MONTHYEARML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23160A1712023-06-0909 June 2023 Form 5.1-1 Post Examination Check Sheet ML23160A1672023-05-18018 May 2023 Form 1.3-1 Post Examination Security Agreement ML23160A1702023-05-18018 May 2023 Form 2.1-1 Examination Prep Checklist SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 ML23160A1832023-03-16016 March 2023 3.4-1 Events and Evolutions Checklist ML23160A1802023-03-16016 March 2023 2.3-1 Examination Outline Quality Checklist ML23160A0542023-03-16016 March 2023 2.3-2 - Operating Test Quality Checklist SVPLTR 23-0002, 2.3-4 - Written Examination Quality Checklist2023-03-16016 March 2023 2.3-4 - Written Examination Quality Checklist ML23160A1782023-03-0606 March 2023 ILT Exam Outline Submittal Letter ML23160A0522023-01-25025 January 2023 ILT Exam Submittal Letter RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 ML22195A1342021-12-0303 December 2021 Nov 2021 Ile ES-403-1-Written Exam Grading Quality Checklist-Signed ML22195A1312021-12-0303 December 2021 Nov 2021 Ile ES-201-3 - Exam Security Agreement ML22195A1272021-12-0303 December 2021 Nov 2021 Ile ES-201-1 Exam Prep Checklist ML22195A1352021-11-15015 November 2021 Nov 2021 Ile Post-Exam Package Submittal Letter 11/15/2021 ML21287A0442021-10-18018 October 2021 Operator Licensing Examination Approval ML22195A2312021-09-19019 September 2021 Nov 2021 Ile Es 401-6 Written Exam Quality Checklist-Signed ML22195A2282021-09-19019 September 2021 Nov 2021 Ile Es 301-6 Competencies Checklist ML22195A2262021-09-19019 September 2021 Nov 2021 Ile Es 301-4 Simulator Scenario Quality Checklist-Signed ML22195A2222021-09-19019 September 2021 Nov 2021 Ile Es 301-3 Operating Test Quality Checklist-Signed ML22195A2372021-09-0707 September 2021 Nov 2021 Ile Written Exam Submittal Letter 09-07-2021 ML22195A2342021-08-16016 August 2021 Nov 2021 Ile Operating Test Submittal Letter 08-16-2021 ML22195A2662021-06-26026 June 2021 Nov 2021 Ile Es 301-5 Transients and Events Checklist ML22195A2632021-06-26026 June 2021 Nov 2021 Ile Es 201-2 Outline Quality Checklist ML22195A2672021-06-0404 June 2021 Nov 2021 Ile Es 201-2 Outlines Submittal Email ML21139A2372021-05-21021 May 2021 Confirmation of Initial License Examination ML22215A1812021-05-14014 May 2021 April 2021 Administered JPMs ML22236A3332021-05-14014 May 2021 Initial License Exam Forms ES-201-3 ML22236A3322021-05-14014 May 2021 Initial License Exam Form ES-403-1 ML22236A3302021-05-14014 May 2021 Initial License Exam Form ES-201-1 ML22236A3842021-05-14014 May 2021 Initial License Exam Letter 21-0029 ML22235A7572021-05-14014 May 2021 April 2021 Form ES-201-2 Written Outline Only ML22235A7562021-05-14014 May 2021 April 2021 Form ES-301-5 SVPLTR 21-0007, April 2021 Submittal Letter2021-05-14014 May 2021 April 2021 Submittal Letter ML22215A2492021-05-14014 May 2021 April 2021 Form ES-401-6 ML22215A2462021-05-14014 May 2021 April 2021 Form ES-301-6 ML22215A2422021-05-14014 May 2021 April 2021 Form ES-301-4 ML22215A2382021-05-14014 May 2021 April 2021 Form ES-301-3 ML22215A1852021-05-14014 May 2021 April 2021 Administered Scenarios ML22236A0172021-05-14014 May 2021 Initial License Exam Forms ES-301-2 ML22236A0162021-05-14014 May 2021 Initial License Exam Forms ES-301-1 ML22216A1872021-05-14014 May 2021 April 2021 Proposed JPMs ML22216A1902021-05-14014 May 2021 April 2021 Proposed Written Exam ML22216A1892021-05-14014 May 2021 April 2021 Proposed Scenarios ML22236A0182021-05-14014 May 2021 Initial License Exam Forms ES-401-1 and ES-401-3 rev1 ML22215A1862021-05-14014 May 2021 April 2021 Administered Written Exam 2023-06-09
