EPID:L-2018-RNW-0023, Dominion'S Presentation on Surry'S SLRA Safety Meeting-Final (for April 17, 2018) (Open) EPID:L-2018-RNW-0024, Dominion'S Presentation on Surry'S SLRA Safety Meeting-Final (for April 17, 2018) (Approved, Closed) | |
Initiation
Administration Questions Answers Results
Other: ML18297A045, ML18319A184, ML18319A252, ML18345A244, ML18351A051, ML19015A243, ML19046A433, ML19098A810, ML19100A254, ML19128A079, ML19169A329, ML19198A059, ML19248C228, ML19267A042, ML19270E741, NRC-2018-0247, Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent | |
MONTHYEARML18121A0342018-03-29029 March 2018
[Table View]Possible Topics for the April 17, 2018 Public Meeting with Dominion on Its Surry SLRA Project stage: Request ML18102A5692018-04-17017 April 2018 Dominion'S Presentation on Surry'S SLRA Safety Meeting-Final (for April 17, 2018) Project stage: Request ML18129A3142018-05-16016 May 2018 04/17/2018 Summary of Pre-Application Meeting with Dominion Energy Regarding the Surry, Units 1 and 2, Subsequent License Renewal Application Project stage: Meeting ML18291A8422018-06-30030 June 2018, 15 October 2018 Submittal of Application for Subsequent Renewed Operating Licenses Project stage: Request ML18291A8362018-06-30030 June 2018 Enclosure 4, Attachment 1: ANP-3679NP, Revision 0, Topical Report Project stage: Request ML18291A8352018-10-15015 October 2018 Submittal of Application for Subsequent Renewed Operating Licenses Project stage: Request ML18291A8342018-10-15015 October 2018 Appendix E - Environmental Report Project stage: Request ML18297A0452018-10-26026 October 2018 Receipt and Availability of the Subsequent License Renewal Application for Surry Power Station, Unit Nos. 1 and 2 Project stage: Other ML18297A0932018-10-26026 October 2018 Receipt and Availability of the Subsequent License Renewal Application (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Request ML18319A2522018-11-16016 November 2018 Subsequent License Renewal Application Online Reference Portal (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Other ML18319A1842018-11-26026 November 2018 Plan for the Operating Experience Audit Regarding the Subsequent License Renewal Application Review (EPID Nos. L-2018-RWN-0023 and L-2018-RNW-0024 Project stage: Other ML18320A2362018-12-0303 December 2018 Acceptance Scheduling and Opportunity for Hearing Letter - v3 Project stage: Acceptance Review ML18320A2352018-12-0303 December 2018 Acceptance Scheduling and Opportunity for Hearing FRN - v2 Project stage: Request NRC-2018-0247, Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent2018-12-12012 December 2018 Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent Lice Project stage: Other ML18345A2442018-12-12012 December 2018 Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent Lice Project stage: Other ML18340A2672018-12-17017 December 2018 Federal Register Notice - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Surry Power Station, Unit Nos. 1 and 2 Project stage: Other ML18340A2652018-12-17017 December 2018, 21 December 2018 Notice of Intent to Prepare an Enviromental Impact Statement and Conduct Scoping Process for Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML18351A0512018-12-18018 December 2018 Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent License Renewal Project stage: Other ML18351A2572018-12-20020 December 2018 U.S. Nuclear Regulatory Commission Approval of Virginia Electric and Power Company'S Request for Withholding Information from Public Disclosure, Regarding the Application for Subsequent License Renewal of Surry Power Station, Unit Nos. 1 an Project stage: Withholding Request Acceptance ML19046A0092018-12-20020 December 2018 Comment (10) from Bettina Rayfield on Surry Power Station, Unit Nos. 1 and 2 Relicensing Project stage: Request ML18340A2662018-12-21021 December 