Line 2: |
Line 2: |
| | number = ML110341352 | | | number = ML110341352 |
| | issue date = 02/14/2011 | | | issue date = 02/14/2011 |
| | title = Byron Station, Units 1 and 2 - Request for Additional Information Related to License Amendment Regarding Ultimate Heat Sink | | | title = Request for Additional Information Related to License Amendment Regarding Ultimate Heat Sink |
| | author name = Mahoney M | | | author name = Mahoney M |
| | author affiliation = NRC/NRR/DORL/LPLIII-2 | | | author affiliation = NRC/NRR/DORL/LPLIII-2 |
Revision as of 04:22, 9 February 2019
Letter Sequence RAI |
---|
|
|
MONTHYEARRS-09-054, License Amendment Request Regarding Ultimate Heat Sink2009-06-30030 June 2009 License Amendment Request Regarding Ultimate Heat Sink Project stage: Request ML0921203572009-07-31031 July 2009 Application Accepted - Byron LAR for Ultimate Heat Sink (ME1669-70) Project stage: Other ML0932006512009-12-11011 December 2009 Request for Additional Information Related to License Amendment Regarding Ultimate Heat Sink Project stage: RAI RS-10-020, Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink2010-01-25025 January 2010 Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink Project stage: Request ML1013805252010-05-18018 May 2010 Additional RAI for Ultimate Heat Sink License Amendment Request (ME1669-70) Project stage: RAI RS-10-112, Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink2010-07-0101 July 2010 Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink Project stage: Request ML1021601902010-08-18018 August 2010 Request for Additional Information Related to License Amendment Regarding Ultimate Heak Sink Project stage: RAI ML1030602892010-11-0202 November 2010 Approved with Comment: Request to Extend the Submittal Date for the Byron UHS RAI Response Project stage: RAI RS-10-184, Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink2010-11-0808 November 2010 Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink Project stage: Request ML1035003172010-12-16016 December 2010 Draft NRC RAI Byron Station, Units 1 and 2 - LAR Ultimate Heat Sink Project stage: Draft RAI ML1036205592010-12-28028 December 2010 Request for Additional Information Related to License Amendment Regarding Ultimate Heat Sink Project stage: RAI RS-11-010, Response to Request for Additional Information Related to License Amendment Regarding Ultimate Heat Sink2011-01-31031 January 2011 Response to Request for Additional Information Related to License Amendment Regarding Ultimate Heat Sink Project stage: Response to RAI ML1103413522011-02-14014 February 2011 Request for Additional Information Related to License Amendment Regarding Ultimate Heat Sink Project stage: RAI ML1104505662011-02-15015 February 2011 3/01/2011 Notice of Forthcoming Meeting with Exelon to Discuss Nrc'S Staff'S Review of the Ultimate Head Sink License Amendment Request for the Byron Station, Units 1 and 2 Project stage: Meeting ML1106201482011-03-10010 March 2011 Summary of Meeting with Exelon Generation Company, LLC to Discuss the Request for Additional Information Related to License Amendment Regarding the Ultimate Heat Sink Project stage: RAI RS-11-035, Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink2011-03-16016 March 2011 Additional Information Supporting Request for License Amendment Regarding Ultimate Heat Sink Project stage: Request RS-11-070, Supplement to Information Supporting Request for License Amendment Regarding Ultimate Heat Sink2011-05-0404 May 2011 Supplement to Information Supporting Request for License Amendment Regarding Ultimate Heat Sink Project stage: Supplement ML1113106332011-06-14014 June 2011 Issuance of Amendments Revision of Technical Specification 3.7.9, Ultimate Heat Sink Project stage: Approval 2010-05-18
[Table View] |
Similar Documents at Byron |
---|
Category:Request for Additional Information (RAI)
MONTHYEARML23297A2352023-10-26026 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection ML23209A7242023-07-31031 July 2023 Request for Information on the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000454/2024010 and 05000455/2024010 ML23198A0372023-07-17017 July 2023 Information Request to Support Upcoming Problem Identification and Resolution (PIR) Inspection at Byron Nuclear Plant ML23172A1172023-06-22022 June 2023 Notification of NRC Fire Protection Team Inspection Request for Information ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23069A0342023-03-0606 March 2023 Unit 1 Lr Commitment 10 RAI Set 1 - (Non-Proprietary) ML23069A0332023-03-0606 March 2023 Email to K. Lueshen Byron and Braidwood Commitment 10 - Request for Additional Information Set 1 ML23115A2412023-01-20020 January 2023 NRR E-mail Capture - Preliminary RAIs Related to L-2022-LLA-0131 - Byron, Unit 2, Reinsertion of an Accident Tolerant Fuel Lead Test Assembly ML22237A0272022-08-25025 August 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22116A1272022-04-26026 April 2022 Unit 2 