{{#Wiki_filter:November 9, 2006LICENSEE:PPL Susquehanna, LLC (PPL)FACILITY:Susquehanna Steam Electric Station, Units 1 and 2 (SSES 1 and 2)
{{#Wiki_filter:November 9, 2006 LICENSEE:       PPL Susquehanna, LLC (PPL)
FACILITY:       Susquehanna Steam Electric Station, Units 1 and 2 (SSES 1 and 2)


==SUBJECT:==
==SUBJECT:==


==SUMMARY==
==SUMMARY==
OF NOVEMBER 6, 2006, CATEGORY 1 WORKING-LEVELMEETING WITH PPL TO DISCUSS THE LICENSEE'S EXTENDED POWER UPRATE (EPU) SUBMITTAL DATED OCTOBER 11, 2006 (AGENCYWIDE DOCUMENTS ACCESS AND MANAGEMENT SYSTEM (ADAMS) ACCESSION NO. ML062900160)On November 6, 2006, a public meeting was held between the Nuclear Regulatory Commission(NRC), and representatives of PPL, the licensee for SSES 1 and 2, and its contractors, General Electric Company, Continuum Dynamics, Incorporated, and MPR Associates at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to conduct a working-level discussion of PPL's October 11, 2006, EPU license amendment application for SSES 1 and 2 related to steam dryer analysis and testing.
OF NOVEMBER 6, 2006, CATEGORY 1 WORKING-LEVEL MEETING WITH PPL TO DISCUSS THE LICENSEES EXTENDED POWER UPRATE (EPU) SUBMITTAL DATED OCTOBER 11, 2006 (AGENCYWIDE DOCUMENTS ACCESS AND MANAGEMENT SYSTEM (ADAMS) ACCESSION NO. ML062900160)
A list of meeting attendees is provided as Enclosure 1. Also provided is a copy of the licensee'sslides (Enclosure 2) presented at the meeting. PPL presented an overview of the major changes in their revised EPU application and alsoprovided a description of their steam dryer and main steam line configurations with the various evaluations and testing methods for analyzing the steam dryers at SSES 1 and 2. PPL also discussed its steam dryer structural evaluation process, uncertainty conditions, and its finite element analysis results.PPL concluded and summarized its presentation by stating that (1) their analysis shows that noacoustic resonances are expected to exist at full EPU conditions, (2) steam line testing demonstrates that no acoustic resonances will exist at the first EPU step and that the main steam lines and attached equipment will be subject to low levels of vibration at the first EPU step, (3) analysis techniques are comprehensive and utilize actual Susquehanna plant data, (4) the steam dryer analysis method was benchmarked against measured Susquehanna strains, and (5) that the EPU steam dryer design will conform to the American Society of Mechanical Engineers design criteria ensuring the steam dryer will maintain its structural integrity.Before the meeting adjourned, the public was given the opportunity to communicate with theNRC staff. One member of the public was in attendance, representing McGraw-Hill Company, and requested the status of the NRC staff's acceptance review of the licensee's EPU application. The NRC staff informed the member of the public that the acceptance review was in progress and would be completed shortly. The member of the public also inquired whether there would be any impacts in the NRC's review schedule when reviewing both PPL applications for license renewal and EPU. The NRC staff informed the member of the public that the review schedule for license renewal is described in a letter dated August 2, 2006 (Agencywide Documents Access and Management System (ADAMS) accession no.ML062140549). The letter documenting the acceptance review results for PPL's license renewal application was issued to PPL on October 26, 2006 (ML062930293). The member of the public chose not to complete any Public Meeting Feedback Forms (NRC Form 659) which were available at the meeting. Please direct any inquiries to me at 301-415-1030, or rvg@nrc.gov./RA/Richard V. Guzman, Project ManagerPlant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-387 and 50-388
On November 6, 2006, a public meeting was held between the Nuclear Regulatory Commission (NRC), and representatives of PPL, the licensee for SSES 1 and 2, and its contractors, General Electric Company, Continuum Dynamics, Incorporated, and MPR Associates at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to conduct a working-level discussion of PPLs October 11, 2006, EPU license amendment application for SSES 1 and 2 related to steam dryer analysis and testing.
A list of meeting attendees is provided as Enclosure 1. Also provided is a copy of the licensees slides (Enclosure 2) presented at the meeting.
PPL presented an overview of the major changes in their revised EPU application and also provided a description of their steam dryer and main steam line configurations with the various evaluations and testing methods for analyzing the steam dryers at SSES 1 and 2. PPL also discussed its steam dryer structural evaluation process, uncertainty conditions, and its finite element analysis results.
PPL concluded and summarized its presentation by stating that (1) their analysis shows that no acoustic resonances are expected to exist at full EPU conditions, (2) steam line testing demonstrates that no acoustic resonances will exist at the first EPU step and that the main steam lines and attached equipment will be subject to low levels of vibration at the first EPU step, (3) analysis techniques are comprehensive and utilize actual Susquehanna plant data, (4) the steam dryer analysis method was benchmarked against measured Susquehanna strains, and (5) that the EPU steam dryer design will conform to the American Society of Mechanical Engineers design criteria ensuring the steam dryer will maintain its structural integrity.
Before the meeting adjourned, the public was given the opportunity to communicate with the NRC staff. One member of the public was in attendance, representing McGraw-Hill Company, and requested the status of the NRC staffs acceptance review of the licensees EPU application. The NRC staff informed the member of the public that the acceptance review was in progress and would be completed shortly. The member of the public also inquired whether there would be any impacts in the NRCs review schedule when reviewing both PPL applications for license renewal and EPU. The NRC staff informed the member of the public that the review schedule for license renewal is described in a letter dated August 2, 2006
 
