Monthly Operating Repts for Oct 1998 for North Anna Power Station,Units 1 & 2.With
ML20195D057
Person / Time
Site: North Anna  
Issue date: 10/31/1998
From: Matthews W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
98-682, NUDOCS 9811170281
Download: ML20195D057 (11)


Text

. -..

. ~.

l VIRGINIA ELECTRIC AND POWER COMPANY j

RICHMOND, VIRGINIA 200 61 November 10,1998 i-United States Nuclear Regulatory Commission Serial No.98-682 Attention: Document Control Desk NAPS /JHL Washington, D. C. 20555 Docket Nos.

50-338 50-339 i

License Nos. NPF-4 l

NPF-7 l

l Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY l

NORTH ANNA POWER STATION UNIT NOS.1 AND 2 jA_ONTHLY OPERATING REPORT Enclosed is the October 1998 Monthly Operating Report for North Anna Power Station i

Units 1 and 2.

Very truly yours,

&&W i

W. R. Matthews Site Vice President l

Enclosure l

Commitments made in this letter: None, cc:

U. S. Nuclear Regulatory Commission Region 11 l

Atlanta Federal Center

-) d/ b n gi '

I 61 Forsyth St., SW, Suite 23T85 l

Atlanta, Georgia 30303 l

Mr. M. J. Morgan NRC Senior Resident inspector North Anna Power Station 9811170281 981031 U

l' PDR ADOCK 05000338 i

R PDR

}

l

VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANfjA POWER STATION MONTHLY OPERATINO REPORT OCTOBER 1998

)

Approved.

b

//

/

Sit 5 Vice President Date I

l l

OPERATING DATA REPORT

~

Docket No : 50-338 Date:

11/05/98

Contact:

W. R. Matthews i

Telephone: (540) 894-2101 1.

Unit Name:

North Anna Unit 1 2.

Reporting Period:.

October,1998 3.

Licensed Thermal Power (MWt):.

2,893 4.

Nameplate Rating (Gross MWe):

979.74

5. - Design Electrical Rating (Net MWe):

907 6.

Maximum Dependable Capacity (Gross MWe):

940 7.

Maximum Dependable Capacity (Net MWe):

893 8.

If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:

N/A 9.

Power Level To Which Restricted, if Any (Net MWe): N/A 10.

Reasons For Restrictions, if Any:

N/A This Month Year-To-Date Cumulative

11. Hours in Reporting Period 745.0 7,296.0 178,476.0
12. Hours Reactor Was Critical 585.9 6,706.2 139,961.2
13. Reactor Reserve Shutdown Hours 24.3 39.2 7,134.2

' 14. Hours Generator On-Line '

566.8 6,628.4 136,795.8

15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1,511,442.1 18,926,310.2 369,460,782.7

]

17. Gross Electrical Energy Generated (MWH) 502.115.0 6,177,082.0 158,347,735.0 1
18. Net Electrical Energy Generated (MWH) 476,205.0 5,872,520.0 115,016,703.0 19.' Unit Service Factor 76.1 %

90.8 %

76.6 %

20. Unit Availability Factor 76.1 %

90.8 %

76.6 %

21. Unit Capacity Factor (Using MDC Net) 71.6 %

90.1 %

72.1 %

22. Unit Capacity Factor (Using DER Net) 70.5 %

88.7 %

71.1 %

23. Unit Forced Outage Rote 0.0%

0.9%

8.0%

24.

Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration of Each):

N/A I

25. If Shut Down at End of Report Period Estimated Date of Start.up:
26. Unit in Test Status (Prior to Commercial Operation):

FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION 4

AVERAGE DAILY UNIT POWER LEVEL Docket No.: 50-338 Unit Name: North Anna Unit 1 Date: 11/05/98

Contact:

W. R. Matthews Telephone: (540) 894-2101

' MONTH:

October,1998 Average Daily Power Level Average Daily Power Level Day (MWe Net)

Day (MWe - Net) 1 000 17 795 2

000 18 850 3'

000 19 919 4

000 20 919 5

000 21 919 6

000 22 919 7

000 23 918 l

8 102 24 919 9-275 25 958 l

l 10 561 26 919 11 847 27 919 l

J 12 892 28 919 13 911 29 920 14 918 30 919 15 919 31 919 16 786 i

l I

4 lNSTRUCTIONS l

i; l On this format, list the average daily unit power level in MWe - Net for each day in the reporting month. Compute i.

to the nearest whole megawatt.

4:

sy.

