ML20135B299: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 13: Line 13:
| document type = CORRESPONDENCE-LETTERS, OUTGOING CORRESPONDENCE
| document type = CORRESPONDENCE-LETTERS, OUTGOING CORRESPONDENCE
| page count = 4
| page count = 4
| project = TAC:M97027
| stage = Other
}}
}}


Line 28: Line 30:
==Dear Mr. Schnell:==
==Dear Mr. Schnell:==


By letter dated November 6,1996, Union Electric Company (UE) submitted its 60-daf response to Generic Letter (GL) 96-05, " Periodic Verification of
By {{letter dated|date=November 6, 1996|text=letter dated November 6,1996}}, Union Electric Company (UE) submitted its 60-daf response to Generic Letter (GL) 96-05, " Periodic Verification of
             - Design-Basis Capability of Safety-Related Motor-0perated Valves," for the l            Callaway Plant, Unit 1. In the response, UE indicated that based on previous staff review of the GL 89-10 program at Callaway, UE did not plan to implement the requested actions in GL 96-05 and considered all actions in GL 96-05 to be closed for the Callaway Plant.
             - Design-Basis Capability of Safety-Related Motor-0perated Valves," for the l            Callaway Plant, Unit 1. In the response, UE indicated that based on previous staff review of the GL 89-10 program at Callaway, UE did not plan to implement the requested actions in GL 96-05 and considered all actions in GL 96-05 to be closed for the Callaway Plant.
l            On June 8,1994, the NRC staff notified you that we had completed our review
l            On June 8,1994, the NRC staff notified you that we had completed our review

Latest revision as of 08:35, 14 December 2021

Discusses GL 96-05 Entitled, Periodic Verification of Design-Basis Capability of Saftey-Related Motor-Operated Valves
ML20135B299
Person / Time
Site: Callaway Ameren icon.png
Issue date: 11/29/1996
From: Thomas K
NRC (Affiliation Not Assigned)
To: Schnell D
UNION ELECTRIC CO.
References
TAC-M97027, NUDOCS 9612040262
Download: ML20135B299 (4)


Text

_ __ _ _

i a ux%

5Z" f<?3

[a D UNITED STATES

. j j 2-NUCLEAR REG 81LATORY COMMISSION WASHINGTON, D.C. 2006&e001 i
          • / November 29, 1996 Mr. Donald F. Schnell Senior Vice President - Nuclear Union Electric Company Post Office Box 149 St. Louis, Missouri 63166 l

SUBJECT:

GENERIC LETTER 96-05, " PERIODIC VERIFICATION OF DESIGN-BASIS CAPABILITY Of CATETY-RELATED MOTOR-0PERATED VALVES" - CALLAWAY PLANT, UNIT I (TAC NO. M97027)

Dear Mr. Schnell:

By letter dated November 6,1996, Union Electric Company (UE) submitted its 60-daf response to Generic Letter (GL) 96-05, " Periodic Verification of

- Design-Basis Capability of Safety-Related Motor-0perated Valves," for the l Callaway Plant, Unit 1. In the response, UE indicated that based on previous staff review of the GL 89-10 program at Callaway, UE did not plan to implement the requested actions in GL 96-05 and considered all actions in GL 96-05 to be closed for the Callaway Plant.

l On June 8,1994, the NRC staff notified you that we had completed our review

! of your GL 89-10 program. In that letter, we referred to your plans to l perform periodic performance verification of your safety-related motor-operated valves (H0Vs) and to continue to monitor industry data to ensure that margin was available to compensate for potential degradation. In the almost 2-1/2 years since the staff reviewed your GL 89-10 program, significant 1 activities have been conducted by the industry and NRC to address long-term '

MOV performance. These activities include:

i l 1. completion of the MOV performance prediction program by the Electric Power Research Institute and NRC issuance of a safety evaluation on the EPRI program;

, 2. preparation of a code case by the American Society of Mechanical l Engineers on an MOV periodic verification program that could be used as l

an alternative to stroke-time testing; and l 3. tests sponsored by the NRC on the aging of valve material samples.

In light of this new information, the staff requested in GL 96-05 that licensees who have developed MOV periodic verification programs in response to GL 89-10, review those programs to determine whether any changes are appropriate. The staff has also learned that the utility owners' groups are considering an industry-wide effort in developing long-term MOV programs in a

response to GL 96-05. Therefore, although the staff considered your MOV gg b 9612040262 961129 PDR ADOCK 05000483 P PDR

1 e . .. .