(Agencywide Documents Access and Management System (ADAMS) accession no.
ML062140549). The letter documenting the acceptance review results for PPLs license renewal application was issued to PPL on October 26, 2006 (ML062930293). The member of the public chose not to complete any Public Meeting Feedback Forms (NRC Form 659) which were available at the meeting.
Please direct any inquiries to me at 301-415-1030, or rvg@nrc.gov.
                                            /RA/
Richard V. Guzman, Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388


==Enclosures:==
==Enclosures:==
: 1. List of Attendees
: 1. List of Attendees
: 2. Licensee's Handouts/Slidescc w/encls: See next page
: 2. Licensees Handouts/Slides cc w/encls: See next page
 
ML063120509 OFFICE LPLI-1/PM                LPLI-1/LA            LPLI-1/BC NAME RGuzman                    SLittle              RLaufer DATE      11/09/06            11/09/06              11/09/06
 
LIST OF ATTENDEES REVIEW MEETING WITH PPL SUSQUEHANNA, LLC REGARDING EXTENDED POWER UPRATE PROPOSED LICENSE AMENDMENT NOVEMBER 6, 2006 - 10:00-12:30, O-8-B-4 NAME                                    ORGANIZATION
: 1. Richard V. Guzman                    NRC
: 2. Richard J. Laufer                    NRC
: 3. Thomas Scarbrough                    NRC
: 4. Kamal Manoly                          NRC
: 5. John Lubinski                        NRC
: 6. Kevin Browning                        PPL Susquehanna
: 7. John A. Bartos                        PPL Susquehanna
: 8. George T. Jones                      PPL Susquehanna
: 9. Michael S. Gorski                    PPL Susquehanna
: 10. Patricia L. Campbell                General Electric
: 11. Dan Pappone                          General Electric
: 12. Bill McCurdy                        MPR Associates
: 13. Edward Bird                          MPR Associates
: 14. Alan Bilanin                        Continuum Dynamics Inc.
: 15. Ching Hang Ng                        NRC
: 16. Tom Alexion                          NRC
: 17. Andy DuBouchet                      NRC
: 18. Paul Duke                            PSEG Nuclear
: 19. Daniel Horner                        McGraw-Hill Company
: 20. George Inch                          Constellation Energy Group
: 21. Gary S. Pavis                        Constellation Energy Group
: 22. Michael Crowthers                    PPL Susquehanna
: 23. John Wu                              NRC
: 24. Vic Shah (by teleconference)        NRC Contractor
: 25. Tom Mulcahy (by teleconference)      NRC Contractor
: 26. Steve Hambric (by teleconference)    NRC Contractor
: 27. Samir Ziada (by teleconference)      NRC Contractor Enclosure 1