2018 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Surry Power Station, Unit Nos. 1 and 2 Project stage: Other ML19024A1992019-01-0808 January 2019 Subsequent License Renewal Scoping Meeting Surry Power Station Units 1 and 2 Project stage: Meeting ML19016A0932019-01-12012 January 2019 Comment (1) of Erica Gray on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19025A1542019-01-13013 January 2019 Comment (9) of W. Frank Adams on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19016A0962019-01-14014 January 2019 Comment (3) of Kay Patrick on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19016A0942019-01-14014 January 2019 Comment (2) of Scott Burger on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19017A0132019-01-16016 January 2019 Comment (4) of Anonymous Individual on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Units 1 and 2 Project stage: Request ML19025A1462019-01-20020 January 2019 Comment (5) of David Martin on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19025A1492019-01-21021 January 2019 Comment (6) of Glen Besa on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19015A2432019-01-22022 January 2019 Plan for the In-Office Regulatory Audit Regarding the Subsequent License Renewal Application Review (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Other ML19025A1522019-01-22022 January 2019 Comment (8) of Randal Owen on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19025A1502019-01-22022 January 2019 Comment (7) of Scott Price on Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 Project stage: Request ML19042A1372019-01-29029 January 2019 Submittal of Supplement to Subsequent License Renewal Operating Licenses Application for Sufficiency Review Change Notice 1 Project stage: Supplement ML19046A4332019-03-0404 March 2019 Report for the Operating Experience Review Audit Regarding the Subsequent License Renewal Application Review (EPID: Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Other ML19044A5562019-03-0404 March 2019 License Renewal Environmental Site Audit Plan Regarding the Surry Power Station, Units 1 and 2, Subsequent License Renewal Application Project stage: Other ML19044A6592019-03-0404 March 2019 License Renewal Severe Accident Mitigation Alternatives Audit Plan Regarding the Surry Power Station, Unit Nos. 1 and 2, Subsequent License Renewal Application Project stage: Other ML19095A6662019-03-31031 March 2019, 2 April 2019 Submittal of Supplement to Subsequent License Renewal Application Change Notice 2 Project stage: Request ML19095A5972019-04-0202 April 2019 Submittal of Supplement to Subsequent License Renewal Application Change Notice 2 Project stage: Supplement ML19095A6002019-04-0202 April 2019 Enclosure 1 - Topics That Require a SLRA Supplement Project stage: Request ML19095A6022019-04-0202 April 2019 Enclosure 2 - SLRA Mark-Ups Change Notice 2 Project stage: Request ML19087A2662019-04-0303 April 2019, 30 April 2019 Environmental Impact Statement for an Early Site Permit (ESP) at the Clinch River Nuclear Site Project stage: Request ML19106A3332019-04-0404 April 2019, 5 April 2019 Draft Environmental Rai'S for Surry Power Station Subsequent License Renewal Application Project stage: Request ML19106A4022019-04-11011 April 2019 Request for Additional Information Set 1 - Surry SLRA Environmental Review Project stage: RAI ML19114A4232019-04-11011 April 2019 Final Environmental Rai'S for Surry Subsequent License Renewal Application Project stage: Request ML19114A4352019-04-11011 April 2019 RAIs 4-4-19 r3 Project stage: RAI ML19107A0192019-04-16016 April 2019, 29 April 2019 Summary of the Subsequent License Renewal Environmental Audit Project stage: Request ML19107A0202019-04-16016 April 2019 Audit Need Update Tracking Spreadsheet Project stage: Request ML19098A8102019-04-17017 April 2019 On-Site Regulatory Audit Regarding the Subsequent License Renewal Application Review (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Other ML19106A4162019-04-25025 April 2019 Summary of the Subsequent License Renewal Severe Accident Mitigation Alternatives Audit Project stage: Other ML19100A2542019-04-29029 April 2019 Schedule Revision for the Subsequent License Renewal Application Review (EPID Nos. L-2018-RNW-0023 and L-2018-RNW-0024) Project stage: Other 2019-01-14 |
