Summary of 5/3/2016 Prelicensing Meeting with Energy Northwest to Discuss License Amendment Request Regarding Emergency Control Room Chiller System at Columbia Generating Station
ML16138A376
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 05/25/2016
From: Klos L
Plant Licensing Branch IV
To:
Energy Northwest
Klos L
References
CAC MF7593
Download: ML16138A376 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 25, 2016 LICENSEE: Energy Northwest FACILITY: Columbia Generating Station

SUBJECT:

SUMMARY

OF MAY 3, 2016, PUBLIC MEETING WITH ENERGY NORTHWEST TO DISCUSS UPCOMING LICENSE AMENDMENT REQUEST REGARDING EMERGENCY CONTROL ROOM CHILLER SYSTEM FOR COLUMBIA GENERATING STATION (CAC NO. MF7593)

On May 3, 2016, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Energy Northwest, the licensee, at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the licensee's upcoming license amendment request (LAR) regarding emergency control room chiller system for Columbia Generating Station. The meeting notice and agenda, dated April 22, 2016, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML16111A018. A list of attendees is provided as Enclosure 1.

The licensee's presentation, available at ADAMS Accession No. ML16134A172, included the LAR's purpose, system description, licensing history and current licensing basis, and LAR approach and analysis.

The NRC staff queried the licensee on any operator actions that would be required for this LAR and how they would be accounted for and analyzed. The licensee described the current consideration of this effects related to the LAR. The licensee was asked about the operation of the future system during low load periods, fall and winter. The licensee responded by describing the operational scheme for the system during those periods.

One member of the public called into the meeting. Public Meeting Feedback forms were not received.

Please direct any inquiries to me at 301-415-5136LJ ov.

I L. John I s, ct Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-397

Enclosure:

List of Attendees cc w/encl: Distribution via Listserv

LIST OF ATTENDEES MAY 3, 2016. MEETING WITH ENERGY NORTHWEST REGARDING UPCOMING LICENSE AMENDMENT REQUEST EMERGENCY CONTROL ROOM CHILLER SYSTEM COLUMBIA GENERATING STATION DOCKET NO. 50-397 John Klos U.S. Nuclear Requlatorv Commission (NRG)

Larry Wheeler NRG Dan Bradley NRG Matthew Hamm NRG Brian Green NRG Naqeswara Karioineni NRG Kaihwa Hsu NRG Don Greqoire* Enerav Northwest (EN)

I Dwayne Gregory* EN Mike 0. Kennedy* EN Alex Javorik EN AliZbib EN Dave Brown EN Lisa Williams EN Engineering Planning and Management Inc.,

Jeff Quinn member of the public

  • participated via phone Enclosure

Meeting Notice: ML16111A018; Meeting Summary: ML16138A376; Handouts: ML16134A172 OFFICE NRR/DORL/LPL4-1 /PM NRR/DORL/LPL4-1 /LA NRR/DORL/LPL4-1 /BC NRR/DORL/LPL4-1/PM NAME JKlos JBurkhardt RPascarelli JKlos DATE 5/24/16 5/18/16 5/25/16 5/25/16