ML063120509OFFICELPLI-1/PMLPLI-1/LALPLI-1/BCNAMERGuzmanSLittleRLauferDATE11/09/0611/09/0611/09/06 LIST OF ATTENDEESREVIEW MEETING WITH PPL SUSQUEHANNA, LLCREGARDING EXTENDED POWER UPRATEPROPOSED LICENSE AMENDMENTNOVEMBER 6, 2006 - 10:00-12:30, O-8-B-4 NAME ORGANIZATION1. Richard V. GuzmanNRC2. Richard J. LauferNRC
MEETING SLIDES Enclosure 2
: 3. Thomas ScarbroughNRC
: 4. Kamal ManolyNRC
: 5. John LubinskiNRC
: 6. Kevin BrowningPPL Susquehanna
: 7. John A. BartosPPL Susquehanna
: 8. George T. JonesPPL Susquehanna
: 9. Michael S. GorskiPPL Susquehanna
: 10. Patricia L. CampbellGeneral Electric
: 11. Dan PapponeGeneral Electric
: 12. Bill McCurdyMPR Associates
: 13. Edward BirdMPR Associates
: 14. Alan BilaninContinuum Dynamics Inc.
: 15. Ching Hang NgNRC
: 16. Tom AlexionNRC
: 17. Andy DuBouchetNRC
: 18. Paul DukePSEG Nuclear
: 19. Daniel HornerMcGraw-Hill Company
: 20. George InchConstellation Energy Group
: 21. Gary S. PavisConstellation Energy Group
: 22. Michael CrowthersPPL Susquehanna
: 23. John WuNRC
: 24. Vic Shah (by teleconference)NRC Contractor
: 25. Tom Mulcahy (by teleconference)NRC Contractor
: 26. Steve Hambric (by teleconference)NRC Contractor
: 27. Samir Ziada (by teleconference)NRC ContractorEnclosure 1 MEETING SLIDESEnclosure 2 Susquehanna Steam Electric Station, Units 1 and 2 cc:
Mr. Britt T. McKinneySr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA  18603-0467Robert A. SacconeGeneral Manager - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA  18603-0467Terry L. HarpsterGeneral Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467Rocco R. SgarroManager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Walter E. MorrisseySupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467Michael H. CrowthersSupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Steven M. CookManager - Quality Assurance PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467Luis A. RamosCommunity Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA  18603-0467Bryan A. Snapp, EsqAssoc. General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA  18101-1179Supervisor - Document Control ServicesPPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Richard W. OsborneAllegheny Electric Cooperative, Inc.
212 Locust Street P.O. Box 1266 Harrisburg, PA  17108-1266Director - Bureau of Radiation ProtectionPennsylvania Department of Environmental Protection P.O. Box 8469 Harrisburg, PA 17105-8469Senior Resident InspectorU.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4Berwick, PA 18603-0035Regional Administrator, Region 1U.S. Nuclear Regulatory Commission


475 Allendale Road King of Prussia, PA 19406Board of SupervisorsSalem Township P.O. Box 405 Berwick, PA 18603-0035Dr. Judith JohnsrudNational Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803}}
Susquehanna Steam Electric Station, Units 1 and 2 cc:
Mr. Britt T. McKinney                            Bryan A. Snapp, Esq Sr. Vice President                                Assoc. General Counsel and Chief Nuclear Officer                        PPL Services Corporation PPL Susquehanna, LLC                              Two North Ninth Street, GENTW3 769 Salem Blvd., NUCSB3                          Allentown, PA 18101-1179 Berwick, PA 18603-0467 Supervisor - Document Control Services Robert A. Saccone                                PPL Susquehanna, LLC General Manager - Nuclear Operations              Two North Ninth Street, GENPL4 PPL Susquehanna, LLC                              Allentown, PA 18101-1179 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467                            Richard W. Osborne Allegheny Electric Cooperative, Inc.
Terry L. Harpster                                212 Locust Street General Manager - Plant Support                  P.O. Box 1266 PPL Susquehanna, LLC                              Harrisburg, PA 17108-1266 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467                            Director - Bureau of Radiation Protection Pennsylvania Department of Rocco R. Sgarro                                    Environmental Protection Manager - Nuclear Regulatory Affairs              P.O. Box 8469 PPL Susquehanna, LLC                              Harrisburg, PA 17105-8469 Two North Ninth Street, GENPL4 Allentown, PA 18101-1179                          Senior Resident Inspector U.S. Nuclear Regulatory Commission Walter E. Morrissey                              P.O. Box 35, NUCSA4 Supervising Engineer                              Berwick, PA 18603-0035 Nuclear Regulatory Affairs PPL Susquehanna, LLC                              Regional Administrator, Region 1 769 Salem Blvd., NUCSA4                          U.S. Nuclear Regulatory Commission Berwick, PA 18603-0467                            475 Allendale Road King of Prussia, PA 19406 Michael H. Crowthers Supervising Engineer                              Board of Supervisors Nuclear Regulatory Affairs                        Salem Township PPL Susquehanna, LLC                              P.O. Box 405 Two North Ninth Street, GENPL4                    Berwick, PA 18603-0035 Allentown, PA 18101-1179 Dr. Judith Johnsrud Steven M. Cook                                    National Energy Committee Manager - Quality Assurance                      Sierra Club PPL Susquehanna, LLC                              443 Orlando Avenue 769 Salem Blvd., NUCSB2                          State College, PA 16803 Berwick, PA 18603-0467 Luis A. Ramos Community Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467}}

