|
|
Line 76: |
Line 76: |
| Inspection Report (IR) 05000348/2016009; 10/10/2016 - 10/14/2016; Joseph M. Farley Nuclear Plant, Unit 1; Post-Approval Site Inspection for License Renewal. | | Inspection Report (IR) 05000348/2016009; 10/10/2016 - 10/14/2016; Joseph M. Farley Nuclear Plant, Unit 1; Post-Approval Site Inspection for License Renewal. |
|
| |
|
| The report covers an inspection conducted by a r egional inspector in accordance with the U.S. Nuclear Regulatory Commission (NRC) Inspector Manual Chapter (IMC) 2515, and NRC Inspection Procedure (IP) 71003, Post-Approval Site Inspection for License Renewal, dated July 1, 2016. | | The report covers an inspection conducted by a r egional inspector in accordance with the U.S. Nuclear Regulatory Commission (NRC) Inspector Manual Chapter (IMC) 2515, and NRC Inspection Procedure (IP) 71003, Post-Approval Site Inspection for License Renewal, dated July 1, 2016. Based on the sample selected for review, the inspectors determined that commitments, license conditions, and regulatory requirements associated with the renewed facility operating license were either being met, or where commitment actions had not been completed, that the licensee had administrative controls in place to ensure completion before the period of extended operation. |
| | |
| Based on the sample selected for review, the inspectors determined that commitments, license conditions, and regulatory requirements associated with the renewed facility operating license were either being met, or where commitment actions had not been completed, that the licensee had administrative controls in place to ensure completion before the period of extended operation. | |
|
| |
|
| The NRC's program for overseeing the safe operati on of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 6. | | The NRC's program for overseeing the safe operati on of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 6. |
|
---|
Category:Inspection Report
MONTHYEARIR 05000348/20244012024-09-10010 September 2024 Security Baseline Inspection Report 05000348-2024401 and 05000364-2024401 IR 05000348/20244022024-08-26026 August 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000348/2024402 and 05000364/2024402 IR 05000348/20240052024-08-26026 August 2024 Updated Inspection Plan for Joseph M. Farley Nuclear Plant, Units 1 and 2 - Report 05000348/2024005 and 05000364/2024005 IR 05000348/20240022024-08-12012 August 2024 – Integrated Inspection Report 05000348-2024002 and 05000364-2024002 and Exercise of Enforcement Discretion IR 05000348/20240012024-04-24024 April 2024 Integrated Inspection Report 05000348/2024001 and 05000364/2024001 IR 05000348/20240102024-04-16016 April 2024 NRC Inspection Report 05000348/2024010 and 05000364/2024010 IR 05000348/20240112024-04-12012 April 2024 Fire Protection Team Inspection Report 05000348/2024011 and 05000364/2024011 IR 05000348/20230062024-02-28028 February 2024 Annual Assessment Letter for Joseph M. Farley Nuclear Plant, Units 1 and 2 - Report 05000348/2023006 and 05000364/2023006 IR 05000348/20230042024-02-0909 February 2024 Integrated Inspection Report 05000348/2023004 and 05000364/2023004 and Exercise of Enforcement Discretion IR 05000348/20230402024-01-24024 January 2024 95001 Supplemental Inspection Report 05000348/2023040 and Follow-Up Assessment Letter ML23346A2222023-12-22022 December 2023 Transmittal of Dam Inspection Report - Public IR 05000348/20230032023-10-24024 October 2023 Integrated Inspection Report 05000348/2023003 and 05000364/2023003 IR 05000348/20230912023-10-19019 October 2023 Final Significance Determination of a White Finding and Notice of Violation and Assessment Followup Letter NRC Inspection Report 05000348/2023091 IR 05000348/20234022023-10-18018 October 2023 Security Baseline Inspection Report 05000348/2023402 and 05000364/2023402 IR 05000348/20234412023-10-12012 October 2023 Supplemental Inspection Report 05000348/2023441 and 05000364/2023441 and Follow-Up Assessment Letter (Cover Letter) IR 05000348/20230902023-08-31031 August 2023 NRC Inspection Report 05000348/2023090 and Preliminary White Finding and Apparent Violation IR 05000348/20330012023-08-14014 August 2023 NRC Operator License Examination Report 05000348/203301 and 05000364/2023302 IR 05000348/20230022023-08-10010 August 2023 Integrated Inspection Report 