MONTHYEARIR 05000373/20243012024-10-31031 October 2024 Initial License Examination Report 05000373/2024301 05000374/2024301 IR 05000373/20244042024-10-23023 October 2024 County Station – Security Baseline Inspection Report 05000373/2024404 and 05000374/2024404 IR 05000373/20244012024-09-27027 September 2024 County Station – Security Baseline Inspection Report 05000373/2024401 and 05000374/2024401 IR 05000373/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Lasalle County Station (Report 05000373/2024005; 05000374/2024005) IR 05000373/20244022024-08-28028 August 2024 County Station - Cyber Security Inspection Report 05000373/2024402 and 05000374/2024402 IR 05000373/20240022024-08-13013 August 2024 County Station - Integrated Inspection Report 05000373/2024002 and 05000374/2024002 IR 05000373/20244202024-08-0505 August 2024 County Station - Security Baseline Inspection Report 05000373 2024420 and 05000374 2024420 IR 05000373/20240102024-05-29029 May 2024 County Station - Commercial Grade Dedication Inspection Report 05000373/2024010 and 05000374/2024010 IR 05000373/20240012024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 ML24131A1512024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 IR 05000373/20244032024-05-0202 May 2024 Public Lasalle County Station - Security Baseline Inspection Report 05000373/2024403 and 05000374/2024403; NRC Investigation Report No. 3-2023-006 IR 05000373/20230062024-02-28028 February 2024 Annual Assessment Letter for Lasalle County Station, Units 1 and 2 (Report 05000373/2023006; 05000374/2023006) IR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 IR 05000373/20234022023-12-20020 December 2023 County Station - Security Baseline Inspection Report 05000373/2023402 and 05000374/2023402 IR 05000373/20230032023-11-0909 November 2023 County Station Integrated Inspection Report 05000373/2023003, 05000374/2023003, and 07200070/2023001 IR 05000373/20234012023-11-0707 November 2023 County Station Security Baseline Inspection Report 05000373/2023401 and 05000374/2023401 IR 05000374/20230102023-10-11011 October 2023 NRC Inspection Report 05000374/2023010 IR 05000373/20233012023-09-15015 September 2023 Errata to NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 IR 05000373/20230022023-08-0101 August 2023 County Station - Integrated Inspection Report 05000373/2023002 and 05000374/2023002 IR 05000373/20230112023-06-26026 June 2023 County Station - Quadrennial Fire Protection Team Inspection Report 05000373/2023011 and 05000374/2023011 IR 05000373/20230012023-05-10010 May 2023 County Station - Integrated Inspection Report 05000373/2023001 and 05000374/2023001 IR 05000373/20220062023-03-0101 March 2023 Annual Assessment Letter for LaSalle County Station, Units 1 and 2 (Report 05000373/2022006 and 05000374/2022006) IR 05000373/20220042023-01-31031 January 2023 County Station - Integrated Inspection Report 05000373/2022004 and 05000374/2022004 IR 05000373/20224042022-12-21021 December 2022 County Station - Material Control and Accounting Program Inspection Report 05000373/2022404 and 05000374/2022404 IR 05000373/20225012022-12-0505 December 2022 County Station - Emergency Preparedness Biennial Exercise Inspection Report 05000373/2022501 and 05000374/2022501 IR 05000373/20224022022-11-17017 November 2022 County Station - Security Baseline Inspection Report 05000373/2022402 and 05000374/2022402 IR 05000373/20220032022-11-0101 November 2022 County Station - Integrated Inspection Report 05000373/2022003 and 05000374/2022003 IR 05000373/20220112022-11-0101 November 2022 County Station Design Basis Assurance Inspection (Teams) Inspection Report 05000373/2022011 and 05000374/2022011 IR 05000373/20224032022-09-15015 September 2022 County Station - Cyber Security Inspection Report 05000373/2022403 and 05000374/2022403 IR 05000373/20220052022-08-22022 August 2022 Updated Inspection Plan for Lasalle County Station (Report 05000373/2022005; 05000374/2022005) IR 05000373/20220022022-08-10010 August 2022 County Station - Integrated Inspection Report 05000373/2022002 and 05000374/2022002 IR 05000373/20224012022-05-18018 May 2022 County Station - Security Baseline Inspection Report 05000373/2022401 and 05000374/2022401 IR 05000373/20220012022-04-26026 April 2022 County Station - Integrated Inspection Report 05000373/2022001 and 05000374/2022001 ML22108A2802022-04-19019 April 2022 Information Request for an NRC Triennial Baseline Design Bases Assurance Inspection (Team) Inspection Report 05000373/2022011 05000374/20220 IR 05000373/20220102022-03-15015 March 2022 County Station License Renewal Phase 2 Report 05000373/2022010 IR 05000373/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000373/2021006 and 05000374/2021006) IR 05000373/20210042022-02-0707 February 2022 County Station Integrated Inspection Report 05000373/2021004 and 05000374/2021004 IR 05000373/20210132022-01-20020 January 2022 County Station Biennial Problem Identification and Resolution Inspection Report 05000373/2021013 and 05000374/2021013 IR 05000373/20214022021-12-15015 December 2021 County Station - Security Baseline Inspection Report 05000373/2021402 and 05000374/2021402 IR 05000373/20210032021-11-0808 November 2021 County Station Integrated Inspection Report 05000373/2021003; 05000374/2021003 and 07200070/2021001 IR 05000373/20210022021-11-0101 November 2021 County Station Integrated Inspection Report 05000373/2021002 and 05000374/2021002 IR 05000373/20210122021-10-28028 October 2021 County Station- 50.59 Team Inspection Report 05000373/2021012 and 05000374/2021012 IR 05000373/20210052021-09-0101 September 2021 Updated Inspection Plan for Lasalle County Station, Units 1 and 2; Report 05000373/2021005 and 05000374/2021005 IR 05000373/20210112021-08-23023 August 2021 County Station - Design Basis Assurance Inspection (Programs) Inspection Report 05000373/2021011 and 05000374/2021011 IR 05000373/20215012021-06-16016 June 2021 County Station - Emergency Preparedness Biennial Exercise Inspection Report 05000373/2021501 and 05000374/2021501 IR 05000373/20214012021-05-18018 May 2021 County Station - Security Baseline Inspection Report 05000373/2021401 and 05000374/2021401 IR 05000373/20210012021-05-0404 May 2021 Lssalle County Station - Integrated Inspection Report 05000373/2021001 and 05000374/2021001 IR 05000374/20210102021-04-0505 April 2021 County Station - Post-Approval Site Inspection for License Renewal (Phase I) Report 05000374/2021010 IR 05000373/20200042021-03-0505 March 2021 Reissue - Lasalle County Station - Integrated Inspection Report 05000373/2020004; 05000374/2020004; 05000373/2020501; 05000374/2020501; 05000373/2020011 and 05000374/2020011 2024-09-27
[Table view] Category:Letter
MONTHYEARIR 05000373/20243012024-10-31031 October 2024 Initial License Examination Report 05000373/2024301 05000374/2024301 IR 05000373/20244042024-10-23023 October 2024 County Station – Security Baseline Inspection Report 05000373/2024404 and 05000374/2024404 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000373/LER-2023-001-01, Air Circuit Breaker (Acb) Mechanically Operated Contacts (MOC) Switch Failed to Actuate2024-10-0909 October 2024 Air Circuit Breaker (Acb) Mechanically Operated Contacts (MOC) Switch Failed to Actuate ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000373/20244012024-09-27027 September 2024 County Station – Security Baseline Inspection Report 05000373/2024401 and 05000374/2024401 ML24263A2062024-09-19019 September 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for LaSalle County Station - Holtec MPC-68MCBS ML24260A0492024-09-16016 September 2024 Operator Licensing Examination Approval - Lasalle County Station, Unit 1 and 2, September 2024 RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000373/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Lasalle County Station (Report 05000373/2024005; 05000374/2024005) IR 05000373/20244022024-08-28028 August 2024 County Station - Cyber Security Inspection Report 05000373/2024402 and 05000374/2024402 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 05000373/LER-2024-004-01, Emergency Diesel Generator Auto-Start and Load Due to Loss of System Auxiliary Transformer2024-08-22022 August 2024 Emergency Diesel Generator Auto-Start and Load Due to Loss of System Auxiliary Transformer IR 05000373/20240022024-08-13013 August 2024 County Station - Integrated Inspection Report 05000373/2024002 and 05000374/2024002 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000373/20244202024-08-0505 August 2024 County Station - Security Baseline Inspection Report 05000373 2024420 and 05000374 2024420 05000373/LER-2024-003-01, Supplement to Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded2024-07-31031 July 2024 Supplement to Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification RS-24-064, Nuclear Radiological Emergency Plan Document Revisions2024-06-28028 June 2024 Nuclear Radiological