| issue date = 01/11/2019
| issue date = 01/11/2019
| title = Ltr. 01/11/19 Perry Nuclear Power Plant - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000440/2019001 (DRS-V.Meghani)
| title = Ltr. 01/11/19 Perry Nuclear Power Plant - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000440/2019001 (DRS-V.Meghani)
| author name = Meghani V L
| author name = Meghani V
| author affiliation = NRC/RGN-III
| author affiliation = NRC/RGN-III
| addressee name = Hamilton D B
| addressee name = Hamilton D
| addressee affiliation = FirstEnergy Nuclear Operating Co
| addressee affiliation = FirstEnergy Nuclear Operating Co
| docket = 05000440
| docket = 05000440
Line 14: Line 14:
| page count = 6
| page count = 6
}}
}}
See also: [[followed by::IR 05000440/2019001]]
See also: [[see also::IR 05000440/2019001]]


=Text=
=Text=
{{#Wiki_filter:January 11, 2019
{{#Wiki_filter:January 11, 2019
  Mr. David B. Hamilton
Mr. David B. Hamilton
Site Vice President  
Site Vice President
FirstEnergy Nuclear Operating Company
FirstEnergy Nuclear Operating Company
Perry Nuclear Power Plant
Perry Nuclear Power Plant
Reg Affairs
Reg Affairs-A210
-A210 10 Center Road, P.O. Box 97  
10 Center Road, P.O. Box 97
Perry, OH 44081-0097 SUBJECT: PERRY NUCLEAR POWER PLANT
Perry, OH 44081-0097
-NOTIFICATION OF NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION
SUBJECT: PERRY NUCLEAR POWER PLANTNOTIFICATION OF NRC
; INSPECTION
              BASELINE INSPECTION AND REQUEST FOR INFORMATION;
REPORT 05000 440/20 19001  Dear Mr. Hamilton: On March 11, 2019 , the U.S. Nuclear Regulatory  
              INSPECTION REPORT 05000440/2019001
Commission (NRC)
Dear Mr. Hamilton:
will begin the Baseline Inservice Inspection Procedure 71111.08. This onsite inspection is scheduled to be performed March 11, 201 9 , through March 22, 201 9. Experience has shown that this inspection is resource intensive both for the NRC inspector and your staff. In order to minimize the impact to your onsite resources, and to ensure a productive inspection for both sides, we have enclosed a request for documents needed for this inspection. These documents have been divided into two groups.
On March 11, 2019, the U.S. Nuclear Regulatory Commission (NRC) will begin the Baseline
    The first group identifies information necessary to ensure that the inspector is adequately prepared. The second group identifies the information the inspector will need upon arrival at the site. It is important that all of these documents are up
Inservice Inspection Procedure 71111.08. This onsite inspection is scheduled to be performed
-to-date, and complete, in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.
March 11, 2019, through March 22, 2019.
  We have discussed the schedule for inspection activities with your staff and understand that  
Experience has shown that this inspection is resource intensive both for the NRC inspector and
our regulatory contact for this inspection will
your staff. In order to minimize the impact to your onsite resources, and to ensure a productive
be Mr. L. Zerr, of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector  
inspection for both sides, we have enclosed a request for documents needed for this inspection.
Mr. V. Meghani
These documents have been divided into two groups.
at 63 0-829-9751 , or via e-mail at vijay.meghani@nrc.gov
The first group identifies information necessary to ensure that the inspector is adequately
This letter does not contain new or amended information collection requirements subject  
prepared. The second group identifies the information the inspector will need upon arrival at
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150
the site. It is important that all of these documents are up-to-date, and complete, in order to
-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.  
minimize the number of additional documents requested during the preparation and/or the
D. Hamilton
onsite portions of the inspection.
-2- This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading
We have discussed the schedule for inspection activities with your staff and understand that
-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations, Part 2.390, "Public Inspections, Exemptions, Requests for Withholding."
our regulatory contact for this inspection will be Mr. L. Zerr, of your organization. If there are
  Sincerely, /RA/   Vijay Meghani, Reactor Inspector
any questions about this inspection or the material requested, please contact the lead inspector
Engineering Branch 1
Mr. V. Meghani at 630-829-9751, or via e-mail at vijay.meghani@nrc.gov.
Division of Reactor Safety
This letter does not contain new or amended information collection requirements subject
  Docket Nos. 50
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
-440 License Nos. NPF-58 Enclosure:
collection requirements were approved by the Office of Management and Budget, Control
  Document Request for Baseline Inservice   Inspection
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
  cc: Distribution via LISTSERV
respond to, a request for information or an information collection requirement unless the
 
