Line 3: |
Line 3: |
| | issue date = 11/16/2018 | | | issue date = 11/16/2018 |
| | title = Subsequent License Renewal Application Online Reference Portal (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) | | | title = Subsequent License Renewal Application Online Reference Portal (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) |
| | author name = Oesterle E R | | | author name = Oesterle E |
| | author affiliation = NRC/NRR/DMLR/MRPB | | | author affiliation = NRC/NRR/DMLR/MRPB |
| | addressee name = Stoddard D G | | | addressee name = Stoddard D |
| | addressee affiliation = Virginia Electric & Power Co (VEPCO) | | | addressee affiliation = Virginia Electric & Power Co (VEPCO) |
| | docket = 05000280, 05000281 | | | docket = 05000280, 05000281 |
Revision as of 19:08, 12 June 2019
Letter Sequence Other |
---|
EPID:L-2018-RNW-0023, Dominion'S Presentation on Surry'S SLRA Safety Meeting-Final (for April 17, 2018) (Open) EPID:L-2018-RNW-0024, Dominion'S Presentation on Surry'S SLRA Safety Meeting-Final (for April 17, 2018) (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement
Results
Other: ML18297A045, ML18319A184, ML18319A252, ML18345A244, ML18351A051, ML19015A243, ML19046A433, ML19098A810, ML19100A254, ML19107A021, ML19128A079, ML19140A449, ML19169A329, ML19198A059, ML19248C228, ML19267A042, ML19270E741, NRC-2018-0247, Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent
|
MONTHYEARML18121A0342018-03-29029 March 2018 Possible Topics for the April 17, 2018 Public Meeting with Dominion on Its Surry SLRA Project stage: Request ML18102A5692018-04-17017 April 2018 Dominion'S Presentation on Surry'S SLRA Safety Meeting-Final (for April 17, 2018) Project stage: Request ML18129A3142018-05-16016 May 2018 04/17/2018 Summary of Pre-Application Meeting with Dominion Energy Regarding the Surry, Units 1 and 2, Subsequent License Renewal Application Project stage: Meeting ML18291A8422018-06-30030 June 2018, 15 October 2018 Submittal of Application for Subsequent Renewed Operating Licenses Project stage: Request ML18291A8362018-06-30030 June 2018 Enclosure 4, Attachment 1: ANP-3679NP, Revision 0, Topical Report Project stage: Request ML18291A8352018-10-15015 October 2018 Submittal of Application for Subsequent Renewed Operating Licenses Project stage: Request ML18291A8342018-10-15015 October 2018 Appendix E - Environmental Report Project stage: Request ML18297A0452018-10-26026 October 2018 Receipt and Availability of the Subsequent License Renewal Application for Surry Power Station, Unit Nos. 1 and 2 Project stage: Other ML18297A0932018-10-26026 October 2018 Receipt and Availability of the Subsequent License Renewal Application (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Request ML18319A2522018-11-16016 November 2018 Subsequent License Renewal Application Online Reference Portal (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Other ML18319A1842018-11-26026 November 2018 Plan for the Operating Experience Audit Regarding the Subsequent License Renewal Application Review (EPID Nos. L-2018-RWN-0023 and L-2018-RNW-0024 Project stage: Other ML18320A2362018-12-0303 December 2018 Acceptance Scheduling and Opportunity for Hearing Letter - v3 Project stage: Acceptance Review ML18320A2352018-12-0303 December 2018 Acceptance Scheduling and Opportunity for Hearing FRN - v2 Project stage: Request NRC-2018-0247, Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent2018-12-12012 December 2018 Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent Lice Project stage: Other ML18345A2442018-12-12012 December 2018 Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent Lice Project stage: Other ML18340A2652018-12-17017 December 2018, 21 December 2018 Notice of Intent to Prepare an Enviromental Impact Statement and Conduct Scoping Process for Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML18340A2672018-12-17017 December 2018 Federal Register Notice - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Surry Power Station, Unit Nos. 1 and 2 Project stage: Other ML18351A0512018-12-18018 December 2018 Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent License Renewal Project stage: Other ML18351A2572018-12-20020 December 2018 U.S. Nuclear Regulatory Commission Approval of Virginia Electric and Power Company'S Request for Withholding Information from Public Disclosure, Regarding the Application for Subsequent License Renewal