IR 05000285/2011005: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(3 intermediate revisions by the same user not shown)
Line 5: Line 5:
| author name = Clark J
| author name = Clark J
| author affiliation = NRC/RGN-IV/DRP
| author affiliation = NRC/RGN-IV/DRP
| addressee name = Bannister D J
| addressee name = Bannister D
| addressee affiliation = Omaha Public Power District
| addressee affiliation = Omaha Public Power District
| docket = 05000285
| docket = 05000285
Line 19: Line 19:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I V 1600 EAST LAMAR BLVD ARLINGTON, TEXAS 76011-4511 February 14, 2012 EA-11-288 David J. Bannister, Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station FC-2-4 P. O. Box 550 Fort Calhoun, NE 68023-0550 Subject: FORT CALHOUN - NRC INTEGRATED INSPECTION REPORT 05000285/2011005
[[Issue date::February 14, 2012]]


EA-11-288 David J. Bannister, Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station FC
==Dear Mr. Bannister:==
-2-4 P. O. Box 550 Fort Calhoun, NE 68023
On December 31, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Fort Calhoun Station. The enclosed integrated inspection report documents the inspection findings, which were discussed on January 9, 2012, with Mr. John Goodell, Division Manager, Nuclear Performance Improvement and Support, and other members of your staff.
-0550 Subject: FORT CALHOUN
- NRC INTEGRATED INSPECTION REPORT 05000285/201 1005


==Dear Mr. Bannister:==
The inspections examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.
On December 31, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Fort Calhoun Station. The enclosed integrated inspection report documents the inspection findings, which were discussed on January 9, 2012, with Mr. John Goodell, Division Manager, Nuclear Performance Improvement and Support, and other members of your staff. The inspections examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.


Two NRC-identified findings and tw o self-revealing finding s of very low safety significance (Green) were identified during this inspection.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.


Four of these findings were determined to involve violations of NRC requirements. Further , a licensee-identified violation, which was determined to be of very low safety significance, is listed in this report.
Two NRC-identified findings and two self-revealing findings of very low safety significance (Green) were identified during this inspection.


The NRC is treating these violations as non-cited violations, consistent with Section 2.3.2 of the NRC Enforcement Policy.
Four of these findings were determined to involve violations of NRC requirements. Further, a licensee-identified violation, which was determined to be of very low safety significance, is listed in this report. The NRC is treating these violations as non-cited violations, consistent with Section 2.3.2 of the NRC Enforcement Policy.


If you contest the violations or the significance of the noncited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, D.C.
If you contest the violations or the significance of the noncited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, D.C.


20555-0001, with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, D.C. 20555
20555-0001, with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001; and the NRC Resident Inspector at the Fort Calhoun Station facility.
-0001; and the NRC Resident Inspector at the Fort Calhoun Station facility.


If you disagree with the cross
If you disagree with the cross-cutting aspect assigned to any finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region IV, and the NRC Resident Inspector at Fort Calhoun.
-cutting aspect assigned to any finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your U N I T E D S T A T E S N U C L E A R R E G U L A T O R Y C O M M I S S I O N R E G I O N I V1600 EAST LAMAR BLVD A R L I N G T O N , T E X A S 7 6 0 1 1-4511 disagreement, to the Regional Administrator, Region IV, and the NRC Resident Inspector at Fort Calhoun.


In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, and its enclosure, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, and its enclosure, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs document system (ADAMS).
-rm/adams.html (the Public Electronic Reading Room).


Sincerely,/R.Deese for/ Jeff Clark, Branch Chief Project Branch F Division of Reactor Projects Docket No.: 50-285 License No.: DPR-40
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).


===Enclosure:===
Sincerely,
Inspection Report 05000 285/2011005 w/  
/R.Deese for/
 
Jeff Clark, Branch Chief Project Branch F Division of Reactor Projects Docket No.: 50-285 License No.: DPR-40 Enclosure: Inspection Report 05000285/2011005 w/ Attachment: Supplemental Information cc w/ enclosure: Electronic Distribution
===Attachment:===
Supplemental Information
 
cc w/ enclosure: Electronic Distribution


=SUMMARY OF FINDINGS=
=SUMMARY OF FINDINGS=
IR 05000 285/2011005; 10/01/2011
IR 05000285/2011005; 10/01/2011 - 12/31/2011; Fort Calhoun Station, Integrated Resident and


- 12/31/2011
Regional Report; Heat Sink Performance, Occupational Dose Assessment.
; Fort Calhoun Station, Integrated Resident and Regional Report;
Heat Sink Performance, Occupational Dose Assessment
. The report covered a 3
-month period of inspection by resident inspectors and three announced baseline inspections by region-based inspectors.


Four Green noncited violations of significance were identified. The significance of most findings is indicated by their color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, "Significance Determination Process."
The report covered a 3-month period of inspection by resident inspectors and three announced baseline inspections by region-based inspectors. Four Green noncited violations of significance were identified. The significance of most findings is indicated by their color (Green, White,
Yellow, or Red) using Inspection Manual Chapter 0609, Significance Determination Process.


Th e crosscutting aspect is determined using Inspection Manual Chapter 0310, "Components within the Cross Cutting Areas.Findings for which the significance determination process does not apply may be Green or be assigned a severity level after NRC management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG
The crosscutting aspect is determined using Inspection Manual Chapter 0310, Components within the Cross Cutting Areas. Findings for which the significance determination process does not apply may be Green or be assigned a severity level after NRC management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.
-1649, "Reactor Oversight Process," Revision 4, dated December 2006.


===A. NRC-Identified Findings and Self-Revealing Findings===
===NRC-Identified Findings and Self-Revealing Findings===


===Cornerstone: Initiating Events===
===Cornerstone: Initiating Events===
: '''Green.'''
: '''Green.'''
A self-revealing noncited violation of Fort Calhoun Station Technical Specification 5.8.1 occurred due to the licensee's failure to follow a procedure for placing the reactor coolant system level monitors into service. This failure resulted in the inadvertent draining of approximately 1
A self-revealing noncited violation of Fort Calhoun Station Technical Specification 5.8.1 occurred due to the licensees failure to follow a procedure for placing the reactor coolant system level monitors into service. This failure resulted in the inadvertent draining of approximately 1,800 gallons of reactor coolant to the reactor coolant drain tank. This issue was entered into the licensees corrective action program as Condition Report 2011-2890.
, 800 gallons of reactor coolant to the reactor coolant drain tank.


This issue was entered into the licensee's corrective action program as Condition Report 2011
The inspectors determined that the licensees failure to follow Procedure OI RC 1A,
-2890. The inspectors determined that the licensee's failure to follow Procedure OI RC 1A , "RCS Instrumentation Operating Instruction," was a performance deficiency. This was a result of the licensee's failure to properly implement a required procedure, and was within the licensee's ability to foresee and correct and should have been prevented. This performance deficiency was more than minor because it could be reasonably viewed as a precursor to a significant event, i.e., could lead to a complete loss of reactor coolant inventory. The inspectors evaluated this finding using Inspection Manual Chapter 0609, Attachment 4, and determined that this finding is associated with the Initiating Events Cornerstone, specifically the primary system loss-of-coolant accident initiator contributor. Since the finding affected the safety of the reactor during a refueling outage, the inspectors further evaluated the finding using Inspection Manual Chapter 0609, Appendix G, "Shutdown Operations Significance Determination Process.Using Attachment 1 of Appendix G, the inspectors determined that a Phase 2 analysis was required because the finding increased the likelihood of a loss of reactor coolant system inventory. A senior reactor analyst determined that the Phase 2 analysis was White, requiring a Phase 3 analysis. The Phase 3 analysis determined that the finding was of very low safety significance (green) because the leak path was small enough to allow sufficient time for operator action. This finding has a cross-cutting aspect in the area of human performance associated with the component of work practices because the licensee failed to communicate human error prevention techniques, such as self- and peer-checking [H.4(a)]. (Section 1R04)
RCS Instrumentation Operating Instruction, was a performance deficiency. This was a result of the licensees failure to properly implement a required procedure, and was within the licensees ability to foresee and correct and should have been prevented. This performance deficiency was more than minor because it could be reasonably viewed as a precursor to a significant event, i.e., could lead to a complete loss of reactor coolant inventory. The inspectors evaluated this finding using Inspection Manual Chapter 0609, Attachment 4, and determined that this finding is associated with the Initiating Events Cornerstone, specifically the primary system loss-of-coolant accident initiator contributor. Since the finding affected the safety of the reactor during a refueling outage, the inspectors further evaluated the finding using Inspection Manual Chapter 0609, Appendix G, Shutdown Operations Significance Determination Process. Using Attachment 1 of Appendix G, the inspectors determined that a Phase 2 analysis was required because the finding increased the likelihood of a loss of reactor coolant system inventory. A senior reactor analyst determined that the Phase 2 analysis was White, requiring a Phase 3 analysis. The Phase 3 analysis determined that the finding was of very low safety significance (green) because the leak path was small enough to allow sufficient time for operator action. This finding has a cross-cutting aspect in the area of human performance associated with the component of work practices because the licensee failed to communicate human error prevention techniques, such as self- and peer-checking [H.4(a)]. (Section 1R04)


===Cornerstone: Mitigating Systems===
===Cornerstone: Mitigating Systems===
: '''Green.'''
: '''Green.'''
The inspectors identified a noncited violation of 10 CFR Part 50, Appendix B, Criterion XI, "Test Control," which requires, in part, that a test program shall be established to assure that all testing required to demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures. Test procedures shall include provisions for assuring that all prerequisites for the given test have been met, that adequate test instrumentation is available and used, and that the test is performed under suitable environmental conditions. Specifically, prior to November 16, 2011, the prerequisite calculated heat loads used to demonstrate validity of the performance testing of component cooling water heat exchanger AC
The inspectors identified a noncited violation of 10 CFR Part 50,
-1A test conditions did not agree to within the expected uncertainty, and ultrasonic flow meters were not calibrated to the appropriate range of test flow conditions. The licensee has entered this violation into their corrective action program as Condition Report 2011
Appendix B, Criterion XI, Test Control, which requires, in part, that a test program shall be established to assure that all testing required to demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures. Test procedures shall include provisions for assuring that all prerequisites for the given test have been met, that adequate test instrumentation is available and used, and that the test is performed under suitable environmental conditions.
-9401. The inspectors determined that the failure to perform testing and evaluation of safety-related heat exchangers in accordance with written procedures was a performance deficiency. This finding is more than minor because it adversely affected the Mitigating Systems Cornerstone objective of equi pment performance to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Additionally, the finding is more than minor because if left uncorrected it could lead to a more significant safety concern, as the failure to perform appropriate performance monitoring testing of the component cooling water heat exchangers could reasonably result in an unrecognized condition of a system failing to fulfill its safety-related function. Using Inspection Manual Chapter 0609, Attachment 4, "Initial Screening and Characterization of Findings," the finding was determined to be of very low safety significance (Green) because it did not represent a loss of system safety function, nor an actual loss of safety function of a single train, and it did not screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event. The inspectors determined that this finding had a crosscutting aspect in the area of human performance, work practices, because the licensee did not communicate human error prevention techniques, such as self- and peer-checking and proper documentation of activities [H.4(a)] (Section 1R07).
 
Specifically, prior to November 16, 2011, the prerequisite calculated heat loads used to demonstrate validity of the performance testing of component cooling water heat exchanger AC-1A test conditions did not agree to within the expected uncertainty, and ultrasonic flow meters were not calibrated to the appropriate range of test flow conditions. The licensee has entered this violation into their corrective action program as Condition Report 2011-9401.
 
The inspectors determined that the failure to perform testing and evaluation of safety-related heat exchangers in accordance with written procedures was a performance deficiency. This finding is more than minor because it adversely affected the Mitigating Systems Cornerstone objective of equipment performance to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage).
 
Additionally, the finding is more than minor because if left uncorrected it could lead to a more significant safety concern, as the failure to perform appropriate performance monitoring testing of the component cooling water heat exchangers could reasonably result in an unrecognized condition of a system failing to fulfill its safety-related function. Using Inspection Manual Chapter 0609, Attachment 4,
        "Initial Screening and Characterization of Findings," the finding was determined to be of very low safety significance (Green) because it did not represent a loss of system safety function, nor an actual loss of safety function of a single train, and it did not screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event. The inspectors determined that this finding had a crosscutting aspect in the area of human performance, work practices, because the licensee did not communicate human error prevention techniques, such as self-and peer-checking and proper documentation of activities [H.4(a)] (Section 1R07).


===Cornerstone: Occupational Radiation Safety===
===Cornerstone: Occupational Radiation Safety===
: '''Green.'''
: '''Green.'''
Inspectors reviewed a self-revealing, noncited violation of Technical Specification 5.8.1 for failure to follow procedures requiring workers to comply with radiological work permit instructions. Specifically, two workers changed the work scope for valve FCV-326 from reassembly to rework using abrasive pads without notifying radiation protection personnel. The licensee's corrective action was to counsel the workers on the importance of adhering to the stated work scope and radiation work permit procedur es. This issue was entered into the licensee's corrective action program as Condition Reports 2011
Inspectors reviewed a self-revealing, noncited violation of Technical Specification 5.8.1 for failure to follow procedures requiring workers to comply with radiological work permit instructions. Specifically, two workers changed the work scope for valve FCV-326 from reassembly to rework using abrasive pads without notifying radiation protection personnel. The licensees corrective action was to counsel the workers on the importance of adhering to the stated work scope and radiation work permit procedures. This issue was entered into the licensees corrective action program as Condition Reports 2011-3944, 2011-3046, and 2011-9795.
-3944, 2011
-3046, and 2011
-9795. The failure to follow the requirements of the radiation work permit as instructed by radiation protection was a performance deficiency.
 
The finding was more than minor because it was associated with the Occupational Radiation Safety Cornerstone attribute of program and process and affected the cornerstone objective of ensuring adequate protection of worker health and safety from exposure to radiation during routine operations. Using the Occupational Radiation Safety Significance Determination Process, the inspector s determined the finding to have very low safety significance because:
  (1) it was not associated with ALARA planning or work controls, (2)there was no overexposure, (3) there was no substantial potential for an overexposure, and (4) the ability to assess dose was not compromised.


The finding was determined to have a human performance crosscutting aspect associated with work practices, because the licensee failed to ensure supervisory and management oversight of work activities, including contractors, such that nuclear safety is supported [H.4(c)] (2RS04).
The failure to follow the requirements of the radiation work permit as instructed by radiation protection was a performance deficiency. The finding was more than minor because it was associated with the Occupational Radiation Safety Cornerstone attribute of program and process and affected the cornerstone objective of ensuring adequate protection of worker health and safety from exposure to radiation during routine operations. Using the Occupational Radiation Safety Significance Determination Process, the inspectors determined the finding to have very low safety significance because: (1) it was not associated with ALARA planning or work controls, (2) there was no overexposure, (3) there was no substantial potential for an overexposure, and (4)the ability to assess dose was not compromised. The finding was determined to have a human performance crosscutting aspect associated with work practices, because the licensee failed to ensure supervisory and management oversight of work activities, including contractors, such that nuclear safety is supported
          [H.4(c)] (2RS04).


===Cornerstone: Emergency Preparedness===
===Cornerstone: Emergency Preparedness===
: '''Green.'''
: '''Green.'''
The inspectors identified a noncited violation of 10 CFR 50.47(b)(10) for failure to develop and put into place guidelines for the choice of protective actions during an emergency that implemented federal guidance.
The inspectors identified a noncited violation of 10 CFR 50.47(b)(10) for failure to develop and put into place guidelines for the choice of protective actions during an emergency that implemented federal guidance. Specifically, licensee guidance did not implement Regulatory Information Summary 2003-012, in that it allowed the subsequent removal of recommendations to evacuate members of the public during a radiological emergency.


Specifically, licensee guidance did not implement Regulatory Information Summary 2003
This finding is more than minor because it affected the Emergency Preparedness Cornerstone attributes of emergency response organization performance and procedure quality. The finding had a credible impact on the cornerstone objective because rescinding an existing protective action recommendation can confuse offsite governmental authorities and the public. The finding is of very low safety significance because it was not a functional failure or degraded planning standard function. The finding was not a degraded planning standard function because the licensees process was capable of producing correct protective action recommendations. This finding has been entered into the licensees corrective action program as Condition Report 2011-8530 (Section 4OA1).
-012 , in that it allowed the subsequent removal of recommendations to evacuate members of the public during a radiological emergency.


This finding is more than minor because it affected the Emergency Preparedness Cornerstone attributes of emergency response organization performance and procedure quality. The finding had a credible impact on the cornerstone objective because rescinding an existing protective action recommendation can confuse offsite governmental authorities and the public. The finding is of very low safety significance because it was not a functional failure or degraded planning standard function. The finding was not a degraded planning standard function because the licensee's process was capable of producing correct protective action recommendations. This finding has been entered into the licensee's corrective action program as Condition Report 2011
===Licensee-Identified Violations===
-8530 (Section 4OA1).


===B. Licensee-Identified Violations===
A violation of very low safety significance, which was identified by the licensee, has been reviewed by the inspectors. Corrective actions taken or planned by the licensee have been entered into the licensees corrective action program. This violation and its corrective actions are listed in Section 4OA7 of this report.
 
A violation of very low safety significance, which was identified by the licensee, has been reviewed by the inspector s. Corrective actions taken or planned by the licensee have been entered into the licensee's corrective action program. This violation and its corrective actions are listed in Section 4OA7 of this report.


=REPORT DETAILS=
=REPORT DETAILS=
Line 117: Line 98:
===Summary of Plant Status===
===Summary of Plant Status===


The station remained in Mode 5 for the entire inspection period
The station remained in Mode 5 for the entire inspection period.


==REACTOR SAFETY==
==REACTOR SAFETY==
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity {{a|1R04}}
{{a|1R04}}
==1R04 Equipment Alignments==
==1R04 Equi pm ent Alignments==
{{IP sample|IP=IP 71111.04}}
{{IP sample|IP=IP 71111.04}}
===.1 Partial Walkdown===
===.1 Partial Walkdown===


a. The inspectors performed partial system walkdowns of the following risk
====a. Inspection Scope====
-significant systems: Inspection Scope April 12, 2011, Reactor Coolant System shutdown level instrumentation lineup October 26, 2011, Shutdown Cooling lineup with HCV
The inspectors performed partial system walkdowns of the following risk-significant systems:
-335 (Shutdown Cooling Heat Exchangers AC
* April 12, 2011, Reactor Coolant System shutdown level instrumentation lineup
-4A&B Inlet Header Isolation Valve) closed The inspectors selected these systems based on their risk significance relative to the reactor safety cornerstones at the time they were inspected. The inspectors attempted to identify any discrepancies that could affect the function of the system, and therefore, potentially increase risk. The inspectors reviewed applicable operating procedures, system diagrams, Updates Safety Analysis Repo rt, technical specification requirements, administrative technical specifications, outstanding work orders, condition reports, and the impact of ongoing work activities on redundant trains of equi pment in order to identify conditions that could have rendered the systems incapable of performing their intended functions. The inspectors also inspected accessible portions of the systems to verify system components and support equipmen t were aligned correctly and operable. The inspectors examined the material condition of the components and observed operating parameters of equipmen t to verify that there were no obvious deficiencies. The inspectors also verified that the licensee had properly identified and resolved equipmen t alignment problems that could cause initiating events or impact the capability of mitigating systems or barriers and entered them into the corrective action program with the appropriate significance characterization. Specific documents reviewed during this inspection are listed in the attachment.
* October 26, 2011, Shutdown Cooling lineup with HCV-335 (Shutdown Cooling Heat Exchangers AC-4A&B Inlet Header Isolation Valve) closed The inspectors selected these systems based on their risk significance relative to the reactor safety cornerstones at the time they were inspected. The inspectors attempted to identify any discrepancies that could affect the function of the system, and therefore, potentially increase risk. The inspectors reviewed applicable operating procedures, system diagrams, Updates Safety Analysis Report, technical specification requirements, administrative technical specifications, outstanding work orders, condition reports, and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have rendered the systems incapable of performing their intended functions. The inspectors also inspected accessible portions of the systems to verify system components and support equipment were aligned correctly and operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no obvious deficiencies. The inspectors also verified that the licensee had properly identified and resolved equipment alignment problems that could cause initiating events or impact the capability of mitigating systems or barriers and entered them into the corrective action program with the appropriate significance characterization. Specific documents reviewed during this inspection are listed in the attachment.


These activities constitute completion of two partial system walkdown s sample as defined in Inspection Procedure
These activities constitute completion of two partial system walkdowns sample as defined in Inspection Procedure 71111.04-05.


==71111.04 - 05.==
====b. Findings====
 
b.


=====Introduction.=====
=====Introduction.=====
A self-revealing noncited violation of Fort Calhoun Station Technical Specification 5.8.1 occurred due to the licensee's failure to follow a procedure while placing the reactor coolant system level monitors into service. This failure resulted in the inadvertent draining of approximately 1,800 gallons of reactor coolant to the reactor coolant drain tank. Findings
A self-revealing noncited violation of Fort Calhoun Station Technical Specification 5.8.1 occurred due to the licensees failure to follow a procedure while placing the reactor coolant system level monitors into service. This failure resulted in the inadvertent draining of approximately 1,800 gallons of reactor coolant to the reactor coolant drain tank.


=====Description.=====
=====Description.=====
On April 12, 2011, the licensee was in the process of placing the reactor coolant system level sight glass (LI-199), the reactor coolant system shutdown level transmitter (LT
On April 12, 2011, the licensee was in the process of placing the reactor coolant system level sight glass (LI-199), the reactor coolant system shutdown level transmitter (LT-197), and the reactor hot leg coolant level transmitter (LT-119) in service using Procedure OI-RC-1A, RCS Instrumentation Operating Instruction. The valve line-up directed the operator to check RC-122 (loop 1 hot leg drain to waste disposal)closed then open RC-128 (loop 1 hot leg refueling level isolation valve).
-197), and the reactor hot leg coolant level transmitter (LT-119) in service using Procedure OI
 
-RC-1A, "RCS Instrumentation Operating Instruction.The valve line-up direct ed the operator to check RC
While performing the valve line-up, the operator opened RC-122 rather than check it closed. At approximately 4:25 p.m., the operator opened RC-128 with no peer-check performed for the operator. This created a flow path for water to be drained from the hot leg to the reactor coolant drain tank. At approximately 4:45 p.m., RC-122 was closed, stopping the draining of reactor coolant. The pressurizer level decreased from 69 percent to 34 percent, which was approximately 1,800 gallons.
-122 (loop 1 hot leg drain to waste disposal
) closed then open RC
-128 (loop 1 hot leg refueling level isolation valve). While performing the valve line
-up, the operator opened RC
-122 rather than check it closed. At approximately 4:25 p
.m., the operator opened RC
-128 with no peer-check performed for the operator. This created a flow path for water to be drained from the hot leg to the reactor coolant drain tank. At approximately 4:45 p.m., RC-122 was closed, stopping the draining of reactor coolant. The pressurizer level decreased from 69 percent to 34 percent, which was approximately 1,800 gallons.  


=====Analysis.=====
=====Analysis.=====
The inspectors determined that the licensee's failure to follow Procedure OI-RC-1A was a performance deficiency. This was a result of the licensee's failure to properly implement a required procedure, and was within the licensee's ability to foresee and correct and should have been prevented. This performance deficiency was more than minor because it could be reasonably viewed as a precursor to a significant event, i.e., could lead to a complete loss of reactor coolant inventory. The inspectors evaluated this finding using Inspection Manual Chapter 0609, Attachment 4, and determined that this finding is associated with the Initiating Events Cornerstone, specifically the primary system loss
The inspectors determined that the licensees failure to follow Procedure OI-RC-1A was a performance deficiency. This was a result of the licensees failure to properly implement a required procedure, and was within the licensees ability to foresee and correct and should have been prevented. This performance deficiency was more than minor because it could be reasonably viewed as a precursor to a significant event, i.e., could lead to a complete loss of reactor coolant inventory. The inspectors evaluated this finding using Inspection Manual Chapter 0609, Attachment 4, and determined that this finding is associated with the Initiating Events Cornerstone, specifically the primary system loss-of-coolant accident initiator contributor. Since the finding affected the safety of the reactor during a refueling outage, the inspectors further evaluated the finding using Inspection Manual Chapter 0609, Appendix G, Shutdown Operations Significance Determination Process. Using Attachment 1 of Appendix G, the inspectors determined that a Phase 2 analysis was required because the finding increased the likelihood of a loss of reactor coolant system inventory. A senior reactor analysis determined that the Phase 2 analysis was White, requiring a Phase 3 analysis.
-of-coolant accident initiator contributor. Since the finding affected the safety of the reactor during a refueling outage, the inspectors further evaluated the finding using Inspection Manual Chapter 0609, Appendix G, "Shutdown Operations Significance Determination Process.Using Attachment 1 of Appendix G, the inspectors determined that a Phase 2 analysis was required because the finding increased the likelihood of a loss of reactor coolant system inventory. A senior reactor analysis determined that the Phase 2 analysis was White, requiring a Phase 3 analysi s. The analyst s performed a Phase 3 Significance Determination Process risk analysis using a modified version of the Fort Calhoun Station at
-power Standardized Probabilistic Analysis Risk model, Version 8.15. The analysts developed an event tree specific to a loss of reactor coolant system inventory outside containment with the reactor in a shutdown condition. The Region IV senior reactor analyst quantified the risk of the event as a conditional core damage probability of 3.0 x 10
-7. The dominant core damage sequence from the model involv ed the following events:
An operator misaligns the level sight glass valve, initiating a 90 g p m drain of the reactor coolant system; Control room operators diagnose that a loss of inventory  is occurring before the shutdown cooling system fails from cavitation; Operators fail to isolate the loss of inventory before the shutdown cooling system fails from cavitation; Operators fail to provide forced feed to the reactor before the shutdown cooling system fails from cavitation; The operating train of shutdown cooling fails from cavitation as level drops below the middle of the primary system hot leg; Operators fail to provide forced feed to the reactor after shutdown cooling has failed; and The reactor core heats up, causing water to boil, resulting in uncovering the active fuel and the onset of fuel damage.