Revision as of 13:12, 23 November 2019

Summary of November 6, 2006, Category 1 Working-Level Meeting with PPL to Discuss the Licensee'S Extended Power Uprate (EPU) Submittal Dated October 11, 2006 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML0629001
ML063120509
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 11/09/2006
From: Richard Guzman
NRC/NRR/ADRO/DORL/LPLI-1
To: Mckinney B
Susquehanna
Guzman R, NRR/DORL, 415-1030
References
Download: ML063120509 (7)


Text

November 9, 2006 LICENSEE: PPL Susquehanna, LLC (PPL)

FACILITY: Susquehanna Steam Electric Station, Units 1 and 2 (SSES 1 and 2)

SUBJECT:

SUMMARY

OF NOVEMBER 6, 2006, CATEGORY 1 WORKING-LEVEL MEETING WITH PPL TO DISCUSS THE LICENSEES EXTENDED POWER UPRATE (EPU) SUBMITTAL DATED OCTOBER 11, 2006 (AGENCYWIDE DOCUMENTS ACCESS AND MANAGEMENT SYSTEM (ADAMS) ACCESSION NO. ML062900160)

On November 6, 2006, a public meeting was held between the Nuclear Regulatory Commission (NRC), and representatives of PPL, the licensee for SSES 1 and 2, and its contractors, General Electric Company, Continuum Dynamics, Incorporated, and MPR Associates at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to conduct a working-level discussion of PPLs October 11, 2006, EPU license amendment application for SSES 1 and 2 related to steam dryer analysis and testing.

A list of meeting attendees is provided as Enclosure 1. Also provided is a copy of the licensees slides (Enclosure 2) presented at the meeting.

PPL presented an overview of the major changes in their revised EPU application and also provided a description of their steam dryer and main steam line configurations with the various evaluations and testing methods for analyzing the steam dryers at SSES 1 and 2. PPL also discussed its steam dryer structural evaluation process, uncertainty conditions, and its finite element analysis results.

PPL concluded and summarized its presentation by stating that (1) their analysis shows that no acoustic resonances are expected to exist at full EPU conditions, (2) steam line testing demonstrates that no acoustic resonances will exist at the first EPU step and that the main steam lines and attached equipment will be subject to low levels of vibration at the first EPU step, (3) analysis techniques are comprehensive and utilize actual Susquehanna plant data, (4) the steam dryer analysis method was benchmarked against measured Susquehanna strains, and (5) that the EPU steam dryer design will conform to the American Society of Mechanical Engineers design criteria ensuring the steam dryer will maintain its structural integrity.

Before the meeting adjourned, the public was given the opportunity to communicate with the NRC staff. One member of the public was in attendance, representing McGraw-Hill Company, and requested the status of the NRC staffs acceptance review of the licensees EPU application. The NRC staff informed the member of the public that the acceptance review was in progress and would be completed shortly. The member of the public also inquired whether there would be any impacts in the NRCs review schedule when reviewing both PPL applications for license renewal and EPU. The NRC staff informed the member of the public that the review schedule for license renewal is described in a letter dated August 2, 2006

(Agencywide Documents Access and Management System (ADAMS) accession no.

ML062140549). The letter documenting the acceptance review results for PPLs license renewal application was issued to PPL on October 26, 2006 (ML062930293). The member of the public chose not to complete any Public Meeting Feedback Forms (NRC Form 659) which were available at the meeting.