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23160A1712023-06-0909 June 2023 Form 5.1-1 Post Examination Check Sheet ML23160A1672023-05-18018 May 2023 Form 1.3-1 Post Examination Security Agreement ML23160A1702023-05-18018 May 2023 Form 2.1-1 Examination Prep Checklist SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 ML23160A1832023-03-16016 March 2023 3.4-1 Events and Evolutions Checklist ML23160A1802023-03-16016 March 2023 2.3-1 Examination Outline Quality Checklist SVPLTR 23-0002, 2.3-4 - Written Examination Quality Checklist2023-03-16016 March 2023 2.3-4 - Written Examination Quality Checklist ML23160A0542023-03-16016 March 2023 2.3-2 - Operating Test Quality Checklist ML23160A1782023-03-0606 March 2023 ILT Exam Outline Submittal Letter ML23160A0522023-01-25025 January 2023 ILT Exam Submittal Letter RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 ML22195A1272021-12-0303 December 2021 Nov 2021 Ile ES-201-1 Exam Prep Checklist ML22195A1312021-12-0303 December 2021 Nov 2021 Ile ES-201-3 - Exam Security Agreement ML22195A1342021-12-0303 December 2021 Nov 2021 Ile ES-403-1-Written Exam Grading Quality Checklist-Signed ML22195A1352021-11-15015 November 2021 Nov 2021 Ile Post-Exam Package Submittal Letter 11/15/2021 ML21287A0442021-10-18018 October 2021 Operator Licensing Examination Approval ML22195A2312021-09-19019 September 2021 Nov 2021 Ile Es 401-6 Written Exam Quality Checklist-Signed ML22195A2282021-09-19019 September 2021 Nov 2021 Ile Es 301-6 Competencies Checklist ML22195A2262021-09-19019 September 2021 Nov 2021 Ile Es 301-4 Simulator Scenario Quality Checklist-Signed ML22195A2222021-09-19019 September 2021 Nov 2021 Ile Es 301-3 Operating Test Quality Checklist-Signed ML22195A2372021-09-0707 September 2021 Nov 2021 Ile Written Exam Submittal Letter 09-07-2021 ML22195A2342021-08-16016 August 2021 Nov 2021 Ile Operating Test Submittal Letter 08-16-2021 ML22195A2662021-06-26026 June 2021 Nov 2021 Ile Es 301-5 Transients and Events Checklist ML22195A2632021-06-26026 June 2021 Nov 2021 Ile Es 201-2 Outline Quality Checklist ML22195A2672021-06-0404 June 2021 Nov 2021 Ile Es 201-2 Outlines Submittal Email ML21139A2372021-05-21021 May 2021 Confirmation of Initial License Examination ML22236A6382021-05-14014 May 2021 April 2021 Initial License Exam Form ES-401-4 ML22215A1812021-05-14014 May 2021 April 2021 Administered JPMs ML22215A1852021-05-14014 May 2021 April 2021 Administered Scenarios ML22236A3332021-05-14014 May 2021 Initial License Exam Forms ES-201-3 ML22236A3322021-05-14014 May 2021 Initial License Exam Form ES-403-1 ML22236A3302021-05-14014 May 2021 Initial License Exam Form ES-201-1 ML22236A3842021-05-14014 May 2021 Initial License Exam Letter 21-0029 ML22235A7572021-05-14014 May 2021 April 2021 Form ES-201-2 Written Outline Only ML22235A7562021-05-14014 May 2021 April 2021 Form ES-301-5 SVPLTR 21-0007, April 2021 Submittal Letter2021-05-14014 May 2021 April 2021 Submittal Letter ML22215A2492021-05-14014 May 2021 April 2021 Form ES-401-6 ML22215A2462021-05-14014 May 2021 April 2021 Form ES-301-6 ML22215A2422021-05-14014 May 2021 April 2021 Form ES-301-4 ML22215A2382021-05-14014 May 2021 April 2021 Form ES-301-3 ML22215A1862021-05-14014 May 2021 April 2021 Administered Written Exam ML22236A6392021-05-14014 May 2021 April 2021 Initial License Exam Form ES-401-9 ML22236A0202021-05-14014 May 2021 Initial License Exam Forms ES-D1 ML22236A6372021-05-14014 May 2021 April 2021 Initial License Exam Form ES-301-7 ML22236A6402021-05-14014 May 2021 April 2021 Initial License Exam Operating Test Outline Comments 2023-06-09
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
Scenario Outline Facility: Dresden Generating Station Scenario No.: 2021-301 ILT-N-2 Op-Test No.: 2021-301 Examiners Operators / crew position
/ ATC
/ BOP
/ CRS Initial Conditions: Unit 2 is at 85% Power.
Site is under a high winds advisory due to inclement weather.
Turnover: A Condensate/Condensate Booster Pump is experiencing high vibrations and needs to be removed from service for maintenance once power is lowered to 82% per DGP 03-01, Power Changes, step G.4.
Critical Tasks: 1. If the RPV level trend is not reversible with an RPV injection source lined up with a pump running, initiate emergency depressurization by opening 5 ADSVs with RPV water level between the Top-of-Active Fuel and the Minimum Steam Cooling RPV Water Level or within 2 1/2 minutes after TAF is reached, whichever is later.
- 2. Per DEOP 100, RPV Control, with automatic ADS timer initiated, inhibit ADS before an automatic actuation occurs.
