In reply to Inspection & Enforcement Bulletin No. 79-09, we have reviewed the Jamesport Nuclear Power Station (JNPS) design and submit the following response.
In reply to Inspection & Enforcement Bulletin No. 79-09, we have reviewed the Jamesport Nuclear Power Station (JNPS) design and submit the following response.
                                                                                              !
Purchase Orders for circuit breakers in safety related systems have not been placed for the Jamesport Nuclear Power Station (JNPS).
Purchase Orders for circuit breakers in safety related systems have not been placed for the Jamesport Nuclear Power Station (JNPS).
Act . rdingly, the particular circuit breakers which will be used are                        ,
Act . rdingly, the particular circuit breakers which will be used are                        ,
Line 31: Line 30:
Should you require further information, please do not hesitate to contact us.
Should you require further information, please do not hesitate to contact us.
Very truly yours,
Very truly yours,
,
[$ o, .ed y R. E. Plaskon Assistant Project Manager Jamesport Nuclear Power Station LG/dm cc:    Mr. John G. Davis, Director Office of Inspection & Enforcement U.S. "uclear Regulatory Commission                                                  j Washington, D.C. 20545 488        143                  2 007soo>ap~s,2-
[$ o, .ed y R. E. Plaskon Assistant Project Manager Jamesport Nuclear Power Station LG/dm cc:    Mr. John G. Davis, Director Office of Inspection & Enforcement U.S. "uclear Regulatory Commission                                                  j Washington, D.C. 20545 488        143                  2 007soo>ap~s,2-
                                             .}}
                                             .}}

Latest revision as of 02:18, 2 February 2020

Responds to IE Bulletin 79-09.Purchase Orders for Circuit Breakers in safety-related Sys Have Not Been Placed.If GE Type AK-2 Circuit Breakers Are Used,Preventive Maint Program Will Be Conducted
ML19247A296
Person / Time
Site: 05000516, 05000517
Issue date: 06/12/1979
From: Plaskon R
LONG ISLAND LIGHTING CO.
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
JNRC-233, NUDOCS 7907300512
Download: ML19247A296 (1)


Text

,

rg j.i.#E,(f,@

.isan.w us LONG ISLAND LIGHTING COM PANY 175 EAST OLD COU N TRY ROAD H IC K SVI L LE. NEW YORK 11801 June 12, 1979 JNRC-233 Mr. Boyce Grier, Director Office of Inspection & Enforcement, Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 Jamecport Nuclear Power Station - Units 1 & 2 Inspection & Enforcement Bulletin No. 79-09 Docket Nos. 50-516 50-517

Dear Mr. Grier:

In reply to Inspection & Enforcement Bulletin No. 79-09, we have reviewed the Jamesport Nuclear Power Station (JNPS) design and submit the following response.

Purchase Orders for circuit breakers in safety related systems have not been placed for the Jamesport Nuclear Power Station (JNPS).

Act . rdingly, the particular circuit breakers which will be used are ,

not known at this point in time. If GE type AK-2 circuit breakers ,

are ultimately used in the JNPS safety related systems, a preventive '

maintenance program will be conducted in accordance with inanufacturer's recommendatious.

Should you require further information, please do not hesitate to contact us.

Very truly yours,

[$ o, .ed y R. E. Plaskon Assistant Project Manager Jamesport Nuclear Power Station LG/dm cc: Mr. John G. Davis, Director Office of Inspection & Enforcement U.S. "uclear Regulatory Commission j Washington, D.C. 20545 488 143 2 007soo>ap~s,2-

.