ML18121A034 | |
Person / Time | |
---|---|
Site: | Surry |
Issue date: | 03/29/2018 |
From: | Wong A NRC/NRR/DMLR/MRPB |
To: | |
Wong A, NRR-DMLR 415-3081 | |
References | |
Download: ML18121A034 (1) | |
Similar Documents at Surry | |
---|---|
Category:Meeting Agenda
MONTHYEARPMNS20241176, Pre-submittal Meeting with Dominion Energy Regarding a Planned License Amendment Request for North Anna Power Station and Surry Power Station to Revise Selected Alternate Source Term Dose Consequence Analyses2024-09-23023 September 2024
[Table view]Pre-submittal Meeting with Dominion Energy Regarding a Planned License Amendment Request for North Anna Power Station and Surry Power Station to Revise Selected Alternate Source Term Dose Consequence Analyses PMNS20240863, Pre-submittal Meeting with Virginia Electric and Power Company (VEPCO) to Discuss Its Proposed License Amendment for Surry Power Station, Units 1 and 22024-06-27027 June 2024 Pre-submittal Meeting with Virginia Electric and Power Company (VEPCO) to Discuss Its Proposed License Amendment for Surry Power Station, Units 1 and 2 PMNS20240758, Notice of Meeting with Dominion Energy Inc. to Discuss Guidance in NUREG-0800 Standard Review Plan (SRP)2024-06-12012 June 2024 Notice of Meeting with Dominion Energy Inc. to Discuss Guidance in NUREG-0800 Standard Review Plan (SRP) PMNS20240556, Annual Assessment Meeting Surry Power Station Annual Assessment Meeting2024-04-18018 April 2024 Annual Assessment Meeting Surry Power Station Annual Assessment Meeting PMNS20231323, Meeting with Virginia Electric and Power Company Regarding License Amendment Request to Revise Emergency Plan Staff Augmentation Times for North Anna Power Station Units 1 and 2 and Surry Power Station Units 1 and 22023-11-27027 November 2023 Meeting with Virginia Electric and Power Company Regarding License Amendment Request to Revise Emergency Plan Staff Augmentation Times for North Anna Power Station Units 1 and 2 and Surry Power Station Units 1 and 2 PMNS20230615, Meeting with Virginia Electric and Power Company Regarding License Amendment Request to Revise Emergency Plan Staff Augmentation Times for North Anna Power Station Units 1 and 2 and Surry Power Station Units 1 and 22023-05-11011 May 2023 Meeting with Virginia Electric and Power Company Regarding License Amendment Request to Revise Emergency Plan Staff Augmentation Times for North Anna Power Station Units 1 and 2 and Surry Power Station Units 1 and 2 PMNS20230430, Assessment Meetingsurry Power Station Annual Assessment Meeting2023-04-13013 April 2023 Assessment Meetingsurry Power Station Annual Assessment Meeting ML22097A2262022-04-13013 April 2022 Presubmittal Presentation April 13, 2022 One-time TS Change of AOT for Unit 2 AFW Piping Replacement PMNS20220318, Public Meeting with the Dominion Energy to Discuss a Planned Emergency Preparedness Submittal for the North Anna Power Station and the Surry Power Station2022-04-0707 April 2022 Public Meeting with the Dominion Energy to Discuss a Planned Emergency Preparedness Submittal for the North Anna Power Station and the Surry Power Station PMNS20220349, Assessment Meetingsurry Power Station Annual Assessment Meeting2022-04-0404 April 2022 Assessment Meetingsurry Power Station Annual Assessment Meeting PMNS20220301, Pre-submittal Meeting with Virginia Electric and Power Company (VEPCO) to Discuss Its Proposed License