Emergency Plan Document Revisions ML24178A2522024-06-27027 June 2024 County Station – Acknowledgement of Response to NRC Inspection Report 05000373/2024001 and 05000374/2024001 and Disputed Non-Cited Violation 05000373/LER-2024-004, Emergency Diesel Generator Auto-Start and Load Due to Loss of Station Auxiliary Transformer2024-06-19019 June 2024 Emergency Diesel Generator Auto-Start and Load Due to Loss of Station Auxiliary Transformer RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations 05000373/LER-2024-003, Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded2024-06-0606 June 2024 Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded IR 05000373/20240102024-05-29029 May 2024 County Station - Commercial Grade Dedication Inspection Report 05000373/2024010 and 05000374/2024010 ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes 05000373/LER-2024-002, Reactor Protection System Half Scram Due to Motor Generator Set Electric Power Monitoring Assembly Output Breaker Trip2024-05-17017 May 2024 Reactor Protection System Half Scram Due to Motor Generator Set Electric Power Monitoring Assembly Output Breaker Trip RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24131A1512024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 IR 05000373/20240012024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000373/LER-2024-001, Core Operating Limits Report Thermal Limits Exceeded2024-04-26026 April 2024 Core Operating Limits Report Thermal Limits Exceeded ML24108A1562024-04-15015 April 2024 Updated Final Safety Analysis Report (Ufsar), Revision 26 and Fire Protection Report (Fpr), Revision 11 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24071A2122024-03-12012 March 2024 County Station - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection IR 05000373/20230062024-02-28028 February 2024 Annual Assessment Letter for Lasalle County Station, Units 1 and 2 (Report 05000373/2023006; 05000374/2023006) RS-24-014, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-02-22022 February 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors ML24018A0682024-02-0909 February 2024 Issuance of Amendment Nos. 262 and 247 Revised Design Bases of Lower Downcomer Braces ML24024A1332024-01-24024 January 2024 Confirmation of Initial License Examination IR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 ML23354A2902024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0028 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23360A6082023-12-27027 December 2023 County Station Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000373/2024010 and 05000374/2024010 ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums 2024-09-06
[Table view] |
Inspection Report - LaSalle - 2019013 |
---|
|
|
Text
November 21, 2019 Mr. Bryan Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2 - NRC INSPECTION OF TEMPORARY INSTRUCTION 2515/194, INSPECTION OF THE LICENSEES IMPLEMENTATION OF INDUSTRY INITIATIVE ASSOCIATED WITH THE OPEN PHASE CONDITION DESIGN VULNERABILITIES IN ELECTRIC POWER SYSTEMS (NRC BULLETIN 2012-01) REPORT 05000373/2019013 AND 05000374/2019013
Dear Mr. Hanson:
On October 4, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Lasalle County Station, Units 1 And 2. On October 4, 2019, the NRC inspectors discussed the results of this inspection with Phil Hansett and other members of your staff. The results of this inspection are documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA Karla Stoedter for/
Robert C. Daley, Chief Engineering Branch 3 Division of Reactor Safety Docket Nos. 05000373 and 05000374 License Nos. NPF-11 and NPF-18
Enclosure:
As stated
Inspection Report
Docket Numbers: 05000373 and 05000374 License Numbers: NPF-11 and NPF-18 Report Numbers: 05000373/2019013 and 05000374/2019013 Enterprise Identifier: I-2019-013-0014 Licensee: Exelon Generation Company, LLC Facility: LaSalle County Station, Units 1 and 2 Location: Marseilles, IL Inspection Dates: September 30, 2019 - October 4, 2019 Inspectors: Ijaz Hafeez, Reactor Inspector Approved By: Robert C. Daley, Chief Engineering Branch 3 Division of Reactor Safety Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an NRC Inspection of Temporary Instruction 2515/194, inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems (NRC BULLETIN 2012-01) at LaSalle County Station, Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations No findings or violations of more than minor significance were identified.
