| : The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at the Dresden Nuclear Power Station | | : The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at the Dresden Nuclear Power Station |
| . The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license applications in connection with this examination and separately provided a list of approved applicants to Mr. Andrew Pullam | | . The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license applications in connection with this examination and separately provided a list of approved applicants to Mr. Andrew Pullam , Training Manager. Note that any examination waivers and application denials have been addressed in separate correspondence. |
| , Training Manager. Note that any examination waivers and application denials have been addressed in separate correspondence. | |
| The NRC has approved the subject examinations and you may administer the written examinations in accordance with Revision 10, of NUREG | | The NRC has approved the subject examinations and you may administer the written examinations in accordance with Revision 10, of NUREG |
| -1021, "Operator Licensing Examination Standards for Power Reactors," during the week of August 15, 2016. The NRC staff will administer the operating tests during the week s of August 8 and 15, 2016. This examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of NUREG | | -1021, "Operator Licensing Examination Standards for Power Reactors," during the week of August 15, 2016. The NRC staff will administer the operating tests during the week s o f August 8 and 15, 2016. This examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of NUREG |
| -1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG | | -1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG |
| -1021 guidelines, and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at 630 | | -1021 guidelines, and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at 630 |
| -829-9834. Please contact your Chief Examiner, Mr. Bruce Palagi at 630-829-9611, if you have any questions or identify any errors or changes in the license level reactor operator (RO) or senior reactor operator (SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant. | | -829-9 834. Please contact your Chief Examiner, Mr. Bruce Palagi at 630-829-9 61 1, if you have any questions or identify any errors or changes in the license level reactor operator (RO) or senior reactor operator (SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant. |
| In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy | | In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy |
|
| |
|
| of this letter will be available electronically for public inspection in the NRC's Public Document B. Hanson Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading | | of this letter will be available electronically for public inspection in the NRC's Public Document B. Hanson Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading |
| -rm/adams.html (the Public Electronic Reading Room). | | -rm/adams.html (the Public Electronic Reading Room). |
| Sincerely, | | Sincerely, |
| | |
| /RA Michael Bielby Acting for/ | | /RA Michael Bielby Acting for/ |
| Robert J. Orlikowski, Chief Operations Branch | | Robert J. Orlikowski, Chief Operations Branch |
|
| |
|
| Division of Reactor Safety Docket No | | Division of Reactor Safety Docket No s. 50-237; 50-249 License No |
| : s. 50-237; 50-249 License No
| |
| : s. DPR-19; DPR-25 cc: Distribution via LISTSERV Andrew Pullam, Training Director | | : s. DPR-19; DPR-25 cc: Distribution via LISTSERV Andrew Pullam, Training Director |
|
| |
|
| B. Hanson Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading | | B. Hanson Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading |
| -rm/adams.html (the Public Electronic Reading Room). | | -rm/adams.html (the Public Electronic Reading Room). |
| Sincerely, | | Sincerely, |
| | |
| /RA Michael Bielby Acting for/ | | /RA Michael Bielby Acting for/ |
| Robert J. Orlikowski, Chief Operations Branch | | Robert J. Orlikowski, Chief Operations Branch |
Line 55: |
Line 50: |
| -2 Resource RidsNrrPMDresden Resource RidsNrrDirsIrib Resource Cynthia Pederson | | -2 Resource RidsNrrPMDresden Resource RidsNrrDirsIrib Resource Cynthia Pederson |
|
| |
|
| Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Maurin Scheetz ADAMS Accession Name: ML16210A415 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII:DRS C RIII:DRS N RIII:DRS N RIII NAME JKweiser: | | Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Maurin Scheetz ADAMS Accession Name: ML16210A415 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII:DRS C RIII:DRS N RIII:DRS N RIII NAME JKweiser: jw BPalagi: MBielby for ROrlikowski: |
| jw BPalagi: MBielby for ROrlikowski: | |