requesting document displays a currently valid Office of Management and Budget Control
D. Hamilton
Number.
-3- Letter to David B. Hamilton
 
from Vijay Meghani
D. Hamilton                                 -2-
dated January 11, 2019. SUBJECT: PERRY NUCLEAR POWER PLANT
This letter and its enclosure will be made available for public inspection and copying at
-NOTIFICATION OF NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
; INSPECTION
accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,
REPORT 05000
Exemptions, Requests for Withholding.
440/2019001 DISTRIBUTION
                                            Sincerely,
: Aida Rivera
                                            /RA/
-Varona RidsNrrPMPerry Resource
                                            Vijay Meghani, Reactor Inspector
RidsNrrDorlLpl3
                                            Engineering Branch 1
RidsNrrDirsIrib Resource
                                            Division of Reactor Safety
Darrell Roberts John Giessner
Docket Nos. 50-440
Jamnes Cameron
License Nos. NPF-58
Allan Barker
Enclosure:
DRPIII DRSIII                           ADAMS Accession Number: ML19014A121
Document Request for Baseline Inservice
  Publicly Available
Inspection
  Non-Publicly Available
cc: Distribution via LISTSERV
  Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
 
  OFFICE RIII       NAME VMeghani:cl
D. Hamilton                                                               -3-
    DATE 01/11/19   OFFICIAL RECORD COPY
Letter to David B. Hamilton from Vijay Meghani dated January 11, 2019.
 
SUBJECT: PERRY NUCLEAR POWER PLANTNOTIFICATION OF NRC
DOCUMENT REQUEST FOR BASELINE INSERVICE INSPECTION
                    BASELINE INSPECTION AND REQUEST FOR INFORMATION;
2 Inspection Report
                    INSPECTION REPORT 05000440/2019001
: 05000 440/20 19 00 1  Inspection
DISTRIBUTION:
Dates: March 11, 201 9, through March 22, 201 9  Inspection
Aida Rivera-Varona
Procedures
RidsNrrPMPerry Resource
: Inspection Procedure 71111-08 , "Inservice Inspection
RidsNrrDorlLpl3
Lead Inspector
RidsNrrDirsIrib Resource
: Vijay Meghani, DRS 630-829-9751 vijay.meghani@nrc.gov
Darrell Roberts
  A. Information for the  
John Giessner
In-Office Preparation Week
Jamnes Cameron
  The following information (electronic copy CD ROM if possible) is requested by March 4, 2019 , to facilitate the selection of specific item
Allan Barker
s that will be reviewed during the onsite inspection week. The inspector will select specific items from the information requested below and request a list of additional documents needed onsite to your staff. We request that the specific items selected from the lists be available and ready for review on the first day of inspection.  
DRPIII
If you have any questions regarding this information, please call the inspector as soon as possible.
DRSIII
  1. For the upcoming outage, a detailed schedule and description of:
ADAMS Accession Number: ML19014A121
  a. Non-Destructive Examinations (NDE s) planned for Class 1 and 2 Systems  
    Publicly Available                       Non-Publicly Available                       Sensitive                 Non-Sensitive
and containment, performed as part of your American Society of Mechanical Engineers (ASME) Code Inservice Inspection (ISI) Program (include edition  
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
and addenda of Code committed to), and NDE
  OFFICE             RIII
s planned for other systems performed as part of a Risk-Informed ISI Program, or other augmented inspection programs commitments
NAME               VMeghani:cl
, as part of an industry initiative; and b. Welding on Code Class 1, 2, or 3 components. For each weld examination, include the weld identification number, description of weld (component name), category, class, type of exam and procedure number, and date of examination
DATE               01/11/19
2. A copy of the NDE procedures and welding procedures
                                                          OFFICIAL RECORD COPY
used to perform the activities identified in A.1 (including NDE calibration and flaw characterization/sizing procedures and Welding Procedure Qualification Records). For ultrasonic examination procedures qualified in accordance with Appendix VIII, of Section XI  
 
