MONTHYEARML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23160A1712023-06-0909 June 2023 Form 5.1-1 Post Examination Check Sheet ML23160A1672023-05-18018 May 2023 Form 1.3-1 Post Examination Security Agreement ML23160A1702023-05-18018 May 2023 Form 2.1-1 Examination Prep Checklist SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 ML23160A1832023-03-16016 March 2023 3.4-1 Events and Evolutions Checklist ML23160A1802023-03-16016 March 2023 2.3-1 Examination Outline Quality Checklist ML23160A0542023-03-16016 March 2023 2.3-2 - Operating Test Quality Checklist SVPLTR 23-0002, 2.3-4 - Written Examination Quality Checklist2023-03-16016 March 2023 2.3-4 - Written Examination Quality Checklist ML23160A1782023-03-0606 March 2023 ILT Exam Outline Submittal Letter ML23160A0522023-01-25025 January 2023 ILT Exam Submittal Letter RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 ML22195A1342021-12-0303 December 2021 Nov 2021 Ile ES-403-1-Written Exam Grading Quality Checklist-Signed ML22195A1312021-12-0303 December 2021 Nov 2021 Ile ES-201-3 - Exam Security Agreement ML22195A1272021-12-0303 December 2021 Nov 2021 Ile ES-201-1 Exam Prep Checklist ML22195A1352021-11-15015 November 2021 Nov 2021 Ile Post-Exam Package Submittal Letter 11/15/2021 ML21287A0442021-10-18018 October 2021 Operator Licensing Examination Approval ML22195A2312021-09-19019 September 2021 Nov 2021 Ile Es 401-6 Written Exam Quality Checklist-Signed ML22195A2282021-09-19019 September 2021 Nov 2021 Ile Es 301-6 Competencies Checklist ML22195A2262021-09-19019 September 2021 Nov 2021 Ile Es 301-4 Simulator Scenario Quality Checklist-Signed ML22195A2222021-09-19019 September 2021 Nov 2021 Ile Es 301-3 Operating Test Quality Checklist-Signed ML22195A2372021-09-0707 September 2021 Nov 2021 Ile Written Exam Submittal Letter 09-07-2021 ML22195A2342021-08-16016 August 2021 Nov 2021 Ile Operating Test Submittal Letter 08-16-2021 ML22195A2662021-06-26026 June 2021 Nov 2021 Ile Es 301-5 Transients and Events Checklist ML22195A2632021-06-26026 June 2021 Nov 2021 Ile Es 201-2 Outline Quality Checklist ML22195A2672021-06-0404 June 2021 Nov 2021 Ile Es 201-2 Outlines Submittal Email ML21139A2372021-05-21021 May 2021 Confirmation of Initial License Examination ML22215A1812021-05-14014 May 2021 April 2021 Administered JPMs ML22236A3332021-05-14014 May 2021 Initial License Exam Forms ES-201-3 ML22236A3322021-05-14014 May 2021 Initial License Exam Form ES-403-1 ML22236A3302021-05-14014 May 2021 Initial License Exam Form ES-201-1 ML22236A3842021-05-14014 May 2021 Initial License Exam Letter 21-0029 ML22235A7572021-05-14014 May 2021 April 2021 Form ES-201-2 Written Outline Only ML22235A7562021-05-14014 May 2021 April 2021 Form ES-301-5 SVPLTR 21-0007, April 2021 Submittal Letter2021-05-14014 May 2021 April 2021 Submittal Letter ML22215A2492021-05-14014 May 2021 April 2021 Form ES-401-6 ML22215A2462021-05-14014 May 2021 April 2021 Form ES-301-6 ML22215A2422021-05-14014 May 2021 April 2021 Form ES-301-4 ML22215A2382021-05-14014 May 2021 April 2021 Form ES-301-3 ML22215A1852021-05-14014 May 2021 April 2021 Administered Scenarios ML22236A0172021-05-14014 May 2021 Initial License Exam Forms ES-301-2 ML22236A0162021-05-14014 May 2021 Initial License Exam Forms ES-301-1 ML22216A1872021-05-14014 May 2021 April 2021 Proposed JPMs ML22216A1902021-05-14014 May 2021 April 2021 Proposed Written Exam ML22216A1892021-05-14014 May 2021 April 2021 Proposed Scenarios ML22236A0182021-05-14014 May 2021 Initial License Exam Forms ES-401-1 and ES-401-3 rev1 ML22215A1862021-05-14014 May 2021 April 2021 Administered Written Exam 2023-06-09
