MONTHYEARML22309A0062022-12-12012 December 2022 Public Non-Sensitive Meeting Summary on Clarification Call with Holtec Regarding Request for Additional Information for Indian Point Unit 2 Master Decommissioning Trust Agreement as Per Indian Point Nuclear Generating Facility Unit 1 and 2 ML21342A1402021-12-0909 December 2021 Summary of Public Meeting in Tarrytown, Ny, to Discuss Indian Point Units 1, 2, and 3 (IPEC) Post-shutdown Decommissioning Activities Report ML21055A9122021-02-24024 February 2021 (E-mail Dated 2/24/2021) Summary of Feb 8, 2021, Pre-submittal Meeting for Relief Request No. IP3-ISI-RR-16, Code Case N-513-4 Periodic Inspection Frequency Extension ML20321A0002020-11-17017 November 2020 Summary of 9/30/20 Pre-Submittal Meeting with Entergy to Discuss Proposed One-Time Exemption Request - Biennial Emergency Preparedness Onsite Evaluated Exercise Requirements ML20289A7322020-10-15015 October 2020 2020 Annual Assessment Meeting for Indian Point - Meeting Summary ML20083F5962020-03-23023 March 2020 Summary of Teleconference with the National Marine Fisheries Service for Indian Point Biological Opinion ML20059P1292020-03-0303 March 2020 Summary of Partially Closed Pre-submittal Public Meeting with Entergy Nuclear Operations, Inc. to Discuss the Proposed License Amendment Request to Replace the Indian Point Unit No. 3 Crane with a New Holtec High-Lift Crane (EPID L:2019-LRM ML19330F5182019-11-29029 November 2019 Summary of Public Meeting Between the NRC and Entergy Regarding Pre-Submittal of a License Transfer Application to Holtec International for Indian Point Energy Center ML19319A0242019-10-0202 October 2019 NEIMA Meeting - Courtney Williams Comments ML19319A0282019-10-0202 October 2019 NEIMA Meeting - Marilyn Elie Comments ML19319A0272019-10-0202 October 2019 NEIMA Meeting - Linda Puglisi Comments ML19319A0252019-10-0202 October 2019 NEIMA Meeting - Jenean Eichenholtz Comments ML19198A2392019-07-17017 July 2019 Annual Assessment Meeting for Indian Point Energy Center - Meeting Summary ML18200A2722018-07-19019 July 2018 Summary of Annual Assessment Meeting for Indian Point Energy Center ML18131A0572018-05-11011 May 2018 Summary of 04/12/2018 Meeting with the State of New York Regarding the Indian Point Generating Unit No. 2 Reactor Pressure Vessel Head Penetration Alternative Weld Repair ML18117A3162018-04-30030 April 2018 Summary of 04/03/2018 Meeting with Entergy on Planned Submittal of Propose Alternative for Reactor Pressure Vessel Head Nozzle Weld Repair ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML18002A2562018-01-30030 January 2018 11/30/2017 and 12/19/2017 Summary Telephone Conference Calls with Entergy Nuclear Operations, Inc., Concerning Request for Additional Information Pertaining to the Indian Point License Renewal Application ML17256A2862017-09-25025 September 2017 Summary of Telephone Call on 09/06/17, Between NRC and Entergy Concerning Next Steps from the Site Audit on 08/1-3/17 ML17180A5032017-09-21021 September 2017 04/19/2017 Summary of Teleconference with Entergy Nuclear Operations, Inc., Concerning Request for Additional Information Pertaining to the Indian Point Unit Nos. 2 and 3 License Renewal Application ML17237A2132017-08-25025 August 2017 Memo E-mail to File -Summary of July 26, 2017, Meeting with Entergy to Discuss Proposed License Amendment Request, New Criticality Safety Analysis ML17173A7672017-07-28028 July 2017 Summary of 6/20/2017 Meeting with Entergy to Discuss Plan for Decommissioning Licensing Actions of Palisades, Pilgrim, Indian Point, Units 2 and 3, and Vermont Yankee ML17160A1652017-06-27027 June 2017 Summary of Telephone Conference Call Held on May 31,2017, Between the NRC and Entergy Nuclear Operations Inc. Concerning Requests for Additional Information Pertaining to the Indian Point, License Renewal Application (TAC Nos. MD5407/MD5408 ML17172A1972017-06-20020 June 2017 Summary of Annual Assessment Meeting for Indian Point Units 2 and 3 ML17157B5422017-06-20020 June 2017 Conference Call on 2nd Round RAIs - Final ML17082A3112017-04-11011 April 2017 Summary of Clarification Call with Entergy Regarding Follow-Up RAIs on ISG-2012-02 ML16281A2162016-10-25025 October 2016 10/04/2016,Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Proposed Changes to the Service Water Integrity Program for the Indian Point Nuclear Generating, Units 2 and 3 (IP2 and IP3) License Renewal Application (LRA) ML16209A3712016-08-17017 August 2016 July 21, 2016, Summary of Conference Call Held Between NRC and Entergy Nuclear Operations, Inc. Concerning the Draft RAI for the Review