ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Dresden Nuclear Station, Units 2 and 3 Date of Examination: November 1 - 11, 2021 Developed: Written: Facility: NRC: // Operating: Facility: NRC:

Days from Chief Examiner's Target Date* Task Description (Reference)

Exam Initials

1. Examination administration date confirmed (C.1.a; C.2.a-b). For NRC-prepared exams,

-240 03/06/2021 RDB arrangements are made for the facility to submit reference materials (C.1.e; C.3.c; Attachment 3).

-210 04/05/2021 2. NRC examiners and facility contact assigned (C.1.d; C.2.f). RDB

3. Facility contact briefed on security and other requirements (C.2.c). As applicable, the facility

-210 04/05/2021 contact submits to the NRC any prescreened K/As for elimination from the written examination RDB outline, with a description of the facilitys prescreening process (ES-401, D.1.b).

-210 04/05/2021 4. Reference material due for NRC-prepared exams (C.1.e; C.3.c; Attachment 3). RDB

-210 04/05/2021 5. Corporate notification letter sent (C.2.e). RDB

6. NRC-developed written examination outline (ES-401-1/2 or ES-401N-1/2 and ES-401-3 or

-195 04/20/2021 ES-401N-3) sent to facility contact (must be on the exam security agreement) (C.1.e-f; C.2.h; RDB C.3.d-e).

7. Operating test outline(s) and other checklists due, including Forms ES-201-2, ES-201-3,

-150 06/04/2021 RDB ES-301-1, ES-301-2, ES-301-5, and ES-D-1, as applicable (C.1.e-f; C.3.d-e).

8. Operating test outline(s) reviewed by the NRC and feedback provided to facility licensee (C.2.h;

-136 06/18/2021 RDB C.3.d-e).

9a. Proposed examinations (JPMs, and scenarios, as applicable) and outlines (Forms ES-301-1, ES-301-2, ES-D-1, ES-401-1/2 or ES-401N-1/2, and ES-401-3 or ES-401N-3);

-75 08/20/2021 supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, ES-401-6, RDB ES-401N-6, and any Form ES-201-2 and ES-201-3 updates); and reference materials due (C.1.e-h; C.3.d).

9b. Proposed written examination due to NRC for review (Per CE resource scheduling.)

-60 09/07/2021 RDB (C.1.e-h; C.3.d).

-60 09/03/2021 10. Preliminary waiver/excusal requests due (C.1.m; C.2.c; ES-202). RDB 09/10/2021 11a. Operating test review completed (C.3.f).

-50 RDB 09/20/2021 11b. Written exam review completed (C.3.f).

12a. Examination review results discussed between the NRC and facility licensee (C.1.i; C.1.k-l;

-35 09/20/2021 RDB C.2.h; C.3.g).

-35 09/20/2021 12b. The NRC and the facility licensee conduct exam preparatory week. RDB

13. Preliminary license applications and waiver/excusal requests, as applicable (NRC Form 398)

-30 10/02/2021 RDB due (C.1.m; C.2.i; ES-202).

14. Final license applications and waiver/excusal requests, as applicable (NRC Form 398), due

-14 10/12/2021 RDB and Form ES-201-4 prepared (C.1.m; C.2.k; ES-202).

-7 10/12/2021 15. Written examinations and operating tests approved by the NRC supervisor (C.2.j-k; C.3.h). RDB

-7 10/12/2021 16. Request facility licensee management feedback on the examination (C.2.l). RDB

17. Final applications reviewed; one or two (if more than 10) applications audited to confirm

-7 10/12/2021 qualifications/eligibility; and examination approval and waiver/excusal letters sent (C.2.k; RDB Attachment 5; ES-202, C.3.j; ES-204).

-7 10/26/2021 18. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k). RDB

-7 10/26/2021 19. Approved scenarios and job performance measures distributed to NRC examiners (C.3.i). RDB

  • Target dates are based on facility prepared examinations and the examination date identified in the corporate Exam Date: 11/01/2021 notification letter. These dates are for planning purposes and may be adjusted on a case by case basis in coordination with the facility licensee.