MONTHYEARML16138A1682016-05-0202 May 2016 Licensee Presentation Regarding Mur Power Uprate for Columbia Generating Station, Pending LAR Project stage: Other ML16138A3292016-05-24024 May 2016 Summary of 5/2/2016 Prelicensing Meeting with Energy Northwest to Discuss Measurement Uncertainty Recapture Power Uprate License Amendment Request at Columbia Generating Station Project stage: Meeting 2016-05-02
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24177A1892024-06-28028 June 2024 Summary of Information Meeting with Question and Answer Session to Discuss the 2023 Annual Assessment of Safety Performance at Columbia Generating Station ML24142A4982024-05-22022 May 2024 Summary of April 17, 2024, Partially Closed Pre-Application Meeting with Energy Northwest Regarding an Extended Power Uprate Combined with Maximum Load Line Limit Analysis Plus for Columbia Generating Station ML23297A2642023-11-0606 November 2023 October 5, 2023, Summary of Teleconference with Energy Northwest Regarding Proposed License Amendment Request to Revise the Emergency Plan for Columbia Generating Station ML23156A2822023-06-0505 June 2023 Summary of Meeting with Q & a Session to Discuss the 2022 Annual Assessment of Safety Performance at CGS ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22067A1832022-03-10010 March 2022 Summary of Energy Northwest Regulatory Conference Columbia Generating Station, Airborne Radioactivity Event Resulting in Preliminary White Finding, March 1, 2022 ML21321A0422021-12-13013 December 2021 Summary of October 22, 2021, Teleconference Meeting with Energy Northwest Regarding Proposed License Amendment Requests to Adopt Technical Specifications Task Force (TSTF)-505, and 10 CFR 50.69 Categorization Program ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21112A3512021-05-0303 May 2021 Summary of March 31, 2021, Pre-Application Teleconference with Energy Northwest to Discuss a Planned LAR Deletion of Certain License Conditions Relating to License Renewal Commitments for Columbia Generating Station ML20322A0362020-11-19019 November 2020 Summary of October 19, 2020, Presubmittal Teleconference with Energy Northwest Regarding Proposed COVID-19 Related Biennial Emergency Preparedness Exercise Exemption Request for Columbia Generating Station ML20314A0462020-11-0909 November 2020 Summary of November 4, 2020, NRC-NMFS Teleconference on Columbia Entrainment Study ML20189A2832020-07-0707 July 2020 Summary of Region IV Annual Assessment Public Meeting ML20101L5352020-04-14014 April 2020 Summary of April 6, 2020, Presubmittal Teleconference Meeting with Energy Northwest, to Discuss a Technical Specification Change License Amendment Request for the Columbia Generating Station ML19030A2152019-02-12012 February 2019 1/24/19, Summary of Presubmittal Teleconference Meeting with Energy Northwest, to Discuss a Shield Wall Deferral License Amendment Request for the Columbia Generating Station ML19030A3192019-02-12012 February 2019 1/17/2019, Summary of Presubmittal Meeting with Energy Northwest, to Discuss an Emergency Control Room Chiller License Amendment Request at Columbia Generating Station ML18354B0992019-01-0303 January 2019 Summary of Pre-Submittal Meeting with Energy Northwest, to Discuss an Emergency Control Room Chiller License Amendment Request for the Columbia Generating Station ML16266A3712016-09-29029 September 2016 Summary of Public Meeting with Energy Northwest to Discuss Upcoming License Amendment Request Regarding Change in Completion Time for Residual Heat Removal Pump a Repair for Columbia Generating Station ML16167A4602016-08-23023 August 2016 Summary of Closed Meeting with Representatives of the Us Army Corps of Engineers, Bureau of Reclamation, and Energy Northwest to Discuss the Flood Analysis Associated with Columbia Generating Station ML16193A0162016-07-14014 July 2016 Summary of 6/30/16 Prelicensing Meeting with Energy Northwest to Discuss License Amendment Request to Revise Emergency Action Levels Based on Nuclear Energy Institute (NEI) 99-01, Revision 6 at Columbia Generating Station ML16138A3762016-05-25025 May 2016 Summary of 5/3/2016 Prelicensing Meeting with Energy Northwest to Discuss License Amendment Request Regarding Emergency Control Room Chiller System at Columbia Generating Station ML16138A3292016-05-24024 May 2016 Summary of 5/2/2016 Prelicensing Meeting with Energy Northwest to Discuss Measurement