of the Indian Point, Units 2 & 3, License Renewal Application, Set 2016-01 (TAC Nos. MD5407 & MD5408) ML16188A0202016-07-0505 July 2016 Summary of Annual Assessment Meeting for Indian Point Units 2 and 3 ML16133A4992016-06-21021 June 2016 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the Indian Point LRA Safety Review ML16035A4802016-02-12012 February 2016 Jsc Meeting Summary Attachment ML15351A2032015-12-30030 December 2015 Summary of Conference Call Held on December 9, 2015, Between the NRC and Entergy Nuclear Operations, Inc. Concerning the Draft Audit Plan for the Service Water Integrity and Fire Water System Aging Management Programs ML15190A2912015-07-22022 July 2015 070115, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review ML15152A0762015-05-29029 May 2015 Summary of Annual Assessment Meeting for Indian Point Units 2 and 3 on 5/20/2015 ML15120A6442015-05-0606 May 2015 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review ML15107A1752015-04-28028 April 2015 041615, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Environmental Review ML15093A5052015-04-14014 April 2015 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the Indian Point LRA Environmental Review ML15051A5022015-03-10010 March 2015 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Environmental Review ML15022A1602015-02-11011 February 2015 and 01/13/15, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Environmental Review ML14197A5832014-09-18018 September 2014 Summary of the June 19, 2014, Category 1 Public Meeting with Entergy to Discuss Seismic Hazard Reevaluations Associated with Implementation of Japan Lessons-Learned Near-Tear Task Force Recommendation 2.1 ML14260A4312014-09-17017 September 2014 Revised Summary of Annual Assessment Meeting for Indian Point Energy Center on 6/4/2014 ML14238A7262014-09-10010 September 2014 Summary of Conference Call Held on July 30, 2014, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations Inc., Regarding a Draft Request for Additional Information on Removal of Certain Aging Management Review Items ML14219A6742014-08-14014 August 2014 July 15, 2014 Summary of Telephone Conference Call Held Between U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning the Environmental Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License R ML14206B1282014-08-0101 August 2014 June 19, 2014 & July 16, 2014 Summary of Conference Calls Held Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Regarding Entergy Response to a Request for Additional Information ML14178A8682014-06-25025 June 2014 Summary of Annual Assessment Meeting for Indian Point Energy Center on 6/4/2014 ML14136A0052014-05-27027 May 2014 Summary of Phone Call Between New York State Department of State and U.S. Nuclear Regulatory Commission on May 7, 2014, Regarding the Coastal Zone Management Act Consistency Review ML14105A3542014-04-24024 April 2014 Summary of Conference Call Held on March 26, 2014, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning a Draft Request for Additional Information on the Reactor Vessel Internals Program ML14078A3992014-03-21021 March 2014 Summary of Conference Call Held on February 20, 2014, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning a Draft Request for Additional Information on LR-ISG-2012-02 and Draft LR-ISG-2013-01 ML13256A0862013-09-24024 September 2013 Summary of Meeting with Entergy Nuclear Operations, Inc. and Netco on Indian Point Unit 2 Spent Fuel Pool Management 2022-12-12
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23171B0442023-06-23023 June 2023 Enclosure - Indian Point Energy Center - Request for Additional Information for Independent Spent Fuel Storage Installation Facility-Only Emergency Plan License Amendment ML22292A2402022-10-21021 October 2022 RAIs for Master Dtf Agreement on IP1 IP2 10 18 2022 ML22103A2442022-04-13013 April 2022 Attachment - Request for Additional Information - License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme for Permanently Defueled Condition for Indian Point Energy Center ML22104A0352022-04-13013 April 2022 Request for Additional Information Related to Exemption Request from Emergency Planning Holtec Decommissioning International, LLC Indian Point Energy Center ML22006A0452022-01-0505 January 2022 PSDAR RAIs Final ML21337A2952021-12-0303 December 2021 Subsequent Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device (E-mail Dated 12/3/2021) ML21183A1602021-06-30030 June 2021 Update Request for Additional Information - Indian Point Energy Center Quality Assurance Program Manual (06/30/2021 