Additional Tracking Items None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
INSPECTION RESULTS
Observation: Detection, Alarms, and General Criteria 2515/194
- (1) Open Phase Conditions (OPCs) that are detected will be alarmed in the Main Control Room (MCR) common annunciator panel.
- (2) See item 2 in table titled Detection, Alarms, and General Criteria Exceptions for inspector identified exceptions.
- (3) The licensees design document, test results and analysis showed that the short time delay (a time delay of 0.65 seconds was selected for the OPC relays to coordinate with the fault clearing time of 345kV switchyard primary and zone 2 relays) used in the open phase condition design/protective scheme is expected to minimize misoperation or spurious trips in the range of voltage unbalances normally expected in the transmission system. The analysis also showed that the time delay may properly coordinated with switchyard fault assumptions. Based on this, the inspector had reasonable assurance that the actuation circuit design would not result in lower overall plant operation reliability. Additionally, the OPC scheme was activated or placed in-service in October of 2017. Since that time, there have not been any inadvertent actuations of this system that resulted in a trip signal or spurious actions.
- (4) No Class-1E circuits were being replaced with non-Class 1E circuits in the design.
- (5) The licensee revised Lasalle Updated Final Safety Analysis Report (UFSAR),
Section 8.3.1.1.2. Offsite Power Sources (SATs), and added the loss of phase protection to Table 8.3-2. The change was incorporated into the UFSAR Report.
See item 5 in table titled Detection, Alarms, and General Criteria Exceptions for inspector identified exceptions.
Observation: Protective Actions Criteria 2515/194
- (1) LaSalle County Station has determined that OPCs are credible events and have implemented design changes to mitigate the effects. EC 387695 and EC 387696 have installed an open phase relay scheme to detect, alarm and protect from open phase conditions.
- (2) The inspectors determined that with an open phase condition present and no accident condition signal, the OPC protection relay system would not adversely affect the function of important-to-safety systems, structures and components when the trip function is active.
As per the design description, the OPC relays will trip the System Auxiliary Transformer (SAT) lockout relays after a 0.65 second time delay. The SAT lockout relays would isolate the SAT by opening both primary and secondary side breakers. After the SAT isolates, an automatic fast transfer connects the safety-related buses fed by the SAT to the Unit Auxiliary Transformer (UAT). The licensees analysis verified that the OPC relays can detect and isolate an OPC prior to any motor damage. The algorithm time delay limits the motors exposure to negative sequence current which helps prevent excessive motor heating.
The Lasalle UFSAR states that during a power loss to the M-G set, the high-inertia flywheel is designed to maintain generator output within 5% of rated values for at least one second to keep the Reactor Protection System (RPS) bus energized. The fast bus transfer from the SAT to UAT recovers the bus voltage allowing RPS operation to be sustained throughout the transient. Analyses completed by the licensee support the ability of this arrangement to be completed within associated time constraints.
See item 2 in table titled Protective Actions Criteria Exceptions for inspector identified exceptions.
- (3) See item 3 in table titled Protective Actions Criteria Exceptions for inspector identified exceptions.
- (4) No surveillance requirements for the SEL 451-5 were added to the plant Technical Specifications.
See item 4 in table titled Protective Actions Criteria Exceptions for inspector identified exceptions.
Observation: Detection, Alarms, and General Criteria Exceptions 2515/194
- (2) Based on review of the licensees calculation for the relay settings used in the OPC algorithms, the inspectors determined that the OPC relay detection does not function under all loading conditions. The design is sensitive enough to identify an OPC when SAT transformer loading is above the MINLOAD threshold. To insure detection of an OPC, the design/implementation of OPC detection at LaSalle has a minimum loading requirement for the SAT transformers. Specifically, an OPC will be detected as long as the primary positive sequence current in the SAT is greater than the MINLOAD (low load)alarm setting. (approximately 3.6MVA (L-003786, Revision 0)). During normal operations, the SATs are routinely loaded above the MINLOAD threshold.