| DATE 07/27/16 07/28/16 07/28/16 OFFICIAL RECORD COPY}} | | DATE 07/27/16 07/28/16 07/28/16 OFFICIAL RECORD COPY}} |
|
---|
Category:Letter
MONTHYEARIR 05000237/20230042024-02-0202 February 2024 Integrated Inspection Report 05000237/2023004 and 05000249/2023004 IR 05000010/20230012024-01-17017 January 2024 NRC Inspection Report 05000010/2023001 (Drss) ML23354A2812024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0031 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 RS-23-121, Sixth Ten-Year Interval Inservice Testing Program2023-11-30030 November 2023 Sixth Ten-Year Interval Inservice Testing Program SVPLTR 23-0037, Core Operating Limits Report for Cycle 292023-11-29029 November 2023 Core Operating Limits Report for Cycle 29 RS-23-119, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums RS-23-107, Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-11-0808 November 2023 Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-102, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23279A0712023-10-0606 October 2023 Response to NRC Dresden Nuclear Power Station, Units 2 and 3 - Comprehensive Engineering Team Inspection Report 05000237/2023011 and 05000249/2023011 ML23269A0662023-09-28028 September 2023 Proposed Alternative Request RV-23H Associated with the Sixth 10-Year Inservice Testing Interval ML23265A1322023-09-27027 September 2023 Proposed Alternative Request RV-03 Associated with the Sixth 10-Year Inservice Testing Interval ML23205A1362023-09-20020 September 2023 Proposed Alternative Request RV-02D Associated with the Sixth IST Interval IR 05000237/20230112023-09-0606 September 2023 Comprehensive Engineering Team Inspection Report 05000237/2023011 and 05000249/2023011 RS-23-071, Application to Adopt TSTF-564, Safety Limit MCPR2023-08-30030 August 2023 Application to Adopt TSTF-564, Safety Limit MCPR RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs IR 05000237/20234022023-08-29029 August 2023 Security Baseline Inspection Report 05000237/2023402 and 05000249/2023402 IR 05000237/20230022023-08-0808 August 2023 Integrated Inspection Report 05000237/2023002 and 05000249/2023002 ML23212A9892023-08-0303 August 2023 Subsequent License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23174A1502023-08-0303 August 2023 Issuance of Amendment Nos. 282 and 275 Control Rod Scram Times ML23193A0052023-07-28028 July 2023 Subsequent License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23192A6292023-07-11011 July 2023 Correction Letter - Issuance of Amendment Nos. 281 and 274 Regarding Transition to GNF3 Fuel (EPID L-2022-LLA-0121) (Non-Proprietary) ML23144A3142023-07-0606 July 2023 Issuance of Amendment Nos. 281 and 274 Transition to GNF3 Fuel (EPID L-2022-LLA-0121) - Nonproprietary ML23187A0462023-07-0606 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2023004 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III SVPLTR 23-0021, Registration of Use of Casks to Store Spent Fuel2023-06-20020 June 2023 Registration of Use of Casks to Store Spent Fuel RS-23-078, Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times2023-06-16016 June 2023 Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20233012023-05-30030 May 2023 NRC Initial License Examination Report 05000237/2023301; 05000249/2023301 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23132A0932023-05-17017 May 2023 Information Meeting (Public Open House) with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Dresden Power Station, Units 2 and 3 RS-23-070, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-05-16016 May 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel SVPLTR 23-0018, Submittal of 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Submittal of 2022 Annual Radiological Environmental Operating Report IR 05000237/20230012023-05-0404 May 2023 Integrated Inspection Report 05000237/2023001 and 05000249/2023001 SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI IR 05000237/20234012023-04-26026 April 2023 Cyber Security Inspection Report 05000237/2023401 and 05000249/2023401 ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration IR 05000237/20235012023-04-21021 April 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000237/2023501 and 05000249/2023501 ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection RS-23-057, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-04-17017 April 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel SVPLTR 23-0014, Annual Dose Report for 20222023-04-15015 April 2023 Annual Dose Report for 2022 ML23088A2242023-04-0505 April 2023 Regulatory Audit Report Regarding License Amendment Request to Transition to GNF3 Fuel ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 2024-02-02
[Table view] Category:License-Operator
