IR 05000348/2023010

From kanterella
Jump to navigation Jump to search
Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 05000348/2023010 and 05000364/2023010
ML23177A046
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 06/29/2023
From: James Baptist
Division of Reactor Safety II
To: Brown R
Southern Nuclear Operating Co
References
IR 2023010
Download: ML23177A046 (1)


Text

SUBJECT:

JOSEPH M. FARLEY NUCLEAR PLANT - COMPREHENSIVE ENGINEERING TEAM INSPECTION (CETI) BASELINE INSPECTION REPORT 05000348/2023010 AND 05000364/2023010

Dear R. Keith Brown:

On June 5, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Joseph M. Farley Nuclear Plant and discussed the results of this inspection with Mr. Delson Erb and other members of your staff. The results of this inspection are documented in the enclosed report.

Eight findings of very low safety significance (Green) are documented in this report. Eight of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Joseph M. Farley Nuclear Plant.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at Joseph M. Farley Nuclear Plant.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

June 29, 2023

Sincerely, James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos. 05000348 and 05000364 License Nos. NPF-2 and NPF-8

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000348 and 05000364

License Numbers:

NPF-2 and NPF-8

Report Numbers:

05000348/2023010 and 05000364/2023010

Enterprise Identifier:

I-2023-010-0041

Licensee:

Southern Nuclear Operating Co., Inc.

Facility:

Joseph M. Farley Nuclear Plant

Location:

Columbia, AL

Inspection Dates:

April 10, 2023 to April 28, 2023

Inspectors:

B. Bishop, Sr. Project Engineer

S. Downey, Senior Reactor Inspector

T. Fanelli, Senior Reactor Inspector

C. Franklin, Reactor Inspector

L. Jones, Senior Reactor Inspector

J. Lizardi-Barreto, Reactor Inspector

G. Nicely, Electrical Contractor

D. Terry-Ward, Reactor Inspector

Approved By:

James B. Baptist, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a comprehensive engineering team inspection (CETI) at Joseph M.

Farley Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Justify the Quality and Reliability for Agastat relays Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000348,05000364/2023010-01 Open/Closed

[H.3] - Change Management 71111.21M The NRC identified a Green finding and associated Non-cited Violation (NCV) of Technical Specifications (TS) 5.4.1.a, "Procedures," and Regulatory Guide (RG) 1.33, Quality Assurance Program Requirements (Operation), dated November 1972, for failure to establish an effective maintenance strategy to assure the quality and reliability of Agastat T3A control relays used in the safety-related systems. The RG in Appendix A,Section I, requires in part, that preventive maintenance schedules should be developed to specify inspection of replacement parts that have a specified lifetime.

Failure to Assure the MCC Component Installation Design Requirements Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000348,05000364/2023010-02 Open/Closed None (NPP)71111.21M The NRC identified a Green finding and associated NCV of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion III, Design Control. For the failure to assure that components could perform their safety functions for the time required in the environmental conditions developed inside the motor control centers (MCCs) located in emergency diesel generator (EDG) room.

Failure to Meet the 10 CFR 50.55a(b)(3)(ii) Valve Program Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000348,05000364/2023010-03 Open/Closed

[H.6] - Design Margins 71111.21M The NRC identified a Green finding and associated NCV of Title 10 CFR Part 50.55a, Codes and Standards, with four examples, for the licensee failure to meet the conditions of the station Motor Operated Valve (MOV) program requirements.

Failure to Assure the Seismic Design of Class 1E Battery Racks Cornerstone Significance Cross-Cutting Aspect Report Section

Initiating Events Green NCV 05000348,05000364/2023010-04 Open/Closed None (NPP)71111.21M The NRC identified two examples of a Green finding and associated NCV of Title 10 CFR Part 50, Appendix B, Criterion III, "Design Control," for the licensee failure to assure the seismic design of Class 1E battery racks. 1. Modifications of the battery racks resulted in a loss of configuration control. 2. The seismic qualification report of record did not assure that the qualification requirements were met.

Failure to Correct Alternate Source Term Leakage Test Requirements Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000348,05000364/2023010-05 Open/Closed

[P.2] -

Evaluation 71111.21M The NRC identified a Green finding and associated NCV of Title 10 CFR Part 50 Appendix B Criterion XVI, "Corrective Actions," for the licensee failure to correct a violation for properly categorizing the MOVs 8809A/B in the Inservice Test (IST) program and begin testing required for the alternate source term (AST) leakage paths.

Failure to Identify Corrosion on MOV 3209B Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000348,05000364/2023010-06 Open/Closed

[P.1] -

Identification 71111.21M The NRC identified a Green finding and associated NCV of Title 10 CFR Part 50 Appendix B Criterion XVI, "Corrective Actions," for the licensee failure to identify corrosion on MOV 3209B that affected its structural integrity.

Inadequate Work Instructions for Cable Bend Radius Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000348,05000364/2023010-07 Open/Closed

[H.5] - Work Management 71111.21M The NRC identified a Green finding and associated NCV of Title 10 CFR Part 50 Appendix B Criterion V, "Instructions, Procedures, and Drawings," for the licensee failure to include precautions about cable bend radius in work orders to replace the Class 1E batteries.

Inadequate Thermal Overload Calculations and Use of Related Software Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000348,05000364/2023010-08 Open/Closed

[H.5] - Work Management 71111.21M The NRC identified a Green finding and associated NCV of Title 10 CFR Part 50, Appendix B,

Criterion III, Design Control, for the licensee failure to assure that Thermal Overload (TOL)relays for MOV circuits were properly sized and documented in quality-controlled calculations and the use of a nonfunctional Plant Data Management System (PDMS) to automatically calculate TOL specifications.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

===71111.21M - Comprehensive Engineering Team Inspection The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Structures, Systems, and Components (SSCs) (IP section 03.01)===

For each component sample, the inspectors reviewed the licensing and design bases. The inspectors reviewed a sample of operator actions, corrective action program documents, internal and external operating experience, test records, preventive maintenance records, work orders, aging management programs, and performed a walkdown of the component or procedure. Additional component specific design attributes reviewed by the inspectors are:

(1) Ultimate Heat Sink

Performance testing of the service water system and UHS (71111.21M, appendix E, UHS item c)

Service water system piping integrity review (71111.21M, appendix E, UHS item d)

Service water pond (71111.21M, appendix E, UHS containment device item a)

(2) Service Water to Auxiliary Building Header Isolation Valves ( Q1P16MOV3084A, Q1P16MOV3084B, Q2P16MOV3084A, Q2P16MOV3084B)

Compliance with UFSAR, TS, and TS Bases

Visual inspection during walkdown of various components in system

Surveillance testing and maintenance records

Aging management

(3) U1 Motor Driven Auxiliary Feedwater to 1B Steam Generator Isolation Valve (Q1N23MOV3764D)

Compliance with Updated Final Safety Analysis Report (UFSAR), Technical Specifications (TS), and TS Bases

Visual inspection during walkdown of various components in system

Setup calculation assumption agreement with installed configuration

Surveillance testing & maintenance records

Conformance with manufacturer instructions for installation, maintenance, testing and operation.

Time critical operator action E01: Response to worst case, MFW line rupture Stop AFW flow to faulted SG a.

Verified the adequacy of the operating procedures to support the design and verify that key operator actions can be performed within the constraints of the design analyses.

b.

Observed demonstration in the simulator used to validate operator actions.

(4) U2 Service Water to Motor Driven Auxiliary Feedwater Isolation Valve (Q2N23MOV3209B)

Compliance with Updated Final Safety Analysis Report (UFSAR), Technical Specifications (TS), and TS Bases

Visual inspection during walkdown of various components in system

Setup calculation assumption agreement with installed configuration

Calibration of demand signal

Surveillance testing & maintenance records

Conformance with manufacturer instructions for installation, maintenance, testing and operation.

Torque/Thrust, voltage load flow and voltage drop, and thermal overload relay sizing, to verify valve and actuator functionality is within acceptable limits.

Reviewed Electrical/Mechanical interfaces to ensure voltages from electrical calcs are translated correctly into the mechanical calcs.

Maintenance and diagnostic testing procedures and latest test results to verify valve and actuator functionality is within acceptable limits.

Time critical operator action E02: Response to loss of normal AFW supply from CST, Align AFW suction to SW a.

Verified the adequacy of the operating procedures to support the design and verify that key operator actions can be performed within the constraints of the design analyses.

b.

Observed demonstration in the simulator used to validate operator actions.

(5) RCS Filter Q1E21F003 and Q2E21F003

Compliance with Updated Final Safety Analysis Report (UFSAR)

Visual inspection during walkdown of various components in system

Walkdown of procedures and equipment used to change out filter

(6) HPR/RHR MOV Unit 2 Q2E11MOV8706A/B

Design Basis documents and calculations including Torque/Thrust, voltage load flow and voltage drop, protective device settings, including thermal overload relay sizing, and EQ documents to verify valve and actuator functionality is within acceptable limits

Reviewed Electrical/Mechanical interfaces to ensure voltages from electrical calcs are translated correctly into the mechanical calcs.

Maintenance and diagnostic testing procedures and latest test results to verify valve and actuator functionality is within acceptable limits.

Time critical operator action E10: Response to dilution during refueling, Isolate dilution path and stop RMW pumps a.

Verified the adequacy of the operating procedures to support the design and verify that key operator actions can be performed within the constraints of the design analyses b.

Observed demonstration in the simulator used to validate operator actions.