RFI for an NRC Triennial Heat Exchanger/Sink Performance Inspection and RFI IR 05000454/2022002 05000455/2022002 ML22091A0852022-04-0101 April 2022 NRR E-mail Capture - Braidwood and Byron - Final RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML21273A3312021-10-0404 October 2021 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Byron Station ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21203A3112021-07-21021 July 2021 NRR E-mail Capture - Final Byron Permanently Defueled Technical Specifications (PDTS) - Second Round RAI ML21189A1602021-07-0808 July 2021 NRR E-mail Capture - Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs ML21189A1612021-07-0808 July 2021 NRR E-mail Capture - Second Round Request for Additional Information - Byron Permanently Defueled Technical Specification Amendment ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21036A1102021-02-0404 February 2021 NRR E-mail Capture - Draft RAIs for Byron Station, Unit Nos. 1 and 2, Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition ML21029A3302021-01-29029 January 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative Request to Use ASME Code Case N-885 ML21004A1452020-12-30030 December 2020 NRR E-mail Capture - Request for Additional Information Regarding Relief Requests Braidwood I4R-11 and Byron I4R-18 ML20329A4852020-11-24024 November 2020 Notification of NRC Fire Protection Team Inspection Request for Information ML20294A5492020-10-21021 October 2020 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML20289A1142020-10-0909 October 2020 NRR E-mail Capture - Preliminary RAIs for LAR Regarding Non-conservative TS EDG Frequency Tolerance ML20077M2212020-03-20020 March 2020 Ti 2515/194 Inspection Documentation Request ML20008D3992020-01-0808 January 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000454/2020001 ML19275H1362019-10-0202 October 2019 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Use ASME Code Case N-879 ML19252C1542019-08-22022 August 2019 NRR E-mail Capture - Issuance of the Remainder of Preliminary RAIs for Braidwood/Byron TSTF-505 Application ML19232A2242019-08-0707 August 2019 NRR E-mail Capture - Partial Issuance of Final RAIs for Braidwood/Byron TSTF-505 Application ML19207A0672019-07-26026 July 2019 NRR E-mail Capture - Partial Issuance of Preliminary RAIs for Braidwood/Byron TSTF-505 Application ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML19032A1062019-02-0101 February 2019 NRR E-mail Capture - Preliminary RAIs for Byron On--time Extension of Completion Time 3.8.1, A.2 ML19011A3452019-01-11011 January 2019 NRR E-mail Capture - Preliminary RAIs Regarding Byron Request to Use ATF LTAs ML18149A2842018-05-24024 May 2018 NRR E-mail Capture - B/B 50.69 RAI - Potential Typo ML18129A1082018-05-0909 May 2018 NRR E-mail Capture - Preliminary RAIs for Braidwood and Byron Stations 50.69 Amendment ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML18022A0422018-01-19019 January 2018 18 Byron Station, Units 1 and 2 - Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection (DRS-I.Hafeez) ML17179A2852017-06-28028 June 2017 NRR E-mail Capture - Request for Additional Information Regarding Braidwood and Byron Amendments to Remove Obsolete License and Technical Specification Items ML17159A6292017-06-0707 June 2017 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML17137A0562017-05-17017 May 2017 Information Request to Support Upcoming Temporary Instruction 191 Inspection at Byron Station, Units 1 and 2 ML17062A4912017-03-0303 March 2017 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative to RPV Threads in Flange Examination (CAC Nos. MF8712-MF8729) ML17019A2022017-01-19019 January 2017 NRR E-mail Capture - Preliminary RAIs for Byron Station TORMIS License Application Request ML16355A0322016-12-19019 December 2016 Notification of NRC Inspection and Request for Information (Msh) ML16343A2522016-12-0808 December 2016 NRR E-mail Capture - Preliminary Request for Additional Information (RAI) Regarding Relief Request I4R-10 ML16196A1102016-07-14014 July 2016 Notification of NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000454/2016004; 05000455/2016004 2023-07-31
[Table view] Category:Letter
MONTHYEARIR 05000454/20230042024-02-0202 February 2024 Integrated Inspection Report 05000454/2023004 and 05000455/2023004 ML24022A2722024-01-23023 January 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000454/2024011 ML24018A0362024-01-17017 January 2024 Paragon Energy Solutions, Defect with Detroit Diesel/Mtu Fuel Injectors P/N R5229660 Cat Id 0001390618 ML23320A1762023-12-13013 December 2023 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0027 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23277A0032023-12-11011 December 2023 Issuance of Amendments Regarding Adoption of TSTF-370 ML23318A5102023-12-0101 December 2023 Relief from the Requirements of the ASME Code IR 05000454/20233012023-11-27027 November 2023 NRC Initial License