Text

Dresden Nuclear Power Station Constellation 6500 North Dresden Road Morris, IL 60450 January 25, 2023 SVPLTR: #23-0002 U.S. Nuclear Regulatory Commission ATTN: NRC Region Ill Administrator 2443 Warrenville Road, Suite 21 O Lisle, IL 60532-4352 Dresden Nuclear Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-19 and DPR-25 NRC Docket Nos. 50-237 and 50-249

Subject:

Submittal of Integrated Initial License Training Examination Materials Enclosed are the examination materials, which Dresden Nuclear Power Station is submitting in support of the initial license exam scheduled for the weeks of April 10 and April 17, 2023. This submittal includes the Senior Reactor Operator and Reactor Operator Written Examinations, Job Performance Measures, and Integrated Plant Operation Scenario Guides.

These examination materials have been developed in accordance with NUREG-1021, "Operator License Examination Standards for Power Reactors," revision 12. Please note that reference materials are attached for each individual examination or item. Some minor modifications may have been made to the Integrated Examination Outline with regards to the operational scenarios to improve balance and content. These changes improve examination quality and are in compliance with NUREG-1021, revision 12. Some modifications or adjustments to the examination material may be required due to procedural changes.

Should you have any questions concerning this letter, please contact Daniel J. Murphy, Regulatory Assurance Manager, at (815) 416-2800. For questions concerning the examination materials, please contact Derek Siuda at (815) 416-4060.

Patrick J. Boyl Site Vice Presic:lent Dresden Nuclear Power Station

Enclosures:

(digitally submitted via NRC Box)

- RO/SRO Composite Examination with references attached

- Control Room Systems and Facility Walk-Through Job Performance Measures with references attached

- Administrative Topic Job Performance Measures with references attached

- Integrated Plant Operation Scenario Guides

- Completed Checklists:

  • Examination Security Agreements (Form 1.3-1)
  • Operating Test Quality Checklist (Form 2.3-2)
  • Written Exam Quality Checklist (Form 2.3-4)
  • Events and Evolutions Checklist (Form 3.4-1) cc (without attachments):

- Chief, NRC Operator Licensing Branch

- NRC Senior Resident Inspector- Dresden Nuclear Power Station

Bee:

- Project Manager - NRR (Unit 2/3)

Site Vice President - Dresden Nuclear Power Station Regulatory Assurance Manager - Dresden Nuclear Power Station Vice President - Licensing and Regulatory Affairs Director, Licensing - Midwest Regional Operating Group Manager, Licensing - Dresden Nuclear Power Station Dresden Station License Coordinator Exelon Document Control Desk Licensing (Hard Copy)

Exelon Document Control Desk Licensing (Electronic Copy)

Human Resources - Dresden Nuclear Power Station Training Manager - Dresden Nuclear Power Station