These events were all the result of operator actions. As documented in NUREG/CR-6883, "The SPAR
The analysts performed a Phase 3 Significance Determination Process risk analysis using a modified version of the Fort Calhoun Station at-power Standardized Probabilistic Analysis Risk model, Version 8.15. The analysts developed an event tree specific to a loss of reactor coolant system inventory outside containment with the reactor in a shutdown condition. The Region IV senior reactor analyst quantified the risk of the event as a conditional core damage probability of 3.0 x 10-7. The dominant core damage sequence from the model involved the following events:
-H Human Reliability Analysis Method," the more time available to a crew to diagnose and act upon an abnormal event the less likely they are to fail in a given task. Because the leak path was sufficiently small (90 g pm) and the amount of water sufficiently large (31,000 gallons), there was additional time for operators to take the actions documented above. As such, the probability of failure for these actions was lower than they would have been with a higher leak rate.
* An operator misaligns the level sight glass valve, initiating a 90 gpm drain of the reactor coolant system;
* Control room operators diagnose that a loss of inventory is occurring before the shutdown cooling system fails from cavitation;
* Operators fail to isolate the loss of inventory before the shutdown cooling system fails from cavitation;
* Operators fail to provide forced feed to the reactor before the shutdown cooling system fails from cavitation;
* The operating train of shutdown cooling fails from cavitation as level drops below the middle of the primary system hot leg;
* Operators fail to provide forced feed to the reactor after shutdown cooling has failed; and
* The reactor core heats up, causing water to boil, resulting in uncovering the active fuel and the onset of fuel damage.


As stated above, the quantified conditional core damage frequency for the event was of 3.0 x 10-7 , thus making this finding of very low risk significance (Green).
These events were all the result of operator actions. As documented in NUREG/CR-6883, The SPAR-H Human Reliability Analysis Method, the more time available to a crew to diagnose and act upon an abnormal event the less likely they are to fail in a given task. Because the leak path was sufficiently small (90 gpm) and the amount of water sufficiently large (31,000 gallons), there was additional time for operators to take the actions documented above. As such, the probability of failure for these actions was lower than they would have been with a higher leak rate.


This finding has a cross-cutting aspect in the area of human performance associated with the component of work practices because the licensee failed to communicate human error prevention techniques, such as self- and peer-checking [H.4(a)].
As stated above, the quantified conditional core damage frequency for the event was of 3.0 x 10-7, thus making this finding of very low risk significance (Green). This finding has a cross-cutting aspect in the area of human performance associated with the component of work practices because the licensee failed to communicate human error prevention techniques, such as self- and peer-checking [H.4(a)].


=====Enforcement.=====
=====Enforcement.=====
Technical Specification 5.8.1.a, "Procedures," states, written procedures and administrative policies shall be established, implemented, and maintained covering the following activities:
Technical Specification 5.8.1.a, Procedures, states, written procedures and administrative policies shall be established, implemented, and maintained covering the following activities:
: (a) The applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, 1978. NRC Regulatory Guide 1.33, "Quality Assurance Program Requirements (Operation)," Appendix A, "Typical Procedures for Pressurized Water Reactors and Boiling Water Reactors," Section 3, "Procedures for Startup, Operation, and Shutdown of Safety
: (a) The applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, 1978. NRC Regulatory Guide 1.33, Quality Assurance Program Requirements (Operation), Appendix A, Typical Procedures for Pressurized Water Reactors and Boiling Water Reactors, Section 3, Procedures for Startup, Operation, and Shutdown of Safety-Related PWR Systems, states, in part, that instructions for energizing, filling, venting, startup and changing modes of operation should be prepared for the Reactor Coolant System. Attachment 3, Placing LT-119, LI-199 and LT-197 In Service, of Fort Calhoun Station Procedure OI-RC-1A, RCS Instrumentation requires the completion of Checklist OI-RC-1A-CL-A. Checklist OI-RC-1A-CL-A indicates that the desired position of RC-122 (loop 1 hot leg drain to waste disposal) is closed. Contrary to the above, on April 12, 2011, in the process of placing reactor coolant system level monitors into service, the licensee failed to properly implement Fort Calhoun Station Procedure OI-RC-1A, RCS Instrumentation and complete Checklist OI-RC-1A-CL-A. Specifically, the licensee opened RC-122, instead
-Related PWR Systems
 
," states, in part, that instructions for energizing, filling, venting, startup and changing modes of operation should be prepared for the Reactor Coolant System. Attachment 3, "Placing LT
of checking it closed. This resulted in the inadvertent draining of approximately 1,800 gallons of reactor coolant to the reactor coolant drain tank. The licensee has entered this condition into their corrective action program as Condition Report 2011-2890.
-119, LI-199 and LT
-197 In Service," of Fort Calhoun Station Procedure OI
-RC-1A, "RCS Instrumentation" requires the completion of Checklist OI
-RC-1A-CL-A. Checklist OI
-RC-1A-CL-A indicates that the desired position of RC
-122 (loop 1 hot leg drain to waste disposal) is closed. Contrary to the above, on April 12, 2011, in the process of placing r eactor coolant system level monitors into service, the licensee failed to properly implement Fort Calhoun Station Procedure OI
-RC-1A, "RCS Instrumentation" and complete Checklist OI
-RC-1A-CL-A. Specifically, the licensee opened RC
-122, instead of checking it closed. This resulted in the inadvertent draining of approximately 1,800 gallons of reactor coolant to the reactor coolant drain tank.


The licensee has entered this condition into their corrective action program as Condition Report 2011
Because this finding was of very low safety significance and it was entered into the licensees corrective action program, this violation is being treated as a noncited violation, consistent with Section 2.3.2 of the NRC Enforcement Policy; NCV 05000285/2011005-01, Failure to Follow Procedure Results in a Loss of Reactor Coolant. (EA-11-288)
-2890. Because this finding was of very low safety significance and it was entered into the licensee's corrective action program, this violation is being treated as a noncited violation, consistent with Section 2.3.2 of the NRC Enforcement Policy; NC V 05000285/201100 5-01, "Failure to Follow Procedure Results in a Loss of Reactor Coolant." (EA-11-288)
{{a|1R05}}
{{a|1R05}}
==1R05 Fire Protection==
==1R05 Fire Protection==
Line 188: Line 151:
===.1 Quarterly Fire Inspection Tours===
===.1 Quarterly Fire Inspection Tours===


a. The inspectors conducted fire protection walkdowns that were focused on availability, accessibility, and the condition of firefighting equipmen t in the following risk
====a. Inspection Scope====
-significant plant areas:
The inspectors conducted fire protection walkdowns that were focused on availability, accessibility, and the condition of firefighting equipment in the following risk-significant plant areas:
Inspection Scope November 28, 2011, Fire Area 32, Compressor Area (Room 19)
* November 28, 2011, Fire Area 32, Compressor Area (Room 19)
November 29, 2011, Fire Area 42, Control Room Complex (Rooms 72  
* November 29, 2011, Fire Area 42, Control Room Complex (Rooms 72 - 81)
- 81) December 19, 2011, Fire Area 34B, Electrical Penetration Area Ground and Intermediate Levels (Room 57)
* December 19, 2011, Fire Area 34B, Electrical Penetration Area Ground and Intermediate Levels (Room 57)
The inspectors reviewed areas to assess if licensee personnel had implemented a fire protection program that adequately controlled combustibles and ignition sources within the plant; effectively maintained fire detection and suppression capability; maintained passive fire protection features in good material condition; and had implemented adequate compensatory measures for out of service, degraded or inoperable fire protection equipmen t, systems, or features, in accordance with the licensee's fire plan. The inspectors selected fire areas based on their overall contribution to internal fire risk as documented in the plant's Individual Plant Examination of External Events with later additional insights, their potential to affect equipmen t that could initiate or mitigate a plant transient, or their impact on the plant's ability to respond to a security event. Using the documents listed in the attachment, the inspectors verified that fire hoses and extinguishers were in their designated locations and available for immediate use; that fire detectors and sprinklers were unobstructed; that transient material loading was within the analyzed limits; and fire doors, dampers, and penetration seals appeared to be in satisfactory condition. The inspectors also verified that minor issues identified during the inspection were entered into the licensee's corrective action program. Specific documents reviewed during this inspection are listed in the attachment.
The inspectors reviewed areas to assess if licensee personnel had implemented a fire protection program that adequately controlled combustibles and ignition sources within the plant; effectively maintained fire detection and suppression capability; maintained passive fire protection features in good material condition; and had implemented adequate compensatory measures for out of service, degraded or inoperable fire protection equipment, systems, or features, in accordance with the licensees fire plan.


These activities constitute completion of three quarterly fire
The inspectors selected fire areas based on their overall contribution to internal fire risk as documented in the plants Individual Plant Examination of External Events with later additional insights, their potential to affect equipment that could initiate or mitigate a plant transient, or their impact on the plants ability to respond to a security event. Using the documents listed in the attachment, the inspectors verified that fire hoses and extinguishers were in their designated locations and available for immediate use; that fire detectors and sprinklers were unobstructed; that transient material loading was within the analyzed limits; and fire doors, dampers, and penetration seals appeared to be in satisfactory condition. The inspectors also verified that minor issues identified during the inspection were entered into the licensees corrective action program.
-protection inspection samples as defined in Inspection Procedure


==71111.05 - 05.==
Specific documents reviewed during this inspection are listed in the attachment.


b. No findings were identified.
These activities constitute completion of three quarterly fire-protection inspection samples as defined in Inspection Procedure 71111.05-05.


Findings
====b. Findings====
No findings were identified.


===.2 Annual Fire Protection Drill Observation===
===.2 Annual Fire Protection Drill Observation===
{{IP sample|IP=IP 71111.05A}}
{{IP sample|IP=IP 71111.05A}}
a. On October 1 5, 2011, the inspectors observed a fire brigade activation to combat a fire in the fabrication shop. The observation evaluated the readiness of the plant fire brigade to fight fires. The inspectors verified that the licensee staff identified deficiencies; openly discussed them in a self
-critical manner at the drill debrief, and took appropriate corrective actions. Specific attributes evaluated were (1)proper wearing of turnout gear and self-contained breathing apparatus; (2)proper use and layout of fire hoses;
: (3) employment of appropriate fire fighting techniques; (4)sufficient firefighting equi pm en t brought to the scene; (5)effectiveness of fire brigade leader communications, command, and control; (6)search for victims and propagation of the fire into other plant areas; (7)smoke removal operations; (8)utilization of preplanned strategies;
: (9) adherence to the preplanned drill scenario; and (10)drill objectives.


Inspection Scope These activities constitute completion of one annual fire
====a. Inspection Scope====
-protection inspection sample as defined in Inspection Procedure
On October 15, 2011, the inspectors observed a fire brigade activation to combat a fire in the fabrication shop. The observation evaluated the readiness of the plant fire brigade to fight fires. The inspectors verified that the licensee staff identified deficiencies; openly discussed them in a self-critical manner at the drill debrief, and took appropriate corrective actions. Specific attributes evaluated were
: (1) proper wearing of turnout gear and self-contained breathing apparatus;
: (2) proper use and layout of fire hoses;
: (3) employment of appropriate fire fighting techniques;
: (4) sufficient firefighting equipment brought to the scene;
: (5) effectiveness of fire brigade leader communications, command, and control;
: (6) search for victims and propagation of the fire into other plant areas;
: (7) smoke removal operations;
: (8) utilization of preplanned strategies;
: (9) adherence to the preplanned drill scenario; and
: (10) drill objectives.


==71111.05 - 05.==
These activities constitute completion of one annual fire-protection inspection sample as defined in Inspection Procedure 71111.05-05.
b. No findings were identified.


Findings
====b. Findings====
{{a|1R06}}
No findings were identified. {{a|1R06}}
==1R06 Flood Protection Measures==
==1R06 Flood Protection Measures==
{{IP sample|IP=IP 71111.06}}
{{IP sample|IP=IP 71111.06}}
a. The inspectors reviewed the Updated Safety Analysis Report, the flooding analysis, and plant procedures to assess susceptibilities involving internal flooding; reviewed the corrective action program to determine if licensee personnel identified and corrected flooding problems; inspected underground bunkers/manholes to verify the adequacy of sump pumps, level alarm circuits, cable splices subject to submergence, and drainage for bunkers/manholes; and verified that operator actions for coping with flooding can reasonably achieve the desired outcomes. The inspectors also inspected the areas listed below to verify the adequacy of equipmen t seals located below the flood line, floor and wall penetration seals, watertight door seals, common drain lines and sumps, sump pumps, level alarms, and control circuits, and temporary or removable flood barriers. Specific documents reviewed during this inspection are listed in the attachment.


Inspection Scope December 22, 2011, Safety Injection and Containment Spray Pump Areas, Rooms 21 and 22 These activities constitute completion of one flood protection measures inspection sample as defined in Inspection Procedure
====a. Inspection Scope====
The inspectors reviewed the Updated Safety Analysis Report, the flooding analysis, and plant procedures to assess susceptibilities involving internal flooding; reviewed the corrective action program to determine if licensee personnel identified and corrected flooding problems; inspected underground bunkers/manholes to verify the adequacy of sump pumps, level alarm circuits, cable splices subject to submergence, and drainage for bunkers/manholes; and verified that operator actions for coping with flooding can reasonably achieve the desired outcomes. The inspectors also inspected the areas listed below to verify the adequacy of equipment seals located below the flood line, floor and wall penetration seals, watertight door seals, common drain lines and sumps, sump pumps, level alarms, and control circuits, and temporary or removable flood barriers.


==71111.06 - 05.==
Specific documents reviewed during this inspection are listed in the attachment.
* December 22, 2011, Safety Injection and Containment Spray Pump Areas, Rooms 21 and 22 These activities constitute completion of one flood protection measures inspection sample as defined in Inspection Procedure 71111.06-05.


b. No findings were identified.
====b. Findings====
 
No findings were identified. {{a|1R07}}
Findings
{{a|1R07}}
==1R07 Heat Sink Performance==
==1R07 Heat Sink Performance==
{{IP sample|IP=IP 71111.07}}
{{IP sample|IP=IP 71111.07}}
a. The inspectors reviewed licensee programs, verified performance against industry standards, and reviewed critical operating parameters and maintenance records for component cooling water heat exchanger AC
-1A, shutdown
-cooling heat exchanger AC-4B, and the spent fuel pool heat exchanger. The inspectors verified that performance tests were satisfactorily conducted for heat exchangers/heat sinks and reviewed for problems or errors; the licensee utilized the periodic maintenance method outlined in EPRI Report NP 7552, "Heat Exchanger Performance Monitoring Guidelines," the licensee properly utilized biofouling controls; the licensee's heat exchanger inspections adequately assessed the state of cleanliness of their tubes; and the heat exchanger was correctly categorized under 10 CFR 50.65, "Requirements for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants."  Specific documents reviewed during this inspection are listed in the attachment.


Inspection Scope These activities constitute completion of three heat sink inspection samples as defined in Inspection Procedure
====a. Inspection Scope====
The inspectors reviewed licensee programs, verified performance against industry standards, and reviewed critical operating parameters and maintenance records for component cooling water heat exchanger AC-1A, shutdown-cooling heat exchanger AC-4B, and the spent fuel pool heat exchanger. The inspectors verified that performance tests were satisfactorily conducted for heat exchangers/heat sinks and reviewed for problems or errors; the licensee utilized the periodic maintenance method outlined in EPRI Report NP 7552, "Heat Exchanger Performance Monitoring Guidelines, the licensee properly utilized biofouling controls; the licensees heat exchanger inspections adequately assessed the state of cleanliness of their tubes; and the heat exchanger was correctly categorized under 10 CFR 50.65, Requirements for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants. Specific documents reviewed during this inspection are listed in the attachment.
 
These activities constitute completion of three heat sink inspection samples as defined in Inspection Procedure 71111.07-05.


==71111.07 - 05.==
====b. Findings====
b. Inadequate Performance Monitoring Test for Component Cooling Water Heat Exchangers Findings
Inadequate Performance Monitoring Test for Component Cooling Water Heat Exchangers    


=====Introduction.=====
=====Introduction.=====
The inspectors identified a Green noncited violation of 10 CFR Part 50, Appendix B, Criterion XI, "Test Control," for the failure to perform component cooling water heat exchanger performance monitoring testing in accordance with station procedures. The licensee did not meet prerequisites for assuring that the calculated tube and shell side heat loads were the same and did not use appropriately calibrated flow monitoring instrumentation.
The inspectors identified a Green noncited violation of 10 CFR Part 50, Appendix B, Criterion XI, Test Control, for the failure to perform component cooling water heat exchanger performance monitoring testing in accordance with station procedures. The licensee did not meet prerequisites for assuring that the calculated tube and shell side heat loads were the same and did not use appropriately calibrated flow monitoring instrumentation.


=====Description.=====
=====Description.=====
The inspectors reviewed test results associated with the October 14, 2010, and March 30, 2011, component cooling water AC
The inspectors reviewed test results associated with the October 14, 2010, and March 30, 2011, component cooling water AC-1A heat exchanger performance monitoring test. The inspectors noted that the calculated heat loads for each side of the heat exchanger differed by 57 percent in the October 14, 2010 test and 19 percent in the March 30, 2011 test. The calculated heat loads for the two sides of the heat exchanger should have been the same for each respective test.
-1A heat exchanger performance monitoring test. The inspectors noted that the calculated heat loads for each side of the heat exchanger differed by 57 percent in the October 14, 2010 test and 19 percent in the March 30, 2011 test. The calculated heat loads for the two sides of the heat exchanger should have been the same for each respective test.
 
The licensee monitors performance of the component cooling water heat exchanger in accordance with Procedures SE-PFT-CCW-0001, Component Cooling Water Heat Exchangers Performance Test, and PED-SEI-16, Evaluation of Heat Exchanger Performance. Procedure PED-SEI-16, Revision 9, Step 5.2.1, Section E, states that


The licensee monitors performance of the component cooling water heat exchanger in accordance with Procedures SE
the calculated tube and shell side heat loads should be within 15 percent. If the difference between the heat loads is higher, the test conditions are not valid and the test cannot be performed. For both the October 14, 2010, and March 30, 2011, component cooling water AC-1A heat exchanger tests, test data was collected and the evaluation of performance was completed despite the heat loads not agreeing within 15 percent. The inspectors performed an extent of condition review of test data and identified several other instances for other heat exchangers in the component cooling water system for which the calculated heat loads exceeded the 15 percent agreement prerequisite.
-PFT-CCW-0001, "Component Cooling Water Heat Exchangers Performance Test," and PED
-SEI-16, "Evaluation of Heat Exchanger Performance."  Procedure PED
-SEI-16, Revision 9, Step 5.2.1, Section E, states that "the calculated tube and shell side heat loads should be within 15 percent. If the difference between the heat loads is higher, the test conditions are not valid and the test cannot be performed.For both the October 14, 2010, and March 30, 2011, component cooling water AC
-1A heat exchanger tests, test data was collected and the evaluation of performance was completed despite the heat loads not agreeing within 15 percent. The inspectors performed an extent of condition review of test data and identified several other instances for other heat exchangers in the component cooling water system for which the calculated heat loads exceeded the 15 percent agreement prerequisite.


The licensee could not provide a technical justification for the use of 15 percent as the acceptance criterion for the heat balance check. Any error between the calculated heat loads should be attributed to the uncertainty in the fluid temperature and flow rate measurements used to determine the heat transfer rates. If the heat loads do not agree to within the expected measurement uncertainty, the disparity could be due to instrument problems, unexpected heat losses from the heat exchanger to ambient surroundings, or bypass flow, in which a portion of the measured flow may not be going through the heat transfer surface. Any such conditions would call into question the validity of the test.
The licensee could not provide a technical justification for the use of 15 percent as the acceptance criterion for the heat balance check. Any error between the calculated heat loads should be attributed to the uncertainty in the fluid temperature and flow rate measurements used to determine the heat transfer rates. If the heat loads do not agree to within the expected measurement uncertainty, the disparity could be due to instrument problems, unexpected heat losses from the heat exchanger to ambient surroundings, or bypass flow, in which a portion of the measured flow may not be going through the heat transfer surface. Any such conditions would call into question the validity of the test.


Furthermore, the check of calculated heat loads does not occur until Step 5.2.1, Section E, of Procedure PED
Furthermore, the check of calculated heat loads does not occur until Step 5.2.1, Section E, of Procedure PED-SEI-16, after all data collection is complete. This step would be more appropriately located in the beginning of the data collection procedure.
-SEI-16, after all data collection is complete. This step would be more appropriately located in the beginning of the data collection procedure. The heat balance check should be a prerequisite to validate that the licensee is obtaining quality test data. Additionally, the check of calculated heat loads did not require that the 15 percent agreement calculation actually be performed and documented and did not require a signature or peer check.
 
The heat balance check should be a prerequisite to validate that the licensee is obtaining quality test data. Additionally, the check of calculated heat loads did not require that the 15 percent agreement calculation actually be performed and documented and did not require a signature or peer check.


The inspectors reviewed calibration records for the portable ultrasonic flow meters used in the component cooling water performance monitoring test. The portable ultrasonic flow meters were calibrated over a range of approximately 100 to 500 gallons per minute. The flow rates used in the heat exchanger test range from approximately 1,000 gallons per minute to 4,000 gallons per minute. The flow meters were verified to have a vendor rated capacity of up to 50,000 gallons per minute, but 500 gallons per minute is the calibration limit of the vendor used by the licensee to perform the flow meter calibration. Using flow meters outside of their range of calibration could produce inaccurate measurements. Inaccurate flow indication would then yield errors in the heat balance check.
The inspectors reviewed calibration records for the portable ultrasonic flow meters used in the component cooling water performance monitoring test. The portable ultrasonic flow meters were calibrated over a range of approximately 100 to 500 gallons per minute. The flow rates used in the heat exchanger test range from approximately 1,000 gallons per minute to 4,000 gallons per minute. The flow meters were verified to have a vendor rated capacity of up to 50,000 gallons per minute, but 500 gallons per minute is the calibration limit of the vendor used by the licensee to perform the flow meter calibration. Using flow meters outside of their range of calibration could produce inaccurate measurements. Inaccurate flow indication would then yield errors in the heat balance check.


This issue was entered into the licensee's corrective action program as Condition Report 2011-9401. One requested action from Condition Report 2011
This issue was entered into the licensees corrective action program as Condition Report 2011-9401. One requested action from Condition Report 2011-9401 was for engineering to evaluate the basis for the 15 percent criterion. The condition report also requested a procedure change to ensure the heat balance check is satisfied before collecting all the test data. The licensees engineering staff performed additional calculations using the most conservative measured heat loads in the most recent tests to demonstrate that the performance of the heat exchangers was still acceptable. The licensee also had an engineering change package in progress to install permanent flow meters for the component cooling heat exchanger performance monitoring test.
-9401 was for engineering to evaluate the basis for the 15 percent criterion. The condition report also requested a procedure change to ensure the heat balance check is satisfied before collecting all the test data. The licensee's engineering staff performed additional calculations using the most conservative measured heat loads in the most recent tests to demonstrate that the performance of the heat exchangers was still acceptable. The licensee also had an engineering change package in progress to install permanent flow meters for the component cooling heat exchanger performance monitoring test.
 
=====Analysis.=====
The failure to perform testing and evaluation of safety-related heat exchangers in accordance with written procedures was a performance deficiency. This finding is more than minor because it adversely affected the Mitigating Systems Cornerstone objective of equipment performance to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Additionally, the finding is more than minor because if left uncorrected it could lead to a more significant safety concern, as the failure to perform appropriate performance monitoring testing of the component cooling water heat exchangers could reasonably result in an unrecognized condition of a system failing to fulfill its safety-related function. Using Manual Chapter 0609, Attachment 4, "Initial Screening and Characterization of Findings," the finding was determined to be of very low safety significance (Green) because it did not represent a loss of system safety function, nor an actual loss of safety function of a single train, and it did not screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event. The inspectors determined that this finding had a crosscutting aspect in the area of human performance, work practices, because the licensee did not communicate human error prevention techniques, such as self- and peer-checking and proper documentation of activities.


Analysis . The failure to perform testing and evaluation of safety
Specifically, the evaluation did not incorporate a requirement that the heat balance check step of the calculation actually be calculated and that step did not require a sign-off or peer-check [H.4(a)].
-related heat exchangers in accordance with written procedures was a performance deficiency. This finding is more than minor because it adversely affected the Mitigating Systems Cornerstone objective of equipmen t performance to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Additionally, the finding is more than minor because if left uncorrected it could lead to a more significant safety concern, as the failure to perform appropriate performance monitoring testing of the component cooling water heat exchangers could reasonably result in an unrecognized condition of a system failing to fulfill its safety
-related function. Using Manual Chapter 0609, Attachment 4, "Initial Screening and Characterization of Findings," the finding was determined to be of very low safety significance (Green) because it did not represent a loss of system safety function, nor an actual loss of safety function of a single train, and it did not screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event. The inspectors determined that this finding had a crosscutting aspect in the area of human performance, work practices, because the licensee did not communicate human error prevention techniques, such as self
- and peer-checking and proper documentation of activities. Specifically, the evaluation did not incorporate a requirement that the heat balance check step of the calculation actually be calculated and that step did not require a sign
-off or peer-check [H.4(a)].