05000348/2023002 and 05000364/2023002, and Apparent Violation IR 05000348/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 05000348/2023010 and 05000364/2023010 IR 05000348/20234402023-05-0505 May 2023 Reissue Farley Units-Final Significance Determination for a Security-Related Greater than Green Finding, Nov and Assessment Followup LTR, IR 05000348/2023440 and 05000364/2023440 - Cover IR 05000348/20230012023-05-0404 May 2023 Integrated Inspection Report 05000348/2023001 and 05000364/2023001 IR 05000348/20230112023-04-13013 April 2023 Biennial Problem Identification and Resolution Inspection Report 05000348/2023011 and 05000364/2023011 IR 05000348/20234012023-03-31031 March 2023 Security Baseline Inspection Report 05000348/2023401 and 05000364/2023401 IR 05000348/20220062023-03-0101 March 2023 Annual Assessment Letter for Joseph M. Farley Nuclear Plant, Units 1 and 2 Report 05000348/2022006 and 05000364/2022006 IR 05000348/20220112023-02-16016 February 2023 NRC Inspection Report 05000348/2022011 IR 05000348/20220902023-02-16016 February 2023 NRC Inspection Report 05000348/2022090 IR 05000348/20220042023-01-23023 January 2023 Integrated Inspection Report 05000348/2022004 and 05000364/2022004 ML22343A0382022-12-13013 December 2022 Notification of Joseph M. Farley Nuclear Plant Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 05000348/2023010 and 05000364/2023010 IR 05000348/20224042022-11-29029 November 2022 Security Baseline Inspection Report 05000348/2022404 and 05000364/2022404 IR 05000348/20224402022-11-0707 November 2022 Special Inspection Report 05000348/2022440 and 05000364/ 2022440 and Preliminary Greater than Green Finding and and Apparent Violation (Cover Letter) IR 05000348/20220032022-10-28028 October 2022 Integrated Inspection Report 05000348/2022003 and 05000364/2022003 IR 05000348/20220502022-09-30030 September 2022 Special Inspection Reactive Report 05000348/2022050 and Apparent Violation IR 05000348/20220052022-08-24024 August 2022 Updated Inspection Plan for Joseph M. Farley Nuclear Plant, Units 1 and 2 - Report 05000348/2022005 and 05000364/2022005 IR 05000348/20220022022-08-12012 August 2022 Integrated Inspection Report 05000348/2022002 and 05000364/2022002 ML22214B8262022-08-0404 August 2022 Security Baseline Inspection Report 05000348/2022403 and 05000364/2022403 IR 05000348/20233012022-08-0101 August 2022 Notification of Licensed Operator Initial Examination 05000348/2023301 and 05000364/2023301 IR 05000348/20224022022-07-26026 July 2022 Security Baseline Inspection Report 05000348/2022402 and 05000364/2022402 IR 05000348/20224012022-05-0606 May 2022 Cyber Security Inspection Report 05000348/2022401 and 05000364/2022401 IR 05000348/20220012022-05-0404 May 2022 Integrated Inspection Report 05000348/2022001 and 05000364/2022001 IR 05000348/20220102022-03-22022 March 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000348/2022010 and 05000364/2022010 IR 05000348/20210062022-03-0202 March 2022 Annual Assessment Letter for Joseph M. Farley Nuclear Plant Units 1 and 2 (Report No. 05000348/2021006 and 05000364/2021006) IR 05000348/20210042022-02-0808 February 2022 Integrated Inspection Report 05000348/2021004 and 05000364/2021004 IR 05000348/20210112021-12-13013 December 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000348/2021011 and 05000364/2021011 ML21347A4422021-12-13013 December 2021 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000348/2022401; 05000364/2022401 IR 05000348/20214032021-12-0202 December 2021 Security Baseline Inspection Report 05000348/2021403 and 05000364/2021403 IR 05000348/20210032021-11-10010 November 2021 Integrated Inspection Report 05000348/2021003, 05000364/2021003, and 07200042/2021001 IR 05000348/20214022021-09-15015 September 2021 Security Baseline Inspection Report 05000348/2021402 and 05000364/2021402 IR 05000348/20210052021-08-24024 August 2021 Updated Inspection Plan for Joseph M. Farley Nuclear Plant Units 1 and 2 (Report 05000348/2021005 and 05000364/2021005) IR 05000348/20213012021-08-18018 August 2021 NRC Operator License Examination Report 05000348/2021301 and 05000364/2021301 IR 05000348/20210022021-07-30030 July 2021 Integrated Inspection Report 05000348/2021002 and 05000364/2021002 and Exercise of Enforcement Discretion 2024-09-10
[Table view] Category:Letter