Uncertainty Recapture Power Uprate License Amendment Request at Columbia Generating Station ML16126A4822016-05-17017 May 2016 Summary of Prelicensing Meeting with Energy Northwest to Discuss License Amendment Request Concerning Portional Reclassification of Reactor Water Cleanup System at Columbia Generating Station ML16138A1682016-05-0202 May 2016 Licensee Presentation Regarding Mur Power Uprate for Columbia Generating Station, Pending LAR ML15187A4442015-07-0606 July 2015 Summary of a Regulatory Conference to Discuss the Safety Significance of a Columbia Finding Emergency Plan Implementing Procedures Did Not Implement Some Protective Action Recommendations Required by the Emergency Plan ML15173A2732015-06-30030 June 2015 Summary of June 4, 2015, Category 1 Public Meeting with Energy Northwest to Discussion Columbia Generating Station Seismic Hazard Reevaluation Associated with Implementation of Japan Lessons-Learned Near-Term Task Force Recommendation 2.1, ML15069A5162015-03-17017 March 2015 2/24/2014 Summary of Presubmittal Meeting with Energy Northwest to Discuss Relief Request for Radwaste Cleanup Piping for Columbia Generating Station ML14168A0452014-07-0808 July 2014 Summary of 6/10/14 Closed Meeting Between U.S. Army Corps of Engineers, U.S. Dept of Interior Bureau of Reclamation, and Energy Northwest to Discuss Flooding Analysis for Columbia Generating Station ML13339B1452013-12-0505 December 2013 Meeting Summary for Public Meeting with Energy Northwest Regarding Columbia Generating Station ML12306A3332012-11-16016 November 2012 Summary of 10/18/12 Pre-licensing Meeting to Discuss Future License Amendment Request to Address Impacts of Remediation Activities Undertaken by Department of Energy in the Owner-Controlled Area at Columbia Generating Station ML12293A0592012-10-18018 October 2012 Summary of Meeting with Energy Northwest Regarding Columbia Generating Station Performance Improvement Initiatives ML12157A2722012-06-11011 June 2012 5/31/2012 Summary of Telephone Conference with Licensees Regarding Near Term Task Force Recommendation 2.1 Seismic Reevaluations - Diablo Canyon, 1 and 2, San Onofre, Units 2 and 3, Columbia Generating Station, and Palo Verde, Units 1, 2, a ML1201201102012-01-12012 January 2012 Summary of Meeting with Energy Northwest Regarding Columbia Generating Station Performance Improvement Initiatives ML11350A0562011-12-21021 December 2011 12/15/11, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Energy Northwest, Concerning the Metal Fatigue and Operating Experience Open Items in the Columbia License Renewal Safety Evaluation Repo ML11339A0872011-12-12012 December 2011 Summary of Telephone Conference Call Held on November 28, 2011, Between the U.S. Nuclear Regulatory Commission and Energy Northwest, Concerning the Upper Shelf Energy Open Item in the Columbia License Renewal Safety Evaluation Report with O ML11339A0852011-12-12012 December 2011 November 8, 2011, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Energy Northwest, Concerning the Metal Fatigue Open Item in the Columbia License Renewal Safety Evaluation Report with Open Items ML11336A1502011-12-12012 December 2011 Summary of Telephone Conference Call Held on November 14, 2011, Between the U.S. Nuclear Regulatory Commission and Energy Northwest, Concerning the Metal Fatigue Open Item in the Columbia License Renewal Safety Evaluation Report with Open I ML11249A0132011-11-21021 November 2011 08/29/2011-Summary of Tele Conf Call Between the USNRC and Energy Northwest, Concerning the Response to the Request for Additional Information Pertaining to the Columbia Generating Station, License Renewal Application ML11311A2662011-11-10010 November 2011 Summary of Tele Conf Call Held on 11/2/11, Between the USNRC and Energy Northwest, Concerning the Core Plate Hold-Down Bolts Open Item in the Columbia License Renewal Safety Evaluation with Open Items ML11305A1762011-11-0303 November 2011 Summary of Tele Conf Call Held on 10/27/11, Between the USNRC and Energy Northwest, Concerning the Metal Fatigue Open Item in the Columbia License Renewal Safety Evaluation with Open Items ML11291A0792011-11-0101 November 2011 09/27/2011 Summary of Public Meetings Conducted to Discuss the Dseis Related to the Review of the Columbia Generating Station License Renewal Application (Tac No. ME3121) ML11273A0012011-10-0404 October 2011 Summary of Teleconf