of the ASME Code, provide documentation supporting the procedure qualification (e.g., the Electric Power Research Institute
              DOCUMENT REQUEST FOR BASELINE INSERVICE INSPECTION
performance demonstration qualification summary sheets).
Inspection Report:             05000440/2019001
  3. A copy of ASME Section XI, Code Relief Requests applicable to the examinations identified in A.1.   4. A copy of the 10
Inspection Dates:               March 11, 2019, through March 22, 2019
-year ISI Program showing those required exams scheduled to be performed this outage, and those which have been completed.
Inspection Procedures:         Inspection Procedure 71111-08, Inservice Inspection
 
Lead Inspector:                 Vijay Meghani, DRS
DOCUMENT REQUEST FOR BASELINE INSERVICE INSPECTION
                                630-829-9751
3 5. A list identifying NDE reports (ultrasonic, radiography, magnetic particle, or dye penetrant), which have identified relevant indications on Code Class 1 and 2 systems since the beginning of the last refueling outage.
                                vijay.meghani@nrc.gov
  6. List with short description of the welds in Code Class 1 and 2 systems, which have been fabricated due to component repair/replacement activities since the beginning of the last refueling outage and identify the
A.     Information for the In-Office Preparation Week
system, weld number, and reference applicable documentation (e.g., NIS
      The following information (electronic copy CD ROM if possible) is requested by
-2 forms with definitions of system and component acronyms).
      March 4, 2019, to facilitate the selection of specific items that will be reviewed during
  7. If reactor vessel weld examinations required by
      the onsite inspection week. The inspector will select specific items from the information
the ASME Code are scheduled to occur during the inspection period, provide a detailed description of the welds to be examined, and the extent of the planned examination.
      requested below and request a list of additional documents needed onsite to your staff.
  8. List with description of ISI
      We request that the specific items selected from the lists be available and ready for
-related issues
      review on the first day of inspection. If you have any questions regarding this
such as piping degradation or damage  
      information, please call the inspector as soon as possible.
(e.g., cracks, wall thinning, wear, microbiologically induced corrosion) or errors identified in piping examinations
      1. For the upcoming outage, a detailed schedule and description of:
that have been
          a. Non-Destructive Examinations (NDEs) planned for Class 1 and 2 Systems
entered into your corrective action system since the beginning of the last refueling outage. Also, include a list of corrective action records associated with foreign material introduced/identified in the reactor vessel or reactor coolant system
              and containment, performed as part of your American Society of Mechanical
since the beginning of the last refueling outage. Provide a copy of evaluations, corrective actions associated with an embedded reflector found on the N1A during UT Support 10 exams in RF16 (2017).
              Engineers (ASME) Code Inservice Inspection (ISI) Program (include edition
   9. Copy of any Title 10 of the Code of Federal Regulations
              and addenda of Code committed to), and NDEs planned for other systems
, Part 21 reports applicable to your structures
              performed as part of a Risk-Informed ISI Program, or other augmented
, systems , or components within the scope of Section XI of the ASME Code that have been identified since the beginning of the last refueling outage. 10. Point of contact information (name and site number) for the Inservice Inspection Program , Aging Management Programs, Site Welding Engineer, and Reactor Internals Inspection Programs-Site and vendor leads.
              inspection programs commitments, as part of an industry initiative; and
  B. Onsite Information to be Provided to the Inspector on the First Day of the Inspection (e.g., Following the Entrance Meeting). Please Provide Hard Copies (e.g., Paper Records) of the Following Documents
          b. Welding on Code Class 1, 2, or 3 components. For each weld examination,
1. For welds selected by the inspector from A.1.
              include the weld identification number, description of weld (component name),
b and A.6 above, provide copies of the following documents:
              category, class, type of exam and procedure number, and date of examination.
  a. Document of the weld number and location (e.g., system, train, branch);
      2. A copy of the NDE procedures and welding procedures used to perform the activities
  b. Document with a detail of the weld construction
          identified in A.1 (including NDE calibration and flaw characterization/sizing
(e.g., drawing); c. Applicable portions of the Design Specification and applicable Code of construction for the weldment (e.g., B31.1 or ASME Section III);
          procedures and Welding Procedure Qualification Records). For ultrasonic
  d. Applicable Code Edition and Addenda for weld procedure
          examination procedures qualified in accordance with Appendix VIII, of Section XI
qualification
          of the ASME Code, provide documentation supporting the procedure qualification
e. Applicable weld procedure
          (e.g., the Electric Power Research Institute performance demonstration qualification
specifications
          summary sheets).
and completed weld data sheets used to fabricate the welds;
      3. A copy of ASME Section XI, Code Relief Requests applicable to the examinations
 