Amendment for Surry Power Station, Units 1 and 22022-03-29029 March 2022 Pre-submittal Meeting with Virginia Electric and Power Company (VEPCO) to Discuss Its Proposed License Amendment for Surry Power Station, Units 1 and 2 PMNS20220113, Pre-submittal Meeting with Virginia Electric Power Company (VEPCO) to Discuss Future License Amendment for Surry Power Station, Units 1 and 22022-02-11011 February 2022 Pre-submittal Meeting with Virginia Electric Power Company (VEPCO) to Discuss Future License Amendment for Surry Power Station, Units 1 and 2 PMNS20210540, Pre-Submittal Meeting - Proposed License Amendment Request (LAR) to Revise the New and Spent Fuel Pool Criticality Analyses for Surry Power Station, Units 1 and 22021-05-11011 May 2021 Pre-Submittal Meeting - Proposed License Amendment Request (LAR) to Revise the New and Spent Fuel Pool Criticality Analyses for Surry Power Station, Units 1 and 2 PMNS20210612, Pre-Submittal Meeting - Proposed License Amendment (LAR) Request to Revise the Licensing Basis for the Turbine Building and the Fuel Building Trolley Support Structures Relative to Tornado Effects for Surry Power Station, Units 1 and 22021-05-10010 May 2021 Pre-Submittal Meeting - Proposed License Amendment (LAR) Request to Revise the Licensing Basis for the Turbine Building and the Fuel Building Trolley Support Structures Relative to Tornado Effects for Surry Power Station, Units 1 and 2 PMNS20210382, the U.S. Nuclear Regulatory Commission (NRC) Will Hold a Webinar to Discuss the Nrc'S Assessment of Safety Performance at the V. C. Summer, North Anna and Surry Power Stations for 20202021-04-12012 April 2021 the U.S. Nuclear Regulatory Commission (NRC) Will Hold a Webinar to Discuss the Nrc'S Assessment of Safety Performance at the V. C. Summer, North Anna and Surry Power Stations for 2020 PMNS20201174, Notice of Pre-Submittal Meeting with Virginia Electric and Power Company (Vepc)2020-10-0101 October 2020 Notice of Pre-Submittal Meeting with Virginia Electric and Power Company (Vepc) PMNS20201170, Notice of Pre-Submittal Meeting with Virginia Electric and Power Company (Vepc)2020-09-30030 September 2020 Notice of Pre-Submittal Meeting with Virginia Electric and Power Company (Vepc) ML18121A0342018-03-29029 March 2018 Possible Topics for the April 17, 2018 Public Meeting with Dominion on Its Surry SLRA ML14076A1112014-03-17017 March 2014 Notice of Public Meeting to Provide an Open Forum to Discuss the Annual Assessment of Surry Power, Units 1 and 2 ML14066A1252014-03-0707 March 2014 March 18, 2014, Notice of Category 3 Public Meeting/Open House Regarding Surry, Units 1 & 2, Annual Assessment ML14065A4942014-03-0606 March 2014 Notice of Category 3 Public Meeting/Open House with Virginia Electric and Power Company to Discuss Surry Power Station Units 1 and 2 Annual Assessment ML14065A5302014-03-0606 March 2014 Notice of Category 3 Public Meeting/Open House with Virginia Electric and Power Company to Discuss Surry Power Station Units 1 and 2 Annual Assessment ML11256A2912010-08-12012 August 2010 Email from R. Guzman, NRR/DORL/LPL1-1 to R. Chang, Res/Dsa/Spb, Soarca Weekly Team Meeting ML0931002542009-11-0909 November 2009 Notice of Conference Call with Virginia Electric and Power Company to Discuss Issues Relating to Surry Power Station ML0730400332007-11-0101 November 2007 Public Meeting Slides for Meeting with Dominion Nuclear ML0726900152007-09-26026 September 2007 Notice of Forthcoming Meeting with Dominion Nuclear to Discuss Proposed Chemical Testing Methods Related to GSI-191, Assessment of Debris Accumulation on PWR Sump Performance, as Proposed by Its Vendor ML0632605122006-11-22022 November 2006 Forthcoming Meeting with Virginia Electric and Power Company. Regarding Main Control Room and Emergency Switchgear Room for Surry Nuclear Station Units 1 and 2 ML0626203902006-09-19019 