Improved Technical Specifications Conversion Milestone Schedule
ML081350505
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 06/17/2008
From: Thomas Wengert
NRC/NRR/ADRO/DORL/LPLIII-2
To: Allen B
FirstEnergy Nuclear Operating Co
Wengert, Thomas
References
TAC MD6398
Download: ML081350505 (5)


Text

June 17, 2008 Mr. Barry S. Allen Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760

SUBJECT:

DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1 - IMPROVED TECHNICAL SPECIFICATIONS CONVERSION MILESTONE SCHEDULE (TAC NO. MD6398)

Dear Mr. Allen:

By letter to the Nuclear Regulatory Commission (NRC) dated August 3, 2007, FirstEnergy Nuclear Operating Company (FENOC) submitted an application requesting to amend the operating license for the Davis-Besse Nuclear Power Station, Unit No. 1 (DBNPS). FENOC has proposed to revise the current technical specifications to the improved technical specifications (ITS) consistent with improved standard technical specifications as described in "Standard Technical Specifications Babcock and Wilcox Plants," Revision 3.1 (STS). STS Revision 3.1 is the December, 2005, update to NUREG-1430, which was published June 2004.

Enclosed is a copy of the revised milestone schedule for the ITS for DBNPS. The milestone date for the NRC issuance of the final ITS and safety evaluation is November 15, 2008.

This revised schedule will supersede the schedule which was previously sent to you by our letter dated February 4, 2008, on the same subject. We have already discussed this revised schedule with members of your staff, and we will continue to conduct weekly status calls between FENOC and NRC staffs to facilitate completion of the review.

If you have any questions regarding this letter, please contact me at 301-415-4037.

Sincerely,

/RA/

Thomas J. Wengert, Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosure:

Milestone Schedule cc w/encls: See next page

Mr. Barry S. Allen June 17, 2008 Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760

SUBJECT:

DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1 - IMPROVED TECHNICAL SPECIFICATIONS CONVERSION MILESTONE SCHEDULE (TAC NO. MD6398)

Dear Mr. Allen:

By letter to the Nuclear Regulatory Commission (NRC) dated August 3, 2007, FirstEnergy Nuclear Operating Company (FENOC) submitted an application requesting to amend the operating license for the Davis-Besse Nuclear Power Station, Unit No. 1 (DBNPS). FENOC has proposed to revise the current technical specifications to the improved technical specifications (ITS) consistent with improved standard technical specifications as described in "Standard Technical Specifications Babcock and Wilcox Plants," Revision 3.1 (STS). STS Revision 3.1 is the December, 2005, update to NUREG-1430, which was published June 2004.

Enclosed is a copy of the revised milestone schedule for the ITS for DBNPS. The milestone date for the NRC issuance of the final ITS and safety evaluation is November 15, 2008.

This revised schedule will supersede the schedule which was previously sent to you by our letter dated February 4, 2008, on the same subject. We have already discussed this revised schedule with members of your staff, and we will continue to conduct weekly status calls between FENOC and NRC staffs to facilitate completion of the review.

If you have any questions regarding this letter, please contact me at 301-415-4037.

Sincerely,

/RA/

Thomas J. Wengert, Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosure:

Milestone Schedule cc w/encls: See next page DISTRIBUTION:

PUBLIC LPL3-2 R/F RidsNrrPMTWengert RidsNrrDirsItsb RidsOgcRp RidsRgn3MailCenter RidsNrrLAEWhitt RidsAcrsAcnw&mMailCenter ALewin, NRR RidsNrrDorlLpl3-2 RidsNrrDorlDpr Accession Number: ML081350505 NRR-106 OFFICE LPL3-2/PM LPL3-2/LA DIRS/ITSB/BC LPL3-2/BC NAME TWengert:sp EWhitt RElliott RGibbs DATE 06 /16/08 06/16/08 05/27/08 06/17/08 OFFICIAL RECORD COPY