          identified in A.1.
DOCUMENT REQUEST FOR BASELINE INSERVICE INSPECTION
      4. A copy of the 10-year ISI Program showing those required exams scheduled to be
4 f. Copies of procedure qualification records supporting the weld procedure
          performed this outage, and those which have been completed.
specification
                                                  2
s;  g. Copies of welders' performance qualification records;
 
  h. Copies of mechanical test reports identified in the procedure qualification records above; i. Copies of the non
          DOCUMENT REQUEST FOR BASELINE INSERVICE INSPECTION
-conformance reports for the selected welds;
  5. A list identifying NDE reports (ultrasonic, radiography, magnetic particle, or dye
  j. Access to radiographs and equipment to view radiographs of the selected welds;
      penetrant), which have identified relevant indications on Code Class 1 and 2 systems
  k. ASME Code Section XI repair replacement plan and reconciliation for  
      since the beginning of the last refueling outage.
replacement components/materials;
  6. List with short description of the welds in Code Class 1 and 2 systems, which have
  l. Certified Material Test Reports for replacement pressure boundary materials
      been fabricated due to component repair/replacement activities since the beginning
; and m. Copies of the
      of the last refueling outage and identify the system, weld number, and reference
NDE required by the construction Code and
      applicable documentation (e.g., NIS-2 forms with definitions of system and
the pre-service examination records required by the ASME Code Section XI for the selected welds.
      component acronyms).
  2. For the ISI
  7. If reactor vessel weld examinations required by the ASME Code are scheduled to
-related corrective action issues selected by the inspector from Item A.7 above, provide a copy of the corrective actions and supporting documentation.
      occur during the inspection period, provide a detailed description of the welds to be
  3. For the NDE reports with relevant indications on Code Class 1 and 2 Systems selected by the inspector fr
      examined, and the extent of the planned examination.
om Item A.4 above, provide a copy of the examination records and associated corrective action documents.
  8. List with description of ISI-related issues such as piping degradation or damage
  4. Updated schedules for  
      (e.g., cracks, wall thinning, wear, microbiologically induced corrosion) or errors
Item A.1 (including schedule showing contingency repair plans if available).
      identified in piping examinations that have been entered into your corrective action
  5. Fabrication Drawings (D size) of the reactor vessel welds if any are to be examined during the outage. Also provide any drawings used by NDE vendor
      system since the beginning of the last refueling outage. Also, include a list of
s to locate these welds.   6. Provide copies of the following standards at the onsite U.S. Nuclear Regulatory Commission
      corrective action records associated with foreign material introduced/identified in
inspection location for the duration of the inspection:
      the reactor vessel or reactor coolant system since the beginning of the last refueling
  a. Sections V, IX, and XI of the ASME Code with Editions applicable to the
      outage. Provide a copy of evaluations, corrective actions associated with an
I SI Program and the Repair/Replacement Program;
      embedded reflector found on the N1A during UT Support 10 exams in RF16 (2017).
and  b. Copy of the performance demonstration initiative (PDI) generic procedures with the latest applicable Revisions that support site qualified ultrasonic examination of piping welds and components (e.g.
   9. Copy of any Title 10 of the Code of Federal Regulations, Part 21 reports applicable
, PDI-U T-1, PDI-UT-2, PDI-UT-3, PDI-UT-10 etc.).   7. Provide training (e.g., Scaffolding, Fall Protection, Foreign Material Exclusion) if required to access the  
      to your structures, systems, or components within the scope of Section XI of the
NDE selected by the inspector for observation.
      ASME Code that have been identified since the beginning of the last refueling
  If you have questions regarding the information requested, please contact the lead inspector.
      outage.
  10. Point of contact information (name and site number) for the Inservice Inspection
      Program, Aging Management Programs, Site Welding Engineer, and Reactor
      Internals Inspection ProgramsSite and vendor leads.
B. Onsite Information to be Provided to the Inspector on the First Day of the
  Inspection (e.g., Following the Entrance Meeting). Please Provide Hard Copies
  (e.g., Paper Records) of the Following Documents.
  1. For welds selected by the inspector from A.1.b and A.6 above, provide copies of the
      following documents:
      a. Document of the weld number and location (e.g., system, train, branch);
      b. Document with a detail of the weld construction (e.g., drawing);
      c. Applicable portions of the Design Specification and applicable Code of
            construction for the weldment (e.g., B31.1 or ASME Section III);
      d. Applicable Code Edition and Addenda for weld procedure qualification;
      e. Applicable weld procedure specifications and completed weld data sheets used
            to fabricate the welds;
                                              3
 
