MONTHYEARIR 05000387/20230042024-02-0707 February 2024 Integrated Inspection Report 05000387/2023004 and 05000388/2023004 PLA-8096, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2024-01-0404 January 2024 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval PLA-8077, Emergency Plan Revision 67 (PLA-8077)2023-12-27027 December 2023 Emergency Plan Revision 67 (PLA-8077) IR 05000387/20230102023-12-11011 December 2023 Fire Protection Team Inspection Report 05000387/2023010 and 05000388/2023010 PLA-8089, Submittal of Revision to Inservice Testing Program Plan2023-12-0505 December 2023 Submittal of Revision to Inservice Testing Program Plan PLA-8084, Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.22023-11-29029 November 2023 Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 ML23345A0682023-11-28028 November 2023 Technical Specification Bases, Manual PLA-8091, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091)2023-11-0808 November 2023 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091) IR 05000387/20230032023-11-0303 November 2023 Integrated Inspection Report 05000387/2023003 and 05000388/2023003 PLA-8082, Proposed Amendment to Licenses NPF-14 and NPF-22: Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2023-11-0202 November 2023 Proposed Amendment to Licenses NPF-14 and NPF-22: Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML23291A1132023-10-12012 October 2023 Submittal of Revision 71 to Updated Final Safety Analysis Report and Revision 25 to Fire Protection Review Report ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23277A0412023-10-0505 October 2023 Notification of Commercial Grade Dedication Inspection (05000387/2024011 and 05000388/2024011) and Request for Information IR 05000387/20233012023-09-20020 September 2023 Initial Operator Licensing Examination Report 05000387/2023301 and 05000388/2023301 ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) IR 05000387/20230052023-08-31031 August 2023 Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2023005 and 05000388/2023005) ML23228A1952023-08-21021 August 2023 Summary of August 10, 2023, Public Observation Meeting Re. Proposed Alternative PLA-8080, Proposed Relief for Valve 251130 (PLA-8080)2023-08-14014 August 2023 Proposed Relief for Valve 251130 (PLA-8080) PLA-8074, Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2023-08-0303 August 2023 Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval IR 05000387/20230022023-08-0101 August 2023 Integrated Inspection Report 05000387/2023002 and 05000388/2023002 ML23195A1852023-07-27027 July 2023 Correction to Technical Specifications Page 3.3-73 in Amendment No. 265 PLA-8076, Unit 2 - 21st Refueling Outage Owner'S Activity Report (PLA-8076)2023-07-20020 July 2023 Unit 2 - 21st Refueling Outage Owner'S Activity Report (PLA-8076) ML23201A0152023-07-20020 July 2023 Operator Licensing Examination Approval ML23200A1012023-07-19019 July 2023 Notification of Conduct of a Fire Protection Team Inspection ML23193A0062023-07-12012 July 2023 Requalification Program Inspection PLA-8078, Submittal of Unit 2 Cycle 22 Core Operating Limits Report, Revision 1, PLA-80782023-07-0505 July 2023 Submittal of Unit 2 Cycle 22 Core Operating Limits Report, Revision 1, PLA-8078 ML23163A1012023-06-12012 June 2023 10 CFR 50.46 Annual Report (Pla 8065) PLA-8054, Proposed Amendment to Licenses NPF-14 and NPF-22: Remove Control Rod Operability Separation Criteria and Replace Reference to Banked Position Withdrawal Sequence with the Analyzed Rod Position Sequence2023-06-0808 June 2023 Proposed Amendment to Licenses NPF-14 and NPF-22: Remove Control Rod Operability Separation Criteria and Replace Reference to Banked Position Withdrawal Sequence with the Analyzed Rod Position Sequence IR 05000387/20234012023-06-0707 June 2023 Security Baseline Inspection Report 05000387/2023401 and 05000388/2023401 PLA-8073, Proposed Relief Request for the Fifth 10-Year Inservice Inspection Interval2023-06-0101 June 2023 Proposed Relief Request for the Fifth 10-Year Inservice Inspection Interval PLA-8064, Response to NRC Regulatory Issue Summary 2023-01 (PLA-8064)2023-05-17017 May 2023 Response to NRC Regulatory Issue Summary 2023-01 (PLA-8064) ML23132A3212023-05-17017 May 2023 Associated Independent Spent Fuel Storage Installation - Issuance of Amendment Nos. 285 and 269 Related to Order Approving Transfer of Licenses PLA-8067, Notification of Completion of Emergence from Bankruptcy (PLA-8067)2023-05-17017 May 2023 Notification of Completion of Emergence from Bankruptcy (PLA-8067) IR 05000387/20230012023-05-12012 May 2023 Integrated Inspection Report 05000387/2023001 and 05000388/2023001 PLA-8066, Notification of Planned Closing Date and Information Identified in March 30, 2023 Order, PLA-80662023-05-0808 May 2023 Notification of Planned Closing Date and Information Identified in March 30, 2023 Order, PLA-8066 PLA-8053, Radiation Exposure Information and Reporting System2023-04-27027 April 2023 Radiation Exposure Information and Reporting System PLA-8058, Annual Radiological Environmental Operating Report (PLA-8058)2023-04-26026 April 2023 Annual Radiological Environmental Operating Report (PLA-8058) PLA-8041, Radioactive Effluent Release Report and Offsite Dose Calculation Manual (PLA-8041)2023-04-25025 April 2023 Radioactive Effluent Release Report and Offsite Dose Calculation Manual (PLA-8041) PLA-8047, 2022 Annual Environmental Operating Report (Nonradiological), PLA-80472023-04-19019 April 2023 2022 Annual Environmental Operating Report (Nonradiological), PLA-8047 PLA-8062, Supplement to Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 252F007B, PLA-80622023-04-11011 April 2023 Supplement to Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 252F007B, PLA-8062 PLA-8061, Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 25F007B, PLA-80612023-04-10010 April 2023 Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 25F007B, PLA-8061 ML23090A2302023-03-31031 March 2023 NRC Decommissioning Funding Status Report PLA-8049 PLA-8060, Submittal of Unit 2 Cycle 22 Core Operating Limits Report (PLA-8060)2023-03-30030 March 2023 Submittal of Unit 2 Cycle 22 Core Operating Limits Report (PLA-8060) ML23095A0572023-03-29029 March 2023 NRC Decommissioning Funding Status Report December 31, 2022 PLA-8057, Application for Order Approving Indirect Transfer of Control of Licenses and Approving Conforming License Amendments- Supplemental Information, PLA-80572023-03-15015 March 2023 Application for Order Approving Indirect Transfer of Control of Licenses and Approving Conforming License Amendments- Supplemental Information, PLA-8057 ML23065A1962023-03-0202 March 2023 EN 56387 Paragon - Part 21 Report Re Defect Identified in Automatic Transfer Switch Pn: NLI-ATS480A400X1 IR 05000387/20220062023-03-0101 March 2023 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2022006 and 05000388/2022006) PLA-8052, (Sses), Proof of Financial Protection and Guarantee of Payment of Deferred Premiums2023-02-13013 February 2023 (Sses), Proof of Financial Protection and Guarantee of Payment of Deferred Premiums IR 05000387/20220042023-02-0808 February 2023 Integrated Inspection Report 05000387/2022004 and 05000388/2022004 ML23010A0882023-01-15015 January 2023 Summary of Regulatory Audit in Support of License Amendment Request to Revise Control Rod Technical Specifications 2024-02-07
[Table view] |
Text
August 2, 2006Mr. Britt T. McKinneySr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3Berwick, PA 18603-0467
SUBJECT:
PRE-APPLICATION ACTIVITIES REGARDING LICENSE RENEWALAPPLICATION REVIEW SCHEDULE FOR SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 (TAC NOS. MD0547 AND MD0548)
Dear Mr. McKinney:
During a public meeting held on April 5, 2006, the U.S. Nuclear Regulatory Commission (NRCor the staff), and representatives of PPL Susquehanna, LLC (or PPL), discussed the approach and schedule for submitting an application for license renewal (LR) in conjunction with a request for a 14 percent extended power uprate (EPU) for Susquehanna Steam Electric Station, Units 1 and 2. The meeting summary can be accessed in the Agencywide DocumentsAccess and Management System, under (Accession No. ML061720220).PPL indicated that they would be filing an application for the EPU this year, and that theinformation demonstrating that the license renewal evaluations bound the uprated conditions,would also be submitted at the time of the staff's approval of the EPU. The LR review would need to consider changes in the current licensing basis (CLB) made as a result of approval of the EPU, and changes in the scope of aging management resulting from the EPU bounding condition. Certain portions of the LR review that are not impacted by the EPU review may beconducted upon successful docketing and acceptance review of the application. Upon approval of the EPU license amendment request, PPL will need to submit an amended LRA at the newpower level. Upon receipt of this amended application, NRC staff will establish the reviewschedule of 22-month without a hearing or 30-month with a hearing requested and granted. This letter was discussed with your staff in a teleconference held on July 26, 2006.Sincerely,/RA/
