August 2, 2006Mr. Britt T. McKinneySr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3Berwick, PA 18603-0467

SUBJECT:

PRE-APPLICATION ACTIVITIES REGARDING LICENSE RENEWALAPPLICATION REVIEW SCHEDULE FOR SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 (TAC NOS. MD0547 AND MD0548)

Dear Mr. McKinney:

During a public meeting held on April 5, 2006, the U.S. Nuclear Regulatory Commission (NRCor the staff), and representatives of PPL Susquehanna, LLC (or PPL), discussed the approach and schedule for submitting an application for license renewal (LR) in conjunction with a request for a 14 percent extended power uprate (EPU) for Susquehanna Steam Electric Station, Units 1 and 2. The meeting summary can be accessed in the Agencywide DocumentsAccess and Management System, under (Accession No. ML061720220).PPL indicated that they would be filing an application for the EPU this year, and that theinformation demonstrating that the license renewal evaluations bound the uprated conditions,would also be submitted at the time of the staff's approval of the EPU. The LR review would need to consider changes in the current licensing basis (CLB) made as a result of approval of the EPU, and changes in the scope of aging management resulting from the EPU bounding condition. Certain portions of the LR review that are not impacted by the EPU review may beconducted upon successful docketing and acceptance review of the application. Upon approval of the EPU license amendment request, PPL will need to submit an amended LRA at the newpower level. Upon receipt of this amended application, NRC staff will establish the reviewschedule of 22-month without a hearing or 30-month with a hearing requested and granted. This letter was discussed with your staff in a teleconference held on July 26, 2006.Sincerely,/RA/

Yoira Diaz Sanabria, Project ManagerLicense Renewal Branch A Division of License Renewal Office of Nuclear Reactor RegulationDocket Nos. 50-387 and 50-388 cc w/encl: See next page August 2, 2006Mr. Britt T. McKinneySr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3Berwick, PA 18603-0467

SUBJECT:

PRE-APPLICATION ACTIVITIES REGARDING LICENSE RENEWALAPPLICATION REVIEW SCHEDULE FOR SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 (TAC NOS. MD0547 AND MD0548)

Dear Mr. McKinney:

During a public meeting held on April 5, 2006, the U.S. Nuclear Regulatory Commission (NRCor the staff), and representatives of PPL Susquehanna, LLC (or PPL), discussed the approach and schedule for submitting an application for license renewal (LR) in conjunction with a request for a 14 percent extended power uprate (EPU) for Susquehanna Steam Electric Station, Units 1 and 2. The meeting summary can be accessed in the Agencywide DocumentsAccess and Management System, under (Accession No. ML061720220).PPL indicated that they would be filing an application for the EPU this year, and that theinformation demonstrating that the license renewal evaluations bound the uprated conditions,would also be submitted at the time of the staff's approval of the EPU. The LR review would need to consider changes in the current licensing basis (CLB) made as a result of approval of the EPU, and changes in the scope of aging management resulting from the EPU bounding condition. Certain portions of the LR review that are not impacted by the EPU review may beconducted upon successful docketing and acceptance review of the application. Upon approval of the EPU license amendment request, PPL will need to submit an amended LRA at the newpower level. Upon receipt of this amended application, NRC staff will establish the reviewschedule of 22-month without a hearing or 30-month with a hearing requested and granted. This letter was discussed with your staff in a teleconference held on July 26, 2006.Sincerely,/RA/Yoira Diaz Sanabria, Project ManagerLicense Renewal Branch A Division of License Renewal Office of Nuclear Reactor RegulationDocket Nos. 50-387 and 50-388cc w/encl: See next page DISTRIBUTION: See next pageAccession Number: ML062140549 OFFICEPM:DLR:RLRALA:DLROGCBC:DLR:RLRAD:DLRNAMEYDiazSanabriaY. Edwardsghawkinsfor jemLLundFgillespie (ptkfor)DATE8/ 2 /068/ 2 /068/ 2 /068/ 1 /068/ 1 /06OFFICIAL RECORD COPY Letter to Britt McKinney from Frank Gillespie dated August 2, 2006

SUBJECT:

PRE-APPLICATION ACTIVITIES REGARDING LICENSE RENEWALAPPLICATION REVIEW SCHEDULE FOR SUSQUEHANNA UNITS 1 AND 2 (TAC NOS. MD0547 AND MD0548)HARD COPYDLR R/FE-MAIL:JFairRWeisman AMurphy RPettis GGalletti DShum GBagchi SSmith (srs3)

SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrAdes


RGuzman BRogers Susquehanna Steam Electric Station, Unit Nos. 1 and 2 cc:

Robert A. SacconeVice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3Berwick, PA 18603-0467Aloysius J. Wrape, IIIGeneral Manager - Performance Improvement and Oversight PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 1 8101-1179Terry L. HarpsterGeneral Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4Berwick, PA 18603-0467Rocco R. SgarroManager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Walter E. MorrisseySupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4Berwick, PA 18603-0467Michael H. CrowthersSupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Steven M. CookManager - Quality Assurance PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2Berwick, PA 18603-0467Luis A. RamosCommunity Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467Bryan A. Snapp, EsqAssoc. General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179Supervisor - Document Control ServicesPPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Richard W. OsborneAllegheny Electric Cooperative, Inc.

212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266Director, Bureau of Radiation ProtectionPennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469Senior Resident InspectorU.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4 Berwick, PA 18603-0035Regional Administrator, Region 1U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406Board of SupervisorsSalem Township

P.O. Box 405 Berwick, PA 18603-0035 Susquehanna Steam Electric Station, Unit Nos. 1 and 2 cc:Dr. Judith JohnsrudNational Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803