MONTHYEARNL-24-0364, Notification of Deferral of Baffle Former Bolt Inspections from Farley 1R33 to 1R342024-10-31031 October 2024 Notification of Deferral of Baffle Former Bolt Inspections from Farley 1R33 to 1R34 NL-24-0392, Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-0022024-10-28028 October 2024 Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-002 NL-24-0396, Response to Request for Additional Information Related to Relief Request to Defer Charging Pump and Mini-Flow Isolation Valve Inservice Testing2024-10-25025 October 2024 Response to Request for Additional Information Related to Relief Request to Defer Charging Pump and Mini-Flow Isolation Valve Inservice Testing NL-24-0384, Request for Alternative RR-PR-04 for Inservice Testing of the 2A, 2B, and 2C Charging Pumps and Mini-Flow Isolation Valves2024-10-18018 October 2024 Request for Alternative RR-PR-04 for Inservice Testing of the 2A, 2B, and 2C Charging Pumps and Mini-Flow Isolation Valves NL-24-0320, License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3,.2024-09-27027 September 2024 License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3,. NL-24-0349, Units 1 and 2 - 10 CFR 26.719(c)(1) 30-Day Report Blind Performance Test Results Inconsistent with Sample Provided2024-09-20020 September 2024 Units 1 and 2 - 10 CFR 26.719(c)(1) 30-Day Report Blind Performance Test Results Inconsistent with Sample Provided NL-24-0341, Response to Request for Additional Information Related to the Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency2024-09-10010 September 2024 Response to Request for Additional Information Related to the Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency IR 05000348/20244012024-09-10010 September 2024 Security Baseline Inspection Report 05000348-2024401 and 05000364-2024401 ML24247A1102024-09-0505 September 2024 Corporate Notification Letter Aka 210-day Letter NUREG Rev 12 NL-24-0259, License Amendment Request to Revise Technical Specification 3.4.14, Reactor Coolant System Pressure Isolation Valve Leakage, Surveillance Requirement 3.4.14.3 Acceptance Criteria and Miscellaneous Obsolete Changes2024-09-0404 September 2024 License Amendment Request to Revise Technical Specification 3.4.14, Reactor Coolant System Pressure Isolation Valve Leakage, Surveillance Requirement 3.4.14.3 Acceptance Criteria and Miscellaneous Obsolete Changes NL-24-0340, Unit 1 - Inservice Inspection Program Owners Activity Report (OAR-1) for Outage 1 R322024-09-0404 September 2024 Unit 1 - Inservice Inspection Program Owners Activity Report (OAR-1) for Outage 1 R32 ML24242A1332024-08-29029 August 2024 Issuance of Amendment Nos. 250 and 247, Regarding License Amendment Request to Revise Technical Specification 3.6.5, Containment Air Temperature, Actions (EPID L-2024-LLA-0098) - Non-Proprietary ML24240A0812024-08-27027 August 2024 License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions - Revised Completion Time ML24233A0022024-08-27027 August 2024 Request for Withholding Information from Public Disclosure for Joseph M. Farley Nuclear Plant, Units 1 and 2, License Amendment Request Supplement to Change Technical Specification 3.6.5, Containment Air Temperature Actions IR 05000348/20240052024-08-26026 August 2024 Updated Inspection Plan for Joseph M. Farley Nuclear Plant, Units 1 and 2 - Report 05000348/2024005 and 05000364/2024005 IR 05000348/20244022024-08-26026 August 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000348/2024402 and 05000364/2024402 ML24226B2112024-08-22022 August 2024 Regulatory Audit Summary in Support of License Amendment Requests to Revise Technical Specification 3.6.5, Containment Air Temperature, Actions NL-24-0321, License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions - Supplemental Information2024-08-16016 August 2024 License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions - Supplemental Information IR 05000348/20240022024-08-12012 August 2024 – Integrated Inspection Report 05000348-2024002 and 05000364-2024002 and Exercise of Enforcement Discretion ML24215A3772024-08-0707 August 2024 2024 Farley Requal Inspection Corporate Notification Letter ML24201A2032024-08-0101 August 2024 Request for Withholding Information from Public Disclosure for Joseph M. Farley Nuclear Plant, Units 1 and 2, License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions ML24200A1392024-07-25025 July 2024 Regulatory Audit in Support of Review of the License Amendment Request to Revise Technical Specification 3.6.5, Containment Air Temperature ML24199A2072024-07-24024 July 2024 TS 3-6-5 LAR - Individual Notice Transmittal Letter and NSHC - Rev 1 (1) - Letter NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 NL-24-0281, License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions2024-07-18018 July 2024 License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions NL-24-0227, Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2024-07-0303 July 2024 Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML24184A0452024-07-0202 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24178A3762024-07-0101 July 2024 Nonacceptance of Requested Licensing Action License Amendment Request to Revise Technical Specification 3.6.5, Containment Air Temperature, Using Risk-Informed Process for Evaluations NL-24-0230, License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-500, Revision 2, DC Electrical Rewrite – Update to TSTF-3602024-06-28028 June 2024 License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-500, Revision 2, DC Electrical Rewrite – Update to TSTF-360 NL-24-0234, Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown2024-06-28028 June 2024 Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in 05000348/LER-2024-002-01, Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel2024-06-19019 June 2024 Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel NL-24-0201, Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2024-06-18018 June 2024 Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) 05000348/LER-2024-001, Pressurizer Safety Valve Lift Pressure Outside of Technical Specifications Limits Due to Setpoint Drift2024-06-17017 June 2024 Pressurizer Safety Valve Lift Pressure Outside of Technical Specifications Limits Due to Setpoint Drift NL-24-0238, RIPE License Amendment Request to Change Containment Air Temperature Actions, Supplemental Information2024-06-14014 June 2024 RIPE License Amendment Request to Change Containment Air Temperature Actions, Supplemental Information NL-24-0229, Notice of Intent to Pursue Subsequent License Renewal2024-06-0707 June 2024 Notice of Intent to Pursue Subsequent License Renewal ML24149A0492024-06-0404 June 2024 SNC Fleet - Regulatory Audit in Support of Review of the License Amendment Request to Revise TS 1.1, Use and Application Definitions, and Add New Technical Specification 5.5.21 and 5.5.17, Online Monitoring Program, ML24143A0412024-05-28028 May 2024 Supplemental Information Needed for Using the Risk-Informed Process for Evaluation for the LAR to Change Technical Specification 3.6.5, Containment Air Temperature, Actions NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 NL-24-0064, Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.52024-05-0303 May 2024 Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.5 NL-24-0188, Cycle 33 Core Operating Limits Report2024-05-0101 May 2024 Cycle 33 Core Operating Limits Report NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 IR 05000348/20240012024-04-24024 April 2024 Integrated Inspection Report 05000348/2024001 and 05000364/2024001 NL-24-0137, RIPE License Amendment Request to Change Containment Air Temperature Actions2024-04-19019 April 2024 RIPE License Amendment Request to Change Containment Air Temperature Actions IR 05000348/20240102024-04-16016 April 2024 NRC Inspection Report 05000348/2024010 and 05000364/2024010 05000364/LER-2024-002, For Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel2024-04-15015 April 2024 For Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel IR 05000348/20240112024-04-12012 April 2024 Fire Protection Team Inspection Report 05000348/2024011 and 05000364/2024011 NL-24-0134, Renewed National Pollutant Discharge Elimination System (NPDES) Permit2024-04-12012 April 2024 Renewed National Pollutant Discharge Elimination System (NPDES) Permit NL-24-0088, Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency2024-04-0505 April 2024 Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency 2024-09-05
[Table view] |
Inspection Report - Farley - 2016009 |
---|
|
|
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 November 7, 2016 Cheryl Vice President
Southern Nuclear Operating Company, Inc.