(7) HPI U2 Q2E21MOV8803B

Design Basis documents and calculations including Torque/Thrust, voltage load flow and voltage drop, protective device settings, including thermal overload relay sizing, and EQ documents to verify valve and actuator functionality is within acceptable limits.

Reviewed Electrical/Mechanical interfaces to ensure voltages from electrical calcs are translated correctly into the mechanical calcs.

Maintenance and diagnostic testing procedures and latest test results to verify valve and actuator functionality is within acceptable limits.

(8) Emergency Diesel Generators (EDG) 1B/2B

Reviewed calculations including voltage load flow and voltage drop, to verify EDG functionality is within acceptable limits.

Latest and prior Integrated Safeguards Testing results to verify compliance with industry and regulatory compliance to verify that the EDG and supporting systems will operate within design basis during a design basis event.

OE applicability from Calvert Cliffs 2010 white violation involving Agastat time delay relay failures in the low lube oil system to determine if the same issue could occur at Farley.

(9) Unit 1 RHR Motor-Operated Valves (MOVs) 8811 and 8812

Compliance with UFSAR

Visual inspection during walkdown of various components in system

Design Basis documents and calculations including Torque/Thrust to verify valve and actuator functionality is within acceptable limits.

Maintenance and diagnostic testing procedures and latest test results to verify valve and actuator functionality is within acceptable limits.

(10) Unit 1 and 2 Auxiliary Building 125 V Batteries and Turbine Driven Auxiliary Feed Water System (TDAFW) 125V Batteries

Compliance with Updated Final Safety Analysis Report (UFSAR)

Visual inspection during walkdown of battery racks, connectors, cables and cell jars.

Review of seismic qualification reports and as-built configuration.

(11) Problem Identification and resolution sample NCV 05000348,05000364/2021011-01, Failure to Properly Categorize MOVs 8809A

& B or Check Valve Q1(2)E11V0028 in the IST Program

Reviewed corrective actions

Compliance with UFSAR

Modifications (IP section 03.02) (1 Sample)

(1) SNC1153264, Unit 1 Encapsulation Vessel Removal from RHR and CS Sump MOVs 10 CFR 50.59 Evaluations/Screening (IP section 03.03) (6 Samples)
(1) SNC1123286 - U1 SW Header Drain Line Addition
(2) SNC1125459 - 2C SW Minimum Flow Line Reinforcement Sleeve Removal
(3) SNC1091429 - U2 Digital Rod Position Indication Advance Display
(4) SNC1127095 - Unit 2 TDAFWP Steam Admission Valve Thrust Washer Shim
(5) SNC1127557 - SF Cask Crane Design
(6) SNC1141168 System R11 - 1B Start-up Transformer Replacement

Operating Experience Samples (IP section 03.04) (2 Samples)

(1) RIS-22-02 Operational Leakage
(2) Information Notice IN 2012-006, Ineffective Use of Vendor Technical Recommendations

INSPECTION RESULTS

Failure to Justify the Quality and Reliability for Agastat relays Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000348,05000364/2023010-01 Open/Closed

[H.3] - Change Management 71111.21M The NRC identified a Green finding and associated Non-cited Violation (NCV) of Technical Specifications (TS) 5.4.1.a, "Procedures," and Regulatory Guide (RG) 1.33, Quality Assurance Program Requirements (Operation), dated November 1972, for failure to establish an effective maintenance strategy to ensure the quality and reliability of Agastat T3A control relays used in the safety-related systems. The RG in Appendix A,Section I, requires in part, that preventive maintenance schedules should be developed to specify inspection of replacement parts that have a specified lifetime.

Description:

The team reviewed engineering justification SNC921616, "Justification for Extension of Expected Service Life for non-Environmental Qualified (EQ) Agastat E7000 Series relays." The team reviewed the sites licensing basis for Class 1E components, which specified that their quality and reliability shall be assured (Institute of Electrical and Electronic Engineers (IEEE) 279-1971, Criteria for Protection Systems for Nuclear Power Generating Stations Sections 4.3 and 4.4 and IEEE 308-1971, IEEE Standard Criteria for Class 1E Power Systems for Nuclear Power Generating Stations Sections 4.8 and 5.4).

The team determined that a failure of a T3A Agastat relay at Calvert Cliffs installed in the same circuits (the EDG lube oil trip circuit) demonstrated quality and reliability concerns after approximately 13 years due to timing drift after substituting a performance monitoring program for the Agastat relays. The NRC conveyed the concerns in information notice 2012-006.

At Farley, the 16-year-old T3A relays replacement period was extended to 30 years based on the SNC921616 justification. The licensee discontinued the vendor recommended 10-year replacement preventive maintenance (PMs) and substituted a performance monitoring program. The team noted that other than a starting and running the EDG bi-monthly, the relay has not had any effective maintenance strategy for PMs, calibrations, or inspections for timing drift. The team's observations were captured in the corrective action program.

In addition, the justification used EPRI report TR300200541 as an input into these decisions. The EPRI report specified that the thermal life for a normally de-energized Agastat can exceed 60 years for mild environments. However, the licensee justification recognized other potential failure mechanisms that the EPRI report does not seem to have considered, such as, degradation of the relay contacts and their associated springs. The justification speculated a recommended life of 30 years instead. The team determined that failure of the diesels due to age related timing drift was a likely failure mechanism in this type of circuit and may not be identified as an actual relay failure. The team determined that the licensees analysis, lack of PMs, and trending did not justify the Agastat reliability for a longer period than what was determined during the original Agastat testing.

Corrective Action References: 109678694, 10967697

Performance Assessment:

Performance Deficiency: The licensees failure to justify the continued quality and reliability of Agastat type 7000 relays for an extended period of 30 years was a performance deficiency. If left uncorrected, it would have the potential to lead to a more significant safety concern in that lack of PMs and inspections of the T3A relay could lead to failure and affect the EDG operation and EOP implementation.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the team determined the design deficiency resulted in a condition where the team had reasonable doubt that the Agastat relays could continue to operate for 30 years without adversely affecting the EDG operation.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Exhibit 2

- Mitigating Systems Screening Questions, Item A. Mitigating SSCs and PRA Functionality (except Reactivity Control Systems), specified that if the finding affected the design or qualification of a mitigating SSC, but it maintained its operability or PRA functionality then it screens to GREEN.

Cross-Cutting Aspect: H.3 - Change Management: Leaders use a systematic process for evaluating and implementing change so that nuclear safety remains the overriding priority.

Enforcement:

Violation: TS 5.4.1.a requires in part, that written procedures shall be established, implemented, and maintained covering the applicable procedures recommended in RG 1.33, Appendix A, November 1972. RG 1.33, Appendix A, November 1972,Section I, requires in part, that preventive maintenance schedules should be developed to specify inspection of replacement parts that have a specified lifetime. The vendor specified lifetime is 25,000 operations or 10 years from the date of manufacture, whichever occurs first, which was exceeded in February of 2017.

Contrary to the above, since June, 2009, the date of installation, the licensee failed to develop and implement a preventive maintenance schedule, or an effective maintenance strategy to ensure the quality and reliability of Agastat control relays in the safety related Unit 2B EDG system.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Assure the MCC Component Installation Design Requirements Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000348,05000364/2023010-02 Open/Closed None (NPP)71111.21M The NRC identified a Green finding and associated NCV of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion III, Design Control, for the failure to assure that components could perform their safety functions for the time required in the environmental conditions developed inside the motor control centers (MCCs) located in the emergency diesel generator (EDG) room.

Description:

The team identified that there are five MCCs in the rooms adjacent to the EDGs. The components inside these five MCCs were specified and procured for operation in a maximum internal MCC temperature of 104 °F, which is the standard commercial qualification for electrical components without specific upgrades for higher temperatures. The design basis temperature in the EDG room general area, outside the MCCs, was specified to be 122 °F. The internal MCC temperature would significantly exceed 122 °F. The temperature rise would be proportional to the dissipated heat from the cumulative wattage of the components inside each MCC cubicle. The licensee documented an evaluation in June 1989, a self-initiated Safety System Assessment (SSS) of the service water intake structure (SWIS), ES-89-1501, identified this potential concern with the long-term operation of the MCCs to support the EDG. The evaluation ES-89-1501, Enclosure 1 item G, Review of Diesel Generator Building HVAC Design (Action II.B), noted that this evaluation specified that the MCCs components were capable of operation at 122 °F but it did not address the higher temperatures inside the MCCs. Enclosure 1 specified that the formal analysis to support this statement would not be completed until June 1990, however, when the team requested the analysis to independently assess the methodology, Farley was unable to locate the formal analysis.

The team determined that the long-term operation of MCC components in the EDG rooms was in question because the licensee was unable to demonstrated acceptability.

Corrective Action References: 10967778

Performance Assessment:

Performance Deficiency: The failure to assure that components could perform their safety functions for the time required in the environmental conditions developed inside the MCCs located in the EDG room was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the deficiency resulted in a condition where the team had reasonable doubt regarding the availability, reliability and capability of the equipment supported by the MCCs during a higher than rated temperature environment.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Exhibit 2

- Mitigating Systems Screening Questions, Item A. Mitigating SSCs and PRA Functionality (except Reactivity Control Systems), specified that if the finding affected the design or qualification of a mitigating SSC, but it maintained its operability or PRA functionality then it screens to GREEN.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, states, in part, design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, using alternate or simplified calculational methods, or by the performance of a suitable testing program.