=====Enforcement.=====
=====Enforcement.=====
Title 10 CFR Part 50, Appendix B, Criterion XI, requires, in part, that a test program shall be established to assure that all testing required demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures. Test procedures shall include provisions for assuring that all prerequisites for the given test have been met, that adequate test instrumentation is available and used, and that the test is performed under suitable environmental conditions. Contrary to the above, prior to November 16, 2011, the licensee did not perform testing of component cooling water heat exchanger AC
Title 10 CFR Part 50, Appendix B, Criterion XI, requires, in part, that a test program shall be established to assure that all testing required demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures. Test procedures shall include provisions for assuring that all prerequisites for the given test have been met, that adequate test instrumentation is available and used, and that the test is performed under suitable environmental conditions. Contrary to the above, prior to November 16, 2011, the licensee did not perform testing of component cooling water heat exchanger AC-1A in accordance with written test procedures, and did not assure that all prerequisites for performance testing were met and that adequate test instrumentation was used.
-1A in accordance with written test procedures, and did not assure that all prerequisites for performance testing were met and that adequate test instrumentation was used. Specifically, the calculated heat loads used to demonstrate validity of test conditions did not agree to within the expected uncertainty, and ultrasonic flow meters were not calibrated to the appropriate range of test flow conditions. This issue was entered into the licensee's corrective action program as Condition Report 2011-9401. Because this finding was determined to be of very low safety significance and was entered into the license's corrective action program, this violation is being treated as a noncited violation consistent with Section 2.3.2 of the NRC Enforcement Policy: NCV 05000285/2011005
 
-0 2 "Inadequate Performance Monitoring Test for Component Cooling Water Heat Exchangers."
Specifically, the calculated heat loads used to demonstrate validity of test conditions did not agree to within the expected uncertainty, and ultrasonic flow meters were not calibrated to the appropriate range of test flow conditions. This issue was entered into the licensees corrective action program as Condition Report 2011-9401. Because this finding was determined to be of very low safety significance and was entered into the licenses corrective action program, this violation is being treated as a noncited violation consistent with Section 2.3.2 of the NRC Enforcement Policy: NCV 05000285/2011005-02 Inadequate Performance Monitoring Test for Component Cooling Water Heat Exchangers.
{{a|1R11}}
{{a|1R11}}
==1R11 Licensed Operator Requalification Program==
==1R11 Licensed Operator Requalification Program==
{{IP sample|IP=IP 71111.11}}
{{IP sample|IP=IP 71111.11}}
a. On November 10, 2011, the inspectors observed a crew of licensed operators in the plant's simulator to verify that operator performance was adequate, evaluators were Inspection Scope identifying and documenting crew performance problems and training was being conducted in accordance with licensee procedures. The inspectors evaluated the following areas:
Licensed operator performance Crew's clarity and formality of communications Crew's ability to take timely actions in the conservative direction Crew's prioritization, interpretation, and verification of annunciator alarms Crew's correct use and implementation of abnormal and emergency procedures


Control board manipulations
====a. Inspection Scope====
On November 10, 2011, the inspectors observed a crew of licensed operators in the plants simulator to verify that operator performance was adequate, evaluators were


Oversight and direction from supervisors
identifying and documenting crew performance problems and training was being conducted in accordance with licensee procedures. The inspectors evaluated the following areas:
* Licensed operator performance
* Crews clarity and formality of communications
* Crews ability to take timely actions in the conservative direction
* Crews prioritization, interpretation, and verification of annunciator alarms
* Crews correct use and implementation of abnormal and emergency procedures
* Control board manipulations
* Oversight and direction from supervisors
* Crews ability to identify and implement appropriate technical specification actions and emergency plan actions and notifications The inspectors compared the crews performance in these areas to pre-established operator action expectations and successful critical task completion requirements.


Crew's ability to identify and implement appropriate technical specification actions and emergency plan actions and notifications The inspectors compared the crew's performance in these areas to pre
Specific documents reviewed during this inspection are listed in the attachment.
-established operator action expectations and successful critical task completion requirements. Specific documents reviewed during this inspection are listed in the attachment.


These activities constitute completion of one quarterly licensed
These activities constitute completion of one quarterly licensed-operator requalification program sample as defined in Inspection Procedure 71111.11.
-operator requalification program sample as defined in Inspection Procedure 71111.11. b. No findings were identified.


Findings
====b. Findings====
{{a|1R12}}
No findings were identified. {{a|1R12}}
==1R12 Maintenance Effectiveness==
==1R12 Maintenance Effectiveness==
{{IP sample|IP=IP 71111.12}}
{{IP sample|IP=IP 71111.12}}
a. The inspectors evaluated degraded performance issues involving the following risk significant systems:
Inspection Scope October 11, 2011, VA
-64A (Control Room Ventilation Filter
)  November 11, 2011, CA
-1C (Air Compressor C)
November 18, 2011, RM
-057 (Condenser Evacuation In
-Line Gas Radiation Monitor)
The inspectors reviewed events such as where ineffective equipmen t maintenance has resulted in valid or invalid automatic actuations of engineered safeguards systems and independently verified the licensee's actions to address system performance or condition problems in terms of the following:
Implementing appropriate work practices Identifying and addressing common cause failures Scoping of systems in accordance with 10 CFR 50.65(b)
Characterizing system reliability issues for performance Charging unavailability for performance


Trending key parameters for condition monitoring Ensuring proper classification in accordance with 10 CFR 50.65(a)(1) or
====a. Inspection Scope====
-(a)(2)  Verifying appropriate performance criteria for structures, systems, and components classified as having an adequate demonstration of performance through preventive maintenance, as described in 10 CFR 50.65(a)(2), or as requiring the establishment of appropriate and adequate goals and corrective actions for systems classified as not having adequate performance, as described in 10 CFR 50.65(a)(1)
The inspectors evaluated degraded performance issues involving the following risk significant systems:
* October 11, 2011, VA-64A (Control Room Ventilation Filter)
* November 11, 2011, CA-1C (Air Compressor C)
* November 18, 2011, RM-057 (Condenser Evacuation In-Line Gas Radiation Monitor)


The inspectors reviewed events such as where ineffective equipment maintenance has resulted in valid or invalid automatic actuations of engineered safeguards systems and independently verified the licensee's actions to address system performance or condition problems in terms of the following:
* Implementing appropriate work practices
* Identifying and addressing common cause failures
* Scoping of systems in accordance with 10 CFR 50.65(b)
* Characterizing system reliability issues for performance
* Charging unavailability for performance
* Trending key parameters for condition monitoring
* Ensuring proper classification in accordance with 10 CFR 50.65(a)(1) or -(a)(2)
* Verifying appropriate performance criteria for structures, systems, and components classified as having an adequate demonstration of performance through preventive maintenance, as described in 10 CFR 50.65(a)(2), or as requiring the establishment of appropriate and adequate goals and corrective actions for systems classified as not having adequate performance, as described in 10 CFR 50.65(a)(1)
The inspectors assessed performance issues with respect to the reliability, availability, and condition monitoring of the system. In addition, the inspectors verified maintenance effectiveness issues were entered into the corrective action program with the appropriate significance characterization. Specific documents reviewed during this inspection are listed in the attachment.
The inspectors assessed performance issues with respect to the reliability, availability, and condition monitoring of the system. In addition, the inspectors verified maintenance effectiveness issues were entered into the corrective action program with the appropriate significance characterization. Specific documents reviewed during this inspection are listed in the attachment.


These activities constitute completion of three quarterly maintenance effectiveness samples as defined in Inspection Procedure
These activities constitute completion of three quarterly maintenance effectiveness samples as defined in Inspection Procedure 71111.12-05.


==71111.12 - 05.==
====b. Findings====
b. No findings were identified.
No findings were identified. {{a|1R13}}
 
Findings
{{a|1R13}}
==1R13 Maintenance Risk Assessments and Emergent Work Control==
==1R13 Maintenance Risk Assessments and Emergent Work Control==
{{IP sample|IP=IP 71111.13}}
{{IP sample|IP=IP 71111.13}}
a. The inspectors reviewed licensee personnel's evaluation and management of plant risk for the maintenance and emergent work activities affecting risk
-significant and safety
-related equipmen t listed below to verify that the appropriate risk assessments were performed prior to removing equipmen t for work: Inspection Scope October 25, 2011, risk management actions with HCV
-335 (shutdown cooling heat exchangers AC-4A&B inlet header isolation valve)  closed  October 30, 2011, risk management actions associate with taking diesel generator 2, and buses 1B3C and 1B3C/4C out of service at the same time December 15, 2011, risk associated with drain down for pressurizer heater in spection  December 16, 2011, risk associated with pressurizer heater replacement The inspectors selected these activities based on potential risk significance relative to the reactor safety cornerstones. As applicable for each activity, the inspectors verified that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4) and that the assessments were accurate and complete. When licensee personnel performed emergent work, the inspectors verified that the licensee personnel promptly assessed and managed plant risk. The inspectors reviewed the scope of maintenance work, discussed the results of the assessment with the licensee's probabilistic risk analyst or shift technical advisor, and verified plant conditions were consistent with the risk assessment. The inspectors also reviewed the technical specification requirements and inspected portions of redundant safety systems, when applicable, to verify risk analysis assumptions were valid, and applicable requirements were met. Specific documents reviewed during this inspection are listed in the attachment.


These activities constitute completion of four maintenance risk assessments and emergent work control inspection samples as defined in Inspection Procedure
====a. Inspection Scope====
The inspectors reviewed licensee personnel's evaluation and management of plant risk for the maintenance and emergent work activities affecting risk-significant and safety-related equipment listed below to verify that the appropriate risk assessments were performed prior to removing equipment for work:
* October 25, 2011, risk management actions with HCV-335 (shutdown cooling heat exchangers AC-4A&B inlet header isolation valve) closed
* October 30, 2011, risk management actions associate with taking diesel generator 2, and buses 1B3C and 1B3C/4C out of service at the same time
* December 15, 2011, risk associated with drain down for pressurizer heater inspection
* December 16, 2011, risk associated with pressurizer heater replacement The inspectors selected these activities based on potential risk significance relative to the reactor safety cornerstones. As applicable for each activity, the inspectors verified that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4)and that the assessments were accurate and complete. When licensee personnel performed emergent work, the inspectors verified that the licensee personnel promptly assessed and managed plant risk. The inspectors reviewed the scope of maintenance work, discussed the results of the assessment with the licensee's probabilistic risk analyst or shift technical advisor, and verified plant conditions were consistent with the risk assessment. The inspectors also reviewed the technical specification requirements and inspected portions of redundant safety systems, when applicable, to verify risk analysis assumptions were valid, and applicable requirements were met. Specific documents reviewed during this inspection are listed in the attachment.


==71111.13 - 05.==
These activities constitute completion of four maintenance risk assessments and emergent work control inspection samples as defined in Inspection Procedure 71111.13-05.
b. No findings were identified.


Findings
====b. Findings====
{{a|1R15}}
No findings were identified. {{a|1R15}}
==1R15 Operability Evaluations==
==1R15 Operability Evaluations==
{{IP sample|IP=IP 71111.15}}
{{IP sample|IP=IP 71111.15}}
a. The inspectors reviewed the following issues:
Inspection Scope November 28, 2011, Operability of HCV
-335 (Shutdown Cooling Heat Exchangers AC
-4A&B Inlet Header Isolation Valve) following replacement of hand wheel key  The inspectors selected these potential operability issues based on the risk significance of the associated components and systems. The inspectors evaluated the technical adequacy of the evaluations to ensure that technical specification operability was properly justified and the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and design criteria in the appropriate sections of the technical specifications and Updated Safety Analysis Report to the licensee personnel's evaluations to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled. The inspectors determined, where appropriate, compliance with bounding limitations associated with the evaluations. Additionally, the inspectors also reviewed a sampling of corrective action documents to verify that the licensee was identifying and correcting any deficiencies associated with operability evaluations. Specific documents reviewed during this inspection are listed in the attachment.


These activities constitute completion of one operability evaluations inspection sample as defined in Inspection Procedure
====a. Inspection Scope====
The inspectors reviewed the following issues:
* November 28, 2011, Operability of HCV-335 (Shutdown Cooling Heat Exchangers AC-4A&B Inlet Header Isolation Valve) following replacement of hand wheel key The inspectors selected these potential operability issues based on the risk significance of the associated components and systems. The inspectors evaluated the technical adequacy of the evaluations to ensure that technical specification operability was properly justified and the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and
 
design criteria in the appropriate sections of the technical specifications and Updated Safety Analysis Report to the licensee personnels evaluations to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled. The inspectors determined, where appropriate, compliance with bounding limitations associated with the evaluations.
 
Additionally, the inspectors also reviewed a sampling of corrective action documents to verify that the licensee was identifying and correcting any deficiencies associated with operability evaluations. Specific documents reviewed during this inspection are listed in the attachment.


==71111.15 - 04==
These activities constitute completion of one operability evaluations inspection sample as defined in Inspection Procedure 71111.15-04
b. No findings were identified.


Findings
====b. Findings====
{{a|1R18}}
No findings were identified. {{a|1R18}}
==1R18 Plant Modifications==
==1R18 Plant Modifications==
{{IP sample|IP=IP 71111.18}}
{{IP sample|IP=IP 71111.18}}
a. To verify that the safety functions of important safety systems were not degraded, the inspectors reviewed the following temporary modifications:
Inspection Scope November 8, 2011: Temporary modifications associated with taking 480 V bus 1B3B out of service for maintenance, specifically, temporary power for the raw water strainer AC
-12A, Loop 2 to Shutdown Cooling Isolation Valve HCV-348, and Diesel Driven Fire Pump FP
-1B  The inspectors reviewed the temporary modifications and the associated safety
-evaluation screening against the system design bases documentation, including the USAR and the technical specifications, and verified that the modification did not adversely affect the system operability/availability. The inspectors also verified that the installation and restoration were consistent with the modification documents and that configuration control was adequate. Additionally, the inspectors verified that the temporary modification was identified on control room drawings, appropriate tags were placed on the affected equipmen t, and licensee personnel evaluated the combined effects on mitigating systems and the integrity of radiological barriers.


These activities constitute completion of one sample for temporary plant modifications as defined in Inspection Procedure
====a. Inspection Scope====
To verify that the safety functions of important safety systems were not degraded, the inspectors reviewed the following temporary modifications:
* November 8, 2011: Temporary modifications associated with taking 480 V bus 1B3B out of service for maintenance, specifically, temporary power for the raw water strainer AC-12A, Loop 2 to Shutdown Cooling Isolation Valve HCV-348, and Diesel Driven Fire Pump FP-1B The inspectors reviewed the temporary modifications and the associated safety-evaluation screening against the system design bases documentation, including the USAR and the technical specifications, and verified that the modification did not adversely affect the system operability/availability. The inspectors also verified that the installation and restoration were consistent with the modification documents and that configuration control was adequate. Additionally, the inspectors verified that the temporary modification was identified on control room drawings, appropriate tags were placed on the affected equipment, and licensee personnel evaluated the combined effects on mitigating systems and the integrity of radiological barriers.


==71111.18 - 05.==
These activities constitute completion of one sample for temporary plant modifications as defined in Inspection Procedure 71111.18-05.
b. No findings were identified.


Findings
====b. Findings====
{{a|R19}}
No findings were identified. {{a|1R19}}
==R19 Postmaintenance Testing==
==1R19 Postmaintenance Testing==
{{IP sample|IP=IP 71111.19}}
{{IP sample|IP=IP 71111.19}}
a. The inspectors reviewed the following postmaintenance activities to verify that procedures and test activities were adequate to ensure system operability and functional capability:
Inspection Scope November 14, 2011, postmaintenance testing of diesel generator 2 following an 18-month overhaul The inspectors selected these activities based upon the structure, system, or component's ability to affect risk. The inspectors evaluated these activities for the following (as applicable):
The effect of testing on the plant had been adequately addressed; testing was adequate for the maintenance performed Acceptance criteria were clear and demonstrated operational readiness; test instrumentation was appropriate


The inspectors evaluated the activities against the technical specifications, the Updated Safety Analysis Report, 10 CFR Part 50 requirements, licensee procedures, and various NRC generic communications to ensure that the test results adequately ensured that the equipmen t met the licensing basis and design requirements. In addition, the inspectors reviewed corrective action documents associated with postmaintenance tests to determine whether the licensee was identifying problems and entering them in the corrective action program and that the problems were being corrected commensurate with their importance to safety. Specific documents reviewed during this inspection are listed in the attachment.
====a. Inspection Scope====
The inspectors reviewed the following postmaintenance activities to verify that procedures and test activities were adequate to ensure system operability and functional capability:
* November 14, 2011, postmaintenance testing of diesel generator 2 following an 18-month overhaul The inspectors selected these activities based upon the structure, system, or component's ability to affect risk. The inspectors evaluated these activities for the following (as applicable):
* The effect of testing on the plant had been adequately addressed; testing was adequate for the maintenance performed
* Acceptance criteria were clear and demonstrated operational readiness; test instrumentation was appropriate The inspectors evaluated the activities against the technical specifications, the Updated Safety Analysis Report, 10 CFR Part 50 requirements, licensee procedures, and various NRC generic communications to ensure that the test results adequately ensured that the equipment met the licensing basis and design requirements. In addition, the inspectors reviewed corrective action documents associated with postmaintenance tests to determine whether the licensee was identifying problems and entering them in the corrective action program and that the problems were being corrected commensurate with their importance to safety. Specific documents reviewed during this inspection are listed in the attachment.


These activities constitute completion of one postmaintenance testing inspection sample as defined in Inspection Procedure
These activities constitute completion of one postmaintenance testing inspection sample as defined in Inspection Procedure 71111.19-05.


==71111.19 - 05.==
====b. Findings====
b. No findings were identified.
No findings were identified. {{a|1R22}}
 
Findings
{{a|1R22}}
==1R22 Surveillance Testing==
==1R22 Surveillance Testing==
{{IP sample|IP=IP 71111.22}}
{{IP sample|IP=IP 71111.22}}
Line 382: Line 343:
====a. Inspection Scope====
====a. Inspection Scope====
The inspectors reviewed the Update Safety Analysis Report, procedure requirements, and technical specifications to ensure that the surveillance activities listed below demonstrated that the systems, structures, and/or components tested were capable of performing their intended safety functions. The inspectors either witnessed or reviewed test data to verify that the significant surveillance test attributes were adequate to address the following:
The inspectors reviewed the Update Safety Analysis Report, procedure requirements, and technical specifications to ensure that the surveillance activities listed below demonstrated that the systems, structures, and/or components tested were capable of performing their intended safety functions. The inspectors either witnessed or reviewed test data to verify that the significant surveillance test attributes were adequate to address the following:
Preconditioning
* Preconditioning
* Evaluation of testing impact on the plant
* Acceptance criteria
* Test equipment
* Procedures
* Jumper/lifted lead controls
* Test data
* Testing frequency and method demonstrated technical specification operability
* Test equipment removal
* Restoration of plant systems
* Fulfillment of ASME Code requirements
* Updating of performance indicator data
* Engineering evaluations, root causes, and bases for returning tested systems, structures, and components not meeting the test acceptance criteria were correct
* Reference setting data
* Annunciators and alarms setpoints The inspectors also verified that licensee personnel identified and implemented any needed corrective actions associated with the surveillance testing.
* October 17, 2011, OP-ST-RW-3004, Raw Water System Category C Valve Inservice Test
* October 25, 2011, EM-ST-ESF-0002, 13.8 KV Emergency Power Periodic Test Specific documents reviewed during this inspection are listed in the attachment.


Evaluation of testing impact on the plant
These activities constitute completion of two surveillance testing inspection samples as defined in Inspection Procedure 71111.22-05.


Acceptance criteria
====b. Findings====
 
No findings were identified. {{a|1EP6}}
Test equipmen t Procedures
 
Jumper/lifted lead controls Test data  Testing frequency and method demonstrated technical specification operability
 
Test equipmen t removal Restoration of plant systems
 
Fulfillment of ASME Code requirements
 
Updating of performance indicator data
 
Engineering evaluations, root causes, and bases for returning tested systems, structures, and components not meeting the test acceptance criteria were correct Reference setting data
 
Annunciators and alarms setpoints The inspectors also verified that licensee personnel identified and implemented any needed corrective actions associated with the surveillance testing.
 
October 17, 2011, OP
-ST-RW-3004, Raw Water System Category C Valve Inservice Test October 25, 2011, EM
-ST-ESF-0002, 13.8 KV Emergency Power Periodic Test Specific documents reviewed during this inspection are listed in the attachment.
 
These activities constitute completion of two surveillance testing inspection samples as defined in Inspection Procedure
 
==71111.22 - 05.==
 
b. No findings were identified.
 
Findings
{{a|1EP6}}
==1EP6 Drill Evaluation==
==1EP6 Drill Evaluation==
{{IP sample|IP=IP 71114.06}}
{{IP sample|IP=IP 71114.06}}
===Cornerstone:===
===Cornerstone: Emergency Preparedness===
Emergency Preparedness


===.1 Training Observations===
===.1 Training Observations===


a. The inspectors observed a simulator training evolution for licensed operators on November 10, 2011, which required emergency plan implementation by a licensee operations crew. This evolution was planned to be evaluated and included in performance indicator data regarding drill and exercise performance.
====a. Inspection Scope====
The inspectors observed a simulator training evolution for licensed operators on November 10, 2011, which required emergency plan implementation by a licensee operations crew. This evolution was planned to be evaluated and included in performance indicator data regarding drill and exercise performance. The inspectors observed event classification and notification activities performed by the crew. The inspectors also attended the post-evolution critique for the scenario. The focus of the inspectors activities was to note any weaknesses and deficiencies in the crews performance and ensure that the licensee evaluators noted the same issues and entered them into the corrective action program. As part of the inspection, the inspectors reviewed the scenario package and other documents listed in the attachment.


The inspectors observed event classification and notification activities performed by the crew. The inspectors also attended the post
These activities constitute completion of one sample as defined in Inspection Procedure 71114.06-05.
-evolution critique for the scenario. The focus of the inspectors' activities was to note any weaknesses and deficiencies in the crew's performance and ensure that the licensee evaluators noted the same issues and entered them into the corrective action program. As part of the inspection, the inspectors reviewed the scenario package and other documents listed in the attachment.


Inspection Scope These activities constitute completion of one sample as defined in Inspection Procedure
====b. Findings====
 
No findings were identified.
==71114.06 - 05.==
b. No findings were identified.
 
Findings 


==RADIATION SAFETY==
==RADIATION SAFETY==


===Cornerstone:===
===Cornerstone: Occupational and Public Radiation Safety===
Occupational and Public Radiation Safety
{{a|2RS0}}
{{a|2RS0}}
==2RS0 4 Occupational Dose Assessment==
==2RS0 4 Occupational Dose Assessment==
Line 443: Line 388:
====a. Inspection Scope====
====a. Inspection Scope====
This area was inspected to:
This area was inspected to:
: (1) determine the accuracy and operability of personal monitoring equipmen t;
: (1) determine the accuracy and operability of personal monitoring equipment;
: (2) determine the accuracy and effectiveness of the licensee's methods for determining total effective dose equivalent; and
: (2) determine the accuracy and effectiveness of the licensees methods for determining total effective dose equivalent; and
: (3) ensure occupational dose is appropriately monitored. The inspectors used the requirements in 10 CFR Part 20, the technical specifications, and the licensee's procedures required by technical specifications as criteria for determining compliance. During the inspection, the inspectors interviewed licensee personnel, performed walkdowns of various portions of the plant, and reviewed the following items:
: (3) ensure occupational dose is appropriately monitored. The inspectors used the requirements in 10 CFR Part 20, the technical specifications, and the licensees procedures required by technical specifications as criteria for determining compliance. During the inspection, the inspectors interviewed licensee personnel, performed walkdowns of various portions of the plant, and reviewed the following items:
External dosimetry accreditation, storage, issue, use, and processing of active and passive dosimeters The technical competency and adequacy of the licensee's internal dosimetry program   Adequacy of the dosimetry program for special dosimetry situations such as declared pregnant workers, multiple dosimetry placement, and neutron dose assessment Audits, self
* External dosimetry accreditation, storage, issue, use, and processing of active and passive dosimeters
-assessments, and corrective action documents related to dose assessment since the last inspection Specific documents reviewed during this inspection are listed in the attachment.
* The technical competency and adequacy of the licensees internal dosimetry program
* Adequacy of the dosimetry program for special dosimetry situations such as declared pregnant workers, multiple dosimetry placement, and neutron dose assessment
* Audits, self-assessments, and corrective action documents related to dose assessment since the last inspection Specific documents reviewed during this inspection are listed in the attachment.


These activities constitute completion of the one required sample as defined in Inspection Procedure
These activities constitute completion of the one required sample as defined in Inspection Procedure 71124.04-05.


==71124.04 - 05.==
====b. Findings====


====b. Findings====
=====Introduction.=====
Introduction
Inspectors reviewed a self-revealing, noncited violation of Technical Specification 5.8.1 for failure to follow Radiation Work Permit 11-2520 and procedures, which required workers to comply with radiological work practices. Specifically, workers changed the work scope approved on the low-pressure safety injection shutdown cooling bypass valve FCV-326 without notifying radiation protection and receiving a re-evaluation of the radiological conditions as required by the radiation work permit.
. Inspectors reviewed a self
-revealing, noncited violation of Technical Specification 5.8.1 for failure to follow Radiation Work Permit 11
-2520 and procedures, which required workers to comply with radiological work practices. Specifically, workers changed the work scope approved on the low
-pressure safety injection shutdown cooling bypass valve FCV
-326 without notifying radiation protection and receiving a re
-evaluation of the radiological conditions as required by the radiation work permit.


=====Description.=====
=====Description.=====
On May 2, 2011, two workers were briefed by radiation protection for radiological conditions associated with reassembly of the low
On May 2, 2011, two workers were briefed by radiation protection for radiological conditions associated with reassembly of the low-pressure safety injection bypass valve FCV-326. Using the latest radiological surveys, as required by procedure, radiation protection staff briefed the workers that the radiation conditions around valve FCV-326 had contamination levels as high as 450,000 disintegrations/100 centimeters squared. The workers were being briefed to perform valve maintenance work in a high radiation area and Radiation Work Permit 11-2520. In accordance with the pre-job briefing, the authorized work scope was only to reassemble the valve, this was non-abrasive work. Yet, the workers used abrasive pads during the course of the valve reassembly, which was unknown to radiation protection. When the two workers exited the radiologically controlled area, they both alarmed the personal contamination monitors. One of the workers had approximately 30,000 disintegrations/100 centimeters squared on his clothing. Both workers were decontaminated. It was determined that the workers had not informed radiation protection personnel that they had changed the work scope in the area by using abrasive pads as required by Radiation Work Permit 11-2520.
-pressure safety injection bypass valve FCV
-326. Using the latest radiological surveys, as required by procedure, radiation protection staff briefed the workers that the radiation conditions around valve FCV-326 had contamination levels as high as 450,000 disintegrations/100 centimeters squared. The workers were being briefed to perform valve maintenance work in a high radiation area and Radiation Work Permit 11
-2520. In accordance with the pre-job briefing, the authorized work scope was only to reassemble the valve, this was non-abrasive work. Yet, the workers used abrasive pads during the course of the valve reassembly, which was unknown to radiation protection. When the two workers exited the radiologically controlled area, they both alarmed the personal contamination monitors. One of the workers had approximately 30,000 disintegrations/100 centimeters squared on his clothing. Both workers were decontaminated. It was determined that the workers had not informed radiation protection personnel that they had changed the work scope in the area by using abrasive pads as required by Radiation Work Permit 11-2520. This additional valve rework was not previously approved during radiation protection's briefing. The licensee's corrective action was to counsel the workers on the importance of adhering to the stated work scope and radiation work permit instructions.