IMPROVED TECHNICAL SPECIFICATION (ITS) CONVERSION MILESTONE SCHEDULE DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1 DOCKET NO. 50-346 Milestone Tasks Milestone as of 9/11/07 Milestone as of 2/04/08 Milestone as of 6/16/08 1

Submittal of ITS Conversion Request 8/3/2007 8/3/2007 8/3/2007 2

NRC Issues Schedule Confirmation Letter 10/1/2007 2/4/2008 2/4/2008 3

NRC Staff Completed Initial Detailed Review &

Posting of all Initial Questions 2/14/2008 2/26/2008 4/2/20081 5/30/20082 4

NRC Staff and FENOC Resolution of Open Q&As

& Pending RAIs N/A 3/27/2008 4/2/20081 6/30/20082 5

Final FENOC Q&A Responses and License Amendment Request Supplements Due 3/14/2008 4/24/2008 5/16/20083 7/30/20084 6

Draft Safety Evaluation (SE) and ITS to FENOC for Factual Information Verification 5/12/2008 7/17/2008 9/18/2008 7

FENOC Submits Comments on Draft SE and ITS to NRC 5/27/2008 7/31/2008 10/2/2008 8

NRC Issues Final ITS and SE 7/30/2008 9/30/2008 11/15/2008 1 Milestone dates for ITS Sections 3.0, 3.1, 3.2, 3.4, 3.6, 4.0.

2 Milestone dates for ITS Sections 1.0, 2.0, 3.3, 3.5, 3.7, 3.8, 3.9, and 5.0.

3 This date represents the date of issuance of the first of two NRC staff-requested FENOC supplements, which should contain the information necessary to complete FENOCs close-out of ITS Sections 3.0, 3.1, 3.2, 3.4, 3.6, and 4.0.

4 This date represents the projected receipt of the second of two NRC staff-requested FENOC supplements. This supplement should contain necessary information to complete FENOCs close-out of remaining ITS Sections 1.0, 2.0, 3.3, 3.5, 3.7, 3.8, 3.9, and 5.0, which are affected by the measurement uncertainty recapture power uprate license amendment request and/or open questions related to other BSI reviews.

Davis-Besse Nuclear Power Station, Unit No. 1 cc:

Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3065 5501 North State Route 2 Oak Harbor, OH 43449-9760 Director, Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P.O. Box 4009 Reynoldsburg, OH 43068-9009 Resident Inspector U.S. Nuclear Regulatory Commission 5503 North State Route 2 Oak Harbor, OH 43449-9760 Stephen Helmer Supervisor, Technical Support Section Bureau of Radiation Protection Ohio Department of Health 35 East Chestnut Street, 7th Floor Columbus, OH 43215 Carol OClaire, Chief, Radiological Branch Ohio Emergency Management Agency 2855 West Dublin Granville Road Columbus, OH 43235-2206 Zack A. Clayton DERR Ohio Environmental Protection Agency P.O. Box 1049 Columbus, OH 43266-0149 State of Ohio - Transportation Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Principal Assistant Attorney General Environmental Enforcement Section State Office Tower 30 East Broad Street, 25th Floor Columbus, OH 43215 President, Board of County Commissioners of Ottawa County Port Clinton, OH 43252 President, Board of County Commissioners of Lucas County One Government Center, Suite 800 Toledo, OH 43604-6506 The Honorable Dennis J. Kucinich United States House of Representatives Washington, D.C. 20515 The Honorable Dennis J. Kucinich United States House of Representatives 14400 Detroit Avenue Lakewood, OH 44107 Joseph J. Hagan President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Corporation Mail Stop A-GO-15 76 South Main Street Akron, OH 44308 Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company 76 South Main Street Akron, OH 44308

Davis-Besse Nuclear Power Station, Unit No.1 cc:

Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Paul A. Harden Vice President, Nuclear Support FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 James H. Lash Senior Vice President of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308