- (5) While the change was incorporated into UFSAR table as a trip to the SAT lockout relays, the revision did not reference any design analysis, discuss design features, discuss theory of operation for the OPC system, or list major components associated with the open phase condition equipment in detail. However, the licensee maintained that the level of detail provided in the UFSAR for the open phase condition protection was consistent with the level of detail provided for other non-safety conditions that provide an input to the associated transformer lockout relay trips.
Observation: Protective Actions Criteria Exceptions 2515/194
- (2) During low loading of the SAT or open phase detection (OPD) relay trouble alarms, manual actions may be required to address the existence of an OPC condition. The inspectors discussed the potential need for manual actions with the licensee and the licensee agreed that the current procedures did not specifically address implementation of protective actions if manual actions were required. The lack of guidance for system response when manual actions are needed, and weaknesses identified in alarm response procedures was captured in IR 04284977, NRC IDD Procedure Enhancement.
- (3) The following information was aggregated from engineering analyses, training materials and conversations with licensee staff as a detailed description of the system operation and performance was not located within the UFSAR.
The inspectors noted that, for the case where an OPC occurs and an accident condition (LOCA) signal are present simultaneously, safety-related equipment would receive a start request and would attempt to start while the OPC exists on the safety-related buses. This first start attempt occurs due to the time delay associated with 1) OPC coordination with other protective features and 2) the time delay associated with detection and actuation of the OPC equipment.
Once the SAT lockout relays isolate the SAT by opening both primary and secondary side breakers, the analysis showed the safety-related undervoltage relaying scheme would automatically separate the engineered safety feature (ESF) busses from the SAT. Subsequently, the Emergency Diesel Generator (EDG) associated with each ESF bus would automatically connect to the ESF bus and allow the ESF loads to be powered from the EDG.
- (4) At the time of this inspection, the licensee had established a functional test schedule which includes testing the relay metering function and verifying relay settings against calculated values. The licensee had not established a periodic setpoint calibration testing schedule to verify relay performance is within the tolerances assumed within the supporting analyses. The licensees relay testing procedure for microprocessor-based relays does not require calibration or setpoint verification.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
2515/194 Calculations L-003750 LaSalle Offsite Power System Open Phase EMPT Evaluation 001
L-003786 Unit 1 and Unit 2 Loss of Phase Detection Relay Settings 003
L-003885 Open Phase Detection LOCA Analysis 1
Corrective Action 04284977 NRC IDD Procedure Enhancement 10/04/2019
Documents
Resulting from
Inspection
Drawings 1E-1-4000FC Key Diagram Essential Div. 2 125V DC Distribution Panel P
2X (1DC12E) and Panel 112Y (1DC13E)
1E-1-4004AG Schematic Diagram Main Power System MP Part 7 K
1E-1-4005DQ Schematic Diagram Auxiliary Power System AP Part 87 M
1E-2-4000A Single Line Diagram Generator, Transformers & 6900V V
Buses Part 1
1E-2-4000NF Relaying & Metering Diagram System Auxiliary G
Transforme242 (2AP91E)
Engineering 387695 Single Phase Fault Mitigation 000
Changes
Procedures LOA-AP-101 Unit 1, AC Power System Abnormal 59
LOR-1PM01J- Sat 142(242) System 1 Prot Relay Trip 3
A117
LOR-1PM01J- Sat 142 Low Load 3
A405
LOR-242 Loss of Sat 242 Loss of Phase Relay Trouble 4
Phase Relay
Trouble
LOR-2PM01J- SAT 242 System 2 Prot Relay Trip 3
A217
LST-2013-040 Single Phase Fault Mitigation Relay (EC 387695) 0
LST-2015-009 Open Phase Condition Concurrent with a LOCA Bus Transfer 0
Logic Change (EC 400355)
MA-LA-773-231 Unit 1, System Aux Transformer Relay and Meter 8
Calibrations By OAD
Inspection Type Designation Description or Title Revision or
Procedure Date
Work Orders 01513170 OAD Perform Bench Testing of Relay SEL-451 Per 12
EC387696
7