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23160A1712023-06-0909 June 2023 Form 5.1-1 Post Examination Check Sheet ML23160A1672023-05-18018 May 2023 Form 1.3-1 Post Examination Security Agreement ML23160A1702023-05-18018 May 2023 Form 2.1-1 Examination Prep Checklist SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 ML23160A1832023-03-16016 March 2023 3.4-1 Events and Evolutions Checklist ML23160A1802023-03-16016 March 2023 2.3-1 Examination Outline Quality Checklist SVPLTR 23-0002, 2.3-4 - Written Examination Quality Checklist2023-03-16016 March 2023 2.3-4 - Written Examination Quality Checklist ML23160A0542023-03-16016 March 2023 2.3-2 - Operating Test Quality Checklist ML23160A1782023-03-0606 March 2023 ILT Exam Outline Submittal Letter ML23160A0522023-01-25025 January 2023 ILT Exam Submittal Letter RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 ML22195A1272021-12-0303 December 2021 Nov 2021 Ile ES-201-1 Exam Prep Checklist ML22195A1312021-12-0303 December 2021 Nov 2021 Ile ES-201-3 - Exam Security Agreement ML22195A1342021-12-0303 December 2021 Nov 2021 Ile ES-403-1-Written Exam Grading Quality Checklist-Signed ML22195A1352021-11-15015 November 2021 Nov 2021 Ile Post-Exam Package Submittal Letter 11/15/2021 ML21287A0442021-10-18018 October 2021 Operator Licensing Examination Approval ML22195A2312021-09-19019 September 2021 Nov 2021 Ile Es 401-6 Written Exam Quality Checklist-Signed ML22195A2282021-09-19019 September 2021 Nov 2021 Ile Es 301-6 Competencies Checklist ML22195A2262021-09-19019 September 2021 Nov 2021 Ile Es 301-4 Simulator Scenario Quality Checklist-Signed ML22195A2222021-09-19019 September 2021 Nov 2021 Ile Es 301-3 Operating Test Quality Checklist-Signed ML22195A2372021-09-0707 September 2021 Nov 2021 Ile Written Exam Submittal Letter 09-07-2021 ML22195A2342021-08-16016 August 2021 Nov 2021 Ile Operating Test Submittal Letter 08-16-2021 ML22195A2662021-06-26026 June 2021 Nov 2021 Ile Es 301-5 Transients and Events Checklist ML22195A2632021-06-26026 June 2021 Nov 2021 Ile Es 201-2 Outline Quality Checklist ML22195A2672021-06-0404 June 2021 Nov 2021 Ile Es 201-2 Outlines Submittal Email ML21139A2372021-05-21021 May 2021 Confirmation of Initial License Examination ML22236A6382021-05-14014 May 2021 April 2021 Initial License Exam Form ES-401-4 ML22215A1812021-05-14014 May 2021 April 2021 Administered JPMs ML22215A1852021-05-14014 May 2021 April 2021 Administered Scenarios ML22236A3332021-05-14014 May 2021 Initial License Exam Forms ES-201-3 ML22236A3322021-05-14014 May 2021 Initial License Exam Form ES-403-1 ML22236A3302021-05-14014 May 2021 Initial License Exam Form ES-201-1 ML22236A3842021-05-14014 May 2021 Initial License Exam Letter 21-0029 ML22235A7572021-05-14014 May 2021 April 2021 Form ES-201-2 Written Outline Only ML22235A7562021-05-14014 May 2021 April 2021 Form ES-301-5 SVPLTR 21-0007, April 2021 Submittal Letter2021-05-14014 May 2021 April 2021 Submittal Letter ML22215A2492021-05-14014 May 2021 April 2021 Form ES-401-6 ML22215A2462021-05-14014 May 2021 April 2021 Form ES-301-6 ML22215A2422021-05-14014 May 2021 April 2021 Form ES-301-4 ML22215A2382021-05-14014 May 2021 April 2021 Form ES-301-3 ML22215A1862021-05-14014 May 2021 April 2021 Administered Written Exam ML22236A6392021-05-14014 May 2021 April 2021 Initial License Exam Form ES-401-9 ML22236A0202021-05-14014 May 2021 Initial License Exam Forms ES-D1 ML22236A6372021-05-14014 May 2021 April 2021 Initial License Exam Form ES-301-7 ML22236A6402021-05-14014 May 2021 April 2021 Initial License Exam Operating Test Outline Comments 2023-06-09
[Table view] |
Text
ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Dresden Nuclear Station, Units 2 and 3 Date of Examination: November 1 - 11, 2021 Developed: Written: Facility: NRC: // Operating: Facility: NRC:
Days from Chief Examiner's Target Date* Task Description (Reference)
Exam Initials
- 1. Examination administration date confirmed (C.1.a; C.2.a-b). For NRC-prepared exams,
-240 03/06/2021 RDB arrangements are made for the facility to submit reference materials (C.1.e; C.3.c; Attachment 3).