!l-l

~

~

- " - ' ~ - -

^

~

Docket No.: 50-338 Unit Name: North Anna Unit 1

'a Date: 11/05/98

Contact:

W. R. Matthews Telephone: (540) 894-2101 NORTH ANNA POWER STATION UNIT NO.:,,1 MONTH: October 1998

SUMMARY

OF OPERATING EXPERIENCE Page 1 of 2 Usted below in chronological sequence is a summary of operating experiences for this month which required load reductions or resulted in significant non-load related incidents.

Qgtp '

Time Data October 1,1998 0000 Began the month in Mode 5.

October 6,1998 1405 Entered Mode 4.

1833 Entered Mode 3.

j October 7,1998 1504 Reactor is critical.

October 8,1998 0915 Closed G-12 breaker. Unit 1 is on-line.

l 2110 Stopped ramp-up at 30% power to perform flux mapping.

]

2158 Unit is in a 30% power chemistry hold.

i October 9,1998 0526 Cleared 30% power chemistry hold and commenced ramp-up.

1615 Holding power at 45.6%,411 MWe to swap feedwater pumps and perform flux mapping.

October 10,1998 0250 Flux mapping complete. Commenced unit ramp-up.

0921 Unit stable at 70% power,660 MWe, for flux mapping.

1615 Flux mapping completed satisfactorily.

October 11,1998 0053 Commenced unrt ramp-up.

0915 Stabilized power at 96%, 926 MWe, for flux mapping.

1707 Commenced ramp-up to 100% power.

l' 1745 Unit at 100% power,965 MWe.

l October 12,1998 1640 Electrohydraulic Control (EHC) oil leak discovered on No.1 governor valve. Commenced unit ramp-down.

i i

r

_..m

.. ~.

.. _. _ ~ _ _ _ _ _ _.... _...

_. ~ _ _...

l g

Docket No.: 50-338 l

Unit Name: North Anna Unit 1 l

Date: 11/05/98

Contact:

W. R. Matthews Telephone: (540) 894-2101 i

NORTH ANNA POWER Sl'ATION UNIT NO.:.1 MONTH: October 1998

SUMMARY

OF OPERATING EXPERIENCE l

l Page 2 of 2 Listed below in chronological sequence is a summary of operating experiences for this month which required load reductions or resulted in significant non-load related incidents.

l Dalt Il!Bf Rela October 12,1998 1700 Isolated leak on No.1 governor valve. Power is stabilized at 93%

i power,905 MWe.

]

2009 Commenced ramp-down to establish full closed signal from EHC system to govemor valve No.1. Unit at 91% power,881 MWe.

i 2026 Stopped ramp-down. Governor valve No.1 is full closed.

l 2105 EHC restored to govemor valve No.1. Commenced ramp-up to 100% power.

1-October 13,1998 0347 Unit at 100% power,965 MWe.

October 16,1998 0003 Commenced ramp-down to pe-form condenser water box maintenance.

0139 Unit at 86% power,845 MWe.

' October 17,1998 1737 Condenser water box maintenance complete. Commenced ramp-up to 90% power.

1857 Holding power at 90%, 858 MWe, to perform calorimetric.

October 18,1998 1652 Commenced ramp-up to 100% power.

2027 Unit at 100% power,962 MWe.

October 31,1998 2400 Ended montn in Mode 1,100% power, 966 MWe.

l f

l l

_ _. -. _.. _ _.. ~. _ _ _. -. - _ _ _ -. _.. _, _... _ _ _..

Docket No.: 50-338 Unit Name: North Anna Unit 1 Date: 10/05/98

Contact:

W. R. Matthews Telephone: (540)894-2101 UNIT SHUTDOWN AND POWER REDUCTION (EQUALTo on GREATER THAN 20%)

REPORT MONTH: September,1998 (1)

(2)

(3)

(4)

(5)

Method Duration of LER No.

System Component Cause & Corrective Action

. Date Type Hours -

Reason Shutting Code Code to Prevent Recurrence 1

Down Reactor 9-13-98 S

177 hrs.

C 1

NA NA NA Continuation of 1998 scheduled refueling 15 mn.

outage.

l (1)

(2)

(3)

F: Forced REASON:

METHOD:

S: Scheduled A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Other (Explain)

E-Operator Training & Licensing Examination F-Administrative G-Operational Error (Explain)

(4)

(5) l Exhibit G -Instructions for Preparation of Data Entry Sheets Exhibit 1 - Same Source I

for Licensee Event Report (LER) File (NUREG 0161) p F

i t

t

- -... - -. - ~ _ -

l OPERATING DATA REPORT l

^

Docket No.: 50-339 Date:

11/05/98

Contact:

W. R. Matthews Telephone: (540) 894-2101 1.

Unit Name:.

North Anna Unit 2 2.