of Surry Power Station, Unit Nos. 1 an Project stage: Withholding Request Acceptance ML19046A0092018-12-20020 December 2018 Comment (10) from Bettina Rayfield on Surry Power Station, Unit Nos. 1 and 2 Relicensing Project stage: Request ML18340A2662018-12-21021 December 2018 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Surry Power Station, Unit Nos. 1 and 2 Project stage: Other ML19024A1992019-01-0808 January 2019 Subsequent License Renewal Scoping Meeting Surry Power Station Units 1 and 2 Project stage: Meeting ML19016A0932019-01-12012 January 2019 Comment (1) of Erica Gray on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19025A1542019-01-13013 January 2019 Comment (9) of W. Frank Adams on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19016A0962019-01-14014 January 2019 Comment (3) of Kay Patrick on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19016A0942019-01-14014 January 2019 Comment (2) of Scott Burger on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19017A0132019-01-16016 January 2019 Comment (4) of Anonymous Individual on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Units 1 and 2 Project stage: Request ML19025A1462019-01-20020 January 2019 Comment (5) of David Martin on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19025A1492019-01-21021 January 2019 Comment (6) of Glen Besa on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19025A1502019-01-22022 January 2019 Comment (7) of Scott Price on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19025A1522019-01-22022 January 2019 Comment (8) of Randal Owen on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19015A2432019-01-22022 January 2019 Plan for the In-Office Regulatory Audit Regarding the Subsequent License Renewal Application Review (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Other ML19042A1372019-01-29029 January 2019 Submittal of Supplement to Subsequent License Renewal Operating Licenses Application for Sufficiency Review Change Notice 1 Project stage: Supplement ML19046A4332019-03-0404 March 2019 Report for the Operating Experience Review Audit Regarding the Subsequent License Renewal Application Review (EPID: Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Other ML19044A6592019-03-0404 March 2019 License Renewal Severe Accident Mitigation Alternatives Audit Plan Regarding the Surry Power Station, Unit Nos. 1 and 2, Subsequent License Renewal Application Project stage: Other ML19044A5562019-03-0404 March 2019 License Renewal Environmental Site Audit Plan Regarding the Surry Power Station, Units 1 and 2, Subsequent License Renewal Application Project stage: Other ML19095A6662019-03-31031 March 2019, 2 April 2019 Submittal of Supplement to Subsequent License Renewal Application Change Notice 2 Project stage: Request ML19095A6022019-04-0202 April 2019 Enclosure 2 - SLRA Mark-Ups Change Notice 2 Project stage: Request ML19095A6002019-04-0202 April 2019 Enclosure 1 - Topics That Require a SLRA Supplement Project stage: Request ML19095A5972019-04-0202 April 2019 Submittal of Supplement to Subsequent License Renewal Application Change Notice 2 Project stage: Supplement ML19087A2662019-04-0303 April 2019, 30 April 2019 Environmental Impact Statement for an Early Site Permit (ESP) at the Clinch River Nuclear Site Project stage: Request ML19106A3332019-04-0404 April 2019, 5 April 2019 Draft Environmental Rai'S for Surry Power Station Subsequent License Renewal Application Project stage: Request ML19114A4352019-04-11011 April 2019 RAIs 4-4-19 r3 Project stage: RAI ML19114A4232019-04-11011 April 2019 Final Environmental Rai'S for Surry Subsequent License Renewal Application Project stage: Request ML19106A4022019-04-11011 April 2019 Request for Additional Information Set 1 - Surry SLRA Environmental Review Project stage: RAI ML19107A0192019-04-16016 April 2019, 29 April 2019 Summary of the Subsequent License Renewal Environmental Audit Project stage: Request ML19107A0202019-04-16016 April 2019 Audit Need Update Tracking Spreadsheet Project stage: Request ML19098A8102019-04-17017 April 2019 On-Site Regulatory Audit Regarding the Subsequent License Renewal Application Review (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Other ML19106A4162019-04-25025 April 2019 Summary of the Subsequent License Renewal Severe Accident Mitigation Alternatives Audit Project stage: Other ML19100A2542019-04-29029 April 2019 Schedule Revision for the Subsequent License Renewal Application Review (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Other 2019-01-14