Analysis . The failure to follow the requirements of the radiation work permit as instructed by radiation protection
This additional valve rework was not previously approved during radiation protections briefing. The licensees corrective action was to counsel the workers on the importance of adhering to the stated work scope and radiation work permit instructions.
, about the radiation work permit , was a performance deficiency.


The finding was more than minor because it was associated with the Occupational Radiation Safety Cornerstone attribute of program and process and affected the cornerstone objective of ensuring adequate protection of worker health and safety from exposure to radiation during routine operations. Using the Occupational Radiation Safety Significance Determination Process, the inspector s determined the finding to have very low safety significance because:
=====Analysis.=====
: (1) it was not associated with ALARA planning or work controls, (2)there was no overexposure,
The failure to follow the requirements of the radiation work permit as instructed by radiation protection, about the radiation work permit, was a performance deficiency. The finding was more than minor because it was associated with the Occupational Radiation Safety Cornerstone attribute of program and process and affected the cornerstone objective of ensuring adequate protection of worker health and safety from exposure to radiation during routine operations. Using the Occupational Radiation Safety Significance Determination Process, the inspectors determined the finding to have very low safety significance because:
: (1) it was not associated with ALARA planning or work controls,
: (2) there was no overexposure,
: (3) there was no substantial potential for an overexposure, and
: (3) there was no substantial potential for an overexposure, and
: (4) the ability to assess dose was not compromised.
: (4) the ability to assess dose was not compromised. The finding was determined to have a human performance crosscutting aspect associated with work practices, because the licensee failed to ensure supervisory and management oversight of work activities, including contractors, such that nuclear safety is supported [H.4(c)].


The finding was determined to have a human performance crosscutting aspect associated with work practices, because the licensee failed to ensure supervisory and management oversight of work activities, including contractors, such that nuclear safety is supported [H.4(c)].
=====Enforcement.=====
Enforcement
Technical Specification 5.8.1 states that written procedures shall be established, implemented and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Quality Assurance Program Requirements, Revision 2, Appendix A, 1978; Section 7(e)(1) of Appendix A of Regulatory Guide 1.33 lists radiation protection procedures for the control of radioactivity, and limiting personnel exposure, including a radiation work permit system. Radiation Protection Plan, Revision 24, Section 2.3.11, states that station personnel are responsible for complying with the requirements in Procedure SO-G-101, Radiation Worker Practices, Revision 33. Procedure SO-G-101, Sections 4.3.2 and 5.4.4, requires that personnel adhere to the requirements listed on the radiation work permit they are using and comply with radiological work practices as established by the radiation protection department. Radiation Work Permit 11-2520 requires workers to contact radiation protection personnel for re-evaluation of radiological conditions if the work scope is changed. Contrary to the above, on May 2, 2011, two workers did not contact radiation protection personnel for a re-evaluation of radiological conditions when they changed the work scope on valve FCV-326 from reassembly to rework using abrasive pads.
. Technical Specification 5.8.1 states that written procedures shall be established, implemented and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, "Quality Assurance Program Requirements," Revision 2, Appendix A, 1978; Section 7(e)(1) of Appendix A of Regulatory Guide 1.33 lists radiation protection procedures for the control of radioactivity, and limiting personnel exposure, including a radiation work permit system.
 
Radiation Protection Plan, Revision 24, Section 2.3.11, states that station personnel are responsible for complying with the requirements in Procedure SO-G-101, "Radiation Worker Practices,"
Revision 33. Procedure SO-G-101, Sections 4.3.2 and 5.4.4, requires that personnel adhere to the requirements listed on the radiation work permit they are using and comply with radiological work practices as established by the radiation protection department. Radiation Work Permit 11
-2520 requires workers to contact radiation protection personnel for re
-evaluation of radiological conditions if the work scope is changed. Contrary to the above, on May 2, 2011, two workers did not contact radiation protection personnel for a re-evaluation of radiological conditions when they changed the work scope on valve FCV
-326 from reassembly to rework using abrasive pads. Consequently, these two individuals were found contaminated when they alarmed the personal contamination monitors. Because this violation is of very low safety significance and was entered into the licensee's corrective action program as Condition Reports 2011
-3944, 2011
-3946, and 2011
-9795, this violation is being treated as a noncited violation, consistent with Section 2.3.2 of the NRC Enforcement Policy:


NCV 05000285/2011005
Consequently, these two individuals were found contaminated when they alarmed the personal contamination monitors. Because this violation is of very low safety significance and was entered into the licensees corrective action program as Condition Reports 2011-3944, 2011-3946, and 2011-9795, this violation is being treated as a noncited violation, consistent with Section 2.3.2 of the NRC Enforcement Policy:
-0 3; "Failure to Follow Radiation Work Permit Instructions."
NCV 05000285/2011005-03; Failure to Follow Radiation Work Permit Instructions.
{{a|2RS0}}
{{a|2RS0}}
==2RS0 5 Radiation Monitoring Instrumentation==
==2RS0 5 Radiation Monitoring Instrumentation==
Line 498: Line 427:
This area was inspected to verify the licensee is assuring the accuracy and operability of radiation monitoring instruments that are used to:
This area was inspected to verify the licensee is assuring the accuracy and operability of radiation monitoring instruments that are used to:
: (1) monitor areas, materials, and workers to ensure a radiologically safe work environment; and
: (1) monitor areas, materials, and workers to ensure a radiologically safe work environment; and
: (2) detect and quantify radioactive process streams and effluent releases. The inspectors used the requirements in 10 CFR Part 20, the technical specifications, and the licensee's procedures required by technical specifications as criteria for determining compliance. During the inspection, the inspector s interviewed licensee personnel, performed walkdowns of various portions of the plant, and reviewed the following items:
: (2) detect and quantify radioactive process streams and effluent releases. The inspectors used the requirements in 10 CFR Part 20, the technical specifications, and the licensees
Selected plant configurations and alignments of process, post-accident, and effluent monitors with descriptions in the Updated Safety Analysis Report and the offsite dose calculation manual Select instrumentation, including effluent monitoring instrument, portable survey instruments, area radiation monitors, continuous air monitors, personnel contamination monitors, portal monitors, and small article monitors to examine their configurations and source checks Calibration and testing of process and effluent monitors, laboratory instrumentation, whole body counters, post
-accident monitoring instrumentation, portal monitors, personnel contamination monitors, small article monitors, portable survey instruments, area radiation monitors, electronic dosimetry, air samplers, continuous air monitors Audits, self
-assessments, and corrective action documents related to radiation monitoring instrumentation since the last inspection Specific documents reviewed during this inspection are listed in the attachment.


These activities constitute completion of the one required sample as defined in Inspection Procedure
procedures required by technical specifications as criteria for determining compliance.


==71124.05 - 05.==
During the inspection, the inspectors interviewed licensee personnel, performed walkdowns of various portions of the plant, and reviewed the following items:
* Selected plant configurations and alignments of process, post-accident, and effluent monitors with descriptions in the Updated Safety Analysis Report and the offsite dose calculation manual
* Select instrumentation, including effluent monitoring instrument, portable survey instruments, area radiation monitors, continuous air monitors, personnel contamination monitors, portal monitors, and small article monitors to examine their configurations and source checks
* Calibration and testing of process and effluent monitors, laboratory instrumentation, whole body counters, post-accident monitoring instrumentation, portal monitors, personnel contamination monitors, small article monitors, portable survey instruments, area radiation monitors, electronic dosimetry, air samplers, continuous air monitors
* Audits, self-assessments, and corrective action documents related to radiation monitoring instrumentation since the last inspection Specific documents reviewed during this inspection are listed in the attachment.
 
These activities constitute completion of the one required sample as defined in Inspection Procedure 71124.05-05.


====b. Findings====
====b. Findings====
Line 511: Line 443:


==OTHER ACTIVITIES==
==OTHER ACTIVITIES==
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Physical Protection
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Physical Protection
{{a|4OA1}}
{{a|4OA1}}
==4OA1 Performance Indicator Verification==
==4OA1 Performance Indicator Verification==
Line 519: Line 451:
===.1 Data Submission Issue===
===.1 Data Submission Issue===


a. The inspectors performed a review of the performance indicator data submitted by the licensee for the third Quarter 20 11 performance indicators for any obvious inconsistencies prior to its public release in accordance with Inspection Manual Chapter 0608, "Performance Indicator Program."
====a. Inspection Scope====
The inspectors performed a review of the performance indicator data submitted by the licensee for the third Quarter 2011 performance indicators for any obvious inconsistencies prior to its public release in accordance with Inspection Manual Chapter 0608, Performance Indicator Program.


Inspection Scope This review was performed as part of the inspectors' normal plant status activities and, as such, did not constitute a separate inspection sample.
This review was performed as part of the inspectors normal plant status activities and, as such, did not constitute a separate inspection sample.


b. No findings were identified.
====b. Findings====
No findings were identified.


Findings
===.2 Mitigating Systems Performance Index - Heat Removal System (MS08)===


===.2 Mitigating Systems Performance Index===
====a. Inspection Scope====
The inspectors sampled licensee submittals for the mitigating systems performance index - heat removal system performance indicator for the period from the fourth quarter 2010 through the third quarter 2011. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6. The inspectors reviewed the licensees operator narrative logs, issue reports, event reports, mitigating systems performance index derivation reports, and NRC integrated inspection reports for the period of October 1, 2010 through September 20, 2011 to validate the accuracy of the submittals.


- Heat Removal System (MS08)a. The inspectors sampled licensee submittals for the mitigating systems performance index - heat removal system performance indicator for the period from the fourth quarter 20 10 through the third quarter 20 11. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99
The inspectors reviewed the mitigating systems performance index component risk co-efficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensees issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in the attachment to this report.
-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6. The inspectors reviewed the licensee's operator narrative logs, issue reports, event reports, mitigating systems performance index derivation reports, and NRC integrated inspection reports for the period of October 1, 20 10 through September 20, 2011 to validate the accuracy of the submittals. The inspectors reviewed the mitigating systems performance index component risk co-efficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensee's issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in the attachment to this report.


Inspection Scope These activities constitute completion of one mitigating systems performance index heat removal system sample as defined in Inspection Procedure 71151-05.
These activities constitute completion of one mitigating systems performance index heat removal system sample as defined in Inspection Procedure 71151-05.


b. No findings were identified.
====b. Findings====
No findings were identified.


Findings
===.3 Mitigating Systems Performance Index - Residual Heat Removal System (MS09)===


===.3 Mitigating Systems Performance Index===
====a. Inspection Scope====
The inspectors sampled licensee submittals for the mitigating systems performance index - residual heat removal system performance indicator for the period from the fourth quarter 2010 through the third quarter 2011. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6. The inspectors reviewed the licensees operator narrative logs, issue reports, event reports, mitigating systems performance index derivation reports, and NRC integrated inspection reports for the period of October 1, 2010 through September 20, 2011 to validate the accuracy of the submittals.


- Residual Heat Removal System (MS09)a. The inspectors sampled licensee submittals for the mitigating systems performance index - residual heat removal system performance indicator for the period from the fourth quarter 2010 through the third quarter 2011. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99
The inspectors reviewed the mitigating systems performance index component risk co-efficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensees issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in the attachment to this report.
-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6. The inspectors reviewed the licensee's operator narrative logs, issue reports, event reports, mitigating systems performance index derivation reports, and NRC integrated inspection reports for the period of October 1, 2010 through September 20, 2011 to validate the accuracy of the submittals. Inspection Sco pe The inspectors reviewed the mitigating systems performance index component risk co-efficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensee's issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in the attachment to this report.


These activities constitute completion of one mitigating systems performance index residual heat removal system sample as defined in Inspection Procedure 71151-05.
These activities constitute completion of one mitigating systems performance index residual heat removal system sample as defined in Inspection Procedure 71151-05.


b. No findings were identified.
====b. Findings====
No findings were identified.


Findings
===.4 Mitigating Systems Performance Index - Cooling Water Systems (MS10)===


===.4 Mitigating Systems Performance Index===
====a. Inspection Scope====
The inspectors sampled licensee submittals for the mitigating systems performance index - cooling water systems performance indicator for the period from the fourth quarter 2010 through the third quarter 2011. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6. The inspectors reviewed the licensees operator narrative logs, issue reports, event reports, mitigating systems performance index derivation reports, and NRC integrated inspection reports for the period of October 1, 2010 through September 20, 2011 to validate the accuracy of the submittals.


- Cooling Water Systems (MS10)a. The inspectors sampled licensee submittals for the mitigating systems performance index - cooling water systems performance indicator for the period from the fourth quarter 2010 through the third quarter 2011. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99
The inspectors reviewed the mitigating systems performance index component risk coefficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensees issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in the attachment to this report.
-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6. The inspectors reviewed the licensee's operator narrative logs, issue reports, event reports, mitigating systems performance index derivation reports, and NRC integrated inspection reports for the period of October 1, 2010 through September 20, 2011 to validate the accuracy of the submittals. The inspectors reviewed the mitigating systems performance index component risk coefficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensee's issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in the attachment to this report.


Inspection Scope These activities constitute completion of one mitigating systems performance index cooling water system sample as defined in Inspection Procedure 71151-05. b. No findings were identified.
These activities constitute completion of one mitigating systems performance index cooling water system sample as defined in Inspection Procedure 71151-05.


Findings
====b. Findings====
No findings were identified.


===.5 Drill/Exercise Performance (EP01)===
===.5 Drill/Exercise Performance (EP01)===


a. The inspectors sampled licensee submittals for the Drill and Exercise Performance, performance indicator for the period from April 2010 through September 2011. To determine the accuracy of the performance indicator data reported during those periods, performance indicator definitions and guidance contained in Nuclear Energy Institute Document 99
====a. Inspection Scope====
-02, "Regulatory Assessment Performance Indicator Guideline," Revisions 5 and 6, were used. The inspectors reviewed the licensee's records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the Nuclear Energy Institute guidance. Specifically, the inspectors reviewed licensee records and processes including procedural guidance on assessing opportunities for the performance indicator; assessments of performance indicator opportunities during predesignated control room simulator training sessions, and performance during other drills. The specific documents reviewed are described in the attachment to this report.
The inspectors sampled licensee submittals for the Drill and Exercise Performance, performance indicator for the period from April 2010 through September 2011. To determine the accuracy of the performance indicator data reported during those periods, performance indicator definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revisions 5 and 6, were used. The inspectors reviewed the licensees records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the Nuclear Energy Institute guidance. Specifically, the inspectors reviewed licensee records and processes including procedural guidance on assessing opportunities for the performance indicator; assessments of performance indicator opportunities during predesignated control room simulator training sessions, and performance during other drills. The specific documents reviewed are described in the attachment to this report.
 
These activities constitute completion of one sample of the drill/exercise performance as defined in Inspection Procedure 71151-05.


Inspection Scope These activities constitute completion of one sample of the drill/exercise performance as defined in Inspection Procedure 71151-05. b.
====b. Findings====


=====Introduction.=====
=====Introduction.=====
A noncited violation was identified by the NRC for the failure of the licensee's guidelines for the choice of protective actions during an emergency to implement federal guidance as required by 10 CFR 50.47(b)(10).
A noncited violation was identified by the NRC for the failure of the licensees guidelines for the choice of protective actions during an emergency to implement federal guidance as required by 10 CFR 50.47(b)(10).


Findings  Description
=====Description.=====
.
The NRC identified the failure of the licensees guidelines for the choice of protective actions during an emergency to implement federal guidance as a performance deficiency. Specifically, the licensee did not implement Regulatory Information Summary 2003-012, Clarification of NRC Guidance for Modifying Protective Actions, dated June 24, 2003, which states, in part, Licensees should not change a PAR until the threat is fully under control.


The NRC identified the failure of the licensee's guidelines for the choice of protective actions during an emergency to implement federal guidance as a performance deficiency. Specifically, the licensee did not implement Regulatory Information Summary 2003-012, "Clarification of NRC Guidance for Modifying Protective Actions," dated June 24, 2003, which states, in part, "-Licensees should not change a PAR until the threat is fully under control."
The licensee conducted an emergency preparedness drill on August 16, 2011. The inspectors reviewed notifications simulated to be made to offsite authorities at 10:48 a.m. and 12:06 p.m. on August 16, 2011, as recorded on Form FC-1188, Fort Calhoun Station - Emergency Notification Form, Revision 26. The inspectors reviewed dose assessment reports generated on August 16, 2011, at 10:34 a.m., 10:38 a.m.,
10:49 a.m., 10:58 a.m., 11:22 a.m., and 12:03 p.m., respectively, as documented on the licensee Update Report to Offsite Authorities, generated using Eagle Version 6.0. The inspectors also reviewed Procedure EOF-7, Protective Action Guidelines, Revision 21.


The licensee conducted an emergency preparedness drill on August 16, 2011. The inspectors reviewed notifications simulated to be made to offsite authorities at 10:48 a.m. and 12:06 p.m. on August 16, 2011, as recorded on Form FC
The licensee transmitted a simulated protective action recommendation to offsite authorities at 10:48 a.m. of evacuate 0-2 miles in all sectors, evacuate 2-5 miles in sectors DEF (D, E, and F), and to take no action between 5-10 miles. The licensee transmitted a simulated protective action recommendation (PAR) to offsite authorities at 12:06 p.m. of evacuate 0-2 miles in all sectors and to take no action between 2-10 miles.
-1188, "Fort Calhoun Station - Emergency Notification Form," Revision 26. The inspectors reviewed dose assessment reports generated on August 16, 2011, at 10:34 a.m., 10:38 a.m., 10:49 a.m., 10:58 a.m., 11:22 a.m., and 12:03 p.m., respectively, as documented on the licensee Update Report to Offsite Authorities, generated using Eagle Version 6.0. The inspectors also reviewed Procedure EOF-7, "Protective Action Guidelines," Revision 21.


The licensee transmitted a simulated protective action recommendation to offsite authorities at 10:48 a.m. of evacuate 0
The inspectors determined that protective action guides were exceeded at the site boundary on dose assessments performed at 11:21 a.m. and 12:03 p.m., and that protective action guides were not exceeded at 2 miles on any dose assessment report.
-2 miles in all sectors, evacuate 2-5 miles in sectors DEF (D, E, and F), and to take no action between 5
-10 miles. The licensee transmitted a simulated protective action recommendation (PAR) to offsite authorities at 12:06 p.m. of evacuate 0
-2 miles in all sectors and to take no action between 2-10 miles.


The inspectors determined that protective action guides were exceeded at the site boundary on dose assessments performed at 11:21 a.m. and 12:03 p.m., and that protective action guides were not exceeded at 2 miles on any dose assessment report. The licensee recommendation at 12:06 p.m. was based on a change in wind direction from 271 degrees to 301 degrees. The 12:06 p.m. notification deleted the previous recommendation to evacuate between 2
The licensee recommendation at 12:06 p.m. was based on a change in wind direction from 271 degrees to 301 degrees. The 12:06 p.m. notification deleted the previous recommendation to evacuate between 2-5 miles in sectors DEF (D, E, and F), because no protective action guide thresholds were currently exceeded at 2 miles.
-5 miles in sectors DEF (D, E, and F), because no protective action guide thresholds were currently exceeded at 2 miles.


The inspectors reviewed the guidance of Regulatory Information Summary 2003
The inspectors reviewed the guidance of Regulatory Information Summary 2003-012, Clarification of NRC Guidance for Modifying Protective Actions, dated June 24, 2003, which states, in part, Licensees should not change a PAR [protective action recommendation] until the threat is fully under control. The inspectors concluded that the licensee should not have deleted the recommendation to evacuate 2-5 miles in sectors DEF (D, E, and F) after it was transmitted at 10:48 p.m. because recommendations not to evacuate an area following a previous evacuation recommendation can be confusing to both offsite governmental authorities and to the public. Attempting to rescind an existing evacuation recommendation can impact the licensees ability to adequately implement protective measures for the public.
-012, "Clarification of NRC Guidance for Modifying Protective Actions," dated June 24, 2003, which states, in part, "-Licensees should not change a PAR [protective action recommendation] until the threat is fully under control.The inspectors concluded that the licensee should not have deleted the recommendation to evacuate 2
-5 miles in sectors DEF (D, E, and F) after it was transmitted at 10:48 p.m. because recommendations not to evacuate an area following a previous evacuation recommendation can be confusing to both offsite governmental authorities and to the public. Attempting to rescind an existing evacuation recommendation can impact the licensee's ability to adequately implement protective measures for the public.


=====Analysis.=====
=====Analysis.=====
The inspectors determined the licensee's failure to have guidelines for the choice of protective actions during an emergency that implement federal guidance is a performance deficiency within the licensee's control. This finding is more than minor because it had a credible impact on safety and affected the Emergency Preparedness Cornerstone attributes of emergency response organization performance and procedure quality. The finding had a credible impact on the cornerstone objective because rescinding an existing protective action recommendation can confuse offsite governmental authorities and the public, and affects the implementation of adequate measures to protect the health and safety of the public. The finding was associated with a violation of NRC requirements. This finding was evaluated using the Emergency Preparedness Significance Determination Process and was determined to be of very low safety significance because it was a failure to comply with NRC requirements, was associated with a risk significant planning standard as defined by Inspection Manual Chapter 0609, Appendix B, and was not a functional failure or degraded planning standard function. The finding was not a degraded planning standard function because the licensee's process was capable of producing correct protective action recommendations.
The inspectors determined the licensees failure to have guidelines for the choice of protective actions during an emergency that implement federal guidance is a performance deficiency within the licensees control. This finding is more than minor because it had a credible impact on safety and affected the Emergency Preparedness Cornerstone attributes of emergency response organization performance and procedure quality. The finding had a credible impact on the cornerstone objective because rescinding an existing protective action recommendation can confuse offsite governmental authorities and the public, and affects the implementation of adequate measures to protect the health and safety of the public. The finding was associated with a violation of NRC requirements. This finding was evaluated using the Emergency Preparedness Significance Determination Process and was determined to be of very low safety significance because it was a failure to comply with NRC requirements, was associated with a risk significant planning standard as defined by Inspection Manual Chapter 0609, Appendix B, and was not a functional failure or degraded planning standard function. The finding was not a degraded planning standard function because the licensees process was capable of producing correct protective action recommendations. This finding has been entered into the licensees corrective action program as Condition Report 2011-8530.
 
This finding has been entered into the licensee's corrective action program as Condition Report 2011
-8530.


=====Enforcement.=====
=====Enforcement.=====
Title 10 of the Code of Federal Regulations, Part 50.47(b)(10) states, in part, "A range of protective actions has been developed for the plume exposure pathway -guidelines for the choice of protective actions during an emergency, consistent with federal guidance, are developed and in place-.Contrary to the above, the licensee did not develop and put into place guidelines for the choice of protective actions during an emergency that were consistent with federal guidance licensee. Specifically, Procedure EOF-7, "Protective Action Guidelines," Revision 21, did not prohibit revising existing protective actions recommendations for evacuation of the public in accordance with the guidance of Regulatory Information Summary 2003
Title 10 of the Code of Federal Regulations, Part 50.47(b)(10) states, in part, A range of protective actions has been developed for the plume exposure pathway guidelines for the choice of protective actions during an emergency, consistent with federal guidance, are developed and in place. Contrary to the above, the licensee did not develop and put into place guidelines for the choice of protective actions during an emergency that were consistent with federal guidance licensee. Specifically, Procedure EOF-7, Protective Action Guidelines, Revision 21, did not prohibit revising existing protective actions recommendations for evacuation of the public in accordance with the guidance of Regulatory Information Summary 2003-012.
-012.


NCV 05000285/2011
NCV 05000285/2011-0005-04, Inadequate licensee procedure for making protective action recommendations.
-0005-0 4 , Inadequate licensee procedure for making protective action recommendations
.


===.6 Emergency Response Organization Drill Participation (EP02)===
===.6 Emergency Response Organization Drill Participation (EP02)===


a. The inspectors sampled licensee submittals for the Emergency Response Organization Drill Participation performance indicator for the period from April 2010 through September 2011. To determine the accuracy of the performance indicator data reported during those periods, performance indicator definitions and guidance contained in Nuclear Energy Institute Document 99
====a. Inspection Scope====
-02, "Regulatory Assessment Performance Indicator Guideline," Revision 5, was used. The inspectors reviewed the licensee's records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the Nuclear Energy Institute guidance. Specifically, the inspectors reviewed licensee records and processes including procedural guidance on assessing opportunities for the performance indicator, rosters of personnel assigned to key emergency response organization positions, and exercise participation records. The specific documents reviewed are described in the attachment to this report.
The inspectors sampled licensee submittals for the Emergency Response Organization Drill Participation performance indicator for the period from April 2010 through September 2011. To determine the accuracy of the performance indicator data reported during those periods, performance indicator definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 5, was used. The inspectors reviewed the licensees records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the Nuclear Energy Institute guidance. Specifically, the inspectors reviewed licensee records and processes including procedural guidance on assessing opportunities for the performance indicator, rosters of personnel assigned to key emergency response organization positions, and exercise participation records. The specific documents reviewed are described in the attachment to this report.


