ML24247A110

From kanterella
Jump to navigation Jump to search
Corporate Notification Letter Aka 210-day Letter NUREG Rev 12
ML24247A110
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 09/05/2024
From: Matthew Endress
NRC/RGN-II/DRS/OLB
To: Dean E
Southern Nuclear Operating Co
References
50-364/25-301 50-364/OL-25
Download: ML24247A110 (1)


Text

Edwin D Dean, Site Vice President Southern Nuclear Operating Company, Inc.

Joseph M. Farley Nuclear Plant 7388 North State Highway 95 Columbia, AL 36319-0470

SUBJECT:

JOSEPH M. FARLEY NUCLEAR PLANT - NOTIFICATION OF LICENSED OPERATOR INITIAL EXAMINATION 05000348/2025301 AND 05000364/2025301

Dear Edwin Dean:

During a telephone conversation on September 3, 2024, between Mr. S. Jackson, Nuclear Operations Instructor, and Mr. Shane Battenfield, Operations Engineer, arrangements were made for the administration of operator licensing examinations at the Farley Nuclear Plant. The on-site preparatory week is scheduled for the week of August 3, 2025. The operating test is scheduled to be administered during the weeks of September 7 - 14, 2025. The written examination is scheduled to be administered the week of September 14, 2025.

As agreed during the telephone conversation, your staff will prepare both the operating test and written examination based on the guidelines in Revision 12 of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The U.S. Nuclear Regulatory Commission (NRC) regional office will discuss with your staff any changes that might be necessary before the examinations are administered. Your staff has also agreed to make copies of all examination materials that are necessary for administering the examination.

To meet the above schedule, it will be necessary for your staff to furnish the operating test outline by April 10, 2025. The previously assigned Chief Examiner, Mr. Mike Kennard, provided the written examination outline to your staff in March 2024. The operating test, written examination, and the supporting reference materials identified in NUREG-1021, Examination Standard (ES)-2.1, Preparing for Operator Licensing Initial Examinations, will be due by June 24, 2025. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized representative of the facility licensee shall approve the outline, examination, and test before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use.

We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Delays in receiving the required materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be cancelled or rescheduled.

To conduct the requested written examinations and operating tests, your staff will need to provide adequate space and accommodations and to make the simulation facility available on the dates noted above. In accordance with ES-3.5, Administering Operating Tests, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, September 5, 2024

D. Dean 2

and levels) generated during the dynamic operating tests until the NRC takes licensing action on all the applications and any adjudicatory actions on any hearing demands are complete.

ES-1.2, Guidelines for Taking NRC Examinations, contains a number of NRC guidelines for the written examinations and operating tests as they are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver or excusal requests (if any) (Office of Management and Budget (OMB) control number 3150-0090) at least 60 days before the first examination date (if possible). Contact Mr. Battenfield to determine the method for submission of the waiver or excusal requests. Preliminary reactor operator and senior reactor operator license applications (OMB control number 3150-0090) and medical certifications (OMB control number 3150-0024) should be submitted at least 30 days before the first examination date. If the NRC does not receive the preliminary applications at least 30 days before the examination date, a postponement may be necessary. Final, signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date.

Although the guidelines for waiver or excusal requests call for their receipt at least 30 days before the first examination date (preliminary) and 14 days before the first examination date (final), the requests should be submitted as early as possible in the process (see the 60-day guideline above). Resolutions resulting from verbal inquiries by the facility licensee to the NRC are not binding. Submittals addressing waivers or excusals, or both, should be in writing (i.e., using NRC Form 398 or as directed by Mr. Battenfield when contacting him to determine the method for submission). The NRC will document its final decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398 submitted for the applicant. The NRC will not provide its decision until the final application is submitted to the agency.

Paperwork Reduction Act Statement This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the OMB, approval number 3150-0018.

The burden to the public for these voluntary information collections is estimated to average 2,250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> per examination or response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collections. Send comments regarding this information collection to the FOIA, Library, and Information Collections Branch (T6-A10M),

U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the OMB reviewer at: OMB Office of Information and Regulatory Affairs (3150-0018), Attn: Desk Officer for the Nuclear Regulatory Commission, 725 17th Street, NW Washington, DC 20503; e-mail:

oira_submission@omb.eop.gov.

Public Protection Notification The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless the document requesting or requiring the collection displays a currently valid OMB control number.

D. Dean 3

In accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding, a copy of this letter and its enclosures will be available electronically for public inspection through the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible on the NRCs Web site at http://www.nrc.gov/reading-rm/adams.html.

Thank you for your cooperation in this matter. Mr. Jackson has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Battenfield at (918-688-4528), (Internet E-mail: shane.battenfield@nrc.gov), or me at (404) 997-4718, (Internet E-mail:

matthew.endress@nrc.gov).

Sincerely, Matthew Endress, Chief Operations Branch 2 Division of Reactor Safety Docket Nos.: 50-348, 50-364 License Nos.: NPF-2, NPF-8 cc: Distribution via ListServ Signed by Endress, Matthew on 09/05/24

ML24247A110 X

SUNSI Review X

Non-Sensitive

Sensitive X

Publicly Available

Non-Publicly Available OFFICE RII/DRS RII/DRS RII/DRS NAME K. Wallace V. Furr M. Endress DATE 09/03/24 09/05/24 09/05/24