Examination Report 05000454/2023301 and 05000455/2023301 BYRON 2023-0065, Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline2023-11-17017 November 2023 Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline BYRON 2023-0063, Day Inservice Inspection Report for Interval 4, Period 3, (B2R24)2023-11-16016 November 2023 Day Inservice Inspection Report for Interval 4, Period 3, (B2R24) IR 05000454/20230032023-11-13013 November 2023 Integrated Inspection Report 05000454/2023003 and 05000455/2023003 and Exercise of Enforcement Discretion RS-23-117, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23313A0852023-11-0909 November 2023 Submittal of 2023-301 Byron Initial License Examination Post-Examination Comments RS-23-114, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2023-11-0101 November 2023 Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML23297A2352023-10-26026 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection RS-23-100, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23278A0272023-10-0505 October 2023 Operator Licensing Examination Approval - Byron Station, October 2023 RS-23-093, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel.2023-09-29029 September 2023 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel. ML23251A1622023-09-29029 September 2023 Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements RS-23-094, Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 752023-09-29029 September 2023 Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 75 RS-23-091, Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals2023-09-26026 September 2023 Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals ML23226A0062023-09-19019 September 2023 Review of License Renewal Commitment Number 10 Submittal ML23180A1692023-09-11011 September 2023 Calvert Cliff Units 1 & 2, and R.E. Ginna Plant - Withdrawal of Proposed Alternatives to American Society of Mechanical Engineers (ASME) Requirements (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and 0094) ML23242A3282023-09-0101 September 2023 Amendment No. 233 Correction IR 05000454/20235012023-08-31031 August 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000454/2023501 and 05000455/2023501 IR 05000454/20230052023-08-30030 August 2023 Updated Inspection Plan for Byron Station (Report 05000454/2023005 and 05000455/2023005) IR 05000454/20230022023-08-0303 August 2023 Integrated Inspection Report 05000454/2023002 and 05000455/2023002 ML23209A7242023-07-31031 July 2023 Request for Information on the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000454/2024010 and 05000455/2024010 ML23192A0362023-07-25025 July 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report ML23122A3022023-07-20020 July 2023 Issuance of Amendments Technical Specifications 2.1.1 and 4.2.1 to Allow a Previously Irradiated Accident Tolerant Fuel Lead Test Assembly to Be Further Irradiated in Unit No. 2 IR 05000454/20234022023-07-18018 July 2023 Baseline Security Inspection Document; 05000454/2023402; 05000455/2023402 ML23198A0372023-07-17017 July 2023 Information Request to Support Upcoming Problem Identification and Resolution (PIR) Inspection at Byron Nuclear Plant ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators ML23172A1172023-06-22022 June 2023 Notification of NRC Fire Protection Team Inspection Request for Information RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23159A1302023-06-0808 June 2023 Day Inservice Inspection Report for Interval 4, Period 3, (B1R25) ML23159A1542023-06-0808 June 2023 2022 Regulatory Commitment Change Summary Report RS-23-075, Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process2023-06-0707 June 2023 Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process ML23157A2832023-06-0606 June 2023 Notification of NRC Baseline Inspection and Request for Information BYRON 2023-0029, Response to Request for Additional Information Regarding Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements2023-06-0101 June 2023 Response to Request for Additional Information Regarding Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements ML23138A1342023-05-18018 May 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Braidwood Station and Byron Station ML23003A7882023-05-11011 May 2023 Report for December 12-16, 2022, Regulatory Audit Regarding Reinsertion of a High Burnup Accident Tolerant Fuel Lead Test Assembly 2024-02-02
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 February 14, 2011 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville.
IL 60555 BYRON STATION, UNIT NOS. 1 AND 2 -REQUEST FOR ADDITIONAL INFORMATION RELATED TO LICENSE AMENDMENT REGARDING ULTIMATE HEAT SINK (TAC NOS. ME1669 AND ME1670)
Dear Mr. Pacilio:
By letter to the Nuclear Regulatory Commission (NRC) dated June 30, 2009, as supplemented by letters dated January 25, July 1. and November 11.2010 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML091831253, ML 100280553.
