Responds to Outlining Concerns Re Info Notice 88-056, Potential Problems W/Silicone Foam Fire Barrier Penetration Seals. Silicone Foam Acceptable Matl Provided Certain Installation Parameters Controlled
ML20055C608
Person / Time
Site: 05000516
Issue date: 05/16/1990
From: Murley T
Office of Nuclear Reactor Regulation
To: Charles Brown
BRAND INDUSTRIAL SERVICES, INC. (BISCO)
Shared Package
ML20055C609 List:
References
IEIN-88-056, IEIN-88-56, NUDOCS 9005290079
Download: ML20055C608 (2)


Text

a,%

+f.*

UNITED STATES j

e[

NUCLEAR REGULATORY COMMISSION n

f sp WASHINGT ON, D. C. 20555

%,.... + p#

MAY 161990 I

1 Mr. Clayton W. Brown, president BISCO Construction Group t

Brand Industrial Services -Inc.

2 1420 Renaissance Drive 1

Park Ridge, Illinois 60068

Dear Mr. Brown:

Your letter dated April 18, 1990, outlined concerns regarding NRC Information Notice No. 88-56, " Potential Problems With Silicone Foam Fire Barrier Penetra-tion Seals." The NRC staff has reviewed NRC Information Notice No. 88-56 and your letter and has concluded the following:

(1) Silicone foam appears to be an acceptable material for fire barrier penetration seals provided certain installation parameters are controlled as discussed in NRC Information Notice No. 88-56.

(2) Experience with silicone foam indicates that the method of installetion (e.g.

dammingtechnique),technicalandqualitycontrolofmaterial, materia 1mixingprocess,pouringandcuringprocess,methodoffinal inspection, and training and experience of installing personnel can affect the quality of the fire barrier penetration seals. One important aspect is whether or not a visual inspection of the silicone foam material is

>erformed. NRC staff inspectors have noted that silicone foam vendors Tave procedurally required a " visual inspection" during the installation stage; however, in practice the temporary or permanent dams have not been removed to perform a visual inspection.

l (3) Variousfirebarrierpenetrationse.1nonconformingconditions(e.g.,

i voids, gaps, and splits) have been reported by licensees in the past.

In order to mitigste these nonconforming conditions, licensees have taken the following corrective actions:

developed programs for inspection and periodic reinspection of installed seals including visual inspection of the silicone foam material repaired nonconforming seals evaluated alternative materials for repairing old seals and install-ing new seals o

developed alternative methods for installing and inspecting new silicone foam seals a

/03 U

6 l

[f3 L

NRC File CENTER COPY 9005290079 900516 PlW ORG NRRB

7 fX e

I MAY f 61990 F

Mr. Clayton W. Brown,

(4) Finally, in your letter dated April 18, 1990, you stated in part, " BISCO has always been aware of this potential problem and designed their system around temporary dams that are removed for proper inspection and any i

i necessary repairs." However, the NRC staff understands that BISCO leaves a dam in place on the bottom side of the floor installation (refer to NRC inspection report 99901020/87-01 and tir. Thomas W. Giimore's letter to i

Ellis W. Merschoff dated June 22, 1987, in response to the NRC report).

If you have any additional comments or concerns, please contact Dr. Carl H.

L Berlinger, Chief of the Generic Comunications Branch.

Sincerely, Off inal cl ced by E

E R.onns I. Eurley Thomas E. Murley, Director Office of Nuclear Reactor Regulation i

DISTRIBUTION TEMurley, NRR FJMiraglia, NF.R WTRussell, NRR CERossi, NRR SA;,

g A

u CHBerlinger, NRR b

t'A NCampbell, NRR gg I h yvo4s%g GHolahan, NRR CSmyre, NRR Or,t M e

CVandenburgh, NRR

.p 2 L &

M**~

DMossburg (YTf0909069) g p( m PBaranowsky, NRR JACalvo NRR M*

i JJPetrosino, NRR

(

PDR (w/incomin )-

L-(Centre D Files w7 incoming)a DCB l

DOEA R/F-OGCB R/F NCampbell R/F

//

f f I [8

  • SEE PREVIOUS PAGE FOR C0llCURRENCE f

'@r Document Name:

LETTER TO BISCO

!W DD TE riey FJ ia 05

/90 05 30

WTRussell (g

  • 0GCB:DOEA:NRR*RVIB:DRIS:NRR *C/0GCB:DOEA:NRR
  • D OEA:NRR NCampbell JJPetrosino CHBeritnger CERossi 05/3/90 05/3/90 05/

05/04/90 05/07/90 L

i i

.c v f c

(?} Sl'l?

N