              DOCUMENT REQUEST FOR BASELINE INSERVICE INSPECTION
          f. Copies of procedure qualification records supporting the weld procedure
              specifications;
          g. Copies of welders performance qualification records;
          h. Copies of mechanical test reports identified in the procedure qualification
              records above;
          i. Copies of the non-conformance reports for the selected welds;
          j. Access to radiographs and equipment to view radiographs of the selected welds;
          k. ASME Code Section XI repair replacement plan and reconciliation for
              replacement components/materials;
          l. Certified Material Test Reports for replacement pressure boundary materials; and
          m. Copies of the NDE required by the construction Code and the pre-service
              examination records required by the ASME Code Section XI for the selected welds.
        2. For the ISI-related corrective action issues selected by the inspector from Item A.7
          above, provide a copy of the corrective actions and supporting documentation.
        3. For the NDE reports with relevant indications on Code Class 1 and 2 Systems
          selected by the inspector from Item A.4 above, provide a copy of the examination
          records and associated corrective action documents.
        4. Updated schedules for Item A.1 (including schedule showing contingency repair
          plans if available).
        5. Fabrication Drawings (D size) of the reactor vessel welds if any are to be examined
          during the outage. Also provide any drawings used by NDE vendors to locate these
          welds.
        6. Provide copies of the following standards at the onsite U.S. Nuclear Regulatory
          Commission inspection location for the duration of the inspection:
          a. Sections V, IX, and XI of the ASME Code with Editions applicable to the
              ISI Program and the Repair/Replacement Program; and
          b. Copy of the performance demonstration initiative (PDI) generic procedures with
              the latest applicable Revisions that support site qualified ultrasonic examination
              of piping welds and components (e.g., PDI-UT-1, PDI-UT-2, PDI-UT-3,
              PDI-UT-10 etc.).
        7. Provide training (e.g., Scaffolding, Fall Protection, Foreign Material Exclusion) if
          required to access the NDE selected by the inspector for observation.
If you have questions regarding the information requested, please contact the lead inspector.
                                                  4
}}
}}

Latest revision as of 07:53, 20 October 2019

Ltr. 01/11/19 Perry Nuclear Power Plant - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000440/2019001 (DRS-V.Meghani)
ML19014A121
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 01/11/2019
From: Vijay Meghani
NRC/RGN-III
To: Hamilton D
FirstEnergy Nuclear Operating Co
References
IR 2019001
Download: ML19014A121 (6)


See also: IR 05000440/2019001

Text

January 11, 2019

Mr. David B. Hamilton

Site Vice President

FirstEnergy Nuclear Operating Company

Perry Nuclear Power Plant

Reg Affairs-A210

10 Center Road, P.O. Box 97

Perry, OH 44081-0097

SUBJECT: PERRY NUCLEAR POWER PLANTNOTIFICATION OF NRC

BASELINE INSPECTION AND REQUEST FOR INFORMATION;

INSPECTION REPORT 05000440/2019001

Dear Mr. Hamilton:

On March 11, 2019, the U.S. Nuclear Regulatory Commission (NRC) will begin the Baseline

Inservice Inspection Procedure 71111.08. This onsite inspection is scheduled to be performed

March 11, 2019, through March 22, 2019.