September 2006 Notice of Meeting with Virginia Electric Power Company (VEPCO) to Discuss Organizational Changes at VEPCO, Etc ML0525606282005-09-13013 September 2005 Notice of Category 1 Meeting W/ VEPCO Surry and ISFSI Related Criticality Analysis Between Part 50 and 72 ML0513100022005-05-10010 May 2005 Notice of Meeting Regarding the plant-specific Implementation of VIPRE-D Topical Report for Dominion, VEPCO, (Surry, North Anna & Millstone) ML0420301852004-07-21021 July 2004 Notice of Meeting with Virginia Electric & Power Company (VEPCO) to Discuss Vepco'S Proposed plant-specific Topical Report That Implements VIPRE-D Code ML0411806032004-04-21021 April 2004 Meeting Summary with Virginia Electric and Power Company to Discuss Risk Significance of Concerns Associated with NRC Response to Potential Fire in Emergency Switchgear ML0325500192003-09-12012 September 2003 Notice of Meeting with Dominion Regarding Proposed Consolidation of the Quality Assurance Programs for Surry, Units 1 and 2, North Anna, Units 1 and 2, Millstone, Units 2 and 3, Nuclear Plants ML0305902342003-02-28028 February 2003 Forthcoming Meeting with Virginia Electric Power Co. to Discuss Control Room Habitability Testing ML0205303982002-01-0808 January 2002 Attachment to the 01/08/2002 Mtg with NEI, Southern Nuclear Operating Company (Snc), Florida Power and Light Company (Fpl), Virginia Electric and Power Company (Vepco), Duke Energy Corporation (Duke), and Exelon Generation Company (Exelon) 2024-09-23 |
Text
File updated March 29, 2018 Possible Topics for the April 17, 2018 Public Meeting with Dominion on its Surry Subsequent License Renewal Application:
- 1. Identification of those generic vs. site-specific issues outlined in the industry owners groups topical reports (e.g., PWROG-17011-NP, Rev 0, PWROG-17031-NP, Rev 0, and PWROG-17033-NP, Rev 0, etc.)
- 2. Reactor Vessel Internals, MRP-227A, environmentally assisted fatigue (EAF), and related GAP analysis
- 3. Concrete degradation
- 4. Cable & electrical AMPs (e.g., XI.E7 High-Voltage Insulators)
- 5. Scoping and screening
- 6. Which program(s) to be continued/discontinued from the first license renewal
- 7. Which program(s) to be initiated for the subsequent license renewal
- 8. Fatigue calculations - how will these calculations be carried out differently for the SLRA compared to they were performed for the first license renewal
- 9. Issued encountered from previous acceptance reviews
- a. Lack of consistency throughout the application (e.g., inconsistencies between Tables 3.6.1 and 3.6.2 in that Table 3.6.2 omits malleable iron and aluminum from the list of high voltage insulators materials, whereas LRA Table 3.6.1 includes malleable iron and aluminum.)
- b. LRAs do not address staff concerns documented in previous reviews (e.g.,
missing fire protection components from the fire protection scoping & screening tables.)
- c. LRAs reference reports and/or methodologies that have not been approved by the NRC (e.g., EPRI Report 1024995 Environmentally Assisted Fatigue Screening, Process and Technical Basis for Identifying EAF Limiting Locations the staff has concerns about the methodology and has not approved this report.
Some LRAs reference this report without including the additional information addressing the staffs concerns.)
- d. Applicants are advised to ensure the CLB issues have been addressed prior to submittal of the LRA so that the CLB issue resolution does not impact the LRA review schedule (e.g., one applicant calculated neutron fluence values by two different methods: one pre-EPU, and one post-EPU; the pre-EPU method associated with the current CLB had not been approved for use at the plant by the NRC. The applicant subsequently submitted a LAR to appropriately to incorporate a single fluence method to cover the PEO, which impacted the LRA review.)