1 l I Mr. D. F. Schnell November 29, 1996 cc:

Professional Nuclear Mr. Neil S. Carns Consulting, Inc. President and Chief Exccutive Officer 19041 Raines Drive Wolf Creek Nuclear Operating Corporation Derwood, Maryland 20855 P.O. Box 411 Burlington, Kansas 66839  ;

Gerald Charnoff, Esq.

Thomas A. Baxter, Esq. Mr. Dan I. Bolef, President Shaw, Pittman, Potts & Trowbridge Kay Drey, Representative 2300 N. Street, N.W. Board of Directors Coalition Washington, D.C. 20037 for the Environment ,

6267 Delmar Boulevard  !

Mr. H. D. Bono University City, Missouri 63130 Supervising Engineer, Site Licensing Mr. Lee Fritz Union Electric Company Presiding Commissioner Post Office Box 620 Callaway County Court House i Fulton, Missouri 65251 10 East Fifth Street i Fulton, Missouri 65151 U.S. Nuclear Regulatory Commission

, Resident Inspector Office Mr. Alan C. Passwater, Manager  !

l 8201 NRC Road Licensing and Fuels  !

Steedman, Missouri 65077-1302 Union Electric Company l Post Office Box 149 Mr. G. L. Randolph, Vice President St. Louis, Missouri 63166 Nuclear Operations Union Electric Company Mr. J. V. Laux, Manager i P.O. Box 620 Quality Assurance l Fulton, Missouri 65251 Union Electric Company l

Post Office Box 620  ;

l Manager - Electric Department Fulton, Missouri 65251

! Missouri Public Service Commission 301 W. High i Post Office Box 360 l Jefferson City, Missouri 65102 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower & Pavilion 611 Ryan Plaza Drive, Suite 400 l Arlingtur., Texas 76011-8064 l Mr. Ronald A. Kucera, Deputy Director Department of Natural Resources P.O. Box 176

Jefferson City, Missouri 65102 1

(

l l

l e .

Mr. Donald Schnell 2-Based on the above, we request that you submit a supplemerit to your 60-day response within 15 days of receipt of this letter, indicating what action (s) you will be taking in response to GL 96-05 to ensure the effectiveness of the current MOV periodic verification program.

If you have any questions, please contact me at (301) 415-1362.

Sincerely, Original signed by:

Kristine M. Thomas, Project Manager 1 Project Directorate IV-2 l Division of Reactor Projects - III/IV Office of Nuclear Reactor Regulation Docket No. 50-483 DISTRIBUTION:

Docket; File cc See next page: PUBLIC~

PDIV-2 Reading JRoe EAdensam WBateman KThomas RWessman, EMEB ,

AHansen ACRS, TWFN ,

OGC, 015B18  ;

WJohnson, RIV I JDyer, RIV EPeyton TScarbrough, EMEB i

DOCUMENT NAME: CAL 97027.LTR (i 0FC N

PDIV-2/PM PDIV-2/LA EMEB48G NAME KTh$$[:ye EN RWeNan DATE 11/$/96 11 % /96 11M/96 0FFICIAL RECORD COPY o

040038

l 1

Mr. Donald Schnell Based on the above, we request that you submit a supplement to your 60-day rc ecse within 15 days of receipt of this letter, indicating what action (s) you will be taking in response to GL 96-05 to ensure the effectiveness of the current MOV periodic verification program.

If you have any questions, please contact me at (301) 415-1362.

Sincerely, Original signed by:

Kristine M. Thomas, Project Manager Project Directorate IV-2 Division of Reactor Projects - III/IV Office of Nuclear Reactor Regulation Docket No. 50-483 DISTRIBUTION:

Docket File i

cc See next page: PUBLIC

! PDIV-2 Reading i JRoe l EAdensam WBateman l KThomas RWessman, EMEB AHansen ACRS, TWFN OGC, 015B18 WJohnson, RIV  ;

JDyer, RIV l EPeyton l TScarbrough, EMEB COCUMENT NAME: CAL 97027.LTR (l h0\2U}(g OFC PDIV-2/PM PDIV-2/LA EMEBIAG 1 l NAME KTh'o$m7:ye EN RWeNan l DATE 11/6/96 l @ /96 11M/96

0FFICIAL RECORD COPY i