Experience has shown that this inspection is resource intensive both for the NRC inspector and

your staff. In order to minimize the impact to your onsite resources, and to ensure a productive

inspection for both sides, we have enclosed a request for documents needed for this inspection.

These documents have been divided into two groups.

The first group identifies information necessary to ensure that the inspector is adequately

prepared. The second group identifies the information the inspector will need upon arrival at

the site. It is important that all of these documents are up-to-date, and complete, in order to

minimize the number of additional documents requested during the preparation and/or the

onsite portions of the inspection.

We have discussed the schedule for inspection activities with your staff and understand that

our regulatory contact for this inspection will be Mr. L. Zerr, of your organization. If there are

any questions about this inspection or the material requested, please contact the lead inspector

Mr. V. Meghani at 630-829-9751, or via e-mail at vijay.meghani@nrc.gov.

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, Control

Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget Control

Number.

D. Hamilton -2-

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,

Exemptions, Requests for Withholding.

Sincerely,

/RA/

Vijay Meghani, Reactor Inspector

Engineering Branch 1

Division of Reactor Safety

Docket Nos. 50-440

License Nos. NPF-58

Enclosure:

Document Request for Baseline Inservice

Inspection

cc: Distribution via LISTSERV

D. Hamilton -3-

Letter to David B. Hamilton from Vijay Meghani dated January 11, 2019.

SUBJECT: PERRY NUCLEAR POWER PLANTNOTIFICATION OF NRC

BASELINE INSPECTION AND REQUEST FOR INFORMATION;

INSPECTION REPORT 05000440/2019001

DISTRIBUTION:

Aida Rivera-Varona

RidsNrrPMPerry Resource

RidsNrrDorlLpl3

RidsNrrDirsIrib Resource

Darrell Roberts

John Giessner

Jamnes Cameron

Allan Barker

DRPIII

DRSIII

ADAMS Accession Number: ML19014A121

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII

NAME VMeghani:cl

DATE 01/11/19

OFFICIAL RECORD COPY

DOCUMENT REQUEST FOR BASELINE INSERVICE INSPECTION

Inspection Report: 05000440/2019001

Inspection Dates: March 11, 2019, through March 22, 2019

Inspection Procedures: Inspection Procedure 71111-08, Inservice Inspection

Lead Inspector: Vijay Meghani, DRS

630-829-9751

vijay.meghani@nrc.gov

A. Information for the In-Office Preparation Week

The following information (electronic copy CD ROM if possible) is requested by

March 4, 2019, to facilitate the selection of specific items that will be reviewed during

the onsite inspection week. The inspector will select specific items from the information

requested below and request a list of additional documents needed onsite to your staff.

We request that the specific items selected from the lists be available and ready for

review on the first day of inspection. If you have any questions regarding this

information, please call the inspector as soon as possible.

1. For the upcoming outage, a detailed schedule and description of:

a. Non-Destructive Examinations (NDEs) planned for Class 1 and 2 Systems

and containment, performed as part of your American Society of Mechanical

Engineers (ASME) Code Inservice Inspection (ISI) Program (include edition

and addenda of Code committed to), and NDEs planned for other systems

performed as part of a Risk-Informed ISI Program, or other augmented

inspection programs commitments, as part of an industry initiative; and

b. Welding on Code Class 1, 2, or 3 components. For each weld examination,

include the weld identification number, description of weld (component name),

category, class, type of exam and procedure number, and date of examination.

2. A copy of the NDE procedures and welding procedures used to perform the activities

identified in A.1 (including NDE calibration and flaw characterization/sizing

procedures and Welding Procedure Qualification Records). For ultrasonic

examination procedures qualified in accordance with Appendix VIII, of Section XI

of the ASME Code, provide documentation supporting the procedure qualification

(e.g., the Electric Power Research Institute performance demonstration qualification

summary sheets).

3. A copy of ASME Section XI, Code Relief Requests applicable to the examinations

identified in A.1.

4. A copy of the 10-year ISI Program showing those required exams scheduled to be

performed this outage, and those which have been completed.