Call Held on Sept. 28, 2011, Between the USNRC and Energy Northwest, Concerning the Draft Request for Additional Information Pertaining to the Columbia Generating Station, License Renewal Application ML11273A0662011-10-0404 October 2011 Summary of the Telephone Conference Call Held on September 29, 2011, Concerning the Inspection Report Pertaining to the Columbia Generating Station, License Renewal Application ML11256A3002011-09-23023 September 2011 Summary of Telephone Conference Call Held on September 12, 2011, Concerning the Draft Request for Additional Information Pertaining to the Columbia Generating Station, License Renewal Application ML11238A1582011-09-14014 September 2011 8/25/11 - Summary of Telephone Conference Call Between NRC and Energy Northwest Concerning Drais Pertaining to the SAMA Review of the Columbia Generating Station License Renewal Application ML11250A0152011-09-0808 September 2011 Summary of Tele Conf Call Held on August 22, 2011, Btw the USNRC and Energy Northwest, Concerning Topics Pertaining to the Columbia Generating Station, License Renewal Application ML11223A3512011-08-23023 August 2011 Summary of Telephone Conference Call Held on August 11, 2011, Between the NRC and Energy Northwest, Concerning the Response to the Request for Additional Information Pertaining to the Columbia Generation Station, LRA ML11230B0892011-08-23023 August 2011 August 17, 2011, Summary of Conference Call Held, Between the U.S. Nuclear Regulatory Commission and Energy Northwest, Concerning the Response to the Request for Additional Information Pertaining to the Columbia Generating Station, LRA ML11216A2532011-08-11011 August 2011 August 3, 2011, Summary of Telephone Conference Call Held Between the NRC and Energy Northwest, Concerning the Response to the Request for Additional Information Pertaining to the Columbia Generating Station, LRA ML11217A0222011-08-11011 August 2011 8/3-4/11, Summary of Telephone Conference Call Held Between Nuclear Regulatory Commission and Energy Northwest, Concerning the Response to the Request for Additional Information Pertaining to the Columbia Generating Station, LRA ML11220A0102011-08-11011 August 2011 February 3, 2011, Summary of Telephone Conference Call Held Between NRC and Energy Northwest, Concerning the Responses to the RAI Pertaining to the Columbia Generating Station, LRA 2024-06-28
[Table view] |
Text
LICENSEE:
Energy Northwest FACILITY:
Columbia Generating Station
SUBJECT:
SUMMARY
OF MAY 2, 2016, PUBLIC MEETING WITH ENERGY NORTHWEST TO DISCUSS UPCOMING LICENSE AMENDMENT REQUEST REGARDING MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE FOR COLUMBIA GENERATING STATION (CAC NO. MF7592) On May 2, 2016, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Energy Northwest, the licensee, at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland.
The purpose of the meeting was to discuss the licensee's upcoming license amendment request (LAR) regarding a measurement uncertainty recapture (MUR) power uprate for Columbia Generating Station. The meeting notice and agenda, dated April 20, 2016, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML16111A015.
A list of attendees is provided in the Enclosure.
The licensee's presentation, available at ADAMS Accession No. ML16138A168, included the LAR background and a discussion of the leading edge flow meter (LEFM) system. The NRC staff queried the licensee about how a review matrix included in NRC Regulatory Issue Summary (RIS) 2002-03, "Guidance on the Content of Measurement Uncertainty Recapture Uprate Applications," dated January 31, 2002 (ADAMS Accession No. ML013530183), would be applied in the LAR. The licensee responded that a matrix would identify where elements of RIS 2002-03 could be found in the LAR. The NRC also inquired if the licensee's grid reliability study would be submitted to the licensee in a timely manner to support the current LAR submission date. The licensee stated that the study was on schedule to support the intended LAR submission date. The staff also asked if a reload analysis would be part of the LAR. The licensee is reviewing the applicability of that study to the LAR. The licensee was asked to address in the LAR the upstream and downstream straight pipe runs for the flow meters and to include information on meeting or exceeding the requirements established during the flow meter laboratory calibration.
