 8
NRC Issues Final ITS and SE 7/30/2008 9/30/2008 11/15/2008 1 Milestone dates for ITS Sections 3.0, 3.1, 3.2, 3.4, 3.6, 4.0.
2 Milestone dates for ITS Sections 1.0, 2.0, 3.3, 3.5, 3.7, 3.8, 3.9, and 5.0.
3 This date represents the date of issuance of the first of two NRC staff-requested FENOC supplements, which should contain the information necessary to complete FENOCs close-out of ITS Sections 3.0, 3.1, 3.2, 3.4, 3.6, and 4.0.
4 This date represents the projected receipt of the second of two NRC staff-requested FENOC supplements. This supplement should contain necessary information to complete FENOCs close-out of remaining ITS Sections 1.0, 2.0, 3.3, 3.5, 3.7, 3.8, 3.9, and 5.0, which are affected by the measurement uncertainty recapture power uprate license amendment request and/or open questions related to other BSI reviews.
Davis-Besse Nuclear Power Station, Unit No. 1 cc:
Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3065 5501 North State Route 2 Oak Harbor, OH 43449-9760 Director, Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P.O. Box 4009 Reynoldsburg, OH 43068-9009 Resident Inspector U.S. Nuclear Regulatory Commission 5503 North State Route 2 Oak Harbor, OH 43449-9760 Stephen Helmer Supervisor, Technical Support Section Bureau of Radiation Protection Ohio Department of Health 35 East Chestnut Street, 7th Floor Columbus, OH 43215 Carol OClaire, Chief, Radiological Branch Ohio Emergency Management Agency 2855 West Dublin Granville Road Columbus, OH 43235-2206 Zack A. Clayton DERR Ohio Environmental Protection Agency P.O. Box 1049 Columbus, OH 43266-0149 State of Ohio - Transportation Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Principal Assistant Attorney General Environmental Enforcement Section State Office Tower 30 East Broad Street, 25th Floor Columbus, OH 43215 President, Board of County Commissioners of Ottawa County Port Clinton, OH 43252 President, Board of County Commissioners of Lucas County One Government Center, Suite 800 Toledo, OH 43604-6506 The Honorable Dennis J. Kucinich United States House of Representatives Washington, D.C. 20515 The Honorable Dennis J. Kucinich United States House of Representatives 14400 Detroit Avenue Lakewood, OH 44107 Joseph J. Hagan President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Corporation Mail Stop A-GO-15 76 South Main Street Akron, OH 44308 Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company 76 South Main Street Akron, OH 44308
Davis-Besse Nuclear Power Station, Unit No.1 cc:
Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Paul A. Harden Vice President, Nuclear Support FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 James H. Lash Senior Vice President of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308