ML101830041 , and ML103120556, respectively).
Exelon Generation Company, LLC (the licensee), submitted a license amendment request for the Byron Station, Unit Nos. 1 and 2, to revise Technical Specification 3.7.9, "Ultimate Heat Sink (UHS)," to add additional essential service water (SX) cooling tower fan requirements as a function of SX pump discharge temperature to reflect the results of a revised analysis for the UHS. The NRC staff is reviewing your submittals, and has determined that additional information is required to complete its review. The specific information requested is addressed in the enclosure to this letter. During a discussion with your staff on February 9, 2011, it was agreed that you would provide a response within 30 days from the date of this letter. Please note that if you do not respond to this letter by the agreed-upon date or provide an acceptable alternate date in writing, we may reject your request for approval under the provisions of 10 CFR 2.108. The NRC staff considers that timely responses to requests for additional information help ensure that sufficient time is available for the NRC staff to review and contribute toward the NRC's goal of efficient and effective use of staff resources.
M. Pacilio -2 If circumstances result in the need to revise the requested response date, please contact me at 301-415-3867 or Nicholas DiFrancesco at 301-415-1115.
/ ichael Mahoney, Project Plant Licensing Branch 111-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket No. STN 50-454 and STN Request for Additional cc w/encl: Distribution REQUEST FOR ADDITIONAL INFORMATION BYRON STATION, UNIT NOS. 1 AND 2 EXELON GENERATION COMPANY, LLC DOCKET NOS. 50-454 AND 50-455 The Nuclear Regulatory Commission (NRC) staff is reviewing Exelon Generation Company, LLC's (the licensee) license amendment request (LAR) for the Byron Station, Unit Nos. 1 and 2 (Byron) dated June 30,2009, as supplemented by letters dated January 25, July 1, and November 11, 2010 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML091831253, ML 100280553, ML 101830041, and ML 103120556, respectively).
The LAR requests to revise Technical Specification (TS) 3.7.9, "Ultimate Heat Sink (UHS)," to add additional essential service water (SX) cooling tower fan requirements as a function of SX pump discharge temperature to reflect the results of a revised analysis for the UHS. The NRC staff has determined that the following additional information is required to complete its review. The UHS is required to be OPERABLE in MODES 1 through 4. Eight cooling tower fans running in fast speed are necessary to ensure basin temperature does not reach 100°F following a LOCA 1I0ss of offsite power at one unit concurrent with the safe shutdown from maximum power of the other unit under bounding conditions.
When 8 fans are not OPERABLE and in fast speed while the plant is in MODES 1 through 4 under bounding conditions, LCO 3.7.9 is not met. As an alternative to shutting down the reactor, the TS allow entry into LCO 3.7.9 Condition A and performance of REQUIRED ACTIONS A.1 and A.2. The Facility Operating License (FOL) for Byron contains a set of rules for the use and application of Byron TS's. The BACKGROUND section on Page 1.3-1 of Byron TS states "The ACTIONS associated with an LCO state Conditions that typically describe the ways in which the requirements of the LCO can fail to be met. Specified with each stated Condition are Required Action(s) and Completion Time(s)." The proposed TS 3.7.9 changes do not appear to conform to the use and application section of Byron TS. That is, the proposed Conditions do not describe the ways in which cooling tower fan requirements can fail to be met. Explain why this unusual format is required, or provide revised proposed TS that conform to the TS use and application section of the Byron FOL ENCLOSURE M. Pacilio If circumstances result in the need to revise the requested response date, please contact me at 301-415-3867 or Nicholas DiFrancesco at 301-415-1115.
Docket No. STN 50-454 and STN Request for Additional cc w/encl: Distribution via RidsNrrPMByron RidsOgcRp RidsNrrDorlDpr NDiFrancesco, RidsNrrDssSnpb ADA M S AcceSSion N o.
Sincerely, IRAJ Michael Mahoney, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation LPL3-2 RlF RidsNrrLASRohrer Resource RidsAcrsAcnw_MailCTR Resource RidsRgn3MailCenter Resource RidsNrrDirsltsb Resource *B sy M emo D ae t d OFFICE LPL3-2IPM LPL3-2/LA LPL3-2/BC DIRS/ITSB/BC LPL3-2/PM NAME MMahoney SRohrer RCarlson (EBrown for) RElliott*
MMahoney DATE 2/8/11 2/8/11 2/14/11 *2/4/11 2114/11 OFFICIAL RECORD