Forwards Rev 39 to Updated FSAR for Susquehanna Steam Electric Station Units 1 & 2 Per 10CFR50.71
ML18040A904
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 07/19/1988
From: Keiser H
PENNSYLVANIA POWER & LIGHT CO.
To: Butler W
Office of Nuclear Reactor Regulation
Shared Package
ML18040A905 List:
References
PLA-3065, NUDOCS 8807290264
Download: ML18040A904 (2)


Text

Pennsylvania Power&Light Company Two North Ninth Street~Allentown, PA 18101-1179

~215/770-5151 Harold W.Keiser Senior V/ce President.

Nuclear 215/770-4194 July 19, 1988 Director of Nuclear Reactor Regulation Attention:

Dr.W.R.Butler, Project Director Project Directorate I-2 Division of Reactor Projects U.S.Nuclear Regulatory Commission Washington DC 20555 FILE R41-2, A17-1 SUSQUEHANNA STEAM ELECTRIC STATION FINAL SAFETY ANALYSIS REPORT REVISION 39 PLA-3065

Dear Dr.Butler:

Pursuant to 10CFR50.71, under separate cover Pennsylvania Power&Light Company is submitting Revision 39 to the Susquehanna SES Final Safety Analysis Report (FSAR).The FSAR changes contained in Revision No.39 were processed in accordance with'0CFR50.59, were required by the NRC, were subjected to a No Significant Hazards Evaluation, or are administrative in nature.Attachment 1 provides a description of the changes to each section of the FSAR.The latest revision of design drawings have also been incorporated as appropriate.

A description of the actual change(s)to the drawings is not provided in Attachment 1.'t should be noted that this Revision 39 does not include any changes associated with the recently installed Diesel Generator E.We are in the process of reviewing those changes and plan a separate Amendment (Revision 40)submittal in September of this year.Also, many of the changes included in this Revision 39 are the result of incorporating the responses to NRC Questions (FSAR Volumes 16,17&18)into the main FSAR text.These changes are considered editorial since the response essentially remain unchanged.

If you have any questions, please contact D.J.Walters at (215)770-6536.Very truly yours,.(~Simtl)H..'lY.KEiSER H.W.Keiser Senior Vice President-Nuclear cc: Document Control Desk (Original)

NRC Region I Mr.F.I.Young-NRC Sr.Resident Inspector Mr.M.C.Thadani-NRC Project Manager

~~~o I SSES PLA-3065 Files R41-2,A17-1 Dr.W.R.Butler bcc: W.E.Barberich S.H.Cantone C.T.Coddington R.M.Harris E.A.Heckman W.H.Hirst D.J.Walters SRMS Corres File A2-3 A2-4 A2-3 A2-3 A2-3 AE A2-3 A6-2 DJW/krp djwg003i(17)