Inspection Scope These activities constitute completion of one sample of the emergency response organization drill participation as defined in Inspection Procedure 71151-05.
These activities constitute completion of one sample of the emergency response organization drill participation as defined in Inspection Procedure 71151-05.


b. No findings were identified.
====b. Findings====
 
No findings were identified.
Findings


===.7 Alert and Notification System (EP03)===
===.7 Alert and Notification System (EP03)===


a. The inspectors sampled licensee submittals for the Alert and Notification System performance indicator for the period from April 2010 through September 2011. To determine the accuracy of the performance indicator data reported during those periods, performance indicator definitions and guidance contained in Nuclear Energy Institute Document 99
====a. Inspection Scope====
-02, "Regulatory Assessment Performance Indicator Guideline," Revision 5, was used. The inspectors reviewed the licensee's records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the Nuclear Energy Institute guidance. Specifically, the inspectors reviewed licensee records and processes including procedural guidance on assessing opportunities for the performance indicator and the results of periodic alert notification system operability tests. The specific documents reviewed are described in the attachment to this report.
The inspectors sampled licensee submittals for the Alert and Notification System performance indicator for the period from April 2010 through September 2011. To determine the accuracy of the performance indicator data reported during those periods, performance indicator definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 5, was used. The inspectors reviewed the licensees records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the Nuclear Energy Institute guidance.


Inspection Scope
Specifically, the inspectors reviewed licensee records and processes including procedural guidance on assessing opportunities for the performance indicator and the results of periodic alert notification system operability tests. The specific documents reviewed are described in the attachment to this report.


These activities constitute completion of one sample of the alert and notification system as defined in Inspection Procedure 71151-05.
These activities constitute completion of one sample of the alert and notification system as defined in Inspection Procedure 71151-05.


b. No findings were identified.
====b. Findings====
 
No findings were identified. {{a|4OA2}}
Findings
{{a|4OA2}}
==4OA2 Identification and Resolution of Problems==
==4OA2 Identification and Resolution of Problems==
{{IP sample|IP=IP 71152}}
{{IP sample|IP=IP 71152}}
===.1 Routine Review of Identification and Resolution of Problems===
===.1 Routine Review of Identification and Resolution of Problems===


a. As part of the various baseline inspection procedures discussed in previous sections of this report, the inspectors routinely reviewed issues during baseline inspection activities and plant status reviews to verify that they were being entered into the licensee's corrective action program at an appropriate threshold, that adequate attention was being given to timely corrective actions, and that adverse trends were identified and addressed. The inspectors reviewed attributes that included the complete and accurate identification of the problem; the timely correction, commensurate with the safety significance; the evaluation and disposition of performance issues, generic implications, common causes, contributing factors, root causes, extent of condition reviews, and previous occurrences reviews; and the classification, prioritization, focus, and timeliness of corrective actions. Minor issues entered into the licensee's corrective action program because of the inspectors' observations are included in the attached list of documents reviewed. Inspection Scope These routine reviews for the identification and resolution of problems did not constitute any additional inspection samples.
====a. Inspection Scope====
As part of the various baseline inspection procedures discussed in previous sections of this report, the inspectors routinely reviewed issues during baseline inspection activities and plant status reviews to verify that they were being entered into the licensees corrective action program at an appropriate threshold, that adequate attention was being given to timely corrective actions, and that adverse trends were identified and addressed. The inspectors reviewed attributes that included the complete and accurate identification of the problem; the timely correction, commensurate with the safety significance; the evaluation and disposition of performance issues, generic implications, common causes, contributing factors, root causes, extent of condition reviews, and previous occurrences reviews; and the classification, prioritization, focus, and timeliness of corrective actions. Minor issues entered into the licensees corrective action program because of the inspectors observations are included in the attached list of documents reviewed.


Instead, by procedure, they were considered an integral part of the inspections performed during the quarter and documented in Section 1 of this report.
These routine reviews for the identification and resolution of problems did not constitute any additional inspection samples. Instead, by procedure, they were considered an integral part of the inspections performed during the quarter and documented in Section 1 of this report.


b. No findings were identified.
====b. Findings====
No findings were identified.


Findings
===.2 Daily Corrective Action Program Reviews===


===.2 Daily Corrective Action Program Reviews===
====a. Inspection Scope====
In order to assist with the identification of repetitive equipment failures and specific human performance issues for follow-up, the inspectors performed a daily screening of items entered into the licensees corrective action program. The inspectors accomplished this through review of the stations daily corrective action documents.


a. In order to assist with the identification of repetitive equipmen t failures and specific human performance issues for follow
The inspectors performed these daily reviews as part of their daily plant status monitoring activities and, as such, did not constitute any separate inspection samples.
-up, the inspectors performed a daily screening of items entered into the licensee's corrective action program. The inspectors accomplished this through review of the station's daily corrective action documents.


Inspection Sc ope  The inspectors performed these daily reviews as part of their daily plant status monitoring activities and, as such, did not constitute any separate inspection samples.
====b. Findings====
No findings were identified.


b. No findings were identified.
===.3 Semi-Annual Trend Review===


Findings
====a. Inspection Scope====
The inspectors performed a review of the licensees corrective action program and associated documents to identify trends that could indicate the existence of a more significant safety issue. The inspectors focused their review on repetitive equipment issues, but also considered the results of daily corrective action item screening discussed in Section 4OA2.2, above, licensee trending efforts, and licensee human performance results. The inspectors nominally considered the 6-month period of June 1, 2011, through November 30, 2011 although some examples expanded beyond those dates where the scope of the trend warranted.


===.3 Semi-Annual Trend Review===
The inspectors also included issues documented outside the normal corrective action program in major equipment problem lists, repetitive and/or rework maintenance lists, departmental problem/challenges lists, system health reports, quality assurance audit/surveillance reports, self-assessment reports, and Maintenance Rule assessments.


a. The inspectors performed a review of the licensee's corrective action program and associated documents to identify trends that could indicate the existence of a more significant safety issue. The inspectors focused their review on repetitive equipmen t issues, but also considered the results of daily corrective action item screening discussed in Section 4OA2.2, above, licensee trending efforts, and licensee human performance results. The inspectors nominally considered the 6
The inspectors compared and contrasted their results with the results contained in the licensees corrective action program trending reports. Corrective actions associated with a sample of the issues identified in the licensees trending reports were reviewed for adequacy.
-month period of June 1, 2011 , through November 30, 2011 although some examples expanded beyond those dates where the scope of the trend warranted.


Inspection Scope The inspectors also included issues documented outside the normal corrective action program in major equipmen t problem lists, repetitive and/or rework maintenance lists, departmental problem/challenges lists, system health reports, quality assurance audit/surveillance reports, self
These activities constitute completion of one single semi-annual trend inspection sample as defined in Inspection Procedure 71152-05.
-assessment reports, and Maintenance Rule assessments. The inspectors compared and contrasted their results with the results contained in the licensee's corrective action program trending reports. Corrective actions associated with a sample of the issues identified in the licensee's trending reports were reviewed for adequacy. These activities constitute completion of one single semi
-annual trend inspection sample as defined in Inspection Procedure


==71152 - 05.==
====b. Findings====
b. No findings were identified.
No findings were identified. {{a|4OA3}}
==4OA3 Event Follow-up==
{{IP sample|IP=IP 71153}}
===.1 (Open) Licensee Event Report 05000285/2011-003-03: Inadequate Flooding Protection===


Findings
Due To Ineffective Oversight During identification and evaluation of flood barriers, unsealed through wall penetrations in the outside wall of the intake, auxiliary and chemistry and radiation protection buildings were identified that are below the licensing basis flood elevation. Additionally a potential flooding issue was identified on the inside of the intake structure. Holes were noted in the floor at the 10076 level, which is the ceiling of the raw water vault.
{{a|4OA3}}
==4OA3 Event Follow==


-up (71153)
A summary of the root causes included: a weak procedure revision process; insufficient oversight of work activities associated with external flood matters; ineffective identification, evaluation and resolution of performance deficiencies related to external flooding; and safe as is mindsets relative to external flooding events.


===.1 (Open) Licensee Event Report 05000285/2011===
The penetrations were temporarily sealed and a configuration change was developed and implemented whereby permanent seals were installed. A one-foot sandbag berm


03:  Inadequate Flooding Protection Due To Ineffective Oversight During identification and evaluation of flood barriers, unsealed through wall penetrations in the outside wall of the intake, auxiliary and chemistry and radiation protection buildings were identified that are below the licensing basis flood elevation. Additionally a potential flooding issue was identified on the inside of the intake structure. Holes were noted in the floor at the 1007'6" level, which is the ceiling of the raw water vault
was placed around the holes. Comprehensive corrective actions to address the root and contributing causes are being addressed through the corrective action program.
. A summary of the root causes included: a weak procedure revision process; insufficient oversight of work activities associated with external flood matters; ineffective identification, evaluation and resolution of performance deficiencies related to external flooding; and "safe as is" mindsets relative to external flooding events.


The penetrations were temporarily sealed and a configuration change was developed and implemented whereby permanent seals were installed. A one-foot sandbag berm was placed around the holes. Comprehensive corrective actions to address the root and contributing causes are being addressed through the corrective action program.
===.2 (Open) Licensee Event Report 05000285/2011-008-01: Fire in Safety Related 480 Volt===


===.2 (Open) Licensee Event Report 05000285/2011===
Electrical Bus On June 7, 2011, at approximately 9:30 a.m. Central Daylight Time, a failure of a safety related 480-volt AC (V) load center supply breaker in the switchgear room occurred (Bus 1B4A). Fire alarms were received in the control room and the Halon system that protects the switchgear rooms discharged. The fire brigade responded and found the room filled with smoke, but no active fire. At 9:40 a.m., Central Daylight Time an Alert was declared for a fire affecting the operability of plant safety systems required to establish or maintain safe shutdown. At 1:13 p.m. Central Daylight Time on June 7, 2011, Fort Calhoun Station exited the Alert after confirming that the fire was extinguished and the area was ventilated to restore access. Shutdown cooling remained in-service during the event.


01:  Fire in Safety Related 480 Volt Electrical Bus On June 7, 2011, at approximately 9
Fort Calhoun Station was also in an emergency classification of a Notification of Unusual Event (NOUE) due to high Missouri River levels.
: 30 a.m. Central Daylight Time, a failure of a safety related 480-volt AC (V) load center supply breaker in the switchgear room occurred (Bus 1B4A). Fire alarms were received in the control room and the Halon system that protects the switchgear rooms discharged. The fire brigade responded and found the room filled with smoke, but no active fire. At 9: 40 a.m., Central Daylight Time an Alert was declared for a fire affecting the operability of plant safety systems required to establish or maintain safe shutdown. At 1: 13 p.m. Central Daylight Time on June 7, 2011, Fort Calhoun Station exited the Alert after confirming that the fire was extinguished and the area was ventilated to restore access. Shutdown cooling remained in-service during the event.


Fort Calhoun Station was also in an emergency classification of a Notification of Unusual Event (NOUE) due to high Missouri River level s.
The root cause of the event was the Fort Calhoun Station design process failed to identify the silver plating of bus bar material as a critical interface when specifying replacements for the original circuit breakers. The design process failure extended to other safety-related 480v load center circuit breakers as well.


The root cause of the event was the Fort Calhoun Station design process failed to identify the silver plating of bus bar material as a critical interface when specifying replacements for the original circuit breakers.
Corrective actions included replacing 480v bus 1B4A and performing bus maintenance.


The design process failure extended to other safety
Affected circuit breaker cradles will be realigned to ensure proper fit in the bus cubicles.
-related 480v load center circuit breakers as well.


Corrective actions included replacing 480 v bus 1B4A and performing bus maintenance. Affected circuit breaker cradles will be realigned to ensure proper fit in the bus cubicles. Maintenance procedures are being revised to enhance maintenance practices.
Maintenance procedures are being revised to enhance maintenance practices.


===.3 (Closed) Licensee Event Report 05000285/2011===
===.3 (Closed) Licensee Event Report 05000285/2011-003-01: Inadequate Flooding===


01:  Inadequate Flooding Protection Due To Ineffective Oversight During identification and evaluation of flood barriers, unsealed through wall penetrations in the outside wall of the intake, auxiliary and chemistry and radiation protection buildings were identified that were below the licensing basis flood elevation.
Protection Due To Ineffective Oversight During identification and evaluation of flood barriers, unsealed through wall penetrations in the outside wall of the intake, auxiliary and chemistry and radiation protection buildings were identified that were below the licensing basis flood elevation.


A summary of the root causes included: a weak procedure revision process; insufficient oversight of work activities associated with external flood matters; ineffective identification, evaluation and resolution of performance deficiencies related to external flooding; and "safe as is" mindsets relative to external flooding events.
A summary of the root causes included: a weak procedure revision process; insufficient oversight of work activities associated with external flood matters; ineffective identification, evaluation and resolution of performance deficiencies related to external flooding; and safe as is mindsets relative to external flooding events.


The penetrations were temporarily sealed and a configuration change was developed and implemented whereby permanent seals were installed. Comprehensive corrective actions to address the root and contributing causes are being addressed through the corrective action program.
The penetrations were temporarily sealed and a configuration change was developed and implemented whereby permanent seals were installed. Comprehensive corrective actions to address the root and contributing causes are being addressed through the corrective action program.
Line 698: Line 621:
The licensee event report is closed. Revision 3 of this licensee event report was submitted on December 17, 2011.
The licensee event report is closed. Revision 3 of this licensee event report was submitted on December 17, 2011.


===.4 (Closed) Licensee Event Report 05000285/2011===
===.4 (Closed) Licensee Event Report 05000285/2011-008-00: Fire in Safety Related 480 Volt===
 
Electrical Bus On June 7, 2011, at approximately 9:30 a.m. Central Daylight Time, a failure of a safety related 480-volt ac (Vac) load center supply breaker in the switchgear room occurred (Bus 1B4A). Fire alarms were received in the control room and the Halon System that protects the switchgear rooms discharged. The fire brigade responded and found the room filled with smoke, but no active fire. At 9:40 a.m., Central Daylight Time an alert was declared for a fire affecting the operability of plant safety systems required to establish or maintain safe shutdown. At 1:13 p.m. Central Daylight Time on June 7, 2011, Fort Calhoun Station exited the alert after confirming that the fire was extinguished and the area was ventilated to restore access.


00:  Fire in Safety Related 480 Volt Electrical Bus On June 7, 2011, at approximately 9:30 a.m. Central Daylight Time, a failure of a safety related 480
Shutdown cooling remained in-service during the event. Fort Calhoun Station was also in an emergency classification of a Notification of Unusual Event (NOUE) due to high Missouri River level.
-volt ac (Vac) load center supply breaker in the switchgear room occurred (Bus 1B4A). Fire alarms were received in the control room and the Halon System that protects the switchgear rooms discharged. The fire brigade responded and found the room filled with smoke, but no active fire. At 9:40 a.m., Central Daylight Time an alert was declared for a fire affecting the operability of plant safety systems required to establish or maintain safe shutdown. At 1:13 p.m. Central Daylight Time on June 7, 2011, Fort Calhoun Station exited the alert after confirming that the fire was extinguished and the area was ventilated to restore access.


Shutdown cooling remained in
A root cause analysis is in progress. The results of the analysis and corrective actions were reported in Revision 1 of this licensee event report (2011-008-01).
-service during the event. Fort Calhoun Station was also in an emergency classification of a Notification of Unusual Event (NOUE) due to high Missouri River level.


A root cause analysis is in progress. The results of the analysis and corrective actions were reported in Revision 1 of this licensee event report (2011 01). The licensee event report is closed. Revision 1 of this licensee event report was submitted on October 27, 2011.
The licensee event report is closed. Revision 1 of this licensee event report was submitted on October 27, 2011.


{{a|4OA6}}
{{a|4OA6}}
==4OA6 Meetings Exit Meeting Summary==
==4OA6 Meetings==
 
===Exit Meeting Summary===
 
On October 20, 2011, the inspectors presented results of the onsite inspection of the emergency preparedness performance indicators to Mr. D. Bannister, Vice President and Chief Nuclear Officer, and other members of the licensees staff. The licensee acknowledged the issues presented. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.
 
On November 18, 2011, the inspectors presented the inspection results of the heat sink performance inspection to Mr. J. Goodell, Division Manager, Nuclear Performance Improvement and Support, and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.


On October 20, 2011, the inspectors presented results of the onsite inspection of the emergency preparedness performance indicators to Mr. D. Bannister, Vice President and Chief Nuclear Officer, and other members of the licensee's staff. The licensee acknowledged the issues presented. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.
On December 2, 2011, the inspectors presented the results of the radiation safety inspections to Mr. D. Bannister, Vice President and Chief Nuclear Officer, and other members of the licensee staff. The licensee acknowledged the issues presented. The


On November 18, 2011, the inspectors presented the inspection results of the heat sink performance inspection to Mr. J. Goodell, Division Manager, Nuclear Performance Improvement and Support
inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.
, and other members of the licensee staff. The licensee acknowledged the issues presented. The inspector s asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.


On December 2, 2011, the inspectors presented the results of the radiation safety inspections to Mr. D. Bannister, Vice President and Chief Nuclear Officer, and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.
On January 9, 2012, the inspectors presented the quarterly inspection results to Mr. J.


On January 9, 2012, the inspectors presented the quarterly inspection results to Mr. J. Goodell, Division Manager, Nuclear Performance Improvement and Support, and other members of the licensee staff. The licensee acknowledged the issues presented. The inspector s asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.
Goodell, Division Manager, Nuclear Performance Improvement and Support, and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.


{{a|4OA7}}
{{a|4OA7}}
==4OA7 Licensee-Identified Violations==
==4OA7 Licensee-Identified Violations==


The following violation of very low safety significance (Green) was identified by the licensee and is a violation of NRC requirements, which meet the criteria of Section VI of the NRC Enforcement Policy, NUREG
The following violation of very low safety significance (Green) was identified by the licensee and is a violation of NRC requirements, which meet the criteria of Section VI of the NRC Enforcement Policy, NUREG-1600, for being dispositioned as a noncited violation.
-1600, for being dispositioned as a noncited violation.
* The inspectors reviewed a licensee-identified, noncited violation of Technical Specification 5.8.1 for failure to follow Radiation Work Permit 11-3530, Task-3, which required workers to wear respiratory protection equipment in the lower cavity. On April 19, 2011, an individual working on the upender in the lower cavity had positive radioactivity results from his lapel air sample. The licensee investigated, performed a dose assessment, and assigned a dose from the lapel air sample of 39 mrem to the worker. The licensee found that the worker did not use respiratory protection equipment as required by the radiation work permit.
 
The inspectors reviewed a licensee
-identified, noncited violation of Technical Specification 5.8.1 for failure to follow Radiation Work Permit 11
-3530, Task
-3, which required workers to wear respiratory protection equipmen t in the lower cavity. On April 19, 2011, an individual working on the upender in the lower cavity had positive radioactivity results from his lapel air sample. The licensee investigated, performed a dose assessment, and assigned a dose from the lapel air sample of 39 mrem to the worker.
 
The licensee found that the worker did not use respiratory protection equipmen t as required by the radiation work permit.


Technical Specification 5.8.1 requires that written procedures shall be established, implemented and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, "Quality Assurance Program Requirements," Revision 2, Appendix A, 1978. Section 7(e)(1) lists radiation protection procedures for the control of radioactivity and limiting personnel exposure, including a radiation work permit system.
Technical Specification 5.8.1 requires that written procedures shall be established, implemented and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Quality Assurance Program Requirements, Revision 2, Appendix A, 1978. Section 7(e)(1) lists radiation protection procedures for the control of radioactivity and limiting personnel exposure, including a radiation work permit system. Radiation Protection Plan, Revision 24, Section 2.3.11, states that station personnel are responsible for complying with the requirements in Procedure SO-G-101, Radiation Worker Practices, Revision 33. Procedure SO-G-101, Sections 4.3.2 and 5.4.4 requires that personnel adhere to the requirements listed on the radiation work permit they are using. Radiation Work Permit 11-3530, Task-3, required workers to wear specified respiratory protection equipment while in the lower cavity.


Radiation Protection Plan, Revision 24, Section 2.3.11, states that station personnel are responsible for complying with the requirements in Procedure SO-G-101, "Radiation Worker Practices,"
Contrary to the above, on April 19, 2011, an individual working on the upender in the lower cavity was determined to be contaminated, and it was determined that the worker did not wear the specified NIOSH approved respiratory protection equipment required by the radiation work permit. Using the Occupational Radiation Safety Significance Determination Process, the inspector determined the finding to have very low safety significance because:
Revision 33. Procedure SO-G-101, Sections 4.3.2 and 5.4.4 requires that personnel adhere to the requirements listed on the radiation work permit they are using. Radiation Work Permit 11
-3530, Task
-3, required workers to wear specified respiratory protection equipmen t while in the lower cavity. Contrary to the above, on April 19, 2011, an individual working on the upender in the lower cavity was determined to be contaminated, and it was determined that the worker did not wear the specified NIOSH approved respiratory protection equipmen t required by the radiation work permit. Using the Occupational Radiation Safety Significance Determination Process, the inspector determined the finding to have very low safety significance because:
: (1) it was not associated with ALARA planning or work controls,
: (1) it was not associated with ALARA planning or work controls,
: (2) there was no overexposure,
: (2) there was no overexposure,
: (3) there was no substantial potential for an overexposure, and
: (3) there was no substantial potential for an overexposure, and
: (4) the ability to assess does was not compromised. This issue was entered into the licensee's corrective action program as Condition Reports 2011
: (4) the ability to assess does was not compromised. This issue was entered into the licensees corrective action program as Condition Reports 2011-3323 and 2011-9794.
-3323 and 2011-9794.


=SUPPLEMENTAL INFORMATION=
=SUPPLEMENTAL INFORMATION=
Line 750: Line 667:


===Licensee Personnel===
===Licensee Personnel===
: [[contact::R. Acker]], Licensing Engineer  
: [[contact::R. Acker]], Licensing Engineer
: [[contact::D. Bannister]], Vice President and Chief Nuclear Officer
: [[contact::D. Bannister]], Vice President and Chief Nuclear Officer
: [[contact::S. Baughn]], Manager, Nuclear Licensing  
: [[contact::S. Baughn]], Manager, Nuclear Licensing
: [[contact::A. Berck]], Supervisor, Emergency Planning
: [[contact::A. Berck]], Supervisor, Emergency Planning
: [[contact::B. Blome]], Manager, Quality
: [[contact::B. Blome]], Manager, Quality
: [[contact::C. Cameron]], Supervisor Regulatory Compliance  
: [[contact::C. Cameron]], Supervisor Regulatory Compliance
: [[contact::M. Cooper]], Licensing Engineer
: [[contact::M. Cooper]], Licensing Engineer
: [[contact::M. Frans]], Manager, Engineering Programs
: [[contact::M. Frans]], Manager, Engineering Programs
: [[contact::S. Gebers]], Manager, Emergency Planning and Health Physics  
: [[contact::S. Gebers]], Manager, Emergency Planning and Health Physics
: [[contact::J. Goodell]], Division Manager, Nuclear Performance Improvement and Support
: [[contact::J. Goodell]], Division Manager, Nuclear Performance Improvement and Support
: [[contact::P. Gunderson]], Supervisor, Radiation Protection
: [[contact::P. Gunderson]], Supervisor, Radiation Protection
: [[contact::J. Herman]], Division Manager, Nuclear Engineering  
: [[contact::J. Herman]], Division Manager, Nuclear Engineering
: [[contact::R. Hodgson]], Manager, Work Managemen
: [[contact::R. Hodgson]], Manager, Work Management
t
: [[contact::T. Jameson]], Supervisor, Radiation Protection
: [[contact::T. Jameson]], Supervisor, Radiation Protection
: [[contact::A. Lollis]], Supervisor, ALARA  
: [[contact::A. Lollis]], Supervisor, ALARA
: [[contact::K. Maassen]], Program Engineer
: [[contact::K. Maassen]], Program Engineer
: [[contact::T. Maine]], Manager, Radiation Protection
: [[contact::T. Maine]], Manager, Radiation Protection
: [[contact::E. Matzke]], Senior Licensing Engineer  
: [[contact::E. Matzke]], Senior Licensing Engineer
: [[contact::T. Nellenbach]], Division Manager, Plant Operations  
: [[contact::T. Nellenbach]], Division Manager, Plant Operations
: [[contact::A. Pallas]], Manager Shift Operations
: [[contact::A. Pallas]], Manager Shift Operations


==LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED==
==LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED==


OPENED  
OPENED
: 05000285/2011
: 05000285/2011-003-03 LER Inadequate Flooding Protection Due To Ineffective Oversight (Section 4OA3)
-003-03 LER Inadequate Flooding Protection Due To Ineffective Oversight
: 05000285/2011-008-01 LER Fire in Safety Related 480 Volt Electrical Bus (Section 4OA3)
(Section 4OA3)
CLOSED
: 05000285/2011
: 05000285/2011-003-01 LER Inadequate Flooding Protection Due To Ineffective Oversight (Section 4OA3)
-008-01 LER Fire in Safety Related 480 Volt Electrical Bus
: 05000285/2011-008-00 LER Fire in Safety Related 480 Volt Electrical Bus (Section 4OA3)
(Section 4OA3)
CLOSED  
: 05000285/2011
-003-01 LER Inadequate Flooding Protection Due To Ineffective Oversight
(Section 4OA3)
: 05000285/2011
-008-00 LER Fire in Safety Related 480 Volt Electrical Bus
(Section 4OA3)
OPENED AND CLOSED
OPENED AND CLOSED
: 05000285/2011005
: 05000285/2011005-01       NCV Failure to Follow Procedure Results in a Loss of Reactor Coolant (Section 1R04)
-01 NCV Failure to Follow Procedure Results in a Loss of Reactor Coolant
Attachment
(Section 1R04)


Attachment
OPENED AND CLOSED
OPENED AND CLOSED
: 05000285/2011005
: 05000285/2011005-02    NCV Inadequate Performance Monitoring Test for Component Cooling Water Heat Exchangers (Section 1R07)
-0 2 NCV Inadequate Performance Monitoring Test for Component Cooling Water Heat Exchangers (Section 1R07)
: 05000285/2011005-03    NCV Failure to Follow Radiation Work Permit Instructions (Section 2RS04)
: 05000285/2011005
: 05000285/2011005-04    NCV Inadequate Licensee Procedure for Making Protective Action Recommendations (Section 4OA1)
-0 3 NCV Failure to Follow Radiation Work Permit Instructions (Section 2RS04)  
: 05000285/2011005
-0 4 NCV Inadequate Licensee Procedure for Making Protective Action Recommendations
(Section 4OA1)


