Revised RAI B3.2-1-a for the Safety Review of Surry Power Station, Units 1 and 2 SLRA (L-2018-RNW-0023_000951) Set 3
ML19304C206
Person / Time
Site: Surry  Dominion icon.png
Issue date: 09/05/2019
From: Sayoc E
NRC/NRR/DNRL/NLRP
To: Stoddard D
Dominion Energy
Wu A, NRR-DNRL 415-2995
Shared Package
ML19304C145 List:
References
CAC 000951, EPID L-2018-RNW-0023, L-2018-RNW-0023/000951
Download: ML19304C206 (1)


Text

From: Wu, Angela To: Lewis, LaShawnna; Edmonds, Yvonne

Subject:

FW: REVISED REQUESTS FOR ADDITIONAL INFORMATION B3.2-1-a FOR THE SAFETY REVIEW OF THE SURRY POWER STATION, UNITS 1 AND 2 SUBSEQUENT LICENSE RENEWAL APPLICATION (L-2018-RNW-0023/000951)

- SET 3 Date: Thursday, October 31, 2019 12:10:24 PM Attachments: TRP 061 Surry SLRA - Revised 2nd Round RAI for B3.2 Neutron Fluence Monitoring AMP.pdf From: Sayoc, Emmanuel Sent: Monday, August 05, 2019 2:08 PM To: Daniel.g.stoddard@dominionenergy.com Cc: Wu, Angela <Angela.Wu@nrc.gov>; Oesterle, Eric <Eric.Oesterle@nrc.gov>; Paul Aitken

<paul.aitken@dominionenergy.com>; Eric A Blocher <Eric.A.Blocher@dominionenergy.com>; Tony Banks <tony.banks@dominionenergy.com>

Subject:

REVISED REQUESTS FOR ADDITIONAL INFORMATION B3.2-1-a FOR THE SAFETY REVIEW OF THE SURRY POWER STATION, UNITS 1 AND 2 SUBSEQUENT LICENSE RENEWAL APPLICATION (L-2018-RNW-0023/000951) - SET 3 Docket No. 50-280 and 50-281

Dear Mr. Stoddard,

On August 2, 2019, the NRC staff sent the 3rd set of Requests for Additional Information (RAI) for the Surry Power Station, Unit Nos. 1 and 2 Subsequent License Renewal Application. The NRC staff has made some modifications to one of the RAI to more clearly document the staffs request. The attached RAI B3.2-1-a on Neutron Fluence Monitoring Aging Management Program is hereby transmitted and supersedes the previously sent version. All other RAI stand as originally transmitted and the response due date is reset to within 30 days of the date of this email (August 5, 2019).

The NRC staff will be placing a copy of this email and attachments in the NRCs Agencywide Documents Access and Management System. If you have any questions please let me know.

Sincerely, Emmanuel Sayoc, Project Manager License Renewal Projects Branch (MRPB)

Division of Materials and License Renewal Office of Nuclear Reactor Regulation Docket No. 50-280 and 50-281 Attachments:

As stated