LER 79-100/03L-0:on 790903,during Steady State Operation, Greater than 12-step Disagreement Was Noted Between Rod Position Indicator D-10 & Group Demand Indication.Caused by Voltage Drift in Signal Conditioning Card
ML19275A227
Person / Time
Site: North Anna Dominion icon.png
Issue date: 09/27/1979
From: Cartwright W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19275A222 List:
References
LER-79-100-03L, LER-79-100-3L, NUDOCS 7910030347
Download: ML19275A227 (2)


Text

NRC FORM 66 U.S. NUCLE AR REGULATORY COMMISSloN

'*

CONTROL BLOCK: l l l f

l l l LICENSEE EVENT REPORT 6

l (PLEASE PRINT OR TYPE ALL P IOUIRED INFORMATIONI 1

l 0 l 81D l l VLICENSEE 7

lAlN CODE l A l S l 1 l@l 0l 0l -l 14 lb 0l 0l 0l Ol 0l -l 0l 230 @l LICENSE NUMBEH 2b 4lLICL1l S1l 1l 1l@lbl C Al l bdl@

  • TYPE .;d CON'T olij '}"y lLl@

,

q 5l 0l 0l 0l 3l 3l 8]@l 01 9l 0l 3] 7] 9 l@ 7) 0 9l 14 2l 7 7l9l@

HEPORTDATE 80

/ 8 ,J 63 DOCKET NUMB E R 6M 63 EVENT DATE EVENT DESCRIPTION AND PROBABLE CONSEQtlENCES h o 2 During steady state operation, a greater than 12 step disagreement was noted between i o 3 l rod position indicator D-10 and the group demand indication. This is contrary to l g) l T.S. 3.1.3.2. The rod position indication was restored 'rithin 8 hourr, as per l This event is reportable as per T.S. 6.9.1.9.b 4

[O s ! Action Statement a.2 of T.S. 3.1.3.2.

[5] The health and si.fety of the general public were not affected by this event. l O 1 l I

EIE]8 I9 i

80 SY S T E *.1 CAUSE CAUSE COVP. VALVE CODE COCE Su3 CODE COMPONENT CODE SUBCODE SU8 CODE

[o 9 lIlFl@ { @ p l @ [I lN lS l? lR lU l@ y @20y @ 18 19 7 e 9 10 In 12 13 Sf 0 VENTI AL OCCURRENCE REPORT HEVISION

_

EVENT YE AR HSPORT NO CODE TYPE NO.

LER AO

@ w!P ' l 7l 9l g l 1l 0 0l 24 26 y

21 23 0l3l 29 l Ll Ju l _._l 38 l0l 12

_2' 22 23 Y F A O OJPLA T ' TH HOUHS 22 58 IT D FOR b B. S PPLit MAN FACTURER d@l zl@ lZ l@ l Zl@

31 J4 3a Jo l0 l0 l0 lY j 3/ 40 gg 41 lN 42 lN 43 g lWl1l2l0lg 44 47 CAUSE OESCRIPTION AND CORRECTIVE ACTIONS h

i o l The cause of this event was a voltage drift in the signal conditioning card. l r, ,

Immediate corrective action was to recalibrate and to perform functional tests.

Further corrective actions have been determined and are presently being pursued. l

,, ;, l LLLI.]

li 141 l 80 7 8 9 ST S *.PCWER OTHER STATUS ISCO HY DISCOVERY DESCRIPTION 31I5I lEl g l 0 9l1lgjNA l l A lgl Operator Observation l ACTIVI TY CONTENT REL ASEO OFRELEASE A*.?OUNT OF ACTIVITY LOCATION OF RELEASE li c "^ l I "A l__J @ Lz J@l PE NSONN LfxPOS ES p ^

'

NU'.'9 9 4 TYPE D E SCRIP T!ON 39 (' ' - ~

' 4 l ,i 10 1 0IOl@lzl@l J l

.

PENS @ NEL NJ  ;ES Nua N E R OESca:PTIO*4

-

.

1AJ1010 3 9 Ol@l11 12 80 I

L O*,; OF OR O A'.' 40E TO F ACILITY TYPE D E SC PIP ilON

"^

lbJl2l@l 1 0 . sn j

-

1 e.)

NHC UE ONW dB ,sdSI"81$sbnm@ NA 7910050 M 7 lllllllllj

,

l [ll 10 68 L> 80 5 7 8 9

.- - 't r' , <+  ;. . (70 V Qq &_9191 0

-

i Virginta Electric and Power Company North Anna Power Station, Unit #1

Attachment:

Page 1 of 1 Docke t No. 50-338 Report No. LER 79-100/03L-0 Description of Event:

During steady state operation, a greater than 12 step disagreement was noted between rod position indicator D-10 and the group demand indication. This is contrary to T.S. 3.1.3.2.

The rod position indication was restored within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> as per Action State-ment a.2 of T.S. 3.1.3.2.

This event is reportable as per T.S. 6.9.1.9.b. and is a generic problem with Unit #2. -

Probabic Consequences of Event:

Operability of the control rod position indication is required to determine control rod position and thereby ensure compliance with the control rod align-ment and insertion limits.

Since the control rod was not misaligned and the position indication was re-stored, there was no effect on the safe operation of the plant. As a result, a t no time was the health and safety of the general public affected.

Cause of Occurrence:

The cause of this event was a voltage drift in the signal conditioning card.

Immediate Corrective Action:

A recalibration and functional test was performed and the IRPI was returned to service.

Scheduled Corrective Action:

Results of an engineering study on IRPI drif t will be implemented.

Action Taken to Prevent Recurrences:

No further corrective action was required.