E-mail) ML21138A9412021-05-18018 May 2021 Request for Additional Information - Indian Point Energy Center Quality Assurance Program Manual (05/18/2021 E-mail) ML21112A2672021-04-22022 April 2021 Subsequent Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device (Public Redacted Version) ML21019A5672021-01-19019 January 2021 Second Round Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device ML21013A0152021-01-12012 January 2021 Draft Request for Additional Information (E-mail Dated 1/12/2021) License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device ML20268C2352020-09-24024 September 2020 Request for Additional Information (E-mail Dated 9/24/20) License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device ML20233B0152020-08-20020 August 2020 Request for Additional Information (E-mail Dated 8/20/20) License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device ML20190A2342020-07-0808 July 2020 Request for Additional Information - Application for Order Consenting to Transfers of Control of Licenses (07/08/2020 E-mail) ML20190A1502020-06-25025 June 2020 (06/25/2020 E-mail) Draft Request for Additional Information Application for Order Consenting to Transfers of Control of Licenses ML20106F2492020-04-15015 April 2020 E-mail (04/15/2020) Request for Additional Information Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic ML20070J7902020-03-10010 March 2020 Request for Information to Support Triennial Baseline Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000286/2020012 ML19045A6252019-02-14014 February 2019 Request for Additional Information - Proposed License Amendment Request Regarding Storage of Fresh and Spent Nuclear Fuel in the Spent Fuel Pool - 2/14/19 E-mail from R.Guzman to M.Mirzai NL-18-053, Response to Request for Additional Information Regarding Relief Request IP3-ISI-RR-11 for Reactor Vessel Weld Inservice Inspection Frequency Extension2018-07-18018 July 2018 Response to Request for Additional Information Regarding Relief Request IP3-ISI-RR-11 for Reactor Vessel Weld Inservice Inspection Frequency Extension ML18155A4842018-06-0404 June 2018 Request for Additional Information Regarding Relief Request IP3-ISI-RR-11, E-mail from R.Guzman to C.Mackaman ML18143B6792018-05-23023 May 2018 Request for Additional Information Regarding LAR for One-Time Extension of the Containment Leakage Rate Test - Email from R.Guzman to M.Mirzai ML18094B0922018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to B. S. Ford RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for ISFSI Docket Nos.: 72-43, 72-51, 72-1044, 72-07, 72-12, and 72-59) ML17296A2352017-10-23023 October 2017 Request for Additional Information -10/23/17 E-mail from R.Guzman to R.Louie Cyber Security Plan Milestone 8 Implementation Schedule (CAC Nos. MF9656, MF9657, MF9658; EPID: L-2017-LLA-0217) ML17277B5482017-10-0303 October 2017 Request for Additional Information - Relief Request IP2-ISI-RR-20 Regarding Weld Examination ML17219A1062017-08-10010 August 2017 Request for Additional Information Regarding Inter-Unit Transfer of Spent Fuel - Shielded Transfer Canister Requests for Additional Information ML17200A0852017-07-19019 July 2017 Request for Additional Information Regarding the Connection of Non-Seismic Boric Acid Recovery System to RWST Seismic Piping ML17197A0002017-07-17017 July 2017 Request for Additional Information Regarding Inter-Unit Transfer of Spent Fuel ML17170A2862017-06-27027 June 2017 RAI Set 2017-06 ML17103A4182017-04-25025 April 2017 Baffle Bolt Rais. Requests for Additional Information for the Review of the Indian Point License Renewal Application (TAC Nos. MD5407 and MD5408) ML17088A4052017-04-20020 April 2017 Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-3 (CAC Nos. MD5407 and MD5408) ML17088A3272017-04-19019 April 2017 Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-02 (CAC Nos. MD5407 and MD5408) ML17100A1282017-04-11011 April 2017 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment of Inter Unit Transfer of Spent Fuel ML17046A2312017-03-0808 March 2017 Request for Additional Information for the Review of the Indian Point License Renewal - Set 2017-01 ML16232A1192016-09-12012 September 2016 Request for Additional Information for the Review of the Indian Point Nuclear Generating Units Nos. 2 and 3, License Renewal Application Environmental Review - Severe Accident Mitigation Alternatives (CAC Nos. MD5411 and MD5412) ML16138A1942016-07-25025 July 2016 Request for Additional Information for the Review of License Renewal Application, Set 2016-01 ML16139A0302016-06-10010 June 2016 Request for