Joseph M. Farley Nuclear Plant
7388 North State Highway 95
Columbia, AL 36319
SUBJECT: JOSEPH M. FARLEY NUCLEAR PLANT, UNIT 1 - U.S. NUCLEAR REGULATORY COMMISSION POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL, INSPECTION REPORT 05000348/2016009
Dear Ms. Gayheart:
On October 14, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed a Post-
Approval Site Inspection for License Renewal at your Joseph M. Farley Nuclear Plant, Unit 1. The enclosed report documents the inspection results that were discussed on October 14, 2016, with you and members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules, regulations, and conditions of your license. The inspectors reviewed selected procedures, records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings were identified.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public inspections, exemptions, requests for withholding" of the NRC's "Agency Rules of Practice and Procedure," a copy of this letter, its Enclosure, and your response (if any), will be available electronically for public inspection in the NRC Public Document Room, or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS); accessible from the NRC Web site at http://www.nrc.gov/
reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,/RA/ Shakur A. Walker, Chief Engineering Branch 3 Division of Reactor Safety
Docket No. 50-348 License No. NPF-2
Enclosure:
NRC Inspection Report 05000348/2016009
w/Attachment:
Supplementary Information
cc: Distribution via Listserv
_________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS RII:DRS SIGNATURE PEC SAW4 NAME PCOOPER SWALKER DATE 11/3/2016 11/7/2016 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO Enclosure U.S. NUCLEAR REGULATORY COMMISSION REGION II
Docket No: 05000348
License No: NPF-2
Report No: 05000348/2016009
Licensee: Southern Nuclear Operating Company, Inc.
Facility: Joseph M. Farley Nuclear Plant, Unit 1
Location: Columbia, AL
Dates: October 10 -14, 2016
Inspector: Paula E. Cooper, Reactor Inspector
Approved by: Shakur A. Walker, Branch Chief Engineering Branch 3 Division of Reactor Safety
SUMMARY
Inspection Report (IR) 05000348/2016009; 10/10/2016 - 10/14/2016; Joseph M. Farley Nuclear Plant, Unit 1; Post-Approval Site Inspection for License Renewal.
The report covers an inspection conducted by a r egional inspector in accordance with the U.S. Nuclear Regulatory Commission (NRC) Inspector Manual Chapter (IMC) 2515, and NRC Inspection Procedure (IP) 71003, Post-Approval Site Inspection for License Renewal, dated July 1, 2016. Based on the sample selected for review, the inspectors determined that commitments, license conditions, and regulatory requirements associated with the renewed facility operating license were either being met, or where commitment actions had not been completed, that the licensee had administrative controls in place to ensure completion before the period of extended operation.
The NRC's program for overseeing the safe operati on of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 6.
No findings were identified during this inspection.