Contrary to the above, since June 1990, the licensee failed to provide for measures to ensure that the components inside the MCCs controlling the EDG could perform their safety functions by the performance of design reviews, using alternate or simplified calculational methods to demonstrate that they would not adversely affect EDG operation.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Meet the 10 CFR 50.55a(b)(3)(ii) Valve Program Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000348,05000364/2023010-03 Open/Closed

[H.6] - Design Margins 71111.21M The NRC identified a Green finding and associated NCV of Title 10 CFR Part 50.55a, Codes and Standards, with four examples, for the licensee failure to meet the conditions of the station MOV program requirements.

Description:

Example one; Title 10 CFR Part 50.55a(b)(3)(ii), OM condition: Motor-Operated Valve (MOV) testing, required in part that licensees must establish a program to ensure that MOVs continue to be capable of performing their design basis safety functions. Southern Company established several MOV program procedures to satisfy the requirements of this rule, which are applicable to Farley. One of these procedures, NMP-ES-017-002, Motor Operated Valve Design Basis Setpoint Determination, Section 4.8, Valve Maximum Thrust and Torque Limits, stated, in part, the valve assembly is subject to structural limitations that must be addressed in establishing a value for the maximum valve operating torque and thrust. The structural capability of the MOV SHALL be established such that no physical damage could occur that would adversely affect the ability of the MOV to perform a safety function. It further stated that:

the structural limits are determined by stress analysis of each of the loaded parts including the body, bonnet, bonnet bolting, yoke, stem, seats, operator and yoke bolting. Loads and load combinations SHALL appropriately represent the conditions (e.g., thrust, torque, line pressure, differential pressure, temperature, or seismic) to which the MOV could be subjected. The Valve Maximum Thrust /

Torque Limits in the open and close directions are obtained from the Maximum Allowable Valve (Weak Link) calculations. In addition, the valve may have a Seismic Thrust Limit that has been evaluated separately from the Weak Link.

The valves structural capability (valve maximum thrust or torque limit) is one of several factors used when calculating MOV margin, as shown in another MOV program procedure, NMP-ES-017-003, Motor Operated Valve Performance Trending and Margin Management. The margin is then used to determine a periodic verification test frequency as part of the licensees committed MOV program. The licensee failed to determine the limiting structural capabilities used to establish the margins for each design basis safety function (open and close as applicable). In response to Generic Letter 89-10, in a letter dated December 28, 1989, the licensee stated that valve vendors and the FNP designers are requested to provide certain design data and that typical of the data requested are maximum valve and actuator thrust ratings. The licensee was using valve structural limits provided to them by the vendors or designers, however, when several source calculations were reviewed by the team it was evident that the calculations had not evaluated internal components of the valves that are required to perform the MOVs design basis safety functions. There were valve components that would have to withstand the stem thrust load that did not have their structural thrust limits determined by stress analysis in the source calculations. This was contrary to the licensees NMP-ES-017-002 requirement to determine the thrust limits for each valve. Since the licensee cannot demonstrate the performance of the MOV active safety functions in accordance with 10 CFR Part 50.55a, the MOVs are in an unanalyzed condition. The team determined that the licensee could not support any operability considerations using margins based on unproven assumptions.

The team reviewed the licensee condition report (CR) 10980342. The team found the some of the content of the CR was inaccurate and contrary to the violation. For instance, the CR stated, that the MOVs have a structural value for the open and closed directions, which are used as design limits. These limits have been developed since the initial implementation of the MOV program under GL 89-10. These limits have been developed from actual Farley test data, vendor supplied data, specific weak link calculations from the valve manufacturer, actuator vendor specific thrust and torque limits, etc. The team was able to determine that these values were taken from seismic calculations that did not, in any way, account for the active components necessary to provide the MOV safety functions. In addition, it stated, that the MOV program valve/actuator design inputs for open and close weak link values are acceptable to ensure MOV performance. The team determined program valve/actuator design inputs for open and close weak link values were not determined by a weak link analysis and were not demonstrated to bound the critical components necessary to perform any of the MOV safety functions. Further, the CR based operability on the historical performance of the MOVs. The team determined that the MOV performance described did not include the design basis conditions required by 10 CFR 50.55a, since the testing relied upon was not performed under design basis conditions and the, at this point unknown, structural limits may be challenged during the design conditions.

After the onsite inspection ended, the licensee found that Westinghouse electric company (WEC) had some seismic specific analyses for the 8000 series MOVs and some seismic specific analyses performed by others for the 3000 series MOVs, None of the analyses addressed the valve components that supported the active safety functions etc. as described above in NMP-ES-017-002. Some of the expected active functions included, but were not limited to, the stem for the close stroke and the stem-to-disc connection for the open stroke. The team determined that single value used by the licensee for both directions form PDMS was not demonstrated to be suitable to bound the structural limits for the MOV safety functions.

The team determined that the failure to stipulate the limiting margins based on the structural capability of the valve active components was an example of the performance deficiency.

Corrective Actions: CR 10967773, CR 10980342: The licensee determined the MOVs were operable. However, the violation must be placed in the corrective action program to restore compliance with the rule 10 CFR 50.55a(b)(3)(ii). The Condition Report (CR) did not recognize the unanalyzed condition that exists since their calculated margins reviewed were not based on the active components necessary to perform the valve safety functions. Complete evaluations of the limiting structural capabilities of valve components need to be performed of the MOVs design basis safety functions. In addition, the CR included language that indicated the licensee belief that it was not necessary to address the specific components necessary to actively accomplish the MOV design basis safety functions. The CR justified the lack of structural analyses because the limits used have been developed from actual Farley test data, vendor supplied data, specific weak link calculations from the valve manufacturer, actuator vendor specific thrust and torque limits, etc., The CR, as written, appeared to justify the currently in-use structural limits without compliance with established licensee programmatic controls for performing the limiting structural analyses which are intended to comply with the MOV program requirement in 10 CFR 50.55a(b)(3)(ii).

Example two; One of the required safety functions of the RHR system is to establish long-term recirculation for reactor cooling after a loss of coolant accidents (LOCA). The containment sump MOVs 8811A/B and MOV8812A/B must open and close to perform this active safety function. Until revision 10 of calculation SM-90-1653-003, the licensee considered approximately 469 psid as the maximum DP across these valves in accordance with Westinghouse WCAP 13097, Volume 3, System Operating Basis for Motor-Operated Valves, Rev. 0. The WCAP was published as part of recommendations for implementing Generic Letter (GL) 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance."

Section 5.2, Design Basis Review, concerned pressure buildup in the RHR piping system at the MOV 8811 and 8812 due to bypass leakage from the piping systems interconnected with the Reactor Coolant System. In addition, it was Identified the RHR piping system can reach these pressures when the RHR pumps are in min-flow recirculation. For design purposes, the potential pressure would be limited by the allowed leakage of the valves and the setpoint of the pressure relief valve in this piping system. The team noted that the allowed leakage across valves in the relevant piping system was 5 gallons per minute, enough to cause this issue. The GL 89-10 stipulations were incorporated into 10 CFR Part 50.55a as MOV requirements.

In 2010, after revision 10 of SM-90-1653-003, the licensee changed the design basis maximum DP of 469 psid to a DP of 69 psid without justifying the change in accordance with 10 CFR Part 50.59 Changes, tests and experiments.. The licensee did not document how or why the change occurred. As a result of the inspection, the licensee determined the valves could be required to open at the 469 psid DP. The prior change was not justified. With the MOV parameters known at the time of the inspection, a negative open margin existed. The MOV motor torque could not meet higher torque required by the higher DP. The higher DPs require higher MOV actuator thrust to successfully operate. To evaluate operability at the time of the inspection, the licensees used test data that was identified by them to be inaccurate.

Because of the significant loss of margin in several valves, the licensee had to change the inputs and methodology used in their calculations to gain a small amount of positive margin. The licensee program required more frequent testing for these valves.

The team determined that the failure to maintain design basis for containment sump valves required DP was an example of the performance deficiency.

Corrective Actions (CR 10966977, CR 10979536): the licensee changed the inputs and methodology used in their calculations to gain a small amount of positive margin.

Example three; Farley lost design control measures for installed MOV brakes. The installed brakes were removed from the site electrical and MOV programs design basis documents without justification. The site did not know that motor brakes were still installed on these MOVs and lost track of the brake specifications and related data. The site cannot produce the letter from 1994 where site claimed that Limitorque stated that the effects of brakes failures would be bounded by a 25% motor torque reduction to determine acceptable MOV margins. The team noted that the brakes are wired in parallel with the motors making them more likely to fail electrically during a design basis accident when plant voltages are unstable hence the design requirement for a 25% torque reduction.

The team reviewed calculation SM-90-1653-002, Attachment C, that specified that there were 14 Class 1E MOV actuators in each unit with installed motor brakes, including inspection sample valves Q1(2)P16MOV3209A&B. The team noted that the site has not maintained the maintenance quality of the brakes. This adversely affects the brakes' reliability and increases their adverse effects on torque reduction. Limitorque maintenance update 92-2 stated, in part, that motor brakes need to be adjusted and maintained for proper operation. It was the brakes proper mechanical operation that limited the torque reduction to 25%.. The lack of brake quality increased the likelihood that brake failure could significantly exceed the 25% torque reduction claimed by the licensee.