Additional Information Regarding Conditional Exemption from End-of-Line Moderator Temperature Coefficient Measurement ML16112A2262016-04-26026 April 2016 Request for Additional Information Regarding Relief Request IP2-ISI-RR-02 Alternative Examination Volume Required by Code Case N-729-1 ML16041A5782016-02-18018 February 2016 Request for Additional Information Related to License Amendment Request Regarding Moderator Temperature Coefficient Measurement Change ML16005A6292016-01-14014 January 2016 Request for Additional Information Regarding Relief Request IP2-RR-19 ML16013A0642016-01-13013 January 2016 NRR E-mail Capture - Request for Additional Information Entergy CNRO-2015-00023 - Revision to Entergy Quality Assurance Program Manual (Fleet Submittal CAC Nos. MF7086-MF7097) ML15341A1662015-12-0707 December 2015 NRR E-mail Capture - Entergy Fleet RR-EN-15-1, Request for Additional Information (CACs MF6341-MF6349) ML15148A4032015-06-29029 June 2015 Request for Additional Information Regarding the Spent Fuel Pool Criticality Analysis ML15156B2742015-06-16016 June 2015 Request for Additional Information Regarding Request to Permanently Extend the Frequency of the Containment Integrated Leak Rate Test ML15125A0972015-05-0606 May 2015 Request for Additional Information Regarding License Amendment to Permanently Extend the Frequency of the Containment Integrated Leak Rate Test ML15071A1012015-05-0404 May 2015 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2015-01 (TAC Nos. MD5407 and MD5408) ML15103A2592015-04-28028 April 2015 Request for Additional Information Regarding the Proposed License Amendment to Extend the Containment Type a Leak Rate Testing Frequency to 15 Years ML15104A5412015-04-22022 April 2015 Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application Environmental Review (TAC Nos. MD5411 and MD5412) ML15072A4172015-03-17017 March 2015 Request for Additional Information Regarding Extension of the Containment Type a Leak Rate Testing Frequency to 15 Years ML14329B2452015-02-18018 February 2015 Request for Additional Information for the Review of the Indian Point Nuclear Generating Units 2 and 3, License Renewal Application Environmental Review (TAC Nos. MD5411 and MD5412) CNRO-2015-00008, Responses to NRC Request for Additional Information Regarding Change in Corporate Form of Entergy Nuclear Holding Company2015-02-18018 February 2015 Responses to NRC Request for Additional Information Regarding Change in Corporate Form of Entergy Nuclear Holding Company 2023-06-23
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 13, 2013 LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: Indian Point Nuclear Generating Station, Units 2 and 3
SUBJECT:
SUMMARY
OF CONFERENCE CALL HELD ON DECEMBER 12, 2012, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING THE REACTOR VESSEL INTERNALS PROGRAM AT INDIAN POINT NUCLEAR GENERATING STATION, UNITS 2 AND 3 - RAI 11A Representatives of the U.S. Nuclear Regulatory Commission (NRC or the staff), and representatives of Entergy Nuclear Operations. Inc., (Entergy or the applicant), held a conference call on December 12, 2012, to provide clarification on a request for additional information (RAI) 11 a, related to the Indian Point (IP) Nuclear Generating Station, Units 2 and 3 license renewal application. The telephone conference call was useful in clarifying the response to the RAI. provides a listing of the participants and Enclosure 2 contains a summary of the discussion.
The applicant had an opportunity to comment on this summary.
Sincerely, John Daily, Senior Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286
Enclosure:
Ust of Participants cc w/encl. Ustserv
February 13, 2013 LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: Indian Point Nuclear Generating Station, Units 2 and 3
SUBJECT:
SUMMARY
OF CONFERENCE CALL HELD ON DECEMBER 12,2012, BEIWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING THE REACTOR VESSEL INTERNALS PROGRAM AT INDIAN POINT NUCLEAR GENERATING STATION, UNITS 2 AND 3 - RAI 11A Representatives of the U.S. Nuclear Regulatory Commission (NRC or the staff), and representatives of Entergy Nuclear Operations, Inc., (Entergy or the applicant), held a conference call on December 12, 2012, to provide clarification on a request for additional information (RAI) 11a, related to the Indian Point (lP) Nuclear Generating Station, Units 2 and 3 license renewal application. The telephone conference call was useful in clarifying the response to the RAI. provides a listing of the participants and Enclosure 2 contains a summary of the discussion.