[Table View] |
Similar Documents at Surry |
---|
Category:Letter
MONTHYEARIR 05000280/20244012024-02-0606 February 2024 Security Baseline Inspection Report 05000280/2024401, 05000281/2024401 and 07200002/2024401 IR 05000280/20230102024-01-18018 January 2024 Age Related Degradation Inspection Report 05000280-2023010 and 05000281-2023010 ML23312A1922024-01-18018 January 2024 Issuance of Amendment Nos. 316 & 316 Regarding a Risk Informed Approach for Tornado Classification of the Fuel Handling Trolley Support Structure ML24003A9022024-01-0303 January 2024 Stations, Units 1 and 2, Emergency Plan Revision - Relocation of the Technical Support Center (TSC) - Editorial Correction IR 05000280/20233012023-12-28028 December 2023 NRC Operator License Examination Report 05000280/2023301 and 05000281/2023301 ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23352A3692023-12-18018 December 2023 Associated Independent Spent Fuel Storage Installation, Revision to Emergency Plan Report of Change ML23334A2342023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23242A2292023-11-0707 November 2023 Issuance of Amendment Nos. 315 and 315, Regarding Emergency Procedure Relocation of the Technical Support Center ML23200A2622023-11-0202 November 2023 Issuance of Amendment Nos. 314 and 314, Regarding Technical Specification and Spent Fuel Pool Criticality Change IR 05000280/20230032023-10-25025 October 2023 Integrated Inspection Report 05000280/2023003 and 05000281/2023003 ML23286A0372023-10-13013 October 2023 Annual Submittal of Technical Specifications Bases Changes Pursuant to Technical Specification 6.4.J ML23285A0922023-10-12012 October 2023 Inservice Testing Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests ML23277A1172023-10-0303 October 2023 Operator Licensing Examination Approval 05000280/2023301 and 05000281/2023301 ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23256A2672023-09-21021 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23244A2352023-09-18018 September 2023 Request to Use a Subsequent Edition of the ASME Code, Section XI ML23230A0012023-09-15015 September 2023 Request to Use a Provision of a Previous Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for Non-Destructive Examinations IR 05000280/20220042023-09-0101 September 2023 Reissue - Surry Power Station - Integrated Inspection Report 05000280/2022004 and 05000281/2022004 ML23244A0142023-08-30030 August 2023 Inservice Inspection Owner'S Activity Report IR 05000280/20230052023-08-23023 August 2023 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2023005 and 05000281/2023005) ML23226A1862023-08-10010 August 2023 Proposed License Amendment Request - Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection Flow Instrumentation ML23220A1492023-08-0707 August 2023 Independent Spent Fuel Storage Installation - Submittal of Cask Registrations for Spent Fuel Storage ML23220A1482023-08-0707 August 2023 Proposed Emergency Plan Revision - Relocation of the Technical Support Center (TSC) Response to Request for Additional Information IR 05000280/20230022023-08-0404 August 2023 Integrated Inspection Report 05000280/2023002 and 05000281/2023002 ML23208A0922023-07-26026 July 2023 Request for Approval of Appendix F of Fleet Report DOM-NAF-2-P Qualification of Framatome ORFEO-GAIA and OORFE-NMGRID CHF Correlations in the Dominion Energy Vipre-D Computer Code Response ML23207A1102023-07-26026 July 2023 NRC Regulatory Issues Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations ML23198A0322023-07-18018 July 2023 Regulatory Audit Report Regarding Review of License Amendment to Modify Emergency Plan Staff Augmentation Times ML23193A9382023-07-18018 July 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors ML23173A0602023-07-11011 July 2023 Audit Summary for License Amendment Request Revision of the Emergency Plan to Support Relocation of the Technical Support Center ML23136B1392023-06-29029 June 2023 Issuance of Amendment No. 313 Administrative Changes to Subsequent Renewed Operating Licenses and Technical Specifications ML23178A1682023-06-26026 June 2023 2022 Annual Report of Emergency Core Cooling System (ECCS) Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML23152A0432023-06-22022 June 2023 Audit Plan License Amendment Requests to Change Emergency