REPORT DETAILS
OTHER ACTIVITIES
4OA5 Other Activities
.1 Post-Approval Site Inspection for License Renewal (Phase 1)
a. Inspection Scope
Implementation of License Conditions and Commitments, including Aging Management Programs: The inspectors reviewed a sample of license renewal activities scheduled for the Unit 1 Fall 2016 refueling outage, which was the last outage prior to the period of extended operation (PEO). The objective of the inspection was to maximize observations of the actual implementation of license renewal activities before the beginning of the PEO (June 26, 2017), and verify that the licensee completed the necessary actions to: (a) comply with the conditions stipulated in the renewed facility operating license; (b) meet the license renewal commitments described in NUREG-1825, "Safety Evaluation Report (SER) Related to the License Renewal of the Joseph M. Farley Nuclear Plant, Units 1 and 2" (ADAMS Accession Number ML050630571); and (c) meet the future activities, including Aging Management Programs (AMPs), described in the Updated Final Safety Analysis Report (UFSAR) supplement submitted pursuant to
10 CFR 54.21(d).
The inspectors reviewed supporting documents; conducted interviews with licensee staff; observed in-process outage activities; and performed visual inspection of structures, systems, and components (SSCs) including those not accessible during power operation. The commitment items and AMPs selected for the inspection sample are summarized below based on their description in Appendix A of the License Renewal Application. The specific inspection activities conducted for each AMP are also described below. Specific documents reviewed are also listed in the report Attachment.
Commitment #6 - Reactor Vessel Internals (RVI) Program This commitment specified that the licensee will submit an inspection plan for the RVI Program for NRC review and approval prior to entering the PEO. The program will be used during the PEO to manage the effects of crack initiation and growth due to irradiation-assisted stress corrosion cracking; loss of fracture toughness due to irradiation embrittlement, thermal embrittlement, or void swelling; or changes in material properties (dimension) due to void swelling.
The inspectors reviewed correspondence submitted to the NRC to verify the commitment was in process as described in the licensee correspondence, and the NRC
SER.
Commitment #7 - Flux Detector Thimble Inspection Program This commitment specified that the new Flux Detector Thimble Inspection Program will be implemented prior to entering the PEO to formalize examinations already being performed. Specifically, this program will be used to identify loss of material due to fretting/wear in the detector thimbles.
The inspectors reviewed vendor correspondence and program documents, to verify the commitment was being implemented as described in the licensee correspondence, and the NRC SER.
Commitment #8 - External Surfaces Monitoring Program
This commitment specified that the new External Surfaces Monitoring Program will be implemented prior to entering the PEO. This program will include periodic visual inspections of external surfaces of carbon steel, low alloy steel, and other susceptible materials in components requiring aging management for license renewal.
The inspectors interviewed plant personnel and program owners during a containment walkdown to confirm the commitment was being implemented as described in the licensee correspondence, and the NRC SER.
Commitment #9 - Buried Piping and Tanks Inspection Program
This commitment specified that the new Buried Piping and Tank Inspection Program will be implemented prior to the PEO. This program will be used to manage the loss of material from external surfaces of in-scope pressure-retaining buried carbon steel piping and tanks and buried stainless steel and copper alloy piping during the PEO. In addition, this program will be consistent with the 10 attributes of the AMP described in NUREG-1801,Section XI.M34, with the exception that it also includes provisions for inspection of buried stainless steel and copper alloy piping.
The inspectors reviewed work orders and program documents, to verify the commitment was being implemented as described in the licensee correspondence, and the NRC SER.
Commitment #10 - One-Time Inspection Program This commitment specified that the One-Time Inspection Program will be implemented prior to the PEO. This program will include measures to verify the effectiveness of various other AMPs and confirm the absence of aging effects requiring management. During this refueling outage, the one-time inspection associated with the ultrasonic thickness measurements of the bottom of the condensate storage tank, as well as the eddy current examination of the Residual Heat Removal Heat Exchanger, was
performed.
The inspectors reviewed and observed portions of the work orders to verify the commitment was completed as described in the licensee correspondence, and the NRC SER.
Commitment #11 - Nickel Alloy Management Program This commitment specified that the licensee will submit an inspection plan for the NiCrFe Component Assessment (Nickel Alloy Management) Program for NRC review and approval at least 24 months prior to entering the PEO. This program will address the potential for primary water stress corrosion cracking in nickel alloy components exposed to the reactor coolant environment.