Please direct any inquiries to me at 301-415-1030, or rvg@nrc.gov.

/RA/

Richard V. Guzman, Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388

Enclosures:

1. List of Attendees
2. Licensees Handouts/Slides cc w/encls: See next page

ML063120509 OFFICE LPLI-1/PM LPLI-1/LA LPLI-1/BC NAME RGuzman SLittle RLaufer DATE 11/09/06 11/09/06 11/09/06

LIST OF ATTENDEES REVIEW MEETING WITH PPL SUSQUEHANNA, LLC REGARDING EXTENDED POWER UPRATE PROPOSED LICENSE AMENDMENT NOVEMBER 6, 2006 - 10:00-12:30, O-8-B-4 NAME ORGANIZATION

1. Richard V. Guzman NRC
2. Richard J. Laufer NRC
3. Thomas Scarbrough NRC
4. Kamal Manoly NRC
5. John Lubinski NRC
6. Kevin Browning PPL Susquehanna
7. John A. Bartos PPL Susquehanna
8. George T. Jones PPL Susquehanna
9. Michael S. Gorski PPL Susquehanna
10. Patricia L. Campbell General Electric
11. Dan Pappone General Electric
12. Bill McCurdy MPR Associates
13. Edward Bird MPR Associates
14. Alan Bilanin Continuum Dynamics Inc.
15. Ching Hang Ng NRC
16. Tom Alexion NRC
17. Andy DuBouchet NRC
18. Paul Duke PSEG Nuclear
19. Daniel Horner McGraw-Hill Company
20. George Inch Constellation Energy Group
21. Gary S. Pavis Constellation Energy Group
22. Michael Crowthers PPL Susquehanna
23. John Wu NRC
24. Vic Shah (by teleconference) NRC Contractor
25. Tom Mulcahy (by teleconference) NRC Contractor
26. Steve Hambric (by teleconference) NRC Contractor
27. Samir Ziada (by teleconference) NRC Contractor Enclosure 1

MEETING SLIDES Enclosure 2

Susquehanna Steam Electric Station, Units 1 and 2 cc:

Mr. Britt T. McKinney Bryan A. Snapp, Esq Sr. Vice President Assoc. General Counsel and Chief Nuclear Officer PPL Services Corporation PPL Susquehanna, LLC Two North Ninth Street, GENTW3 769 Salem Blvd., NUCSB3 Allentown, PA 18101-1179 Berwick, PA 18603-0467 Supervisor - Document Control Services Robert A. Saccone PPL Susquehanna, LLC General Manager - Nuclear Operations Two North Ninth Street, GENPL4 PPL Susquehanna, LLC Allentown, PA 18101-1179 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467 Richard W. Osborne Allegheny Electric Cooperative, Inc.

Terry L. Harpster 212 Locust Street General Manager - Plant Support P.O. Box 1266 PPL Susquehanna, LLC Harrisburg, PA 17108-1266 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Director - Bureau of Radiation Protection Pennsylvania Department of Rocco R. Sgarro Environmental Protection Manager - Nuclear Regulatory Affairs P.O. Box 8469 PPL Susquehanna, LLC Harrisburg, PA 17105-8469 Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Senior Resident Inspector U.S. Nuclear Regulatory Commission Walter E. Morrissey P.O. Box 35, NUCSA4 Supervising Engineer Berwick, PA 18603-0035 Nuclear Regulatory Affairs PPL Susquehanna, LLC Regional Administrator, Region 1 769 Salem Blvd., NUCSA4 U.S. Nuclear Regulatory Commission Berwick, PA 18603-0467 475 Allendale Road King of Prussia, PA 19406 Michael H. Crowthers Supervising Engineer Board of Supervisors Nuclear Regulatory Affairs Salem Township PPL Susquehanna, LLC P.O. Box 405 Two North Ninth Street, GENPL4 Berwick, PA 18603-0035 Allentown, PA 18101-1179 Dr. Judith Johnsrud Steven M. Cook National Energy Committee Manager - Quality Assurance Sierra Club PPL Susquehanna, LLC 443 Orlando Avenue 769 Salem Blvd., NUCSB2 State College, PA 16803 Berwick, PA 18603-0467 Luis A. Ramos Community Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467