2

DOCUMENT REQUEST FOR BASELINE INSERVICE INSPECTION

5. A list identifying NDE reports (ultrasonic, radiography, magnetic particle, or dye

penetrant), which have identified relevant indications on Code Class 1 and 2 systems

since the beginning of the last refueling outage.

6. List with short description of the welds in Code Class 1 and 2 systems, which have

been fabricated due to component repair/replacement activities since the beginning

of the last refueling outage and identify the system, weld number, and reference

applicable documentation (e.g., NIS-2 forms with definitions of system and

component acronyms).

7. If reactor vessel weld examinations required by the ASME Code are scheduled to

occur during the inspection period, provide a detailed description of the welds to be

examined, and the extent of the planned examination.

8. List with description of ISI-related issues such as piping degradation or damage

(e.g., cracks, wall thinning, wear, microbiologically induced corrosion) or errors

identified in piping examinations that have been entered into your corrective action

system since the beginning of the last refueling outage. Also, include a list of

corrective action records associated with foreign material introduced/identified in

the reactor vessel or reactor coolant system since the beginning of the last refueling

outage. Provide a copy of evaluations, corrective actions associated with an

embedded reflector found on the N1A during UT Support 10 exams in RF16 (2017).

9. Copy of any Title 10 of the Code of Federal Regulations, Part 21 reports applicable

to your structures, systems, or components within the scope of Section XI of the

ASME Code that have been identified since the beginning of the last refueling

outage.

10. Point of contact information (name and site number) for the Inservice Inspection

Program, Aging Management Programs, Site Welding Engineer, and Reactor

Internals Inspection ProgramsSite and vendor leads.

B. Onsite Information to be Provided to the Inspector on the First Day of the

Inspection (e.g., Following the Entrance Meeting). Please Provide Hard Copies

(e.g., Paper Records) of the Following Documents.

1. For welds selected by the inspector from A.1.b and A.6 above, provide copies of the

following documents:

a. Document of the weld number and location (e.g., system, train, branch);

b. Document with a detail of the weld construction (e.g., drawing);

c. Applicable portions of the Design Specification and applicable Code of

construction for the weldment (e.g., B31.1 or ASME Section III);

d. Applicable Code Edition and Addenda for weld procedure qualification;

e. Applicable weld procedure specifications and completed weld data sheets used

to fabricate the welds;

3

DOCUMENT REQUEST FOR BASELINE INSERVICE INSPECTION

f. Copies of procedure qualification records supporting the weld procedure

specifications;

g. Copies of welders performance qualification records;

h. Copies of mechanical test reports identified in the procedure qualification

records above;

i. Copies of the non-conformance reports for the selected welds;

j. Access to radiographs and equipment to view radiographs of the selected welds;

k. ASME Code Section XI repair replacement plan and reconciliation for

replacement components/materials;

l. Certified Material Test Reports for replacement pressure boundary materials; and

m. Copies of the NDE required by the construction Code and the pre-service

examination records required by the ASME Code Section XI for the selected welds.

2. For the ISI-related corrective action issues selected by the inspector from Item A.7

above, provide a copy of the corrective actions and supporting documentation.

3. For the NDE reports with relevant indications on Code Class 1 and 2 Systems

selected by the inspector from Item A.4 above, provide a copy of the examination

records and associated corrective action documents.

4. Updated schedules for Item A.1 (including schedule showing contingency repair

plans if available).

5. Fabrication Drawings (D size) of the reactor vessel welds if any are to be examined

during the outage. Also provide any drawings used by NDE vendors to locate these

welds.

6. Provide copies of the following standards at the onsite U.S. Nuclear Regulatory

Commission inspection location for the duration of the inspection:

a. Sections V, IX, and XI of the ASME Code with Editions applicable to the

ISI Program and the Repair/Replacement Program; and

b. Copy of the performance demonstration initiative (PDI) generic procedures with

the latest applicable Revisions that support site qualified ultrasonic examination

of piping welds and components (e.g., PDI-UT-1, PDI-UT-2, PDI-UT-3,

PDI-UT-10 etc.).

7. Provide training (e.g., Scaffolding, Fall Protection, Foreign Material Exclusion) if

required to access the NDE selected by the inspector for observation.

If you have questions regarding the information requested, please contact the lead inspector.