In addition, with brakes applied to the motor, the reduced MOV rpm will increase the MOV stroke times, some, significantly. The subject motors have maximum allowable stroke times. This effect on stroke time has not been addressed. Since the brakes and motors are wired in parallel, potential higher currents from degraded brakes during DBAs could cause TOL relays to trip causing the MOVs to fail.

The team determined that the failure to maintain design control measures for maintaining configuration of motor brakes installed on MOVs was an example of the performance deficiency.

Corrective actions:CR 10967483: Farley performed preliminary re-runs of the applicable MIDAS calcs with the 25% torque reduction and determined a significant reduction in margin that required a change to testing frequencies. If left uncorrected, it would have the potential to lead to a more significant safety concern in that MOVs that have installed motor brakes could adversely affect MOV operation and EOP implementation.

Example four; Generic letter 89-10 Attachment A and Supplement 6 gave notice that rotor degradation must be addressed in the MOV program. The PWR and BWR licensee owners groups developed reports for the inspection of this phenomenon and provided examples for when the rotors are considered degraded or failed. The licensee created procedure NMP-ES-017-009 based on the owners group report (BWROG-TP-09-005, Inspection of Motor Operated Valve Limitorque AC Motors with Magnesium Rotors.) This procedure provided visual acceptance criteria for degraded rotors to ensure MOV operability. The procedure established the conditional visual criteria that reveal the onset of degradation. Further, the owners group documents specified that degradation could lead to MOV failures during operation where more severe conditions may exist. The team noted that the sump isolation MOVs were removed from there protective shells and the sump valve rooms are a location where more severe conditions could exist.

The team sampled inspection reports of the sump isolation MOVs that have magnesium rotors. The report SNC1047269, dated 9/18/2022, for MOV-8811 documented no degradation when compared to the acceptance criteria. The as found condition was recorded as superior. The teams review of the photographic evidence however, revealed that the magnesiums corrosion on both ends of the rotor exceeded the degraded examples in the procedure and the owners group reports. The report SNC479239, dated 2/27/2014, for MOV-8812 also documented no degradation and was removed from the inspection program without photographic evidence. The completed procedure for MOV-8812 also reported no degradation and thus was removed from the program. The as found condition was recorded as satisfactory, which was below the superior rating record for 8811. The team believed removing the motor from the magnesium inspection program was in error.

The team determined that the documented degradation together with the modification that removed MOV protective shells that insulated the MOVs from severe conditions could cause the MOVs to fail in a DBA.

The team determined that the failure to identify magnesium rotor degradation was an example of the performance deficiency.

Corrective actions: CR 10979515: The licensee entered this into the corrective action program to re-evaluate how the visual inspections are performed.

Corrective Action References: CR 10967773, CR 10980342, CR 10966977, CR 10979536, CR 10967483, CR 10979515

Performance Assessment:

Performance Deficiency: The licensee failure to meet the conditions of the station MOV program requirements was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to meet the MOV program requirements adversely affected the availability, reliability, and capability of MOVs required to respond to initiating events to prevent undesirable consequences.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Exhibit 2

- Mitigating Systems Screening Questions, Item A. Mitigating SSCs and PRA Functionality (except Reactivity Control Systems), specified that if the finding affected the design or qualification of a mitigating SSC, but it maintained its operability or PRA functionality then it screens to GREEN. The licensee determined they had reasonable assurance of MOV operability given the historical performance of the valves under non-design basis conditions.

Cross-Cutting Aspect: H.6 - Design Margins: The organization operates and maintains equipment within design margins. Margins are carefully guarded and changed only through a systematic and rigorous process. Special attention is placed on maintaining fission product barriers, defense-in-depth, and safety related equipment.

Enforcement:

Violation: 10 CFR Part 50.55a(b)(3)(ii) required in part that licensees must establish a program to ensure that MOVs continue to be capable of performing their design basis safety functions.

Contrary to the above, the licensee did not establish a program that ensured that MOVs continue to be capable of performing their design basis safety functions. Specifically, the program, as implemented, did not ensure the MOVs structural limits would not be exceeded, during the performance of their design basis safety functions, did not ensure to maintain design basis for containment sump valves required DP, did not ensure design control measures for maintaining configuration of motor brakes installed on MOVs, and did not ensure the identification of magnesium rotor degradation.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Assure the Seismic Design of Class 1E Battery Racks Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000348,05000364/2023010-04 Open/Closed None (NPP)71111.21M The NRC identified two examples of a Green finding and associated NCV of Title 10 Part 50, Appendix B, Criterion III, "Design Control," for the licensee failure to assure the seismic design of Class 1E battery racks. 1. Modifications of the battery racks resulted in a loss of configuration control. 2. The seismic qualification report of record did not assure that the qualification requirements were met.

Description:

The team reviewed the site licensing basis for seismic qualification, IEEE 344-1975, IEEE Recommended Practices for Seismic Qualification of Class 1E Equipment for Nuclear Power Generating Stations. This standard provides the requirements for qualification by testing, analysis, or a combination of testing and analysis. This included earthquake environment and equipment response to it, i.e., equipment with bolted connections that can produce impacts, rattling, chatter, or banging. Impacts such as these can be transmitted throughout the racks and result in increased acceleration levels at frequencies much higher than originally considered. In addition, Section 7.3, Extrapolation for Similar Equipment, required, in part, that for complex equipment, test results are combined with preceding analysis to produce a verified analytical model that can be used to qualify the similar equipment.

1. Modifications of the battery racks resulted in a loss of configuration control:

To inform walkdowns, the team reviewed drawing U-211521, 125V Station Battery Auxiliary Building Rack 2A/2B Layout. The team noted that the layout required channel/spring nuts to be seated on the Unistrut rail channel sections such as the slots in the spring nuts were fully engaged with the rails folded edges. During the walkdown, the team observed that a number of these spring nuts were misaligned (improperly seated) and some not engaged (loose) from the Unistrut. The misaligned spring nuts can come dislodged from the Unistrut channel due to seismic vibrations. This made the racks improperly assembled. The team observed that this condition could cause increased equipment responses as described above. The team found improperly installed spring nut in all four Class 1E battery rooms.

The team reviewed U419471, GNB Battery Racks Modifications for C&D TYPE LCU-27, and noted that this document provided instructions to modify the existing battery racks to fit new smaller battery cells (LCU-27). The modification required changes to the racks including tie rods and shims. For this, the racks were partially disassembled and reassembled. The team determined this was the source of the improperly assembled racks. The team determined that, for some racks, the misaligned spring nuts were grouped such that those segments could become dislodged as supports for battery cells.

2. The seismic qualification report of record did not assure that the qualification requirements

were met:

The team requested the seismic qualification reports to determine the effects of the improper rack assembly. The team reviewed seismic qualification reports U419743 and U279795. The team noted that the qualification was determined by a combination of test and analysis. The report did not model the as built configuration of the racks for analysis including the number of rack sections, rack size and frame construction. In addition, they did not address the modification to the racks or the changes for the new battery cells.

The team reviewed a credited test performed in WYLE Test No. 43450-1 which concluded that the testing response spectra completely envelope the Farley Plant seismic spectra OBE

[operating basis earthquake] and SSE [safe shutdown earthquake] RRS [required response spectrum] at all test frequencies without exception. The team noted that the test was of a completely different type and size of rack than the racks installed at Farley.

None of these qualification reports documented a similarity analysis and extrapolation analysis of the seismic differences, bolted connections, including natural/resonant frequencies between the various reports and as built racks. This did not meet qualification requirements in the licensing basis. As such, the team determined that there was no objective evidence to support the statement made in U419471 about the rack modifications, which stated, in part, the differences do not degrade the seismicity below acceptable limits (may require some additional analyses or testing) including any additional supporting data.

Further, the GNB Battery Rack Design Analysis, ES-84-279, Seismic Calculation of Battery Racks, documented natural frequencies that deviated from those specified in the Farley qualification reports (U419743 and U279795). It specified that the rack structure exhibited high rigid frequencies in several directions and high frequency in another, and this was not reconciled by the licensee. The qualification did not address the criteria for bolted connections as described in the first paragraph of this description.

The licensee qualification did not meet the licensing basis for seismic qualification, and thus the team could not use them to support the verification of the seismic qualification of these battery racks.

Corrective Actions: The licensee corrected the observable misaligned spring nuts. Approximately half the population of spring nuts cannot be inspected without specialized tools. The licensee is continuing to determine the qualified status of the racks.

Corrective Action References: Condition Reports 10964538 and 10967767

Performance Assessment:

Performance Deficiency: The licensees failure to assure the seismic design of Class 1E battery racks met qualification requirements was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, installation of the battery racks in a way that could not meet a seismically qualified condition and the lack of a qualification record that meets the site licensing basis adversely affected the reliability and capability of the rack to perform in a seismic environment.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The team screened the significance of the finding using Exhibit 2 and Exhibit 4 of IMC 0609 Appendix A and determined that a detailed risk evaluation was required because the condition involved the potential degradation of the ability of the Class 1E batteries to mitigate the impact of a seismic event as a result of the performance deficiency. A detailed risk evaluation was performed by a regional Senior Reactor Analyst using SAPHIRE Version 8.2.8 and NRC Farley SPAR model Version 8.81. A conditional analysis was performed for Unit 1 and for Unit 2 to evaluate the risk increase due to the failure to ensure the seismic qualification of the Class 1E batteries. A maximum SDP condition exposure period of one year was assessed for all seismic initiators to account for battery failure due to either battery rack nonconformances or the lack of seismic qualification integrity. No credit was provided in the analysis for post-failure recovery of equipment impacted by performance deficiency. For conservatism no credit was provided in the analysis for FLEX mitigation strategies. The dominant sequences involved a seismic initiator followed by consequential small break loss of coolant accident and loss of offsite power accompanied by seismic-induced failure of the 600 Volt load centers. The risk of the finding was mitigated by the relatively low seismic event initiator frequencies for Farley. The analysis determined that the estimated increase in Core Damage Frequency (CDF) and Large Early Release Frequency (LERF) was less than 1E-06/year for delta-CDF and less than 1E-07/year for delta-LERF, representing a finding of very low safety significance (GREEN) for Unit 1 and for Unit 2 Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion III, Design Control, required, in part, that measures shall include provisions to assure that appropriate quality standards are specified and included in design documents and that deviations from such standards are controlled.