MONTHYEARML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23160A1712023-06-0909 June 2023 Form 5.1-1 Post Examination Check Sheet ML23160A1672023-05-18018 May 2023 Form 1.3-1 Post Examination Security Agreement ML23160A1702023-05-18018 May 2023 Form 2.1-1 Examination Prep Checklist SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 ML23160A1832023-03-16016 March 2023 3.4-1 Events and Evolutions Checklist ML23160A1802023-03-16016 March 2023 2.3-1 Examination Outline Quality Checklist ML23160A0542023-03-16016 March 2023 2.3-2 - Operating Test Quality Checklist SVPLTR 23-0002, 2.3-4 - Written Examination Quality Checklist2023-03-16016 March 2023 2.3-4 - Written Examination Quality Checklist ML23160A1782023-03-0606 March 2023 ILT Exam Outline Submittal Letter ML23160A0522023-01-25025 January 2023 ILT Exam Submittal Letter RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 ML22195A1342021-12-0303 December 2021 Nov 2021 Ile ES-403-1-Written Exam Grading Quality Checklist-Signed ML22195A1312021-12-0303 December 2021 Nov 2021 Ile ES-201-3 - Exam Security Agreement ML22195A1272021-12-0303 December 2021 Nov 2021 Ile ES-201-1 Exam Prep Checklist ML22195A1352021-11-15015 November 2021 Nov 2021 Ile Post-Exam Package Submittal Letter 11/15/2021 ML21287A0442021-10-18018 October 2021 Operator Licensing Examination Approval ML22195A2312021-09-19019 September 2021 Nov 2021 Ile Es 401-6 Written Exam Quality Checklist-Signed ML22195A2282021-09-19019 September 2021 Nov 2021 Ile Es 301-6 Competencies Checklist ML22195A2262021-09-19019 September 2021 Nov 2021 Ile Es 301-4 Simulator Scenario Quality Checklist-Signed ML22195A2222021-09-19019 September 2021 Nov 2021 Ile Es 301-3 Operating Test Quality Checklist-Signed ML22195A2372021-09-0707 September 2021 Nov 2021 Ile Written Exam Submittal Letter 09-07-2021 ML22195A2342021-08-16016 August 2021 Nov 2021 Ile Operating Test Submittal Letter 08-16-2021 ML22195A2662021-06-26026 June 2021 Nov 2021 Ile Es 301-5 Transients and Events Checklist ML22195A2632021-06-26026 June 2021 Nov 2021 Ile Es 201-2 Outline Quality Checklist ML22195A2672021-06-0404 June 2021 Nov 2021 Ile Es 201-2 Outlines Submittal Email ML21139A2372021-05-21021 May 2021 Confirmation of Initial License Examination ML22215A1812021-05-14014 May 2021 April 2021 Administered JPMs ML22236A3332021-05-14014 May 2021 Initial License Exam Forms ES-201-3 ML22236A3322021-05-14014 May 2021 Initial License Exam Form ES-403-1 ML22236A3302021-05-14014 May 2021 Initial License Exam Form ES-201-1 ML22236A3842021-05-14014 May 2021 Initial License Exam Letter 21-0029 ML22235A7572021-05-14014 May 2021 April 2021 Form ES-201-2 Written Outline Only ML22235A7562021-05-14014 May 2021 April 2021 Form ES-301-5 SVPLTR 21-0007, April 2021 Submittal Letter2021-05-14014 May 2021 April 2021 Submittal Letter ML22215A2492021-05-14014 May 2021 April 2021 Form ES-401-6 ML22215A2462021-05-14014 May 2021 April 2021 Form ES-301-6 ML22215A2422021-05-14014 May 2021 April 2021 Form ES-301-4 ML22215A2382021-05-14014 May 2021 April 2021 Form ES-301-3 ML22215A1852021-05-14014 May 2021 April 2021 Administered Scenarios ML22236A0172021-05-14014 May 2021 Initial License Exam Forms ES-301-2 ML22236A0162021-05-14014 May 2021 Initial License Exam Forms ES-301-1 ML22216A1872021-05-14014 May 2021 April 2021 Proposed JPMs ML22216A1902021-05-14014 May 2021 April 2021 Proposed Written Exam ML22216A1892021-05-14014 May 2021 April 2021 Proposed Scenarios ML22236A0182021-05-14014 May 2021 Initial License Exam Forms ES-401-1 and ES-401-3 rev1 ML22215A1862021-05-14014 May 2021 April 2021 Administered Written Exam 2023-06-09
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23160A1712023-06-0909 June 2023 Form 5.1-1 Post Examination Check Sheet ML23160A1672023-05-18018 May 2023 Form 1.3-1 Post Examination Security Agreement ML23160A1702023-05-18018 May 2023 Form 2.1-1 Examination Prep Checklist SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 ML23160A1832023-03-16016 March 2023 3.4-1 Events and Evolutions Checklist ML23160A1802023-03-16016 March 2023 2.3-1 Examination Outline Quality Checklist SVPLTR 23-0002, 2.3-4 - Written Examination Quality Checklist2023-03-16016 March 2023 2.3-4 - Written Examination Quality Checklist ML23160A0542023-03-16016 March 2023 2.3-2 - Operating Test Quality Checklist ML23160A1782023-03-0606 March 2023 ILT Exam Outline Submittal Letter ML23160A0522023-01-25025 January 2023 ILT Exam Submittal Letter RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 ML22195A1272021-12-0303 December 2021 Nov 2021 Ile ES-201-1 Exam Prep Checklist ML22195A1312021-12-0303 December 2021 Nov 2021 Ile ES-201-3 - Exam Security Agreement ML22195A1342021-12-0303 December 2021 Nov 2021 Ile ES-403-1-Written Exam Grading Quality Checklist-Signed ML22195A1352021-11-15015 November 2021 Nov 2021 Ile Post-Exam Package Submittal Letter 11/15/2021 ML21287A0442021-10-18018 October 2021 Operator Licensing Examination Approval