==LIST OF DOCUMENTS REVIEWED==
==LIST OF DOCUMENTS REVIEWED==
==Section 1RO4: Equip.m.ent Alignment==
: PROCEDURES
: NUMBER TITLE REVISION
: OI-SC-2 Shutdown Cooling Operation and Termination
: OI-SC-3 Alternate Shutdown Cooling Utilizing Containment Spray Pumps
: DRAWINGS NUMBER TITLE REVISION
: E-23866-210-130 Safety Injection and Containment Spray System Flow Diagram P&ID, Sheet 1
: 111
==Section 1RO5: Fire Protection==
: PROCEDURES
: NUMBER TITLE REVISION
: SO-G-28 Standing Order, Station Fire Plan
: SO-G-58 Standing Order, Control of Fire Protection System Impairments
: SO-G-91 Standing Order, Control and Transportation of Combustible Materials
: SO-G-102 Standing Order, Fire Protection Program Plan
: SO-G-103 Standing Order, Fire Protection Operability Criteria and Surveillance Requirements
: Attachment
: MISCELLANEOUS DOCUMENTS
: NUMBER TITLE REVISION
: EA-FC-97-001 Fire hazards Analysis Manual
: FC05814 UFHA Combustible Loading Calculation
: FCDR092011
: Fire in Fab Shop
: USAR 9.11 Updated Safety Analysis Report, Fire Protection Systems
==Section 1RO6: Flood Protection Measures==
: PROCEDURES
: NUMBER TITLE REVISION
: AOP-10 Loss of Circulating Water
: AOP-11 Loss of Component Cooling Water
: AOP-18 Loss of Raw Water
: DRAWINGS NUMBER TITLE REVISION E-23866-210-130 Composite Flow Diagram, Safety Injection and Containment Spray System P&ID
: MISCELLANEOUS DOCUMENTS NUMBER TITLE REVISION / DATE USAR, Appendix M
: Postulated High Energy Line Rupture Outside the Containment Individual Plant Examination Submittal December, 1993
==Section 1RO7: Heat Sink Performance==
: PROCEDURES
: NUMBER TITLE DATE
: AOP-18 Loss of Raw Water
: CH-AD-0035 Microbiologically Induced/Influenced Corrosion Monitoring Program
: 3 
: Attachment
: PROCEDURES
: NUMBER TITLE DATE
: CH-AD-0048 Environment Inspection for Biofouling Organisms
: OD-PP-N-3 Strategic Water Plan
: OP-P.M.-RW-0001 Raw Water System Interface Valve Actuation Test
: PBD-17 Service Water Reliability
: PED-SEI-16 Evaluation of Heat Exchanger Performance
: PE-RR-CCW-0100 Disassembly, Cleaning, and Repair of CCW Heat Exchanger-Raw Water Side
: PE-RR-CCW-0101 Removal and Reinstallation of Shutdown Cooling Heat Exchanger Heads
: SE-PFT-CCW-0001 Component Cooling Water Heat Exchangers Performance Test
: 13
: SE-PFT-CCW-0004 SFP Heat Exchanger Performance Test
: SE-PFT-CCW-0012
: AC-4B Shutdown Cooling Heat Exchanger Performance Test
: 5
: SO-M-28 Control of Measuring and Test Equi pm ent
: 71
: CALCULATIONS
: NUMBER TITLE REVISION / DATE
: EAR 27057 Uncertainty Analysis for the Heat Exchanger Testing Program June 10, 1999
: EAR 96032 Evaluation of CCW Heat Exchangers Post
: DBA Performance with 5 Percent Plugged Tubes March 8, 1996
: FC03130 Spent Fuel Pool Heat Removal Study of Expanded Spent Fuel Storage
: FC05693 Component Cooling Water System Design Heat Loads and Flows 0 FC05742 Acceptance Criteria for CCW Heat Exchanger Performance
: FC07529 FCS RW/CCW Gothic Model
- Additional Cases
: Attachment
: MISCELLANEOUS DOCUMENTS
: NUMBER TITLE REVISION / DATE
: 0903648 Certificate of Calibration for Panametrics Flowmeter MT
-22702 October 14, 2009
: 1001042 Certificate of Calibration for Panametrics Flowmeter MT
-22703 February 24, 2010
: 1002565 Certificate of Calibration for Panametrics Flowmeter MT
-22700 May 20, 2010
: 1003708 Certificate of Calibration for Panametrics Flowmeter MT
-22701 October 15, 2010
: WORK ORDERS
: 00125468-02
: 00188897-01
: 00201320-01
: 00247271-01
: 00328308-01
: 00341977-01
: 00362751-01
: 00377572-01
: 00388929-01
: 00396368-01
: 00413547-01
: 9201881
: CONDITION REPORTS
: 2004-1831 2007-1235 2008-6484 2008-7046 2011-1050 2011-2209 2011-4600 2011-4855 2011-9375 2011-9401
==Section 1R11: Licensed Operator Requalification Program==
: PROCEDURES
: NUMBER TITLE REVISION LOR
: TP.M.P Licensed Operator Requal Training Program Master Plan
: OPD-3-11 Licensed Activation and Watch station Maintenance
: SO-G-26 Training and Qualification Programs Standing Orders
==Section 1R12: Maintenance Effectiveness==
: CONDITION REPORTS
: 2008-6557 2009-0731 2009-1295 2009-1753 2009-1760 2009-2065 2009-3846 2010-0870 2010-4499 2011-0850 2011-1316 2011-1452 2011-2261 2011-5466 2011-7616
: PROCEDURES
: NUMBER TITLE REVISION
: PBD-16 Program Basis Document, Maintenance Rule
: PED-SEI-34 Maintenance Rule Program
: Attachment
: MISCELLANEOUS DOCUMENTS
: TITLE REVISION / DATE Maintenance Rule Scoping Data Sheet CTRLAC
: Maintenance Rule Scoping Data Sheet MOVDAO
: 5a Maintenance Rule Scoping Data Sheet CMPRES
: Status of Equip.m.ent in MR Category (a)(1) or (a)(1) review September 22, 2011
==Section 1R13: Maintenance Risk Assessment and Emergent Work Controls==
: PROCEDURES
: NUMBER TITLE REVISION
: SO-G-87 Non-Routine Activities Requiring Formalized Plans
: SO-M-100 Standing Order, Conduct of Maintenance
: SO-M-101 Standing Order, Maintenance Work Control
: SO-O-21 Shutdown Operations Protection Plan
: MISCELLANEOUS DOCUMENTS TITLE DATE Shift Outage Manager's Report October 25, 2011
: Shift Outage Manager's Report October 30, 2011
: Fort Calhoun Power Station Plan of the Day December 15, 2011
: Fort Calhoun Power Station Plan of the Day December 16, 2011
==Section 1R15: Operability Evaluations==
: CONDITION REPORTS
: 2011-7468 2011-7477 2011-8186 2011-9344 2011-9494 2011-9578 2011-9588       
: Attachment
==Section 1R18: Plant Modifications==
: MISCELLANEOUS DOCUMENTS
: NUMBER TITLE DATE
: EC 54439 Provide Temporary Power to AC
-12A and
: HCV-348 November 7, 2011
: EC 54451 Provide Temporary Power to FP
-1B-BC and
: FP-1B-HTR November 7, 2011
==Section 1R19: Postmaintenance Testing==
: WORK ORDERS
: 357858
: 388485
: 398643
: 398647
: 398634
: PROCEDURES
: NUMBER TITLE REVISION
: MM-P.M.-DG-0002 Diesel Generator DG
-2 Inspection
: OP-ST-DG-0002 Diesel Generator 2 Check
==Section 1R22: Surveillance Testing==
: WORK ORDERS
: 2103
: PROCEDURES
: NUMBER TITLE REVISION
: EM-ST-ESF-0002 13.8 KV Emergency Power Periodic Test
: OP-ST-RW-3004 Raw Water System Category C Valve Inservice Test
==Section 1EP6: Drill Evaluation==
: PROCEDURES
: NUMBER TITLE REVISION
: TBD-EPIP-OSC-1A Recognition Category A
- Abnormal Rad Levels/Radiological Effluent
: TBD-EPIP-OSC-1C Recognition Category C
- Cold Shutdown/Refueling
: Attachment
: PROCEDURES
: NUMBER TITLE REVISION System Malfunction
: TBD-EPIP-OSC-1F Recognition Category F
- Fission Product Barrier Degradation
: TBD-EPIP-OSC-1H Recognition Category H
- Hazards and Other Conditions Affecting Plant Safety
: TBD-EPIP-O
: SC-1S Recognition Category S
- System Malfunction
: MISCELLANEOUS DOCUMENTS
: TITLE DATE Scenario Manual Volume 1, Nov 2011 Training Drill November 10, 2011
: Section 2RS04:
: Occupational Dose Assessment
: PROCEDURES
: NUMBER TITLE REVISION
: RP-650 Internal Dosimetry Program
: RP-655 In-Vitro Bioassay Sampling
: RP-656 Bioassay Calculations
: RP-AD-600 Dosimetry Program
: CONDITION REPORTS
: 2010-2483 2011-2011 2011-3103 2011-3239 2011-3323 2011-3944 2011-3946 2011-4318 2011-4352
: RADIOLOGICAL SURVEYS
: NUMBER TITLE DATE 11-0515 Pre-Job Survey FH
-5 Flange April 15, 2011
: 11-0550 Pre-job Survey FH
-5 Flange Removal April 15, 2011
: 11-0910 Removal of FCV
-326 for Repair May 2, 2011
: 11-0924
: FCV-326 for Repair and Contamination Follow-Up May 2, 2011
: Attachment
: RADIATION WORK PERMITS
: NUMBER TITLE DATE 11-2512 Reactor Head Disassembly and Transport to Head Stand April 16, 2011
: 11-2520 Valve Maintenance in High Radiation Areas March 14, 2011
: 11-3520 Fuel Handling Fuel Mods and Associated Task March 10, 2011
: Section 2RS05:
: Radiation Monitoring Instrumentation
: PROCEDURES
: NUMBER TITLE REVISION
: IC-CP-02-0100 Calibration of Ludlum Model 177
: IC-CP-02-0213 Calibration of the Tennelec LB4100 Alpha/Beta Counter
: IC-CP-02-0611 Calibration of CM11 Alpha/Beta
-Gamma Monitor
: IC-CP-07-0008 Calibration of Eberline P.M.-7 Portal Monitor
: IC-CP-07-0009 Calibration of Eberline PCM
-2 6
: RP-CP-07-0207 Calibration of the CANBERRA Whole Body Counters
: MISCELLANEOUS DOCUMENTS
: Certificate of Calibration Beta Standard Source #B2
-271
: Certificate of Calibration Alpha Source #2535/91
: Certificate of Calibration Gamma Source #16921
-22
: CONDITION REPORTS
: 2008-4297 2009-1829 2009-2259 2009-3443 2010-4533 2011-2608 2011-2609 2011-9846
: CALIBRATION DOCUMENTS
: TITLE DATE Electronic and Secondary Calibration of Radiation Monitor, RM
-055 April 23, 2010
: Electronic and Secondary Calibration of Radiation Monitor, RM
-052 June 21, 2010
: MGP Telepole, Serial #6603
-066 January 26, 2011 
: Attachment
: CALIBRATION DOCUMENTS
: TITLE DATE MGP Telepole, Serial #6603
-092 January 26, 2011
: NE Technology Small Articles Monitor
: SAM 11, Serial #215
: February 3, 2011
: NE Technology Small Articles Monitor
: SAM 11, Serial #228
: February 3, 2011
: CM11 Alpha/Beta
-Gamma Monitor, Serial #637
: February 5, 2011
: Ludlum Model 177, Serial #49447
: February 7, 2011
: Eberline RO
-20 Survey Meter, Serial #2720
: March 28, 2011
==Section 4OA1: Performance Indicator Verification==
: CONDITION REPORTS
: 2010-3178 2010-4858 2010-4859 2010-4865 2010-4898 2010-4947 2010-4983 2010-4985 2010-5086 2010-5090 2010-5129 2010-5234 2010-5244 2010-5281 2010-5324 2010-5337 2010-5344 2010-5387 2010-5393 2010-5406 2010-5416 2010-5421 2010-5428 2010-5478 2010-5480 2010-5494 2010-5502 2010-5600 2010-5617 2010-5618 2010-5636 2010-5637 2010-5674 2010-5702 2010-5711 2010-5741 2010-5749 2010-5773 2010-5810 2010-5823 2010-5824 2010-5825 2010-5826 2010-5840 2010-5930 2010-5935 2010-5936 2010-5957 2010-5958 2010-5960 2010-5969 2010-6000 2010-6051 2010-6100 2010-6108 2010-6136 2010-6137 2010-6150 2010-6159 2010-6163 2010-6178 2010-6330 2010-6340 2010-6359 2010-6373 2010-6430 2010-6497 2010-6516 2010-6531 2010-6566 2010-6584 2010-6592 2010-6640 2010-6700 2010-6701 2010-6726 2010-6755 2010-6758 2010-6760 2010-6774 2010-6784 2010-6785 2010-6802 2010-6898 2011-0022 2011-0033 2011-0052 2011-0080 2011-0089 2011-0095 2011-0125 2011-0127 2011-0155 2011-0171 2011-0178 2011-0206 2011-0223 2011-0250 2011-0251 2011-0253 2011-0256 2011-0262 2011-0292 2011-0302 2011-0343 2011-0378 2011-0440 2011-0454 2011-0456 2011-0460 2011-0490 2011-0525 2011-0528 2011-0536 2011-0540 2011-0598 2011-0605 2011-0658 2011-0679 2011-0718 
: Attachment
: CONDITION REPORTS
: 2011-0741 2011-0839 2011-0862 2011-0921 2011-1007 2011-1121 2011-1130 2011-1132 2011-1137 2011-1169 2011-1259 2011-1298 2011-1308 2011-1323 2011-1336 2011-1340 2011-1341 2011-1399 2011-1422 2011-1469 2011-1569 2011-1598 2011-1614 2011-1630 2011-1662 2011-1774 2011-1793 2011-1801 2011-1803 2011-1917 2011-1933 2011-1934 2011-1952 2011-1965 2011-1988 2011-1993 2011-2024 2011-2070 2011-2075 2011-2229 2011-2354 2011-2380 2011-2399 2011-2417 2011-2463 2011-2505 2011-2507 2011-2540 2011-2553 2011-2588 2011-2617 2011-2628 2011-2651 2011-2666 2011-2691 2011-2697 2011-2699 2011-2720 2011-2726 2011-2737 2011-2937 2011-2949 2011-2957 2011-3003 2011-3035 2011-3182 2011-3190 2011-3195 2011-3216 2011-3219 2011-3222 2011-3232 2011-3247 2011-3285 2011-3341 2011-3382 2011-3391 2011-3395 2011-3414 2011-3416 2011-3464 2011-3521 2011-3566 2011-3572 2011-3576 2011-3843 2011-3846 2011-3850 2011-3912 2011-3948 2011-3960 2011-3994 2011-4026 2011-4042 2011-4043 2011-4072 2011-4075 2011-4137 2011-4194 2011-4231 2011-4250 2011-4260 2011-4345 2011-4362 2011-4406 2011-4409 2011-4414 2011-4485 2011-4510 2011-4513 2011-4543 2011-4576 2011-4620 2011-4696 2011-4771 2011-4773 2011-4789 2011-4798 2011-4843 2011-4844 2011-4855 2011-4883 2011-4894 2011-4898 2011-4902 2011-4914 2011-4926 2011-4963 2011-5030 2011-5032 2011-5047 2011-5109 2011-5110 2011-5127 2011-5128 2011-5135 2011-5149 2011-5173 2011-5215 2011-5230 2011-5242 2011-5243 2011-5307 2011-5492 2011-5513 2011-5643 2011-5770 2011-5775 2011-5793 2011-5824 2011-5843 2011-5872 2011-5911 2011-5932 2011-5976 2011-6057 2011-6067 2011-6107 2011-6117 2011-6195 2011-6198 2011-6216 2011-6219 2011-6221 2011-6251 2011-6323 2011-6365 2011-6427 2011-6448 2011-6471 2011-6478 2011-6492 2011-6512 2011-6708 2011-6719 2011-6751 2011-6757 2011-6787 2011-6798 2011-6802 2011-6812 2011-6876 2011-6910 2011-6934 2011-6936 2011-6977 2011-6996 2011-7010 2011-7018 2011-7023 2011-7061 2011-7155 2011-7157 2011-7184 2011-7262 2011-7298 2011-7328 2011-7340 2011-7401 2011-7421 2011-7433 2011-7447 2011-7469 2011-7519 2011-7538 2011-7564 2011-7622 2011-7695 2011-7827 2011-7831 2011-7832 2011-7841 2011-8259 2011-8530 2011-8531 2111-9634     
: Attachment
: MISCELLANEOUS DOCUMENTS
: NUMBER TITLE REVISION / DATE
: Various Operator Logs October 1, 2010 to September 30, 2011
: Omaha Public Power District, Report submitted to FEMA for Upgrading the Outdoor Public Warning System July 2004
: EOF-7 Protective Action Guidelines and 21
: EPDM-14 Emergency Preparedness Performance Indicator Program
: MSPI Mitigating Systems Performance Index
: NEI 99-02 Regulatory Assessment Performance Indicator Guideline
: OSC-1 Emergency Classification
: OSC-1A Emergency Classification Technical Basis Document


==Section 4OA2: Identification and Resolution of Problems==
: MISCELLANEOUS DOCUMENTS
: TITLE DATE Omaha Public Power District Performance Indicators October 2011
: Omaha Public Power District Performance Indicators November 2011
}}
}}

Latest revision as of 01:41, 21 December 2019

IR 05000285-11-005, on 10/01/2011 12/31/2011, Fort Calhoun Station, Integrated Resident and Regional Report, Heat Sink Performance, Occupational Dose Assessment
ML120450922
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 02/14/2012
From: Clark J
NRC/RGN-IV/DRP
To: Bannister D
Omaha Public Power District
References
ea-11-288 IR-11-005
Download: ML120450922 (47)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I V 1600 EAST LAMAR BLVD ARLINGTON, TEXAS 76011-4511 February 14, 2012 EA-11-288 David J. Bannister, Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station FC-2-4 P. O. Box 550 Fort Calhoun, NE 68023-0550 Subject: FORT CALHOUN - NRC INTEGRATED INSPECTION REPORT 05000285/2011005

Dear Mr. Bannister:

On December 31, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Fort Calhoun Station. The enclosed integrated inspection report documents the inspection findings, which were discussed on January 9, 2012, with Mr. John Goodell, Division Manager, Nuclear Performance Improvement and Support, and other members of your staff.

The inspections examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

Two NRC-identified findings and two self-revealing findings of very low safety significance (Green) were identified during this inspection.

Four of these findings were determined to involve violations of NRC requirements. Further, a licensee-identified violation, which was determined to be of very low safety significance, is listed in this report. The NRC is treating these violations as non-cited violations, consistent with Section 2.3.2 of the NRC Enforcement Policy.

If you contest the violations or the significance of the noncited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, D.C.

20555-0001, with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001; and the NRC Resident Inspector at the Fort Calhoun Station facility.

If you disagree with the cross-cutting aspect assigned to any finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region IV, and the NRC Resident Inspector at Fort Calhoun.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, and its enclosure, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/R.Deese for/

Jeff Clark, Branch Chief Project Branch F Division of Reactor Projects Docket No.: 50-285 License No.: DPR-40 Enclosure: Inspection Report 05000285/2011005 w/ Attachment: Supplemental Information cc w/ enclosure: Electronic Distribution

SUMMARY OF FINDINGS

IR 05000285/2011005; 10/01/2011 - 12/31/2011; Fort Calhoun Station, Integrated Resident and

Regional Report; Heat Sink Performance, Occupational Dose Assessment.

The report covered a 3-month period of inspection by resident inspectors and three announced baseline inspections by region-based inspectors. Four Green noncited violations of significance were identified. The significance of most findings is indicated by their color (Green, White,

Yellow, or Red) using Inspection Manual Chapter 0609, Significance Determination Process.

The crosscutting aspect is determined using Inspection Manual Chapter 0310, Components within the Cross Cutting Areas. Findings for which the significance determination process does not apply may be Green or be assigned a severity level after NRC management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.

NRC-Identified Findings and Self-Revealing Findings

Cornerstone: Initiating Events

Green.

A self-revealing noncited violation of Fort Calhoun Station Technical Specification 5.8.1 occurred due to the licensees failure to follow a procedure for placing the reactor coolant system level monitors into service. This failure resulted in the inadvertent draining of approximately 1,800 gallons of reactor coolant to the reactor coolant drain tank. This issue was entered into the licensees corrective action program as Condition Report 2011-2890.

The inspectors determined that the licensees failure to follow Procedure OI RC 1A,

RCS Instrumentation Operating Instruction, was a performance deficiency. This was a result of the licensees failure to properly implement a required procedure, and was within the licensees ability to foresee and correct and should have been prevented. This performance deficiency was more than minor because it could be reasonably viewed as a precursor to a significant event, i.e., could lead to a complete loss of reactor coolant inventory. The inspectors evaluated this finding using Inspection Manual Chapter 0609, Attachment 4, and determined that this finding is associated with the Initiating Events Cornerstone, specifically the primary system loss-of-coolant accident initiator contributor. Since the finding affected the safety of the reactor during a refueling outage, the inspectors further evaluated the finding using Inspection Manual Chapter 0609, Appendix G, Shutdown Operations Significance Determination Process. Using Attachment 1 of Appendix G, the inspectors determined that a Phase 2 analysis was required because the finding increased the likelihood of a loss of reactor coolant system inventory. A senior reactor analyst determined that the Phase 2 analysis was White, requiring a Phase 3 analysis. The Phase 3 analysis determined that the finding was of very low safety significance (green) because the leak path was small enough to allow sufficient time for operator action. This finding has a cross-cutting aspect in the area of human performance associated with the component of work practices because the licensee failed to communicate human error prevention techniques, such as self- and peer-checking H.4(a). (Section 1R04)

Cornerstone: Mitigating Systems

Green.

The inspectors identified a noncited violation of 10 CFR Part 50,

Appendix B, Criterion XI, Test Control, which requires, in part, that a test program shall be established to assure that all testing required to demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures. Test procedures shall include provisions for assuring that all prerequisites for the given test have been met, that adequate test instrumentation is available and used, and that the test is performed under suitable environmental conditions.

Specifically, prior to November 16, 2011, the prerequisite calculated heat loads used to demonstrate validity of the performance testing of component cooling water heat exchanger AC-1A test conditions did not agree to within the expected uncertainty, and ultrasonic flow meters were not calibrated to the appropriate range of test flow conditions. The licensee has entered this violation into their corrective action program as Condition Report 2011-9401.

The inspectors determined that the failure to perform testing and evaluation of safety-related heat exchangers in accordance with written procedures was a performance deficiency. This finding is more than minor because it adversely affected the Mitigating Systems Cornerstone objective of equipment performance to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage).

Additionally, the finding is more than minor because if left uncorrected it could lead to a more significant safety concern, as the failure to perform appropriate performance monitoring testing of the component cooling water heat exchangers could reasonably result in an unrecognized condition of a system failing to fulfill its safety-related function. Using Inspection Manual Chapter 0609, Attachment 4,

"Initial Screening and Characterization of Findings," the finding was determined to be of very low safety significance (Green) because it did not represent a loss of system safety function, nor an actual loss of safety function of a single train, and it did not screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event. The inspectors determined that this finding had a crosscutting aspect in the area of human performance, work practices, because the licensee did not communicate human error prevention techniques, such as self-and peer-checking and proper documentation of activities H.4(a) (Section 1R07).

Cornerstone: Occupational Radiation Safety

Green.

Inspectors reviewed a self-revealing, noncited violation of Technical Specification 5.8.1 for failure to follow procedures requiring workers to comply with radiological work permit instructions. Specifically, two workers changed the work scope for valve FCV-326 from reassembly to rework using abrasive pads without notifying radiation protection personnel. The licensees corrective action was to counsel the workers on the importance of adhering to the stated work scope and radiation work permit procedures. This issue was entered into the licensees corrective action program as Condition Reports 2011-3944, 2011-3046, and 2011-9795.

The failure to follow the requirements of the radiation work permit as instructed by radiation protection was a performance deficiency. The finding was more than minor because it was associated with the Occupational Radiation Safety Cornerstone attribute of program and process and affected the cornerstone objective of ensuring adequate protection of worker health and safety from exposure to radiation during routine operations. Using the Occupational Radiation Safety Significance Determination Process, the inspectors determined the finding to have very low safety significance because: (1) it was not associated with ALARA planning or work controls, (2) there was no overexposure, (3) there was no substantial potential for an overexposure, and (4)the ability to assess dose was not compromised. The finding was determined to have a human performance crosscutting aspect associated with work practices, because the licensee failed to ensure supervisory and management oversight of work activities, including contractors, such that nuclear safety is supported

H.4(c) (2RS04).

Cornerstone: Emergency Preparedness

Green.

The inspectors identified a noncited violation of 10 CFR 50.47(b)(10) for failure to develop and put into place guidelines for the choice of protective actions during an emergency that implemented federal guidance. Specifically, licensee guidance did not implement Regulatory Information Summary 2003-012, in that it allowed the subsequent removal of recommendations to evacuate members of the public during a radiological emergency.

This finding is more than minor because it affected the Emergency Preparedness Cornerstone attributes of emergency response organization performance and procedure quality. The finding had a credible impact on the cornerstone objective because rescinding an existing protective action recommendation can confuse offsite governmental authorities and the public. The finding is of very low safety significance because it was not a functional failure or degraded planning standard function. The finding was not a degraded planning standard function because the licensees process was capable of producing correct protective action recommendations. This finding has been entered into the licensees corrective action program as Condition Report 2011-8530 (Section 4OA1).

Licensee-Identified Violations

A violation of very low safety significance, which was identified by the licensee, has been reviewed by the inspectors. Corrective actions taken or planned by the licensee have been entered into the licensees corrective action program. This violation and its corrective actions are listed in Section 4OA7 of this report.