Reporting Period:...

October,1998 3.

Licensed Thermal Power (MWt):.

2,893

4. - Nameplate Rating (Gross MWe):

979~

5.

Design Electrical Rating (Net MWe):

907 6.

Maximum Dependable Capacity (Gross MWe):.

944 7.

Maximum Dependable Capacity (Net MWe):

897 8.

If Changes Occur in Capacity Ratings (items Number 3 Through 7) Since Last Report, Give Reasons:

N/A 1

9.

Power Level To Which Restricted, if Any (Net MWe): N/A 10.

Reasons For Restrictions, if Any:

N/A This Month Year-To-Date Cumulative 11.

Hours in Reporting Period 745.0 7,296.0 156,744.0 12, Hours Reactor Was Critical 745.0 6,609.8 132,324.2 l

13.

Reactor Reserve Shutdown Hours 0.0 57.3 7,241.5 14.

Hours Generator On-Line 745.0 6,587.1 131,109.3 15.

Unit Reserve Shutdown Hours 0.0 0.0 0.0 16.

Gross Thermal Energy Generated (MWH) 2,154,864.1 18,699,766.7 359,492,946.7

17. - Gross Electrical Energy Generated (MWH) 700,910.0 6,072,941.0 117,575,455.0 18.

Net Electrical Energy Generated (MWH) 666,046.0 5,769,828.0 112,297,796.0 19.

Unit Service Factor 100.0 %

90.3%

83.6 %

20.

Unit Availabihty Factor 100.0%

90.3 %

83.6 %

21.

Unit Capacity Factor (Using MDC Net) 99.7 %

88.2 %

79.7 %

22.

Unit Capacity Factor (Using DER Net) 98.6 %

87.2 %

79.0% -

23.

Unit Forced Outage Rate 0.0%

0.3%

4.8%

24. Shutdowns Scheduled Over Next 6' Months (Type, Date, and Duration of Each):

9 None

25. If Shut Down at End of Report Period, Estimated Date of Start-up:

N/A

26. Unit in Test Status (Prior to Commercial Operation):

FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

AVERAGE DAILY UNIT POWER LEVEL l

Docket No.: 50-339 Unit Name: North Anna Unit 2 Date: 11/05/98

Contact:

W. R. Matthews Telephone: (540)894-2101

' MONTH:

October,1998 Average Daily Power Level '

Average Daily Power Level DaL (MWe - Net)

Day (MWe - Net) 1

-888 17 894 2

889 18 895 1

3 890 19 896 4

890 20 896 i

1 5

887 21 896 6

889 22 895 7

889 23 896 8

890 24 896 9

891 25 898 10 893 26 898 l

11 893 27 898 12 895 28 898 13 895 29 898 14 896 30 898 15 896 31 897 16 894 l

INSTRUCTIONS On this format, list the average daily unit power level in MWe - Net for each day in the reporting month. Compute to the nearest whole megawatt.

(...

~

J Docket No.: 50-339 Unit Name: North Anna Unit 2 Date:

11/05/98

Contact:

W. R. Matthews Telephone: (540) 894-2101 NORTH ANNA POWER STATION UNIT NO.:,2 MONTH: October 1998

SUMMARY

OF OPERATING EXPERIENCE

'l Page 1 of 1 -

. Listed below in chror.ological sequence is a summary of operating experiences for the month which required load reductions or resulted in significant non-load related incidents.

E.W.g li_m_,g 9.g!t,g October 1,1998 0000 Began the month in Mode 1,100% power,935 MWe.

October 31,1998 2400 Ended the monti, in Mode 1,100% power, 944 MWe.

i l,

', 1

~

l Docket No.: 50-339 Unit Name: North Anna Unit 2 Date: 11/05/98

Contact:

W. R. Matthews Telephone: (540) 894-2131 UNIT SHUTDOWN AND POWER REDUCTION (EQuALTo oR GREATER THAN 20%)

REPORT MONTH: October,1998 (1)

(2)

(3)

(4)

(5)

Method Duration of LER No.

System Compcnent Cause & Corrective Action Date Type Hours Reason Shutting Code Code to Prevent Recurrence Down Rx None during the reporting period.

l I

l l

(1)

(2)

(3)

F: Forced REASON:

METHOD:

S: Scheduled A-Equipment Failure (Explain) 1 - Manual 8-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Other (Explain)

E-Operator Training & Licensing Examination F.-

Administrative G-Operational Error (Explain)

(4)

(5)

Exhibit G -Instructions for Preparation of Data Entry Sheets Exhibit 1 - Same Source for Licensee Event Report (LER) File (NUREG 0161) 4 3

l'

_