ML22195A2312021-09-19019 September 2021 Nov 2021 Ile Es 401-6 Written Exam Quality Checklist-Signed ML22195A2282021-09-19019 September 2021 Nov 2021 Ile Es 301-6 Competencies Checklist ML22195A2262021-09-19019 September 2021 Nov 2021 Ile Es 301-4 Simulator Scenario Quality Checklist-Signed ML22195A2222021-09-19019 September 2021 Nov 2021 Ile Es 301-3 Operating Test Quality Checklist-Signed ML22195A2372021-09-0707 September 2021 Nov 2021 Ile Written Exam Submittal Letter 09-07-2021 ML22195A2342021-08-16016 August 2021 Nov 2021 Ile Operating Test Submittal Letter 08-16-2021 ML22195A2662021-06-26026 June 2021 Nov 2021 Ile Es 301-5 Transients and Events Checklist ML22195A2632021-06-26026 June 2021 Nov 2021 Ile Es 201-2 Outline Quality Checklist ML22195A2672021-06-0404 June 2021 Nov 2021 Ile Es 201-2 Outlines Submittal Email ML21139A2372021-05-21021 May 2021 Confirmation of Initial License Examination ML22236A6382021-05-14014 May 2021 April 2021 Initial License Exam Form ES-401-4 ML22215A1812021-05-14014 May 2021 April 2021 Administered JPMs ML22215A1852021-05-14014 May 2021 April 2021 Administered Scenarios ML22236A3332021-05-14014 May 2021 Initial License Exam Forms ES-201-3 ML22236A3322021-05-14014 May 2021 Initial License Exam Form ES-403-1 ML22236A3302021-05-14014 May 2021 Initial License Exam Form ES-201-1 ML22236A3842021-05-14014 May 2021 Initial License Exam Letter 21-0029 ML22235A7572021-05-14014 May 2021 April 2021 Form ES-201-2 Written Outline Only ML22235A7562021-05-14014 May 2021 April 2021 Form ES-301-5 SVPLTR 21-0007, April 2021 Submittal Letter2021-05-14014 May 2021 April 2021 Submittal Letter ML22215A2492021-05-14014 May 2021 April 2021 Form ES-401-6 ML22215A2462021-05-14014 May 2021 April 2021 Form ES-301-6 ML22215A2422021-05-14014 May 2021 April 2021 Form ES-301-4 ML22215A2382021-05-14014 May 2021 April 2021 Form ES-301-3 ML22215A1862021-05-14014 May 2021 April 2021 Administered Written Exam ML22236A6392021-05-14014 May 2021 April 2021 Initial License Exam Form ES-401-9 ML22236A0202021-05-14014 May 2021 Initial License Exam Forms ES-D1 ML22236A6372021-05-14014 May 2021 April 2021 Initial License Exam Form ES-301-7 ML22236A6402021-05-14014 May 2021 April 2021 Initial License Exam Operating Test Outline Comments 2023-06-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUIT E 210 LISLE, IL 60532
-4352 July 28, 2016 Mr. Bryan C. Hanson Senior VP, Exelon Generation Co., LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
OPERATOR LICENSING EXAMINATION APPROVAL Dear Mr. Hanson
- The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at the Dresden Nuclear Power Station
. The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license applications in connection with this examination and separately provided a list of approved applicants to Mr. Andrew Pullam , Training Manager. Note that any examination waivers and application denials have been addressed in separate correspondence.
The NRC has approved the subject examinations and you may administer the written examinations in accordance with Revision 10, of NUREG
-1021, "Operator Licensing Examination Standards for Power Reactors," during the week of August 15, 2016. The NRC staff will administer the operating tests during the week s o f August 8 and 15, 2016. This examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of NUREG
-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG
-1021 guidelines, and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at 630
-829-9 834. Please contact your Chief Examiner, Mr. Bruce Palagi at 630-829-9 61 1, if you have any questions or identify any errors or changes in the license level reactor operator (RO) or senior reactor operator (SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy
of this letter will be available electronically for public inspection in the NRC's Public Document B. Hanson Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA Michael Bielby Acting for/
Robert J. Orlikowski, Chief Operations Branch
Division of Reactor Safety Docket No s. 50-237; 50-249 License No
- s. DPR-19; DPR-25 cc: Distribution via LISTSERV Andrew Pullam, Training Director
B. Hanson Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA Michael Bielby Acting for/
Robert J. Orlikowski, Chief Operations Branch
Division of Reactor Safety Docket Nos. 50
-237; 50-249 License Nos. DPR
-19; DPR-25 cc: Distribution via LISTSERV Andrew Pullam, Training Director DISTRIBUTION
- Jeremy Bowen RidsNrrDorlLpl3
-2 Resource RidsNrrPMDresden Resource RidsNrrDirsIrib Resource Cynthia Pederson
Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Maurin Scheetz ADAMS Accession Name: ML16210A415 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII:DRS C RIII:DRS N RIII:DRS N RIII NAME JKweiser: jw BPalagi: MBielby for ROrlikowski:
DATE 07/27/16 07/28/16 07/28/16 OFFICIAL RECORD COPY