Yoira Diaz Sanabria, Project ManagerLicense Renewal Branch A Division of License Renewal Office of Nuclear Reactor RegulationDocket Nos. 50-387 and 50-388 cc w/encl: See next page August 2, 2006Mr. Britt T. McKinneySr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3Berwick, PA 18603-0467
SUBJECT:
PRE-APPLICATION ACTIVITIES REGARDING LICENSE RENEWALAPPLICATION REVIEW SCHEDULE FOR SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 (TAC NOS. MD0547 AND MD0548)
Dear Mr. McKinney:
During a public meeting held on April 5, 2006, the U.S. Nuclear Regulatory Commission (NRCor the staff), and representatives of PPL Susquehanna, LLC (or PPL), discussed the approach and schedule for submitting an application for license renewal (LR) in conjunction with a request for a 14 percent extended power uprate (EPU) for Susquehanna Steam Electric Station, Units 1 and 2. The meeting summary can be accessed in the Agencywide DocumentsAccess and Management System, under (Accession No. ML061720220).PPL indicated that they would be filing an application for the EPU this year, and that theinformation demonstrating that the license renewal evaluations bound the uprated conditions,would also be submitted at the time of the staff's approval of the EPU. The LR review would need to consider changes in the current licensing basis (CLB) made as a result of approval of the EPU, and changes in the scope of aging management resulting from the EPU bounding condition. Certain portions of the LR review that are not impacted by the EPU review may beconducted upon successful docketing and acceptance review of the application. Upon approval of the EPU license amendment request, PPL will need to submit an amended LRA at the newpower level. Upon receipt of this amended application, NRC staff will establish the reviewschedule of 22-month without a hearing or 30-month with a hearing requested and granted. This letter was discussed with your staff in a teleconference held on July 26, 2006.Sincerely,/RA/Yoira Diaz Sanabria, Project ManagerLicense Renewal Branch A Division of License Renewal Office of Nuclear Reactor RegulationDocket Nos. 50-387 and 50-388cc w/encl: See next page DISTRIBUTION: See next pageAccession Number: ML062140549 OFFICEPM:DLR:RLRALA:DLROGCBC:DLR:RLRAD:DLRNAMEYDiazSanabriaY. Edwardsghawkinsfor jemLLundFgillespie (ptkfor)DATE8/ 2 /068/ 2 /068/ 2 /068/ 1 /068/ 1 /06OFFICIAL RECORD COPY Letter to Britt McKinney from Frank Gillespie dated August 2, 2006
SUBJECT:
PRE-APPLICATION ACTIVITIES REGARDING LICENSE RENEWALAPPLICATION REVIEW SCHEDULE FOR SUSQUEHANNA UNITS 1 AND 2 (TAC NOS. MD0547 AND MD0548)HARD COPYDLR R/FE-MAIL:JFairRWeisman AMurphy RPettis GGalletti DShum GBagchi SSmith (srs3)
SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrAdes
RGuzman BRogers Susquehanna Steam Electric Station, Unit Nos. 1 and 2 cc:
Robert A. SacconeVice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3Berwick, PA 18603-0467Aloysius J. Wrape, IIIGeneral Manager - Performance Improvement and Oversight PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 1 8101-1179Terry L. HarpsterGeneral Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4Berwick, PA 18603-0467Rocco R. SgarroManager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Walter E. MorrisseySupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4Berwick, PA 18603-0467Michael H. CrowthersSupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Steven M. CookManager - Quality Assurance PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2Berwick, PA 18603-0467Luis A. RamosCommunity Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467Bryan A. Snapp, EsqAssoc. General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179Supervisor - Document Control ServicesPPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Richard W. OsborneAllegheny Electric Cooperative, Inc.
212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266Director, Bureau of Radiation ProtectionPennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469Senior Resident InspectorU.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4 Berwick, PA 18603-0035Regional Administrator, Region 1U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406Board of SupervisorsSalem Township
P.O. Box 405 Berwick, PA 18603-0035 Susquehanna Steam Electric Station, Unit Nos. 1 and 2 cc:Dr. Judith JohnsrudNational Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803