Contrary to the above, the licensee failed to assure that deviations from applicable quality standards and requirements for the seismic design and installation of safety-related battery racks were controlled.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Correct Alternate Source Term Leakage Test Requirements Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000348,05000364/2023010-05 Open/Closed

[P.2] -

Evaluation 71111.21M The NRC identified a Green finding and associated NCV of Title 10 CFR Part 50, Appendix B Criterion XVI, "Corrective Actions," for the licensee failure to correct a violation for properly categorizing Motor Operated Valves (MOVs) 8809A/B in the Inservice Test (IST) program and begin testing required for the alternate source term (AST) leakage paths.

Description:

The licensee was issued a violation for the failure to properly categorize the MOVs 8809A/B in the Inservice Test (IST) program and begin leak checking the valves that isolate the Refueling Water Storage Tank (RWST) from the Residual Heat Removal (RHR)system during sump recirculation after a Design Basis Accident (DBA) (NCV 05000348,05000364/2021011-01). The licensee corrective actions did not address the American Society of Mechanical Engineers (ASME) classification or leakage requirements for the 8809A/B MOVs. As a result of a licensee amendment to use AST for offsite dose requirements, the RWST became a radiation leakage path with a specific allowed leakage amount. This makes the valves in this path ASME category A with prescribed leakage test requirements.

The team pointed out that the Updated Final Safety Analysis Report (UFSAR) Section 15.4.1.7.4, RWST Release Pathway, stated in part, the ESF leakage pathways include those through valves that isolate containment sump water from interfacing systems. Seat leakage past valves which isolate recirculation flow to the RWST is included. The adjusted leakage rate from the sump, through the RWST, to the environment is modeled as a direct connection between the sump and the environment. Further, that the UFSAR Table 6.3-7, Single Active Failure Analysis for Emergency Core Cooling System Components Short-Term Phase, and long-Term Phase, stated in part Residual heat removal pumps suction line to refueling water storage tank - [if] Fails to close - [the] Check valve in series with one gate valve operation of only one valve required. There are two gate valves (8809A/B) each in series with the same check valve (Q1(2)E11V0028) to the RWST.

The team determined that the valves that isolate containment sump water, from the UFSAR Section 15.4.1.7.4, included both gate valves and the check valve. The team determined that the licensee failed to correct the violation related to leak checking the AST pathway through the RWST as described in the UFSAR.

Corrective Actions: The licensee will develop operational testing that can measure and assure the active leakage as required in the AST calculations values at design basis temperature and pressures.

Corrective Action References: CR 10967853

Performance Assessment:

Performance Deficiency: The failure to correct a violation for properly categorizing the MOVs 8809A/B in the IST program and begin testing required for the AST leakage paths was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the SSC and Barrier Performance attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, higher leakage through the MOV 8809A/B valve does not provide reasonable assurance that physical design barriers protect the public from radionuclide releases.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix H, Containment Integrity SDP. The team determined this was a type B finding because it would not have an impact on CDF. The team used Section 6.1, Approach for Assessing Type B Findings at Full Power, Step 2: Screening of Finding to determine if the finding was associated with an SSC(s) important to LERF, using Table 6.1 Phase 1 Screening-Type B Findings. The team determined the finding to be GREEN because the finding screened out of this process.

Cross-Cutting Aspect: P.2 - Evaluation: The organization thoroughly evaluates issues to ensure that resolutions address causes and extent of conditions commensurate with their safety significance.

Enforcement:

Violation: 10 CFR Part 50 Appendix B, Criterion XVI, states, in part, conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and corrected.

Contrary to the above, since (the POV inspection) the licensee failed to correct a nonconformance with ensuring leakage requirements for MOVs 8809 A/B in accordance with the sites commitments to the AST required leakage paths.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Identify Corrosion on MOV 3209B Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000348,05000364/2023010-06 Open/Closed

[P.1] -

Identification 71111.21M The NRC identified a Green finding and associated NCV of Title 10 CFR Part 50, Appendix B Criterion XVI, "Corrective Actions," for the licensee failure to identify corrosion on MOV 3209B that affected its structural integrity.

Description:

The team walked down the service water supply valve (MOV 3209B) to the motor driven auxiliary feed water pump. The team identified that water leakage down the sides of the MOV caused significant corrosion on the bonnet. The amount of corrosion adversely affected the integrity of the MOV. The licensee had not identified this corrosion. The team noted that there was a leakage path t0 the valve body below insulation that was installed around it. The insulation obscured observation of this area. With the amount of corrosion on the bonnet, there is an increased likelihood that the body is corroded.

Corrective Actions: The licensee is performing a ultrasonic test to determine how much material has deteriorated from the bonnet.

Corrective Action References: CR 10962571

Performance Assessment:

Performance Deficiency: The failure to identify corrosion on MOV 3209B that affected its structural integrity was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, a failure of the bonnet integrity would allow flooding of the AFW pump room and disable an alternate water source for the AFW pump.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Exhibit 2 - Mitigating Systems Screening Questions, Item A, The degraded condition did not represent a loss of the PRA function of one or more non-TS trains of equipment designated as risk-significant in accordance with the licensees maintenance rule program for greater than 3 days - Screen to GREEN Cross-Cutting Aspect: P.1 - Identification: The organization implements a corrective action program with a low threshold for identifying issues. Individuals identify issues completely, accurately, and in a timely manner in accordance with the program.

Enforcement:

Violation: Title 10 CFR Part 50 Appendix B, Criterion XVI, "Corrective Actions," states, in part, measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and corrected.

Contrary to the above, the licensee failed to implement measures to assure that conditions adverse to quality, such as deficiencies, deviations, defective material and equipment were promptly identified. Specifically, the licensee failed to inspect MOV 3209B to identify corrosion that effects the structural integrity of the valve.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Inadequate Work Instructions for Cable Bend Radius Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000348,05000364/2023010-07 Open/Closed

[H.5] - Work Management 71111.21M The NRC identified a Green finding and associated NCV of Title 10 CFR Part 50, Appendix B Criterion V, "Instructions, Procedures, and Drawings," for the licensee failure to include precautions about cable bend radius in work orders to replace the Class 1E batteries.

Description:

The team identified that the 2A Class 1E batteries main power cable exceeded the specified bend radius. The radius was approximately 4-inches when licensee procedure, NMP-ES-038-GL02, required a 20-inch radius. Several of the other Class 1E battery cables appeared questionable. The team reviewed several work orders that were used to replace all the Class 1E batteries. There were no precautions, limitations, or other information to control the cable bend radius as work instructions. Excessive cable bends if left uncorrected can cause insulation breakdown and flashover of the conductor to the nearest conductor resulting in short circuit and an unavailability of the battery. In addition, these batteries are replaced every 13 to 15 years when necessary. The act of unbending tight cable bends on large stiff cables and then re-bending them to connect the new batteries fatigues the copper strands which could cause arcing inside the cable at stress fractures. This can cause failures of the batteries from flash overs.

Corrective Actions: The licensee created work orders to check the cable insulation for any signs of cracking as well as a check for hot spots using thermal imaging camera. Long-term, the bend radius should be restored.

Corrective Action References: CR 10964531

Performance Assessment:

Performance Deficiency: The failure to include precautions about cable bend radius in work orders to replace the Class 1E batteries was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, Excessive cable bends if left uncorrected can cause insulation breakdown and flashover of the conductor to the nearest conductor resulting in short circuit and an unavailability of the battery.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Exhibit 2

- Mitigating Systems Screening Questions, item A. Mitigating SSCs and PRA Functionality (except Reactivity Control Systems), specified that if the finding affected the design or qualification of a mitigating SSC, but it maintained its operability or PRA functionality then it screens to GREEN.

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of planning, controlling, and executing work activities such that nuclear safety is the overriding priority. The work process includes the identification and management of risk commensurate to the work and the need for coordination with different groups or job activities.

Enforcement:

Violation: Title 10 CFR 50 Appendix B Criterion V, " Instructions, Procedures, and Drawings,"

states, in part, activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances.

Contrary to the above, the licensee failed to prescribe activities affecting quality by documented instructions of a type appropriate to the circumstances in battery replacement work orders.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Inadequate Thermal Overload Calculations and Use of Related Software Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000348,05000364/2023010-08 Open/Closed

[H.5] - Work Management 71111.21M The NRC identified a Green finding and associated NCV of Title 10 CFR Part 50, Appendix B, Criterion III, Design Control for the licensee failure to assure that Thermal Overload (TOL)relays for MOV circuits were properly sized and documented in quality-controlled calculations and the use of a nonfunctional Plant Data Management System (PDMS) to automatically calculate TOL specifications.