There was also a discussion regarding availability of the LEFM operational data for review to validate instrument performance.
The licensee stated that the LEFM flowmeters were installed during the R22 refueling outage in 2015 and that operational data could be made available to the NRC staff as needed. The licensee was also asked to consider in the LAR LEFM failure modes and the effects on plant operation while in reduced accuracy modes of operation.
The NRC staff also asked the licensee if there are any new, changed, or deleted operator actions associated with the MUR power uprate. The licensee responded that only one new operator action, related to monitoring of power level, will be added. The NRC staff asked the licensee to identify if there will be any changes to the Human System Interface identified in the proposed LAR. The licensee stated that the changes to the Human System Interface will be limited to flashing lights on the process computer and possibly an audible alarm. The licensee also confirmed that the submittal will contain a section discussion Human Performance evaluation.
One member of the public was in attendance.
Public Meeting Feedback forms were not received.
Please direct any inquiries to me at 301-415-513 Docket No. 50-397
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv n los, Project Manager ant Ucensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation LIST OF ATTENDEES MAY 2, 2016, MEETING WITH ENERGY NORTHWEST REGARDING UPCOMING LICENSE AMENDMENT REQUEST MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE COLUMBIA GENERATING STATION DOCKET NO. 50-397 John Klos U.S. Nuclear Regulatory Commission (NRC) Subinov Mazumdar NRC Steve Jones NRC Gursharan Singh NRC Richard Stattel NRC Victoria Huckabee NRC Alexander Chereskin NRC Eric Oesterle NRC Russell Haskell NRC Shie-Jeng Peng NRC Kaihwa Hsu NRC Swagata Som NRC Matt Yoder* NRC Marqaret Chernoff NRC Ali Zbib Enerav Northwest (EN) Dave Brown EN Dave Kettering EN Alex Javorik EN Jim Brownell EN Dan Moon EN Lisa Williams EN Larry King General Electric, member of the public *participated via phone Enclosure licensee to identify if there will be any changes to the Human System Interface identified in the proposed LAR. The licensee stated that the changes to the Human System Interface will be limited to flashing lights on the process computer and possibly an audible alarm. The licensee also confirmed that the submittal will contain a section discussion Human Performance evaluation.
One member of the public was in attendance.
Public Meeting Feedback forms were not received.
Please direct any inquiries to me at 301-415-5136 or John.Klos@nrc.gov.
Docket No. 50-397
Enclosure:
List of Attendees IRA/ L. John Klos, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL4-1 r/f RidsACRS_MailCTR Resource RidsNrrDeEeeb Resource RidsNrrDeEicb Resource RidsNrrDeEmcb Resource RidsNrrDeEpnb Resource RidsNrrDeEsgb Resource RidsNrrDorl Resource RidsNrrDorllpl4-1 Resource RidsNrrDraAphb Resource RidsNrrDssSbpb Resource RidsNrrDssSbpb Resource RidsNrrDssSrxb Resource RidsNrrDssStsb Resource RidsNrrLAJBurkhardt Resource RidsNrrPMColumbia Resource RidsRgn4MailCenter Resource RStattel, NRR/DE/EICB SMazumdar, NRR/DE/EICB MChernoff, NRR/DSS/STSB RHaskell, NRR/DORL/LPL3-2 KHsu, NRR/DE/EMCB AChereskin, NRR/DE/ESGB VHuckabee, NRR/DRA/APHB SPeng, NRR/DSS/SRXB GSingh, NRR/DE/EICB SSom, NRR/DE/EEEB MYoder, NRR/DE/ESGB EOesterle, NRR/DSS/SRXB SJones, NRR/DSS/SBPB TWertz, NRR JBowen, EDO RIV ADAMS Accession No. Meeting Notice ML16111A015; Meeting Summary ML16138A329; Handouts ML16138A168 OFFICE NRR/DORL/LPL4-1
/PM NRR/DORL/LPL4-1
/LA NRR/DORL/LPL4-1/BC NRR/DORL/LPL4-1/PM NAME JKlos JBurkhardt RPascarelli, LMK for JKlos DATE 5/19/16 5/18/16 5/20/2016 5/24/2016 OFFICIAL RECORD COPY