The inspectors reviewed correspondence submitted to the NRC, which was submitted 24 months prior to entering the PEO, to verify the commitment was completed as described in the licensee co rrespondence, and the NRC SER.
Commitment #12 - Inaccessible Power Cables Not Subject to 10 CFR 50.49 Environmental Qualification Requirements This commitment specified that the Inaccessible Power Cables Not Subject to 10 CFR 50.49 Environmental Qualification Requirements Program will be implemented prior to the PEO, with subsequent tests performed at least every 6 years thereafter. During this refueling outage, the licensee implemented the portion of the program associated with the inaccessible medium voltage cables that are simultaneously exposed to significant moisture and voltage.
The inspectors reviewed test results, procedures, and work orders to verify the commitment was completed as described in the licensee correspondence, and the NRC
SER.
Review of Newly-Identified SSCs: This inspection requirement will be completed during the Phase 2 implementation of IP 71003.
Descriptions of AMPs and Time-Limited Aging Analysis (TLAA) in the UFSAR Supplement: The review of the description of AMPs and TLAAs in the UFSAR supplement submitted pursuant 10 CFR 54.21(d) will be completed during the Phase 2 implementation of IP 71003.
Review of License Renewal Commitment Changes: This inspection requirement will be completed during the Phase 2 implementation of IP 71003.
b. Findings and Observations
No findings were identified.
4OA6 Management Meetings
.1 Exit Meeting Summary
On October 14, 2016, the inspector presented the inspection results to Cheryl A. Gayheart, Vice President, and other members of station staff. The inspectors verified that no proprietary information was retained by the inspectors or documented in this report.
ATTACHMENT:
SUPPLEMENTARY INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
Julie Collier, Licensing
Kassondra Moore, LR Engineering
Dan Meendering, LR Aging Management Program Coordinator
Scott Walden, LR Civil/ Seismic Tyler Campbell, LR Medium Voltage Cables
NRC
- P. Niebaum, Senior Resident Inspector
- K. Miller, Resident Inspector
LIST OF DOCUMENTS REVIEWED
Buried Piping and Tanks Inspection Program
- NMP-ES-036, Underground Pipe and Tanks Monitoring Program, Ver. 13
- NMP-ES-036-001, Underground Pipe and Tanks Monitoring Program Implementation, Ver. 10 WO#SNC356988, Install Pull Box 1AN1M211 and Connect Associated Conduits, 1/4/12
- Flux Detector Thimble Inspection Program
- FNP0-SYP-22.0, Flux Detector Thimble Inspection Program, Ver. 1.0
- Letter From Larry E Markel, Westinghouse, to Cheryl A. Gayheart, Southern Nuclear Operating
- Company, Joseph M. Farley Nuclear Plant, Transmittal of
- LTR-SEE-III-15-79, Flux Thimble Eddy Current Evaluation and
- USRS-15-9, Field Service Report for Farley 1R26, 6/18/15
- Nickel Alloy Management Program Letter From C.R. Pierce, Southern Company, to U.S. NRC, Joseph M. Farley Nuclear Plant -
- Units 1 and 2, License Renewal Commitment Item 11, 6/22/15
- Reactor Vessel Internals (RVI) Program Letter from C.R. Pierce, Southern Nuclear, to U.S. NRC, Joseph M. Farley Nuclear Plant -
- Unit 1 and 2, License Renewal Commitment Item 6, 8/12/15
- One-Time Inspection Program WO#SNC799315, UT Thickness on Bottom of CST, 10/9/16
- AMP Aging Management Programs
- BWRVIP Boiling Water Reactors Vessel and Internals Project
- IP Inspection Procedure
- PEO Period of Extended Operation
- SER Safety Evaluation Report
- SSC Systems, Structures, or Components
- TLAA Time-Limited Aging Analysis
- UFSAR Updated Final Safety Analysis Report
- UT Ultrasonic Examination
- WO Work Orders