Description:

The team reviewed SNC1086636 (Unit 1) and SNC1112528 (Unit 2) which installed permanent jumpers to bypass Class 1E TOL relays in MOVs in accordance with Regulatory Guide (RG) 1.106, Thermal Overload Protection for Electric Motors on Motor operated Valves, Rev. 1. The team noted that the RG was an acceptable method that allowed the licensee to either bypass the TOLs during power operation or to size them properly and periodically test them. The team reviewed calculations associated with TOLs (their use and sizing). Calculations SE-SNC5299029-001 Unit 1 Minimum expected Voltage Study Version 2, Attachment 6 and SE-SNC5299029-002 Unit 2 Minimum expected Voltage Study, Version 1, Attachment 6, both specified that PDMS was the source for TOL relay sizing calculation.

Calculation SE-94-0-0378-001, MOV Combination Starter Component Sizes and settings, Rev.5, for Units 1 and 2, Section 3 stated, in part the PDMS calculation provides a range of acceptable TOLs based on this input. Section 6.3 states PDMS is used to determine TOL heater sizes for MOVs and section 6.3.4 states Operational criteria for the valve must be met and there should be adequate motor protection for the TOL to be considered properly sized. The TOLs in these circuits were in use during power operation prior to the modifications. Correct sizing calculations ensure that TOL devices would not prevent the MOVs from performing their safety functions.

The team requested the sizing calculations but was informed that PDMS reports do not document the calculations. The team inquired about the qualifications and capabilities of the PDMS software since it was a qualified vendor supplied TOL sizing software. In response, they submitted procedure DS-CM-001 PDMS Software Use and Access Control, Version 3.1 for review. The procedure stated, in part, that this procedure applies to the use of PDMS for engineering and data management activitiesOutputs from PDMS are used for the preparation of design change documents, studies, and in design change implementation, and that PDMS is a nuclear safety-related software program supplied by Jensen Hughes that has the capability to store and analyze design information in electronic format.

The inspectors noted that PDMS TOL sizing capabilities were not specified in this procedure. The licensee stipulated that the TOL feature was a new custom feature. The team inquired about the qualification of this feature and was informed that it did not have a separate qualification. The team asked for a walkthrough of the feature. The licensee randomly selected seven TOLs sizing calculations in the PDMS. The seven samples produced incorrect TOL sizing. The sizes generated would not protect the motors. The licensee informed the team that, historically, they were generating TOL specifications by the use of alternate methods and entering the specification values into the PDMS database because PDMS has never been able to correctly size TOLs. The alternate TOL sizing was not supported by documented Class 1E calculations. The team questioned how this met Appendix B requirements since this TOL feature was specified in most of the licensee Class 1E electrical procedures that the team reviewed. There was no acceptable answer. In addition, the team noted that the PDMS inputs for this feature were incorrectly entered. The incorrect motor damage curve, M1480A with a 12s time to damage, was entered into PDMS for MOV Q2E1MOV8803B. The correct damage curve should have been M1480 with an 8s time to damage. This incorrect input would cause an incorrect TOL sizing calculation even if perform by traditional methods. The team noted that this was not the cause of the prior incorrect PDMS TOL sizing. That appeared to be a software design and quality error.

The team noted that procedure NMP-ES-039-001, Calculations - Preparation and Revision, Version 7.0 specified, in part, that calculations utilizing analytical software (PDMS Sizing Calc) required a documented calculation to confirm the outputs of the software. The team requested the calculation(s). The licensee could not provide any Class 1E calculation(s) to support the TOL sizing for any MOV. Corrective action document 10967713 was issued.

Corrective Action References: CR 10967713

Performance Assessment:

Performance Deficiency: The failure to assure that TOL relays in MOV circuits were properly sized and documented in quality-controlled calculations and the use of a nonfunctional PDMS to automatically calculate TOL specifications was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, incorrectly sized TOLs could adversely affect the reliable operation of safety related MOVs when they are required to operate.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Exhibit 2

- Mitigating Systems Screening Questions, item A. Mitigating SSCs and PRA Functionality (except Reactivity Control Systems), specified that if the finding affected the design or qualification of a mitigating SSC, but it maintained its operability or PRA functionality then it screens to GREEN.

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of planning, controlling, and executing work activities such that nuclear safety is the overriding priority. The work process includes the identification and management of risk commensurate to the work and the need for coordination with different groups or job activities.

Enforcement:

Violation: Title 10 CFR Part Part 50, Appendix B, Criterion III, Design Control, states, in part, design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, using alternate or simplified calculational methods, or by the performance of a suitable testing program.

Contrary to the above, as of April 2023, measures had not been established to verify and ensure that Thermal Overload relays installed in thirty-four

(34) safety-related MOV circuits by the performance of design reviews, using alternate or simplified calculational methods to demonstrate that they would not adversely affect MOV operation.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On April 27, 2023, the inspectors presented the Technical Debrief inspection results to Mr. Keith Brown and other members of the licensee staff.

On May 2, 2023, the inspectors presented the design basis assurance inspection (teams) inspection results to Mr. Delson Erb and other members of the licensee staff.

On June 5, 2023, the inspectors presented the Re-exit inspection results to Mr. Delson Erb and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Calculations

A350972

Criteria for Selection/Evaluation of TOLs

Rev. 1

71111.21M

Calculations

E-095

Battery Capability Verification

Rev. 14

71111.21M

Calculations

ES-84-279

Seismic Calculation of Battery Racks

October 5,

1984

71111.21M

Calculations

ES-87-882

FNP Battery Racks

November

11, 1987

71111.21M

Calculations

FNP-

Q1E11MOV8706A

MIDAS Calc for MOV 8706A

Rev. 3

71111.21M

Calculations

FNP-

Q1E21MOV8803B

MIDAS Calc for MOV8803B

Rev. 2

71111.21M

Calculations

FNP-

Q1N23MOV3209B

Thrust And Torque Calculation FNP-Q2N23MOV3209B

(FNPS-2)

Rev. 2

71111.21M

Calculations

Job No. 7597-

03/20

Joseph M. Farley Nuclear Units 1 and 2 Final Seismic

Response Spectra

December

1972

71111.21M

Calculations

SC-90-1-6421-001

Farley Unit 1 &2 Qualify Lighting Support for 2/1 Lighting

Support-Aux Bldg.