REPORT DETAILS

Summary of Plant Status

The station remained in Mode 5 for the entire inspection period.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R04 Equipment Alignments

.1 Partial Walkdown

a. Inspection Scope

The inspectors performed partial system walkdowns of the following risk-significant systems:

  • October 26, 2011, Shutdown Cooling lineup with HCV-335 (Shutdown Cooling Heat Exchangers AC-4A&B Inlet Header Isolation Valve) closed The inspectors selected these systems based on their risk significance relative to the reactor safety cornerstones at the time they were inspected. The inspectors attempted to identify any discrepancies that could affect the function of the system, and therefore, potentially increase risk. The inspectors reviewed applicable operating procedures, system diagrams, Updates Safety Analysis Report, technical specification requirements, administrative technical specifications, outstanding work orders, condition reports, and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have rendered the systems incapable of performing their intended functions. The inspectors also inspected accessible portions of the systems to verify system components and support equipment were aligned correctly and operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no obvious deficiencies. The inspectors also verified that the licensee had properly identified and resolved equipment alignment problems that could cause initiating events or impact the capability of mitigating systems or barriers and entered them into the corrective action program with the appropriate significance characterization. Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of two partial system walkdowns sample as defined in Inspection Procedure 71111.04-05.

b. Findings

Introduction.

A self-revealing noncited violation of Fort Calhoun Station Technical Specification 5.8.1 occurred due to the licensees failure to follow a procedure while placing the reactor coolant system level monitors into service. This failure resulted in the inadvertent draining of approximately 1,800 gallons of reactor coolant to the reactor coolant drain tank.

Description.

On April 12, 2011, the licensee was in the process of placing the reactor coolant system level sight glass (LI-199), the reactor coolant system shutdown level transmitter (LT-197), and the reactor hot leg coolant level transmitter (LT-119) in service using Procedure OI-RC-1A, RCS Instrumentation Operating Instruction. The valve line-up directed the operator to check RC-122 (loop 1 hot leg drain to waste disposal)closed then open RC-128 (loop 1 hot leg refueling level isolation valve).

While performing the valve line-up, the operator opened RC-122 rather than check it closed. At approximately 4:25 p.m., the operator opened RC-128 with no peer-check performed for the operator. This created a flow path for water to be drained from the hot leg to the reactor coolant drain tank. At approximately 4:45 p.m., RC-122 was closed, stopping the draining of reactor coolant. The pressurizer level decreased from 69 percent to 34 percent, which was approximately 1,800 gallons.

Analysis.

The inspectors determined that the licensees failure to follow Procedure OI-RC-1A was a performance deficiency. This was a result of the licensees failure to properly implement a required procedure, and was within the licensees ability to foresee and correct and should have been prevented. This performance deficiency was more than minor because it could be reasonably viewed as a precursor to a significant event, i.e., could lead to a complete loss of reactor coolant inventory. The inspectors evaluated this finding using Inspection Manual Chapter 0609, Attachment 4, and determined that this finding is associated with the Initiating Events Cornerstone, specifically the primary system loss-of-coolant accident initiator contributor. Since the finding affected the safety of the reactor during a refueling outage, the inspectors further evaluated the finding using Inspection Manual Chapter 0609, Appendix G, Shutdown Operations Significance Determination Process. Using Attachment 1 of Appendix G, the inspectors determined that a Phase 2 analysis was required because the finding increased the likelihood of a loss of reactor coolant system inventory. A senior reactor analysis determined that the Phase 2 analysis was White, requiring a Phase 3 analysis.

The analysts performed a Phase 3 Significance Determination Process risk analysis using a modified version of the Fort Calhoun Station at-power Standardized Probabilistic Analysis Risk model, Version 8.15. The analysts developed an event tree specific to a loss of reactor coolant system inventory outside containment with the reactor in a shutdown condition. The Region IV senior reactor analyst quantified the risk of the event as a conditional core damage probability of 3.0 x 10-7. The dominant core damage sequence from the model involved the following events:

  • Control room operators diagnose that a loss of inventory is occurring before the shutdown cooling system fails from cavitation;
  • Operators fail to isolate the loss of inventory before the shutdown cooling system fails from cavitation;
  • Operators fail to provide forced feed to the reactor before the shutdown cooling system fails from cavitation;
  • The operating train of shutdown cooling fails from cavitation as level drops below the middle of the primary system hot leg;
  • Operators fail to provide forced feed to the reactor after shutdown cooling has failed; and
  • The reactor core heats up, causing water to boil, resulting in uncovering the active fuel and the onset of fuel damage.

These events were all the result of operator actions. As documented in NUREG/CR-6883, The SPAR-H Human Reliability Analysis Method, the more time available to a crew to diagnose and act upon an abnormal event the less likely they are to fail in a given task. Because the leak path was sufficiently small (90 gpm) and the amount of water sufficiently large (31,000 gallons), there was additional time for operators to take the actions documented above. As such, the probability of failure for these actions was lower than they would have been with a higher leak rate.

As stated above, the quantified conditional core damage frequency for the event was of 3.0 x 10-7, thus making this finding of very low risk significance (Green). This finding has a cross-cutting aspect in the area of human performance associated with the component of work practices because the licensee failed to communicate human error prevention techniques, such as self- and peer-checking H.4(a).

Enforcement.

Technical Specification 5.8.1.a, Procedures, states, written procedures and administrative policies shall be established, implemented, and maintained covering the following activities:

(a) The applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, 1978. NRC Regulatory Guide 1.33, Quality Assurance Program Requirements (Operation), Appendix A, Typical Procedures for Pressurized Water Reactors and Boiling Water Reactors, Section 3, Procedures for Startup, Operation, and Shutdown of Safety-Related PWR Systems, states, in part, that instructions for energizing, filling, venting, startup and changing modes of operation should be prepared for the Reactor Coolant System. Attachment 3, Placing LT-119, LI-199 and LT-197 In Service, of Fort Calhoun Station Procedure OI-RC-1A, RCS Instrumentation requires the completion of Checklist OI-RC-1A-CL-A. Checklist OI-RC-1A-CL-A indicates that the desired position of RC-122 (loop 1 hot leg drain to waste disposal) is closed. Contrary to the above, on April 12, 2011, in the process of placing reactor coolant system level monitors into service, the licensee failed to properly implement Fort Calhoun Station Procedure OI-RC-1A, RCS Instrumentation and complete Checklist OI-RC-1A-CL-A. Specifically, the licensee opened RC-122, instead

of checking it closed. This resulted in the inadvertent draining of approximately 1,800 gallons of reactor coolant to the reactor coolant drain tank. The licensee has entered this condition into their corrective action program as Condition Report 2011-2890.

Because this finding was of very low safety significance and it was entered into the licensees corrective action program, this violation is being treated as a noncited violation, consistent with Section 2.3.2 of the NRC Enforcement Policy; NCV 05000285/2011005-01, Failure to Follow Procedure Results in a Loss of Reactor Coolant. (EA-11-288)

1R05 Fire Protection

.1 Quarterly Fire Inspection Tours

a. Inspection Scope

The inspectors conducted fire protection walkdowns that were focused on availability, accessibility, and the condition of firefighting equipment in the following risk-significant plant areas:

  • November 28, 2011, Fire Area 32, Compressor Area (Room 19)
  • November 29, 2011, Fire Area 42, Control Room Complex (Rooms 72 - 81)
  • December 19, 2011, Fire Area 34B, Electrical Penetration Area Ground and Intermediate Levels (Room 57)

The inspectors reviewed areas to assess if licensee personnel had implemented a fire protection program that adequately controlled combustibles and ignition sources within the plant; effectively maintained fire detection and suppression capability; maintained passive fire protection features in good material condition; and had implemented adequate compensatory measures for out of service, degraded or inoperable fire protection equipment, systems, or features, in accordance with the licensees fire plan.

The inspectors selected fire areas based on their overall contribution to internal fire risk as documented in the plants Individual Plant Examination of External Events with later additional insights, their potential to affect equipment that could initiate or mitigate a plant transient, or their impact on the plants ability to respond to a security event. Using the documents listed in the attachment, the inspectors verified that fire hoses and extinguishers were in their designated locations and available for immediate use; that fire detectors and sprinklers were unobstructed; that transient material loading was within the analyzed limits; and fire doors, dampers, and penetration seals appeared to be in satisfactory condition. The inspectors also verified that minor issues identified during the inspection were entered into the licensees corrective action program.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of three quarterly fire-protection inspection samples as defined in Inspection Procedure 71111.05-05.

b. Findings

No findings were identified.

.2 Annual Fire Protection Drill Observation

a. Inspection Scope

On October 15, 2011, the inspectors observed a fire brigade activation to combat a fire in the fabrication shop. The observation evaluated the readiness of the plant fire brigade to fight fires. The inspectors verified that the licensee staff identified deficiencies; openly discussed them in a self-critical manner at the drill debrief, and took appropriate corrective actions. Specific attributes evaluated were

(1) proper wearing of turnout gear and self-contained breathing apparatus;
(2) proper use and layout of fire hoses;
(3) employment of appropriate fire fighting techniques;
(4) sufficient firefighting equipment brought to the scene;
(5) effectiveness of fire brigade leader communications, command, and control;
(6) search for victims and propagation of the fire into other plant areas;
(7) smoke removal operations;
(8) utilization of preplanned strategies;
(9) adherence to the preplanned drill scenario; and
(10) drill objectives.

These activities constitute completion of one annual fire-protection inspection sample as defined in Inspection Procedure 71111.05-05.

b. Findings

No findings were identified.

1R06 Flood Protection Measures

a. Inspection Scope

The inspectors reviewed the Updated Safety Analysis Report, the flooding analysis, and plant procedures to assess susceptibilities involving internal flooding; reviewed the corrective action program to determine if licensee personnel identified and corrected flooding problems; inspected underground bunkers/manholes to verify the adequacy of sump pumps, level alarm circuits, cable splices subject to submergence, and drainage for bunkers/manholes; and verified that operator actions for coping with flooding can reasonably achieve the desired outcomes. The inspectors also inspected the areas listed below to verify the adequacy of equipment seals located below the flood line, floor and wall penetration seals, watertight door seals, common drain lines and sumps, sump pumps, level alarms, and control circuits, and temporary or removable flood barriers.

Specific documents reviewed during this inspection are listed in the attachment.

  • December 22, 2011, Safety Injection and Containment Spray Pump Areas, Rooms 21 and 22 These activities constitute completion of one flood protection measures inspection sample as defined in Inspection Procedure 71111.06-05.

b. Findings

No findings were identified.

1R07 Heat Sink Performance

a. Inspection Scope

The inspectors reviewed licensee programs, verified performance against industry standards, and reviewed critical operating parameters and maintenance records for component cooling water heat exchanger AC-1A, shutdown-cooling heat exchanger AC-4B, and the spent fuel pool heat exchanger. The inspectors verified that performance tests were satisfactorily conducted for heat exchangers/heat sinks and reviewed for problems or errors; the licensee utilized the periodic maintenance method outlined in EPRI Report NP 7552, "Heat Exchanger Performance Monitoring Guidelines, the licensee properly utilized biofouling controls; the licensees heat exchanger inspections adequately assessed the state of cleanliness of their tubes; and the heat exchanger was correctly categorized under 10 CFR 50.65, Requirements for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants. Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of three heat sink inspection samples as defined in Inspection Procedure 71111.07-05.

b. Findings

Inadequate Performance Monitoring Test for Component Cooling Water Heat Exchangers

Introduction.

The inspectors identified a Green noncited violation of 10 CFR Part 50, Appendix B, Criterion XI, Test Control, for the failure to perform component cooling water heat exchanger performance monitoring testing in accordance with station procedures. The licensee did not meet prerequisites for assuring that the calculated tube and shell side heat loads were the same and did not use appropriately calibrated flow monitoring instrumentation.

Description.

The inspectors reviewed test results associated with the October 14, 2010, and March 30, 2011, component cooling water AC-1A heat exchanger performance monitoring test. The inspectors noted that the calculated heat loads for each side of the heat exchanger differed by 57 percent in the October 14, 2010 test and 19 percent in the March 30, 2011 test. The calculated heat loads for the two sides of the heat exchanger should have been the same for each respective test.

The licensee monitors performance of the component cooling water heat exchanger in accordance with Procedures SE-PFT-CCW-0001, Component Cooling Water Heat Exchangers Performance Test, and PED-SEI-16, Evaluation of Heat Exchanger Performance. Procedure PED-SEI-16, Revision 9, Step 5.2.1, Section E, states that

the calculated tube and shell side heat loads should be within 15 percent. If the difference between the heat loads is higher, the test conditions are not valid and the test cannot be performed. For both the October 14, 2010, and March 30, 2011, component cooling water AC-1A heat exchanger tests, test data was collected and the evaluation of performance was completed despite the heat loads not agreeing within 15 percent. The inspectors performed an extent of condition review of test data and identified several other instances for other heat exchangers in the component cooling water system for which the calculated heat loads exceeded the 15 percent agreement prerequisite.

The licensee could not provide a technical justification for the use of 15 percent as the acceptance criterion for the heat balance check. Any error between the calculated heat loads should be attributed to the uncertainty in the fluid temperature and flow rate measurements used to determine the heat transfer rates. If the heat loads do not agree to within the expected measurement uncertainty, the disparity could be due to instrument problems, unexpected heat losses from the heat exchanger to ambient surroundings, or bypass flow, in which a portion of the measured flow may not be going through the heat transfer surface. Any such conditions would call into question the validity of the test.

Furthermore, the check of calculated heat loads does not occur until Step 5.2.1, Section E, of Procedure PED-SEI-16, after all data collection is complete. This step would be more appropriately located in the beginning of the data collection procedure.

The heat balance check should be a prerequisite to validate that the licensee is obtaining quality test data. Additionally, the check of calculated heat loads did not require that the 15 percent agreement calculation actually be performed and documented and did not require a signature or peer check.

The inspectors reviewed calibration records for the portable ultrasonic flow meters used in the component cooling water performance monitoring test. The portable ultrasonic flow meters were calibrated over a range of approximately 100 to 500 gallons per minute. The flow rates used in the heat exchanger test range from approximately 1,000 gallons per minute to 4,000 gallons per minute. The flow meters were verified to have a vendor rated capacity of up to 50,000 gallons per minute, but 500 gallons per minute is the calibration limit of the vendor used by the licensee to perform the flow meter calibration. Using flow meters outside of their range of calibration could produce inaccurate measurements. Inaccurate flow indication would then yield errors in the heat balance check.

This issue was entered into the licensees corrective action program as Condition Report 2011-9401. One requested action from Condition Report 2011-9401 was for engineering to evaluate the basis for the 15 percent criterion. The condition report also requested a procedure change to ensure the heat balance check is satisfied before collecting all the test data. The licensees engineering staff performed additional calculations using the most conservative measured heat loads in the most recent tests to demonstrate that the performance of the heat exchangers was still acceptable. The licensee also had an engineering change package in progress to install permanent flow meters for the component cooling heat exchanger performance monitoring test.

Analysis.

The failure to perform testing and evaluation of safety-related heat exchangers in accordance with written procedures was a performance deficiency. This finding is more than minor because it adversely affected the Mitigating Systems Cornerstone objective of equipment performance to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Additionally, the finding is more than minor because if left uncorrected it could lead to a more significant safety concern, as the failure to perform appropriate performance monitoring testing of the component cooling water heat exchangers could reasonably result in an unrecognized condition of a system failing to fulfill its safety-related function. Using Manual Chapter 0609, Attachment 4, "Initial Screening and Characterization of Findings," the finding was determined to be of very low safety significance (Green) because it did not represent a loss of system safety function, nor an actual loss of safety function of a single train, and it did not screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event. The inspectors determined that this finding had a crosscutting aspect in the area of human performance, work practices, because the licensee did not communicate human error prevention techniques, such as self- and peer-checking and proper documentation of activities.

Specifically, the evaluation did not incorporate a requirement that the heat balance check step of the calculation actually be calculated and that step did not require a sign-off or peer-check H.4(a).

Enforcement.

Title 10 CFR Part 50, Appendix B, Criterion XI, requires, in part, that a test program shall be established to assure that all testing required demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures. Test procedures shall include provisions for assuring that all prerequisites for the given test have been met, that adequate test instrumentation is available and used, and that the test is performed under suitable environmental conditions. Contrary to the above, prior to November 16, 2011, the licensee did not perform testing of component cooling water heat exchanger AC-1A in accordance with written test procedures, and did not assure that all prerequisites for performance testing were met and that adequate test instrumentation was used.

Specifically, the calculated heat loads used to demonstrate validity of test conditions did not agree to within the expected uncertainty, and ultrasonic flow meters were not calibrated to the appropriate range of test flow conditions. This issue was entered into the licensees corrective action program as Condition Report 2011-9401. Because this finding was determined to be of very low safety significance and was entered into the licenses corrective action program, this violation is being treated as a noncited violation consistent with Section 2.3.2 of the NRC Enforcement Policy: NCV 05000285/2011005-02 Inadequate Performance Monitoring Test for Component Cooling Water Heat Exchangers.

1R11 Licensed Operator Requalification Program

a. Inspection Scope

On November 10, 2011, the inspectors observed a crew of licensed operators in the plants simulator to verify that operator performance was adequate, evaluators were

identifying and documenting crew performance problems and training was being conducted in accordance with licensee procedures. The inspectors evaluated the following areas:

  • Licensed operator performance
  • Crews clarity and formality of communications
  • Crews ability to take timely actions in the conservative direction
  • Crews prioritization, interpretation, and verification of annunciator alarms
  • Crews correct use and implementation of abnormal and emergency procedures
  • Control board manipulations
  • Oversight and direction from supervisors
  • Crews ability to identify and implement appropriate technical specification actions and emergency plan actions and notifications The inspectors compared the crews performance in these areas to pre-established operator action expectations and successful critical task completion requirements.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one quarterly licensed-operator requalification program sample as defined in Inspection Procedure 71111.11.

b. Findings

No findings were identified.

1R12 Maintenance Effectiveness

a. Inspection Scope

The inspectors evaluated degraded performance issues involving the following risk significant systems:

  • October 11, 2011, VA-64A (Control Room Ventilation Filter)
  • November 11, 2011, CA-1C (Air Compressor C)
  • November 18, 2011, RM-057 (Condenser Evacuation In-Line Gas Radiation Monitor)

The inspectors reviewed events such as where ineffective equipment maintenance has resulted in valid or invalid automatic actuations of engineered safeguards systems and independently verified the licensee's actions to address system performance or condition problems in terms of the following:

  • Implementing appropriate work practices
  • Identifying and addressing common cause failures
  • Characterizing system reliability issues for performance
  • Charging unavailability for performance
  • Trending key parameters for condition monitoring
  • Verifying appropriate performance criteria for structures, systems, and components classified as having an adequate demonstration of performance through preventive maintenance, as described in 10 CFR 50.65(a)(2), or as requiring the establishment of appropriate and adequate goals and corrective actions for systems classified as not having adequate performance, as described in 10 CFR 50.65(a)(1)

The inspectors assessed performance issues with respect to the reliability, availability, and condition monitoring of the system. In addition, the inspectors verified maintenance effectiveness issues were entered into the corrective action program with the appropriate significance characterization. Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of three quarterly maintenance effectiveness samples as defined in Inspection Procedure 71111.12-05.

b. Findings

No findings were identified.

1R13 Maintenance Risk Assessments and Emergent Work Control

a. Inspection Scope

The inspectors reviewed licensee personnel's evaluation and management of plant risk for the maintenance and emergent work activities affecting risk-significant and safety-related equipment listed below to verify that the appropriate risk assessments were performed prior to removing equipment for work:

  • October 25, 2011, risk management actions with HCV-335 (shutdown cooling heat exchangers AC-4A&B inlet header isolation valve) closed
  • October 30, 2011, risk management actions associate with taking diesel generator 2, and buses 1B3C and 1B3C/4C out of service at the same time
  • December 15, 2011, risk associated with drain down for pressurizer heater inspection
  • December 16, 2011, risk associated with pressurizer heater replacement The inspectors selected these activities based on potential risk significance relative to the reactor safety cornerstones. As applicable for each activity, the inspectors verified that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4)and that the assessments were accurate and complete. When licensee personnel performed emergent work, the inspectors verified that the licensee personnel promptly assessed and managed plant risk. The inspectors reviewed the scope of maintenance work, discussed the results of the assessment with the licensee's probabilistic risk analyst or shift technical advisor, and verified plant conditions were consistent with the risk assessment. The inspectors also reviewed the technical specification requirements and inspected portions of redundant safety systems, when applicable, to verify risk analysis assumptions were valid, and applicable requirements were met. Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of four maintenance risk assessments and emergent work control inspection samples as defined in Inspection Procedure 71111.13-05.

b. Findings

No findings were identified.

1R15 Operability Evaluations

a. Inspection Scope

The inspectors reviewed the following issues:

  • November 28, 2011, Operability of HCV-335 (Shutdown Cooling Heat Exchangers AC-4A&B Inlet Header Isolation Valve) following replacement of hand wheel key The inspectors selected these potential operability issues based on the risk significance of the associated components and systems. The inspectors evaluated the technical adequacy of the evaluations to ensure that technical specification operability was properly justified and the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and

design criteria in the appropriate sections of the technical specifications and Updated Safety Analysis Report to the licensee personnels evaluations to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled. The inspectors determined, where appropriate, compliance with bounding limitations associated with the evaluations.

Additionally, the inspectors also reviewed a sampling of corrective action documents to verify that the licensee was identifying and correcting any deficiencies associated with operability evaluations. Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one operability evaluations inspection sample as defined in Inspection Procedure 71111.15-04

b. Findings

No findings were identified.

1R18 Plant Modifications

a. Inspection Scope

To verify that the safety functions of important safety systems were not degraded, the inspectors reviewed the following temporary modifications:

  • November 8, 2011: Temporary modifications associated with taking 480 V bus 1B3B out of service for maintenance, specifically, temporary power for the raw water strainer AC-12A, Loop 2 to Shutdown Cooling Isolation Valve HCV-348, and Diesel Driven Fire Pump FP-1B The inspectors reviewed the temporary modifications and the associated safety-evaluation screening against the system design bases documentation, including the USAR and the technical specifications, and verified that the modification did not adversely affect the system operability/availability. The inspectors also verified that the installation and restoration were consistent with the modification documents and that configuration control was adequate. Additionally, the inspectors verified that the temporary modification was identified on control room drawings, appropriate tags were placed on the affected equipment, and licensee personnel evaluated the combined effects on mitigating systems and the integrity of radiological barriers.

These activities constitute completion of one sample for temporary plant modifications as defined in Inspection Procedure 71111.18-05.

b. Findings

No findings were identified.

1R19 Postmaintenance Testing

a. Inspection Scope

The inspectors reviewed the following postmaintenance activities to verify that procedures and test activities were adequate to ensure system operability and functional capability:

  • November 14, 2011, postmaintenance testing of diesel generator 2 following an 18-month overhaul The inspectors selected these activities based upon the structure, system, or component's ability to affect risk. The inspectors evaluated these activities for the following (as applicable):
  • The effect of testing on the plant had been adequately addressed; testing was adequate for the maintenance performed
  • Acceptance criteria were clear and demonstrated operational readiness; test instrumentation was appropriate The inspectors evaluated the activities against the technical specifications, the Updated Safety Analysis Report, 10 CFR Part 50 requirements, licensee procedures, and various NRC generic communications to ensure that the test results adequately ensured that the equipment met the licensing basis and design requirements. In addition, the inspectors reviewed corrective action documents associated with postmaintenance tests to determine whether the licensee was identifying problems and entering them in the corrective action program and that the problems were being corrected commensurate with their importance to safety. Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one postmaintenance testing inspection sample as defined in Inspection Procedure 71111.19-05.

b. Findings

No findings were identified.

1R22 Surveillance Testing

a. Inspection Scope

The inspectors reviewed the Update Safety Analysis Report, procedure requirements, and technical specifications to ensure that the surveillance activities listed below demonstrated that the systems, structures, and/or components tested were capable of performing their intended safety functions. The inspectors either witnessed or reviewed test data to verify that the significant surveillance test attributes were adequate to address the following:

  • Preconditioning
  • Evaluation of testing impact on the plant
  • Acceptance criteria
  • Test equipment
  • Procedures
  • Jumper/lifted lead controls
  • Test data
  • Testing frequency and method demonstrated technical specification operability
  • Test equipment removal
  • Restoration of plant systems
  • Fulfillment of ASME Code requirements
  • Updating of performance indicator data
  • Engineering evaluations, root causes, and bases for returning tested systems, structures, and components not meeting the test acceptance criteria were correct
  • Reference setting data
  • Annunciators and alarms setpoints The inspectors also verified that licensee personnel identified and implemented any needed corrective actions associated with the surveillance testing.
  • October 17, 2011, OP-ST-RW-3004, Raw Water System Category C Valve Inservice Test
  • October 25, 2011, EM-ST-ESF-0002, 13.8 KV Emergency Power Periodic Test Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of two surveillance testing inspection samples as defined in Inspection Procedure 71111.22-05.

b. Findings

No findings were identified.

1EP6 Drill Evaluation

Cornerstone: Emergency Preparedness

.1 Training Observations

a. Inspection Scope

The inspectors observed a simulator training evolution for licensed operators on November 10, 2011, which required emergency plan implementation by a licensee operations crew. This evolution was planned to be evaluated and included in performance indicator data regarding drill and exercise performance. The inspectors observed event classification and notification activities performed by the crew. The inspectors also attended the post-evolution critique for the scenario. The focus of the inspectors activities was to note any weaknesses and deficiencies in the crews performance and ensure that the licensee evaluators noted the same issues and entered them into the corrective action program. As part of the inspection, the inspectors reviewed the scenario package and other documents listed in the attachment.

These activities constitute completion of one sample as defined in Inspection Procedure 71114.06-05.

b. Findings

No findings were identified.