Plan Staff Augmentation Times ML23153A1732023-06-16016 June 2023 Correction to Amendment Nos. 346 & 286 Millstone, 294 & 277 North Anna, 311 & 311 Surry, and 225 Summer to Revise Technical Specifications to Adopt TSTF-554,Rev Reactor Coolant Leakage Requirement ML23163A2352023-06-12012 June 2023 Request to Use a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for the SPS Sixth Inservice Inspection (Isi) Intervals and VCSNS Fifth ISI Interval ML23151A6612023-05-31031 May 2023 ES-2.1-1, Surry 2023-301 Corporate Notification Letter (Revised) ML23167B0072023-05-31031 May 2023 Proposed Emergency Plan Revision - Relocation of the Technical Support Center (TSC) Supplemental Information - LOCA Dose Calculation Summary ML23117A0952023-05-10010 May 2023 Audit Plan License Amendment Request to Support Relocation of the Technical Support Center ML23130A3742023-05-10010 May 2023 Request to Delay NRC Intial Licensing Examination 2024-02-06
[Table view] |
Text
November 16, 2018 Mr. Daniel G. Stoddard Senior Vice President and Chief Nuclear Officer Innsbrook Technical Center 5000 Dominion Blvd Glen Allen, VA 23060-6711
SUBJECT:
SURRY POWER STATION, UNIT NO S. 1 AND 2, SUBSEQUENT LICENSE RENEWAL APPLICATION ONLINE REFERENCE PORTAL (EPID NOS. L
-2018-RNW-0023 AND L
-2018-RNW-0024)
Dear Mr. Stoddard,
By letter dated October 15
, 2018 (Agencywide Documents Access and Management System (ADAMS) Package Accession No.
ML18291A842), Virginia Electric and Power Company (Dominion Energy Virginia) submitted to the U.S. Nuclear Regulatory Commission (NRC or staff) an application to renew the Renewed Facility Operating License Nos.
DPR-32 and DPR-37 for the Surry Power Station (SPS), Unit No s. 1 and 2. The NRC staff continues to seek approaches to improve efficiency and support an effective review. One method to increase efficiency of the NRC staff's review of the subsequent license renewal application (SLRA) is the use of an online reference portal that will allow the NRC staff and associated contractors limited, read
-only access to the documents and other reference materials cited in and in support of the SLRA. The online reference portal will allow the review of documents referenced in the SLRA. In cases where the NRC staff identifies documents as necessary to support its determination in the safety evaluation report, or its environmental impact statement, the NRC staff will request that those documents be submitted on the docket.
The use of the online reference portal will be in accordance with the following restrictions:
The online reference portal will be password
-protected, and passwords will be distributed only to NRC staff members and contractors directly involved in the SPS SLRA review on a need
-to-know basis.
The online reference portal will not support any printing, saving, or downloading functions.
The NRC staff members and contractors given password access to the online reference portal will be informed of the conditions related to the use of the online reference portal by NRC project managers.
The conditions associated with the online reference portal will be maintained throughout its use during the SPS SLRA review process.
D. Stoddard Documents posted to the online reference portal will be limited to basis and other reference material cited in the SLRA, unless otherwise agreed upon by Dominion Energy Virginia and NRC management.
It is requested that the portal be fully populated with plant documents and well organized to facilitate efficient search capability and ease of use no later than 5 days after application acceptance for all NRC staff members and contractors directly involved in the SPS SLRA review , with the exception of Briana Grange , Tam Tran , and Michelle Moser who will need access to the portal no later than November 23, 2018.
If you have any questions on this matter, please contact Mr. Emmanuel Sayoc by telephone at 301-415-4084 or via e
-mail at Emmanuel.Sayoc@nrc.gov
. Sincerely, /RA/ Eric R. Oesterle, Chief License Renewal Projects Branch Division of Materials and License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50
-280 and 50
-281 cc: Listserv
ML18319A252
- concurred via email OFFICE PM:MRPB:DMLR PM:MRPB:DMLR PM:MRPB:DMLR PM:MRPB:DMLR NAME AWu SLent ESayoc* TTran DATE 11/15/2018 11/15/2018 11/16/2018 11/15/2018 OFFICE OGC (NLO) BC:MENB:DMLR BC:MRPB:DMLR NAME BHarris* BBeasley* EOesterle DATE 11/16/2018 11/15/18 11/16/2018