-210 04/05/2021 2. NRC examiners and facility contact assigned (C.1.d; C.2.f). RDB
- 3. Facility contact briefed on security and other requirements (C.2.c). As applicable, the facility
-210 04/05/2021 contact submits to the NRC any prescreened K/As for elimination from the written examination RDB outline, with a description of the facilitys prescreening process (ES-401, D.1.b).
-210 04/05/2021 4. Reference material due for NRC-prepared exams (C.1.e; C.3.c; Attachment 3). RDB
-210 04/05/2021 5. Corporate notification letter sent (C.2.e). RDB
- 6. NRC-developed written examination outline (ES-401-1/2 or ES-401N-1/2 and ES-401-3 or
-195 04/20/2021 ES-401N-3) sent to facility contact (must be on the exam security agreement) (C.1.e-f; C.2.h; RDB C.3.d-e).
- 7. Operating test outline(s) and other checklists due, including Forms ES-201-2, ES-201-3,
-150 06/04/2021 RDB ES-301-1, ES-301-2, ES-301-5, and ES-D-1, as applicable (C.1.e-f; C.3.d-e).
- 8. Operating test outline(s) reviewed by the NRC and feedback provided to facility licensee (C.2.h;
-136 06/18/2021 RDB C.3.d-e).
9a. Proposed examinations (JPMs, and scenarios, as applicable) and outlines (Forms ES-301-1, ES-301-2, ES-D-1, ES-401-1/2 or ES-401N-1/2, and ES-401-3 or ES-401N-3);
-75 08/20/2021 supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, ES-401-6, RDB ES-401N-6, and any Form ES-201-2 and ES-201-3 updates); and reference materials due (C.1.e-h; C.3.d).
9b. Proposed written examination due to NRC for review (Per CE resource scheduling.)
-60 09/07/2021 RDB (C.1.e-h; C.3.d).
-60 09/03/2021 10. Preliminary waiver/excusal requests due (C.1.m; C.2.c; ES-202). RDB 09/10/2021 11a. Operating test review completed (C.3.f).
-50 RDB 09/20/2021 11b. Written exam review completed (C.3.f).
12a. Examination review results discussed between the NRC and facility licensee (C.1.i; C.1.k-l;
-35 09/20/2021 RDB C.2.h; C.3.g).
-35 09/20/2021 12b. The NRC and the facility licensee conduct exam preparatory week. RDB
- 13. Preliminary license applications and waiver/excusal requests, as applicable (NRC Form 398)
-30 10/02/2021 RDB due (C.1.m; C.2.i; ES-202).
- 14. Final license applications and waiver/excusal requests, as applicable (NRC Form 398), due
-14 10/12/2021 RDB and Form ES-201-4 prepared (C.1.m; C.2.k; ES-202).
-7 10/12/2021 15. Written examinations and operating tests approved by the NRC supervisor (C.2.j-k; C.3.h). RDB
-7 10/12/2021 16. Request facility licensee management feedback on the examination (C.2.l). RDB
- 17. Final applications reviewed; one or two (if more than 10) applications audited to confirm
-7 10/12/2021 qualifications/eligibility; and examination approval and waiver/excusal letters sent (C.2.k; RDB Attachment 5; ES-202, C.3.j; ES-204).
-7 10/26/2021 18. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k). RDB
-7 10/26/2021 19. Approved scenarios and job performance measures distributed to NRC examiners (C.3.i). RDB
- Target dates are based on facility prepared examinations and the examination date identified in the corporate Exam Date: 11/01/2021 notification letter. These dates are for planning purposes and may be adjusted on a case by case basis in coordination with the facility licensee.