71111.21M

Calculations

SE-90-1653-001

MOV Thrust Requirements

Rev. 17

71111.21M

Calculations

SE-90-1653-002

Non-LOCA MOV Starting Voltages

Rev. 6

71111.21M

Calculations

SE-90-1714-12

Overload Heater Sizing and Resistance

Rev. 5

71111.21M

Calculations

SE-90-1714-12

Overload Heater Sizing and Resistance

Rev. 5

71111.21M

Calculations

SE-91-1976-1

Motor Starter Control Circuit Study

Rev. 7

71111.21M

Calculations

SE-94-0-0378-001

MOV Combination Starter Component Sizes & Settings

Rev. 5

71111.21M

Calculations

SE-94-0-0378-001

MOV Combination Starter Component Sizes and settings

Rev. 5

71111.21M

Calculations

SE-99-0-2010-001

Verification Package for Computer Software used to

calculate MOV thermal Overload Heater sizes

10/27/99

71111.21M

Calculations

SE-SNC529029-

001

Unit 1 Minimum Expected Voltage Study

Version 2

71111.21M

Calculations

SE-SNC529029-

2

Unit 2 Minimum Expected Voltage Study

Version 1

71111.21M

Calculations

SJ-SNC529029-

001

Determination of Setpoints, Reset Points, and LOOP

Uncertainties for 4160V Degraded Voltage Relays

Rev. 1

71111.21M

Calculations

SM-90-1653-001

MOV Thrust Requirements for Gate & Glob

Version 17

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Calculations

SM-90-1653-002

Reduced Voltage Torque/Thrust Capability for Gate & Globe

Valves in the FNP MOV Program

Version 23

71111.21M

Calculations

SM-90-1653-002

Reduced Voltage Torque/Thrust Capability

Rev. 23

71111.21M

Calculations

SM-90-1653-003

Design Basis Differential Pressure for the MOV Program

71111.21M

Calculations

SM-90-1653-003

Design Basis Differential Pressure for the MOV Program

71111.21M

Calculations

SM-92-2216-03

Expected Temp Inside the EDG Building

Rev. 2

71111.21M

Calculations

SM-94-0470-005

Unit 2 Load Study Summary

Rev. 8

71111.21M

Calculations

SM-94-0470-007

Unit 2 As-Built Load Study

Rev. 9

71111.21M

Calculations

SM-97-1407-002

Condensate Storage Tank (CST) Low-Low Level Setpoint

Version 1

71111.21M

Calculations

SM-SNC5290029-

2

Unit 2 Minimum Expected Voltage Study

Rev. 1

71111.21M

Calculations

U279795

Report Number QR-74314-01 Environmental and Seismic

Qualification Report of Type LCU-27 125 Volt DC Station

Service Batteries 2A & 2B Auxiliary Building

May 12,

1993

71111.21M

Calculations

U400445, 7697-03

MOV 3209B Seismic Analysis 8" 50# O.S.Y. Gate Valve

2/20/1973

71111.21M

Calculations

U405413

MOV 3764D - Seismic Analysis - Velan 4 inch gate vlv

2/8/1974

71111.21M

Calculations

U419743

Environmental and Seismic Qualification Report - Auxiliary

Building 125 Volt DC Station Batteries 1A & 1B

71111.21M

Calculations

U735621

Seismic & Environmental Qualification Report of 125 Volt

DC 4LCY-07 Battery & 2-Step Battery Rack, 1-Tier Battery

Rack

71111.21M

Calculations

V-EC-1321

Seismic Analysis of MOV 8803A/B

11/16/1992

71111.21M

Calculations

V-EC-703

Seismic Analysis of MOV 8811/8812

10/27/1989

71111.21M

Corrective Action

Documents

10653474

Engineering review of thermal overload methodology in

calculations

10/10/19

71111.21M

Corrective Action

Documents

10894266,

210736,

10705431,

10759281,

10777260,

10951159,

10653474,

206648,

10781626,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

10777229,

10932243,

10735066,

10902518,

10742390,

10735066,

10964675,

10965380,

10935351,

10939868,

10653474

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10962571

NRC Identified - Rust build up on valve Q2N23V0014B

04/05/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10964188

NRC CETI walkdown results - Q1E11MOV8812B

04/12/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10964531

NRC identified cable bend radius

04/13/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10964536

NRC identified light fixture issue

04/13/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10964538

NRC Identified - Seismic concern on 1B/2B aux bldg battery

racks

04/13/2023

71111.21M

Corrective Action

Documents

Resulting from

CR 10964675

NMP-OS-014-001 Attachment 2 needs to be updated based

on a change to FNP-1/2-EEP-0.0

04/14/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Inspection

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10965378

MOV actuator Q1E11MOV8811B needs painted

04/18/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10965380

NMP-OS-014-001 Attachment 2 needs to be updated based

on a change to FNP-1/2-ESP-0.1

04/18/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10965508

for boric acid on Q1E11MOV8811B

04/18/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10965915

Minor Revision Required for NMP-ES-017-009

04/20/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10966072

NRC Identified - Seismic Concern on U1 TDAFW UPS

Battery Rack Bracing

04/20/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10966892

Identified - Rust build-up on Q1P16V001A flange

04/25/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10966977

Change in Maximum DP for Containment Sump Valves

Inadequately Documented

04/25/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10966990

NRC Identified - Analysis for U1/2 MOV 3209 A/B

04/25/2023

71111.21M

Corrective Action

CR 10967359

NRC Identified - Seismic concern on 2A aux bldg. battery

04/26/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Resulting from

Inspection

racks

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967469

23 NRC CETI documentation - mag rotor inspection

Q1E11MOV8811B

04/26/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967477

23 NRC CETI inspection - mag rotor inspection

Q1E11MOV8812B

04/27/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967479

MOV Trend CR - 2023 NRC CETI inspection

Q1E21MOV8803B

04/27/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967482

23 NRC CETI inspection - test equipment used on

Q1E11MOV8812B

04/27/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967483

23 NRC CETI inspection - motor brakes on specific

MOVs

04/27/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967506

23 NRC CETI inspection - use of EPRI PPM

04/27/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967710

NRC Finding: Failure to perform adequate corrective action

for CR 10777260

04/27/2023

71111.21M

Corrective Action

Documents

Resulting from

CR 10967713

23 NRC CETI: PDMS TOL Sizing

04/27/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Inspection

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967767

23 NRC CETI - AB Battery Rack Seismic Qualification

Report

04/27/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967773

23 NRC CETI - Weak Link Analysis Document Request

04/28/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967778

23 NRC CETI Inspection - EDG Room Temp and MCCs

04/28/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967802

23 NRC CETI - 2A AB Battery Lighting II/I concern

04/28/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967839

23 NRC CETI - EDG steady state TS limit of 3740V

04/28/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10967853

23 NRC CETI - MOV 8809 Inadequate Corrective Action

04/28/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10968803

23 NRC CETI - 1B EDG SI Test

05/03/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10972352

Inactivation of PM without adequate justification

05/17/2023

71111.21M

Corrective Action

CR 10972742

23 NRC CETI - Failure to perform adequate corrective

05/18/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Resulting from

Inspection

actions for CR 10777260 and TE 1083113

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10972749

23 NRC CETI - Inadequate justification of Agastat service

life extension

05/18/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10973935

23 NRC CETI inaccurate test documentation on

Q1E11MOV8811B

05/23/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10974521

23 NRC CETI - Failure to evaluate environmental

conditions of MCCS in EDG rooms

05/25/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10976358

23 NRC CETI - Invalid seismic qualification of AB battery

racks 1A/B and 2A/B

06/01/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10979135

Follow up to 2023 NRC CETI inspection CR 10967483

06/12/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10979515

Follow up to 2023 NRC CETI inspection CR 10973935

(magnesium rotor inspection)

06/13/2023

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10979536

23 NRC CETI - Maximum Differential Pressure Change

Not Justified for CTMT Sump Isolation Valves

06/13/2023

71111.21M

Corrective Action

Documents

Resulting from

CR 10980310

23 NRC CETI - Magnesium Rotor Inspection

06/15/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Inspection

71111.21M

Corrective Action

Documents

Resulting from

Inspection

CR 10980342

NRC CETI Issue of Weak Link / Seismic Analysis

06/15/2023

71111.21M

Drawings

A-177542

Lighting Details & Notes, Series Drawing Sheets 1 through

71111.21M

Drawings

B-203554

Electrical Conduit Supports General Notes, Series Drawing

Sheets 1

71111.21M

Drawings

B-203554

Electrical Conduit Supports Standard Types, Series

Drawing Sheets 2 through 25

71111.21M

Drawings

B207556 Sht 10

600V MCC 2V

Rev. 0

71111.21M

Drawings

D-175007

P&ID Auxiliary Feedwater System

Version 1

71111.21M

Drawings

D-177608

Elementary Diagram - Charging/SI Pumps 575V motor

operated Valves

Version 6

71111.21M

Drawings

D-177620

Elementary Diagram 575V Motor Operated Valves Sh. 17A

- AFW Pump Discharge MOV's

Rev. 1

71111.21M

Drawings

D-181900 28A

Installation Details for Environmentally Qualified

Telemecanique (ITE) Motor Control Center 1U, SH 28A

Version 7

71111.21M

Drawings

D-181900 28B

Installation Details for Environmentally Qualified

Telemecanique (ITE) Motor Control Center 1V, SH 28B

Version 6

71111.21M

Drawings

D-203096

Unit 2 Key Diagram

Rev. 0

71111.21M

Drawings

D-207006

Single Line - 4160V Switchgear Bus 2G

Rev. 0

71111.21M

Drawings

D-207044

Single Line - 4160V Switchgear Bus 2L

Rev. 2

71111.21M

Drawings

D-207570

Unit 2 575V MOV8706A

Rev. 1

71111.21M

Drawings

D-207614

Unit 2 575V MOV88013B-AB

Rev. 1

71111.21M

Drawings

D-207626

Unit 2 575V MOV3209B

Rev. 1

71111.21M

Drawings

U-211521

25V Station Battery Auxiliary Building Rack 2A/2B Layout

71111.21M

Drawings

U-278948

Gate Valve 300# Motor Operator 14 Class Q2E11V025A

71111.21M

Drawings

U-732406

Interface Control Drawings (ICD'S) Containment Sump

Passive Strainer/Screen

71111.21M

Drawings

U176261

Battery Rack 1A & 1B Layout of 60 Cells (Heavy Seismic

Resistant)

71111.21M

Drawings

U205093

8" 150# OSY Gate Valve

2/15/1975

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Drawings

U259520

4" 900# Pressure-Seal Gate Valve

Version 1

71111.21M

Drawings

U735431

Tow Step & Single Tier EP3 4LCY-7 Battery Racks

71111.21M

Engineering

Changes

SNC1085311

2R28-4kV Breaker Replacement

Rev. 2

71111.21M

Engineering

Changes

SNC1086636

U1 LOCA MOV TOL Sizing Degraded

Rev. 1

71111.21M

Engineering

Changes

SNC1112528

Bypass Thermal Overloads for Unit 2 LOCA Motor Operated

Valves

Rev. 1

71111.21M

Engineering

Changes

SNC1123286

U1 SW Header Drain Line Addition

Rev. 0

71111.21M

Engineering

Changes

SNC1125459

2C SW Minimum Flow Line Reinforcement Sleeve Removal

Rev. 0

71111.21M

Engineering

Changes

SNC1127561

By-pass Unit 1 and Unit 2 LOCA MOVs (online)

Rev. 0

71111.21M

Engineering

Changes

SNC1141168

1B Startup Transformer 1B Replacement Change Package

Rev. 0

71111.21M

Engineering

Changes

SNC1255545

Replace General Electric (GE) AK DC Breakers

Rev. 5

71111.21M

Engineering

Changes

SNC1426773

Replace and re-route cable for FT477, FT487, FT497, and

PT446

Rev. 1

71111.21M

Engineering

Evaluations

1053781

Technical Evaluation Quality Record, Engineering review of

thermal overload methodology in calculations

2/21/20

71111.21M

Engineering

Evaluations

22582

Determine if MOV Procedures have been updated to

remove and reinstall the jumper during Testing

03/09/23

71111.21M

Engineering

Evaluations

22890

Update Documents: DBAI FASA: MOV Thermal Overload

Bypass Modification

Issues

03/01/23

71111.21M

Engineering

Evaluations

22892

Determine if DCP requires an update: DBAI FASA: MOV

Thermal Overload bypass modification issue

03/01/23

71111.21M

Engineering

Evaluations

2071575301-02

NSSS MOV Test Differential Pressure Determination

71111.21M

Engineering

Evaluations

FNP-0-ESB-1.2

Farley Nuclear Plant Specific Background Document For

FNP-1/2-ESP-1.2 L Post LOCA Cooldown And

Depressurization

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Miscellaneous

1.106

Regulatory Guide 1.106, Thermal Overload Protection for

Electric Motors on motor-operated valves

Rev. 1

71111.21M

Miscellaneous

CFR 50.59

Screening

SNC1091429

U2 DRPI Advanced Display System

Version 1.0

71111.21M

Miscellaneous

1075584

FASA - Power Operated Valves Inspection

Rev. 3

71111.21M

Miscellaneous

1083113

FASA POV: Calc SE-91-1976-1 Update for Clarification

2/24/2021

71111.21M

Miscellaneous

1095167

NON-LOCA MOV Analysis needed

10/22/2021

71111.21M

Miscellaneous

10CFR 50.59

Screening DECP

SNC1127557

Spent Fuel Cask Crane Upgrades

Version 1.0

71111.21M

Miscellaneous

A-181004

Functional System Description Electrical Distribution

System

Version 58.0

71111.21M

Miscellaneous

A-350972

Criteria for selection/Evaluation of Thermal overload heaters

and recommendations for selection of magnetic breaker

setpoints for the Telemacanique (ITE-Gould) motor control

center starters controlling the motor operated valve

actuators.