The applicant had an opportunity to comment on this summary.
Sincerely,
/ra!
John Daily, Senior Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286
Enclosure:
List of Participants cc w/encl: Listserv ADAMS Accession No.: ML13015A364 *via email OFFICE PM:DLRlRPBl LA:DLRlRPB1* BC:DLRlRPBl D:DLRlRPBl NAME JDaily YEdmonds DMorey JDaily DATE 2/4113 1123/13 2/12113 13
REQUEST FOR ADDITIONAL INFORMATION CONFERENCE CALL INDIAN POINT ENERGY CENTER, LICENSE RENEWAL APPLICATION REACTOR VESSEL INTERNALS PROGRAM AND MRP-227-A RAI11A LIST OF PARTICIPANTS December 12,2012 I PARTICIPANT AFFILIATION i John Daily Nuclear Regulatory Commission (NRC)
I Jeff Poehler NRC i Pat Purtcher NRC i Roger Waters Entergy f---
Nelson Azevedo Entergy Ted Ivy Entergy Bob Dolansky Entergy I Cheryl Boggess Westinghouse
-
I Randy Lott Westinghouse Joshua McKinley Westinghouse i Karli Szweda ingl
REQUEST FOR ADDITIONAL INFORMATION CONFERENCE CALL INDIAN POINT ENERGY CENTER, UNITS 2 AND 3 LICENSE RENEWAL APPLICATION REACTOR VESSEL INTERNALS PROGRAM AND MRP-227-A RAI11A December 12, 2012 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc. (Entergy or the applicant) held a telephone conference call on December 12,2012, to discuss staff aging management questions related to the applicant's Reactor Vessel Internals Aging Management Program, in the Indian Point Energy Center (lPEC), Units 2 and 3, license renewal application (LRA). The telephone conference call was useful in clarifying the requests for additional information (RAls) on the issue.
RAI-11a, Reactor Vessel Internals Program and MRP-227-A The staff noted that it had requested additional information on the approach to be used for the plant-specific evaluation of the lower support column bodies. The applicant's response indicates it plans to use an approach using the screening criteria for thermal aging embrittlement susceptibility from the staff's letter "License Renewal Issue No. 98-0030, Thermal Aging Embrittlement of Cast Austenitic Stainless Steel Components," dated May 19, 2000 (NRC ADAMS Accession No. ML003717179). The applicant had provided a table of screening criteria based on chemistry, casting method, and delta ferrite content. The staff also noted its recommendation that, in order to account for a potential synergistic effect on loss of fracture toughness due to the combined effects of thermal embrittlement (TE) and neutron irradiation embrittlement (IE), the applicant should perform component-specific assessments for components that will experience neutron fluence of 1x1017 neutrons per square centimeter (n/cm 2) or greater. Finally, the staff noted that MRP-191 indicates a threshold value that is significantly different from this recommendation.
The staff and Entergy discussed these issues and agreed to clarify the RAI in that, if the applicant desired to use a fluence value other than 1x1017 n/cm 2, then it will add justification as to why its stated threshold value is appropriate for Units 2 and 3.
In addition, in view of an expected industry template response to this issue due to be released in January 2013, the staff and Entergy agreed that the reply window for this RAI set would be 90 days from date of issue so the applicant can take the template into account in its response.
The applicant agreed that it would take the staff's questions into account as it prepares its response to RAI 11a. Both the staff and the applicant agreed that the discussion was useful in clarifying the RAI.
(Note: subsequent to the call it was determined to combine RAls 11 a and 15a into one issue letter, in January 2013.)
SUB..IECT:
SUMMARY
OF CONFERENCE CALL HELD ON DECEMBER 12, 2012, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING THE REACTOR VESSEL INTERNALS PROGRAM AT INDIAN POINT NUCLEAR GENERATING STATION, UNITS 2 AND 3 - RAI 11A DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDeEvib Resource RidsOgcMailCenter Resource DWrona GMeyer, RI KGreen RConte, RI JPoehler JBoska PCataldo, RI DScrenci, RI OPA NMcNamara, RI NSheehan, RI OPA DJackson, RI BWelling, RI BMizuno, OGC OAvegbusi, RI STurk,OGC MCatts, RI SBurnell, OPA MHalter, RI DMclntyre, OPA EDacus,OCA