Event Malf. Event Event No. No. Type* Description #
1 NONE R ATC Lower Power with flow 2 NONE N BOP Secure RFP and C/CB Pump 3 HPRMBRKP C/T BOP / CRS HPCI Isolation due to Steam Leak 4 RDPPBTRP C/T ATC / CRS CRD Pump Trip 5 CSP501B C/T BOP / CRS Core Spray System Low Pressure 6 X10 C ATC RFP Vent Fan Trip 7 F41 M Team Recirc Leak in DW - Manual Scram CS2AFTC 8 C BOP Core Spray Pump Fails to Auto Start CSLAUPPA RLMRASP 9 M Team Loss of Feed - Emergency Depressurization on Level RLMRBSP
- (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor, (T)ech Spec
- (New) - Event not used on previous 2 NRC Exams, (Pre) - Event used on previous 2 NRC Exams
Scenario Outline Facility: Dresden Generating Station Scenario No.: 2021-301 ILT-N-3 Op-Test No.: 2021-301 Examiners Operators / crew position
/ ATC
/ BOP
/ CRS Initial Conditions: Unit 2 is at 72% Power.
U2 Isolation Condenser is OOS for 2-1301-3 valve motor replacement.
Turnover: During initial power ascension following a refuel outage, 345kV Bus Tie 4-5 CB tripped. Repairs have been completed and the 345kV Switchyard is ready to be returned to a normal lineup. Once restored, continue on with power ascension to raise reactor power to 90% using recirc flow per QNE guidance.
Critical Tasks: 1. With reactor scram required and reactor not shutdown, act per DEOP 400-5, Failure to Scram, to reduce power by inserting negative reactivity before Torus temperature reaches 110oF.
- 2. Once DEOP 400-5, Failure to Scram, is entered -AND- reactor power is > 6% -AND- reactor level is > the Top-of-Active Fuel - AND- drywell pressure is > 2 psig or an ERV is open -AND- torus temperature is > 110o F, terminate and prevent injection (with exception of SBLC and CRD) into the RPV prior to exceeding Heat Capacity Temperature Limit (HCTL).
Event Malf. Event Event No. No. Type* Description #
1 NONE N BOP Restore 345kV Bus Tie 4-5 Circuit Breaker 2 NONE R ATC Raise Reactor Power using Recirc Flow 3 RR02A C/T ATC / CRS Recirc Pump Speed Controller Failure RADRBVAH VGDSTBYA 4 C/T BOP / CRS RB Vent Rad Monitor Fails Upscale, SBGT Fails to Auto Start VGDPRIMA VGDSTRTA 5 T50 C BOP Stator Water Cooling Pump Trip 6 CIGP1I M Team Spurious Group 1 - SCRAM RDHLVFPA RDHLDEGA 7 M Team Hydraulic ATWS RDHLVFPB RDHLDEGB SCRLFVAD 8 C ATC SBLC Relief Valve Fails Open SCRLFVBD
- (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor, (T)ech Spec
- (New) - Event not used on previous 2 NRC Exams, (Pre) - Event used on previous 2 NRC Exams
Scenario Outline Facility: Dresden Generating Station Scenario No.: 2021-301 ILT-N-4 Op-Test No.: 2021-301 Examiners Operators / crew position
/ ATC
/ BOP
/ CRS Initial Conditions: Unit 2 is in Mode 2. Reactor Power is stable at 7%
Turnover: Per DGP 01-01, Unit Startup, step G.57, stop rejecting to the Condenser with RWCU. Once complete, continue raising power to 10% per DGP 01-01 in preparation to put the Mode Switch in RUN.
Critical Tasks: 1. When RPV water level cannot be determined by multiple direct or indirect indications as defined by DEOP 0010-10, exit DEOP 100 and enter DEOP 400-1, RPV Flooding before DW radiation levels exceed 100 R/hr.
- 2. When conditions are met per DEOP 400-1, RPV Flooding, the minimum number (2 ADSVs) of available ADSVs for RPV depressurization are opened before DW radiation levels exceed 100 R/hr to allow RPV injection with high capacity, low pressure sources (Condensate/Feedwater, LPCI and/or CS).
- 3. Following RPV depressurization during non-ATWS RPV Flooding, and before DW radiation levels exceed 100 R/hr, maximize injection with high capacity, low pressure sources (Condensate/Feedwater, LPCI and/or CS) and do not divert available RPV injection flow paths until the RPV is flooded to the Main Steam Lines.
Event Malf. Event Event No. No. Type* Description #
1 NONE N BOP Secure Rejecting to Condenser with RWCU 2 NONE R ATC Raise Power with Rods 3 ADS3ESD C/T BOP / CRS ERV Spurious Open WTPPDSH1 4 HWWTPPDSH(1) C BOP Degraded TBCCW Pump HWWTBPMP(1)
NII17POT 5 I/T ATC / CRS IRM Fails Upscale - Partial Half Scram B15 6 NVM100BP M TEAM Medium Range Level Reference Leg Leak, Rise in DW Press - Scram 7 B12 C ATC Electrical ATWS NVM100AP NVM129AP 8 M TEAM Loss of Level Indication - RPV Flooding NVM106AP/BP NVML112P
- (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor, (T)ech Spec
- (New) - Event not used on previous 2 NRC Exams, (Pre) - Event used on previous 2 NRC Exams