Rev.1

71111.21M

Miscellaneous

A181010

Functional System Description Auxiliary Feedwater System

Version 38

71111.21M

Miscellaneous

Action Item

2009202247

3/26/2009

71111.21M

Miscellaneous

C93166

CCSI Letter December 2007

2/21/2007

71111.21M

Miscellaneous

IP-ENG-001

Standard Design Process (EB-17-06)

Rev. 3

71111.21M

Miscellaneous

Item/Service

Identification

1330116

Plug, Pipe, Size: 6 INCH; Material; Cast Iron; Head; Square;

Construction; Black

9/14/2021

71111.21M

Miscellaneous

LDCR 2021-029

SNC 1091429

U2 Digital Rod Position Indication Advanced Display

System

Version 1.0

71111.21M

Miscellaneous

LDCR 2021-058

DECP

SNC1127557

Spent Fuel Cask crane Upgrades

Version 1.0

71111.21M

Miscellaneous

NMP-GM-003-F19

Design Basis Assurance Inspection FASA

Rev. 5

71111.21M

Miscellaneous

SM-SNC338705-

004

AFW-CST Reference Summary

Version 3

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Miscellaneous

SNC1141168

10CFR50 Screening for 1B Startup Transformer

Replacement

Rev. 2

71111.21M

Miscellaneous

SNC921616 Seq 1

Justification for Extension of Expected Service Life -

Agastat E7000 series

Rev. 4

71111.21M

Miscellaneous

U-518612

Procedure Reference Manual Instruction Book for CCSI

1045DEP Nuclear Diaphragms for All Storage Tanks

Version 1.0

71111.21M

Miscellaneous

U258824

Instruction Manual-Velan Motor Operated, Manual Valves

and Air Operated Valves

Version 1.0

71111.21M

Miscellaneous

U280317

Limitorque Valve Operator Instructions & Manual

Rev. M

71111.21M

Miscellaneous

U737125

Siemens MSV-FSV Operation/Instruction Manual

Rev. 3

71111.21M

Miscellaneous

V-EC-1869

Applicability of BWROG Mag Rotor Inspection Report to

PWRs

Rev. 2

71111.21M

Procedures

DS-CM-001

PDMS Software Use and Access Control

Version 3.1

71111.21M

Procedures

FNP-0-EMP-

1313.16

Maintenance of Seimens 4.16kV Circuit Breakers

Rev. 7

71111.21M

Procedures

FNP-0-EMP-

23.01

Inspection of MCCs

Rev. 33

71111.21M

Procedures

FNP-0-EMP-

1512.02

Molded Case Circuit Breakers Inspection and Test

Rev. 54

71111.21M

Procedures

FNP-0-M-114.0

External Surfaces Monitoring Program

Version 7.0

71111.21M

Procedures

FNP-0-PMP-500.0

Installation and Inspection of Electrical Field Cables

18.1

71111.21M

Procedures

FNP-0-STP-24.6

Service Water Buried Pipe Inspection

Version 17.1

71111.21M

Procedures

FNP-1-AOP-14.0

Secondary System Leakage

Version 15.0

71111.21M

Procedures

FNP-1-AOP-27.0

Emergency Boration

Version 18.0

71111.21M

Procedures

FNP-1-ARP-1.6

Main Control Board Annunciator Panel F

Version 93.0

71111.21M

Procedures

FNP-1-ARP-1.9

Main Control Board Annunciator Panel J

Version 54.1

71111.21M

Procedures

FNP-1-EEP-0

Reactor Trip or Safety Injection

Revision

56.0

71111.21M

Procedures

FNP-1-ESP-0.1

Reactor Trip Response

Revision

2.0

71111.21M

Procedures

FNP-1-SOP-21.0

Condensate and Feedwater System

Version 135

71111.21M

Procedures

FNP-1-SOP-22.0

Auxiliary Feedwater System

Version 84.0

71111.21M

Procedures

NMP-AD-008

Applicability Determinations

Version 22.1

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Procedures

NMP-AD-010

CFR 50.59 Screenings and Evaluations

Version 17.1

71111.21M

Procedures

NMP-AD-011

CFR 72.48 Screenings and Evaluations

Version 11.1

71111.21M

Procedures

NMP-AD-043

Regulatory Correspondence Control

Version 7.0

71111.21M

Procedures

NMP-ES-017

Motor-Operated Valve Program

71111.21M

Procedures

NMP-ES-017-008

MOV Mechanical and Electrical Inspections

Version 11.5

71111.21M

Procedures

NMP-ES-017-008

MOV Mechanical and Electrical Inspections

Version 11.2

71111.21M

Procedures

NMP-ES-017-020

MOV Electrical Checkout and Adjustment for SMB/SB

Actuator

Version 6.9

71111.21M

Procedures

NMP-ES-017-021

MOV Diagnostic Procedure for VOTES Infinity

Version 2.4

71111.21M

Procedures

NMP-ES-017-021

MOV Diagnostic Procedure for VOTES Infinity

Version 2.3

71111.21M

Procedures

NMP-ES-017-022

Teledyne Quick Stem Sensor

Version 1.2

71111.21M

Procedures

NMP-ES-036-001

Underground Pipe and Tanks Monitoring Program

Implementation

Version 12.0

71111.21M

Procedures

NMP-ES-038-

GL02

Electrical Design Guideline

4.1

71111.21M

Procedures

NMP-ES-039-001

Calculations - Preparation and Revision

Version 10.3

71111.21M

Procedures

NMP-ES-058

ETAP Files Control

Rev. 5

71111.21M

Procedures

NMP-ES-069-001

Fleet Service Water Program Instructions

Version 3.4

71111.21M

Procedures

NMP-FLS-003

Electrical Work Practices

Version 12.5

71111.21M

Procedures

NMP-GM-016-002

Non-Corrective Action Program (CAP) Business Item

Instructions

Version 8.0

71111.21M

Procedures

NMP-MA-018

Plant Electrical Component Temporary Configuration

Control

Version 4.3

71111.21M

Procedures

NMP-MA-018-F01

Plant Electrical Component Temporary Configuration

Control Documentation

Version 3.3

71111.21M

Procedures

SS-1125-001

Specification for Uninterruptible Power Supply (UPS)

Turbine Driven Auxiliary Feedwater System (TDAFW) for

Farley Nuclear Plant-Units 1 & 2

71111.21M

Procedures

U419471

GNB Battery Racks Modifications for C&D TYPE LCU-27

71111.21M

Procedures

U735428

Battery Rack Assembly Instructions

71111.21M

Procedures

Westinghouse

WCAP 13097

Volume 3, System Operating Basis for Motor-Operated

Valves

71111.21M

Work Orders

SNC 1057207

OHI - Q2R42E002B - Replace 2B Aux Building Battery

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Bank

71111.21M

Work Orders

SNC1089551

Q1E11MOV8812B - Install Stem Protector

71111.21M

Work Orders

SNC1137341

Q1R17BKRFUT4 Install Jumpers for Sizing Degrade DCP

Rev. 0

71111.21M

Work Orders

SNC1148512

Q1E21F003 - Pre-Outage RCS Filter Replacement

Rev. 0

71111.21M

Work Orders

SNC1272519

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB02 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1272520

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB03 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1272566

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB04 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1272621

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB06 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1272697

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB07 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1272743

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB08 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1272817

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB10 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1272903

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB11 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1273136

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB15 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1273170

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB18 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1273171

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB19 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1383002

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB02 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1383052

Preform Pre-Outage inspection and testing of breaker

Q1R42BKRLB04 per DECP SNC1255545

Rev. 0

71111.21M

Work Orders

SNC1411972

Clean the Boric Acid Residue and Check the Packing

Torque on MOV Q1E11MOV8811B

71111.21M

Work Orders

SNC1432383

RCS Filter DP High - Replace U2 RCS Filter

Rev. 0

71111.21M

Work Orders

SNC383463,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SNC782471,

SNC831500,

SNC1150131,

SNC950814

71111.21M

Work Orders

WO FNP-1-STP-

40.0B

Safety Injection with Loss of Offsite Power Test 1B

Rev. 13