Responds to IE Bulletin 79-23.Purchase Order for Emergency Diesel Generators Has Not Been Placed.Will Ensure Compliance by Testing Generator During Preoperational Test Program
ML19256F159
Person / Time
Site: 05000516, 05000517
Issue date: 10/29/1979
From: Plaskon R
LONG ISLAND LIGHTING CO.
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-79-23, NUDOCS 7911210554
Download: ML19256F159 (1)


Text

- --

a

/Eg'O LONG ISLAND LIGHTING COM PANY

.awaunaw 175 EAST OLO COUNTRY ROAD H tCKSVI LLE. NEW YORK 11801 October 29, 1979 JNRC-240 Mr. Boyce Grier, Director Office of Inspection & Enforcement, Region 1 U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 Jamesport Nuclear Power Station - Units 1 & 2 Inspection & Enforcement Bulletin No. 79-23 Docket Nos. 50-516 50-517

Dear Mr. Grier:

In reply to Inspection & Enforcement (IE) Bulletin No. 79-23, Potential Failure of Emergency Diesel Generator Field Exciter Transformer, we have reviewed the Jamesport Nuclear Power Station (JNPS) design and submit the following response.

The Purchase Order for the JNPS Emergency Diesel Generators has not been placed. Accordingly, the Emergency Diesel Generator vendor is not known at this time.

Nevertheless, prior to issuing a Purchase Order, we will ensure that the concern raised in Action Item 1 of IE Bulletin No. 79-23 has been investigated and adequate corrective action, if required, is implemented. In addition, the installed unit will be tested during the plant pre-operational test program in sccordance with Action Item 2 of this IE Bulletin.

Should you require further information, please do not hesitate to contact us.

Very truly yours, c fY o

R.'E. Plaskon Assistant Project Manager Jamesport Nuclear Power Station LG/dm cc: Mr. Victor Stello, Director Office of Inspection & Enforcement U.S. Nuclear Regulatory Commission Washington, D.C. 20545 } }/8 .)35 7911210 k