RADIATION SAFETY

Cornerstone: Occupational and Public Radiation Safety

2RS0 4 Occupational Dose Assessment

a. Inspection Scope

This area was inspected to:

(1) determine the accuracy and operability of personal monitoring equipment;
(2) determine the accuracy and effectiveness of the licensees methods for determining total effective dose equivalent; and
(3) ensure occupational dose is appropriately monitored. The inspectors used the requirements in 10 CFR Part 20, the technical specifications, and the licensees procedures required by technical specifications as criteria for determining compliance. During the inspection, the inspectors interviewed licensee personnel, performed walkdowns of various portions of the plant, and reviewed the following items:
  • External dosimetry accreditation, storage, issue, use, and processing of active and passive dosimeters
  • The technical competency and adequacy of the licensees internal dosimetry program
  • Adequacy of the dosimetry program for special dosimetry situations such as declared pregnant workers, multiple dosimetry placement, and neutron dose assessment
  • Audits, self-assessments, and corrective action documents related to dose assessment since the last inspection Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of the one required sample as defined in Inspection Procedure 71124.04-05.

b. Findings

Introduction.

Inspectors reviewed a self-revealing, noncited violation of Technical Specification 5.8.1 for failure to follow Radiation Work Permit 11-2520 and procedures, which required workers to comply with radiological work practices. Specifically, workers changed the work scope approved on the low-pressure safety injection shutdown cooling bypass valve FCV-326 without notifying radiation protection and receiving a re-evaluation of the radiological conditions as required by the radiation work permit.

Description.

On May 2, 2011, two workers were briefed by radiation protection for radiological conditions associated with reassembly of the low-pressure safety injection bypass valve FCV-326. Using the latest radiological surveys, as required by procedure, radiation protection staff briefed the workers that the radiation conditions around valve FCV-326 had contamination levels as high as 450,000 disintegrations/100 centimeters squared. The workers were being briefed to perform valve maintenance work in a high radiation area and Radiation Work Permit 11-2520. In accordance with the pre-job briefing, the authorized work scope was only to reassemble the valve, this was non-abrasive work. Yet, the workers used abrasive pads during the course of the valve reassembly, which was unknown to radiation protection. When the two workers exited the radiologically controlled area, they both alarmed the personal contamination monitors. One of the workers had approximately 30,000 disintegrations/100 centimeters squared on his clothing. Both workers were decontaminated. It was determined that the workers had not informed radiation protection personnel that they had changed the work scope in the area by using abrasive pads as required by Radiation Work Permit 11-2520.

This additional valve rework was not previously approved during radiation protections briefing. The licensees corrective action was to counsel the workers on the importance of adhering to the stated work scope and radiation work permit instructions.

Analysis.

The failure to follow the requirements of the radiation work permit as instructed by radiation protection, about the radiation work permit, was a performance deficiency. The finding was more than minor because it was associated with the Occupational Radiation Safety Cornerstone attribute of program and process and affected the cornerstone objective of ensuring adequate protection of worker health and safety from exposure to radiation during routine operations. Using the Occupational Radiation Safety Significance Determination Process, the inspectors determined the finding to have very low safety significance because:

(1) it was not associated with ALARA planning or work controls,
(2) there was no overexposure,
(3) there was no substantial potential for an overexposure, and
(4) the ability to assess dose was not compromised. The finding was determined to have a human performance crosscutting aspect associated with work practices, because the licensee failed to ensure supervisory and management oversight of work activities, including contractors, such that nuclear safety is supported H.4(c).
Enforcement.

Technical Specification 5.8.1 states that written procedures shall be established, implemented and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Quality Assurance Program Requirements, Revision 2, Appendix A, 1978; Section 7(e)(1) of Appendix A of Regulatory Guide 1.33 lists radiation protection procedures for the control of radioactivity, and limiting personnel exposure, including a radiation work permit system. Radiation Protection Plan, Revision 24, Section 2.3.11, states that station personnel are responsible for complying with the requirements in Procedure SO-G-101, Radiation Worker Practices, Revision 33. Procedure SO-G-101, Sections 4.3.2 and 5.4.4, requires that personnel adhere to the requirements listed on the radiation work permit they are using and comply with radiological work practices as established by the radiation protection department. Radiation Work Permit 11-2520 requires workers to contact radiation protection personnel for re-evaluation of radiological conditions if the work scope is changed. Contrary to the above, on May 2, 2011, two workers did not contact radiation protection personnel for a re-evaluation of radiological conditions when they changed the work scope on valve FCV-326 from reassembly to rework using abrasive pads.

Consequently, these two individuals were found contaminated when they alarmed the personal contamination monitors. Because this violation is of very low safety significance and was entered into the licensees corrective action program as Condition Reports 2011-3944, 2011-3946, and 2011-9795, this violation is being treated as a noncited violation, consistent with Section 2.3.2 of the NRC Enforcement Policy:

NCV 05000285/2011005-03; Failure to Follow Radiation Work Permit Instructions.

2RS0 5 Radiation Monitoring Instrumentation

a. Inspection Scope

This area was inspected to verify the licensee is assuring the accuracy and operability of radiation monitoring instruments that are used to:

(1) monitor areas, materials, and workers to ensure a radiologically safe work environment; and
(2) detect and quantify radioactive process streams and effluent releases. The inspectors used the requirements in 10 CFR Part 20, the technical specifications, and the licensees

procedures required by technical specifications as criteria for determining compliance.

During the inspection, the inspectors interviewed licensee personnel, performed walkdowns of various portions of the plant, and reviewed the following items:

  • Selected plant configurations and alignments of process, post-accident, and effluent monitors with descriptions in the Updated Safety Analysis Report and the offsite dose calculation manual
  • Select instrumentation, including effluent monitoring instrument, portable survey instruments, area radiation monitors, continuous air monitors, personnel contamination monitors, portal monitors, and small article monitors to examine their configurations and source checks
  • Calibration and testing of process and effluent monitors, laboratory instrumentation, whole body counters, post-accident monitoring instrumentation, portal monitors, personnel contamination monitors, small article monitors, portable survey instruments, area radiation monitors, electronic dosimetry, air samplers, continuous air monitors
  • Audits, self-assessments, and corrective action documents related to radiation monitoring instrumentation since the last inspection Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of the one required sample as defined in Inspection Procedure 71124.05-05.

b. Findings

No findings were identified.

OTHER ACTIVITIES

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Physical Protection

4OA1 Performance Indicator Verification

)

.1 Data Submission Issue

a. Inspection Scope

The inspectors performed a review of the performance indicator data submitted by the licensee for the third Quarter 2011 performance indicators for any obvious inconsistencies prior to its public release in accordance with Inspection Manual Chapter 0608, Performance Indicator Program.

This review was performed as part of the inspectors normal plant status activities and, as such, did not constitute a separate inspection sample.

b. Findings

No findings were identified.

.2 Mitigating Systems Performance Index - Heat Removal System (MS08)

a. Inspection Scope

The inspectors sampled licensee submittals for the mitigating systems performance index - heat removal system performance indicator for the period from the fourth quarter 2010 through the third quarter 2011. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6. The inspectors reviewed the licensees operator narrative logs, issue reports, event reports, mitigating systems performance index derivation reports, and NRC integrated inspection reports for the period of October 1, 2010 through September 20, 2011 to validate the accuracy of the submittals.

The inspectors reviewed the mitigating systems performance index component risk co-efficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensees issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in the attachment to this report.

These activities constitute completion of one mitigating systems performance index heat removal system sample as defined in Inspection Procedure 71151-05.

b. Findings

No findings were identified.

.3 Mitigating Systems Performance Index - Residual Heat Removal System (MS09)

a. Inspection Scope

The inspectors sampled licensee submittals for the mitigating systems performance index - residual heat removal system performance indicator for the period from the fourth quarter 2010 through the third quarter 2011. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6. The inspectors reviewed the licensees operator narrative logs, issue reports, event reports, mitigating systems performance index derivation reports, and NRC integrated inspection reports for the period of October 1, 2010 through September 20, 2011 to validate the accuracy of the submittals.

The inspectors reviewed the mitigating systems performance index component risk co-efficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensees issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in the attachment to this report.

These activities constitute completion of one mitigating systems performance index residual heat removal system sample as defined in Inspection Procedure 71151-05.

b. Findings

No findings were identified.

.4 Mitigating Systems Performance Index - Cooling Water Systems (MS10)

a. Inspection Scope

The inspectors sampled licensee submittals for the mitigating systems performance index - cooling water systems performance indicator for the period from the fourth quarter 2010 through the third quarter 2011. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6. The inspectors reviewed the licensees operator narrative logs, issue reports, event reports, mitigating systems performance index derivation reports, and NRC integrated inspection reports for the period of October 1, 2010 through September 20, 2011 to validate the accuracy of the submittals.

The inspectors reviewed the mitigating systems performance index component risk coefficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensees issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in the attachment to this report.

These activities constitute completion of one mitigating systems performance index cooling water system sample as defined in Inspection Procedure 71151-05.

b. Findings

No findings were identified.

.5 Drill/Exercise Performance (EP01)

a. Inspection Scope

The inspectors sampled licensee submittals for the Drill and Exercise Performance, performance indicator for the period from April 2010 through September 2011. To determine the accuracy of the performance indicator data reported during those periods, performance indicator definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revisions 5 and 6, were used. The inspectors reviewed the licensees records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the Nuclear Energy Institute guidance. Specifically, the inspectors reviewed licensee records and processes including procedural guidance on assessing opportunities for the performance indicator; assessments of performance indicator opportunities during predesignated control room simulator training sessions, and performance during other drills. The specific documents reviewed are described in the attachment to this report.

These activities constitute completion of one sample of the drill/exercise performance as defined in Inspection Procedure 71151-05.

b. Findings

Introduction.

A noncited violation was identified by the NRC for the failure of the licensees guidelines for the choice of protective actions during an emergency to implement federal guidance as required by 10 CFR 50.47(b)(10).

Description.

The NRC identified the failure of the licensees guidelines for the choice of protective actions during an emergency to implement federal guidance as a performance deficiency. Specifically, the licensee did not implement Regulatory Information Summary 2003-012, Clarification of NRC Guidance for Modifying Protective Actions, dated June 24, 2003, which states, in part, Licensees should not change a PAR until the threat is fully under control.

The licensee conducted an emergency preparedness drill on August 16, 2011. The inspectors reviewed notifications simulated to be made to offsite authorities at 10:48 a.m. and 12:06 p.m. on August 16, 2011, as recorded on Form FC-1188, Fort Calhoun Station - Emergency Notification Form, Revision 26. The inspectors reviewed dose assessment reports generated on August 16, 2011, at 10:34 a.m., 10:38 a.m.,

10:49 a.m., 10:58 a.m., 11:22 a.m., and 12:03 p.m., respectively, as documented on the licensee Update Report to Offsite Authorities, generated using Eagle Version 6.0. The inspectors also reviewed Procedure EOF-7, Protective Action Guidelines, Revision 21.

The licensee transmitted a simulated protective action recommendation to offsite authorities at 10:48 a.m. of evacuate 0-2 miles in all sectors, evacuate 2-5 miles in sectors DEF (D, E, and F), and to take no action between 5-10 miles. The licensee transmitted a simulated protective action recommendation (PAR) to offsite authorities at 12:06 p.m. of evacuate 0-2 miles in all sectors and to take no action between 2-10 miles.

The inspectors determined that protective action guides were exceeded at the site boundary on dose assessments performed at 11:21 a.m. and 12:03 p.m., and that protective action guides were not exceeded at 2 miles on any dose assessment report.

The licensee recommendation at 12:06 p.m. was based on a change in wind direction from 271 degrees to 301 degrees. The 12:06 p.m. notification deleted the previous recommendation to evacuate between 2-5 miles in sectors DEF (D, E, and F), because no protective action guide thresholds were currently exceeded at 2 miles.

The inspectors reviewed the guidance of Regulatory Information Summary 2003-012, Clarification of NRC Guidance for Modifying Protective Actions, dated June 24, 2003, which states, in part, Licensees should not change a PAR [protective action recommendation] until the threat is fully under control. The inspectors concluded that the licensee should not have deleted the recommendation to evacuate 2-5 miles in sectors DEF (D, E, and F) after it was transmitted at 10:48 p.m. because recommendations not to evacuate an area following a previous evacuation recommendation can be confusing to both offsite governmental authorities and to the public. Attempting to rescind an existing evacuation recommendation can impact the licensees ability to adequately implement protective measures for the public.

Analysis.

The inspectors determined the licensees failure to have guidelines for the choice of protective actions during an emergency that implement federal guidance is a performance deficiency within the licensees control. This finding is more than minor because it had a credible impact on safety and affected the Emergency Preparedness Cornerstone attributes of emergency response organization performance and procedure quality. The finding had a credible impact on the cornerstone objective because rescinding an existing protective action recommendation can confuse offsite governmental authorities and the public, and affects the implementation of adequate measures to protect the health and safety of the public. The finding was associated with a violation of NRC requirements. This finding was evaluated using the Emergency Preparedness Significance Determination Process and was determined to be of very low safety significance because it was a failure to comply with NRC requirements, was associated with a risk significant planning standard as defined by Inspection Manual Chapter 0609, Appendix B, and was not a functional failure or degraded planning standard function. The finding was not a degraded planning standard function because the licensees process was capable of producing correct protective action recommendations. This finding has been entered into the licensees corrective action program as Condition Report 2011-8530.

Enforcement.

Title 10 of the Code of Federal Regulations, Part 50.47(b)(10) states, in part, A range of protective actions has been developed for the plume exposure pathway guidelines for the choice of protective actions during an emergency, consistent with federal guidance, are developed and in place. Contrary to the above, the licensee did not develop and put into place guidelines for the choice of protective actions during an emergency that were consistent with federal guidance licensee. Specifically, Procedure EOF-7, Protective Action Guidelines, Revision 21, did not prohibit revising existing protective actions recommendations for evacuation of the public in accordance with the guidance of Regulatory Information Summary 2003-012.

NCV 05000285/2011-0005-04, Inadequate licensee procedure for making protective action recommendations.

.6 Emergency Response Organization Drill Participation (EP02)

a. Inspection Scope

The inspectors sampled licensee submittals for the Emergency Response Organization Drill Participation performance indicator for the period from April 2010 through September 2011. To determine the accuracy of the performance indicator data reported during those periods, performance indicator definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 5, was used. The inspectors reviewed the licensees records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the Nuclear Energy Institute guidance. Specifically, the inspectors reviewed licensee records and processes including procedural guidance on assessing opportunities for the performance indicator, rosters of personnel assigned to key emergency response organization positions, and exercise participation records. The specific documents reviewed are described in the attachment to this report.

These activities constitute completion of one sample of the emergency response organization drill participation as defined in Inspection Procedure 71151-05.

b. Findings

No findings were identified.

.7 Alert and Notification System (EP03)

a. Inspection Scope

The inspectors sampled licensee submittals for the Alert and Notification System performance indicator for the period from April 2010 through September 2011. To determine the accuracy of the performance indicator data reported during those periods, performance indicator definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 5, was used. The inspectors reviewed the licensees records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the Nuclear Energy Institute guidance.

Specifically, the inspectors reviewed licensee records and processes including procedural guidance on assessing opportunities for the performance indicator and the results of periodic alert notification system operability tests. The specific documents reviewed are described in the attachment to this report.

These activities constitute completion of one sample of the alert and notification system as defined in Inspection Procedure 71151-05.

b. Findings

No findings were identified.

4OA2 Identification and Resolution of Problems

.1 Routine Review of Identification and Resolution of Problems

a. Inspection Scope

As part of the various baseline inspection procedures discussed in previous sections of this report, the inspectors routinely reviewed issues during baseline inspection activities and plant status reviews to verify that they were being entered into the licensees corrective action program at an appropriate threshold, that adequate attention was being given to timely corrective actions, and that adverse trends were identified and addressed. The inspectors reviewed attributes that included the complete and accurate identification of the problem; the timely correction, commensurate with the safety significance; the evaluation and disposition of performance issues, generic implications, common causes, contributing factors, root causes, extent of condition reviews, and previous occurrences reviews; and the classification, prioritization, focus, and timeliness of corrective actions. Minor issues entered into the licensees corrective action program because of the inspectors observations are included in the attached list of documents reviewed.

These routine reviews for the identification and resolution of problems did not constitute any additional inspection samples. Instead, by procedure, they were considered an integral part of the inspections performed during the quarter and documented in Section 1 of this report.

b. Findings

No findings were identified.

.2 Daily Corrective Action Program Reviews

a. Inspection Scope

In order to assist with the identification of repetitive equipment failures and specific human performance issues for follow-up, the inspectors performed a daily screening of items entered into the licensees corrective action program. The inspectors accomplished this through review of the stations daily corrective action documents.

The inspectors performed these daily reviews as part of their daily plant status monitoring activities and, as such, did not constitute any separate inspection samples.

b. Findings

No findings were identified.

.3 Semi-Annual Trend Review

a. Inspection Scope

The inspectors performed a review of the licensees corrective action program and associated documents to identify trends that could indicate the existence of a more significant safety issue. The inspectors focused their review on repetitive equipment issues, but also considered the results of daily corrective action item screening discussed in Section 4OA2.2, above, licensee trending efforts, and licensee human performance results. The inspectors nominally considered the 6-month period of June 1, 2011, through November 30, 2011 although some examples expanded beyond those dates where the scope of the trend warranted.

The inspectors also included issues documented outside the normal corrective action program in major equipment problem lists, repetitive and/or rework maintenance lists, departmental problem/challenges lists, system health reports, quality assurance audit/surveillance reports, self-assessment reports, and Maintenance Rule assessments.

The inspectors compared and contrasted their results with the results contained in the licensees corrective action program trending reports. Corrective actions associated with a sample of the issues identified in the licensees trending reports were reviewed for adequacy.

These activities constitute completion of one single semi-annual trend inspection sample as defined in Inspection Procedure 71152-05.

b. Findings

No findings were identified.

4OA3 Event Follow-up

.1 (Open) Licensee Event Report 05000285/2011-003-03: Inadequate Flooding Protection

Due To Ineffective Oversight During identification and evaluation of flood barriers, unsealed through wall penetrations in the outside wall of the intake, auxiliary and chemistry and radiation protection buildings were identified that are below the licensing basis flood elevation. Additionally a potential flooding issue was identified on the inside of the intake structure. Holes were noted in the floor at the 10076 level, which is the ceiling of the raw water vault.

A summary of the root causes included: a weak procedure revision process; insufficient oversight of work activities associated with external flood matters; ineffective identification, evaluation and resolution of performance deficiencies related to external flooding; and safe as is mindsets relative to external flooding events.

The penetrations were temporarily sealed and a configuration change was developed and implemented whereby permanent seals were installed. A one-foot sandbag berm

was placed around the holes. Comprehensive corrective actions to address the root and contributing causes are being addressed through the corrective action program.

.2 (Open) Licensee Event Report 05000285/2011-008-01: Fire in Safety Related 480 Volt

Electrical Bus On June 7, 2011, at approximately 9:30 a.m. Central Daylight Time, a failure of a safety related 480-volt AC (V) load center supply breaker in the switchgear room occurred (Bus 1B4A). Fire alarms were received in the control room and the Halon system that protects the switchgear rooms discharged. The fire brigade responded and found the room filled with smoke, but no active fire. At 9:40 a.m., Central Daylight Time an Alert was declared for a fire affecting the operability of plant safety systems required to establish or maintain safe shutdown. At 1:13 p.m. Central Daylight Time on June 7, 2011, Fort Calhoun Station exited the Alert after confirming that the fire was extinguished and the area was ventilated to restore access. Shutdown cooling remained in-service during the event.

Fort Calhoun Station was also in an emergency classification of a Notification of Unusual Event (NOUE) due to high Missouri River levels.

The root cause of the event was the Fort Calhoun Station design process failed to identify the silver plating of bus bar material as a critical interface when specifying replacements for the original circuit breakers. The design process failure extended to other safety-related 480v load center circuit breakers as well.

Corrective actions included replacing 480v bus 1B4A and performing bus maintenance.

Affected circuit breaker cradles will be realigned to ensure proper fit in the bus cubicles.

Maintenance procedures are being revised to enhance maintenance practices.

.3 (Closed) Licensee Event Report 05000285/2011-003-01: Inadequate Flooding

Protection Due To Ineffective Oversight During identification and evaluation of flood barriers, unsealed through wall penetrations in the outside wall of the intake, auxiliary and chemistry and radiation protection buildings were identified that were below the licensing basis flood elevation.

A summary of the root causes included: a weak procedure revision process; insufficient oversight of work activities associated with external flood matters; ineffective identification, evaluation and resolution of performance deficiencies related to external flooding; and safe as is mindsets relative to external flooding events.

The penetrations were temporarily sealed and a configuration change was developed and implemented whereby permanent seals were installed. Comprehensive corrective actions to address the root and contributing causes are being addressed through the corrective action program.

The licensee event report is closed. Revision 3 of this licensee event report was submitted on December 17, 2011.

.4 (Closed) Licensee Event Report 05000285/2011-008-00: Fire in Safety Related 480 Volt

Electrical Bus On June 7, 2011, at approximately 9:30 a.m. Central Daylight Time, a failure of a safety related 480-volt ac (Vac) load center supply breaker in the switchgear room occurred (Bus 1B4A). Fire alarms were received in the control room and the Halon System that protects the switchgear rooms discharged. The fire brigade responded and found the room filled with smoke, but no active fire. At 9:40 a.m., Central Daylight Time an alert was declared for a fire affecting the operability of plant safety systems required to establish or maintain safe shutdown. At 1:13 p.m. Central Daylight Time on June 7, 2011, Fort Calhoun Station exited the alert after confirming that the fire was extinguished and the area was ventilated to restore access.

Shutdown cooling remained in-service during the event. Fort Calhoun Station was also in an emergency classification of a Notification of Unusual Event (NOUE) due to high Missouri River level.

A root cause analysis is in progress. The results of the analysis and corrective actions were reported in Revision 1 of this licensee event report (2011-008-01).

The licensee event report is closed. Revision 1 of this licensee event report was submitted on October 27, 2011.

4OA6 Meetings

Exit Meeting Summary

On October 20, 2011, the inspectors presented results of the onsite inspection of the emergency preparedness performance indicators to Mr. D. Bannister, Vice President and Chief Nuclear Officer, and other members of the licensees staff. The licensee acknowledged the issues presented. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.

On November 18, 2011, the inspectors presented the inspection results of the heat sink performance inspection to Mr. J. Goodell, Division Manager, Nuclear Performance Improvement and Support, and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.

On December 2, 2011, the inspectors presented the results of the radiation safety inspections to Mr. D. Bannister, Vice President and Chief Nuclear Officer, and other members of the licensee staff. The licensee acknowledged the issues presented. The

inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.

On January 9, 2012, the inspectors presented the quarterly inspection results to Mr. J.

Goodell, Division Manager, Nuclear Performance Improvement and Support, and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.

4OA7 Licensee-Identified Violations

The following violation of very low safety significance (Green) was identified by the licensee and is a violation of NRC requirements, which meet the criteria of Section VI of the NRC Enforcement Policy, NUREG-1600, for being dispositioned as a noncited violation.

  • The inspectors reviewed a licensee-identified, noncited violation of Technical Specification 5.8.1 for failure to follow Radiation Work Permit 11-3530, Task-3, which required workers to wear respiratory protection equipment in the lower cavity. On April 19, 2011, an individual working on the upender in the lower cavity had positive radioactivity results from his lapel air sample. The licensee investigated, performed a dose assessment, and assigned a dose from the lapel air sample of 39 mrem to the worker. The licensee found that the worker did not use respiratory protection equipment as required by the radiation work permit.

Technical Specification 5.8.1 requires that written procedures shall be established, implemented and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Quality Assurance Program Requirements, Revision 2, Appendix A, 1978. Section 7(e)(1) lists radiation protection procedures for the control of radioactivity and limiting personnel exposure, including a radiation work permit system. Radiation Protection Plan, Revision 24, Section 2.3.11, states that station personnel are responsible for complying with the requirements in Procedure SO-G-101, Radiation Worker Practices, Revision 33. Procedure SO-G-101, Sections 4.3.2 and 5.4.4 requires that personnel adhere to the requirements listed on the radiation work permit they are using. Radiation Work Permit 11-3530, Task-3, required workers to wear specified respiratory protection equipment while in the lower cavity.

Contrary to the above, on April 19, 2011, an individual working on the upender in the lower cavity was determined to be contaminated, and it was determined that the worker did not wear the specified NIOSH approved respiratory protection equipment required by the radiation work permit. Using the Occupational Radiation Safety Significance Determination Process, the inspector determined the finding to have very low safety significance because:

(1) it was not associated with ALARA planning or work controls,
(2) there was no overexposure,
(3) there was no substantial potential for an overexposure, and
(4) the ability to assess does was not compromised. This issue was entered into the licensees corrective action program as Condition Reports 2011-3323 and 2011-9794.

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

R. Acker, Licensing Engineer
D. Bannister, Vice President and Chief Nuclear Officer
S. Baughn, Manager, Nuclear Licensing
A. Berck, Supervisor, Emergency Planning
B. Blome, Manager, Quality
C. Cameron, Supervisor Regulatory Compliance
M. Cooper, Licensing Engineer
M. Frans, Manager, Engineering Programs
S. Gebers, Manager, Emergency Planning and Health Physics
J. Goodell, Division Manager, Nuclear Performance Improvement and Support
P. Gunderson, Supervisor, Radiation Protection
J. Herman, Division Manager, Nuclear Engineering
R. Hodgson, Manager, Work Management
T. Jameson, Supervisor, Radiation Protection
A. Lollis, Supervisor, ALARA
K. Maassen, Program Engineer
T. Maine, Manager, Radiation Protection
E. Matzke, Senior Licensing Engineer
T. Nellenbach, Division Manager, Plant Operations
A. Pallas, Manager Shift Operations

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

OPENED

05000285/2011-003-03 LER Inadequate Flooding Protection Due To Ineffective Oversight (Section 4OA3)
05000285/2011-008-01 LER Fire in Safety Related 480 Volt Electrical Bus (Section 4OA3)

CLOSED

05000285/2011-003-01 LER Inadequate Flooding Protection Due To Ineffective Oversight (Section 4OA3)
05000285/2011-008-00 LER Fire in Safety Related 480 Volt Electrical Bus (Section 4OA3)

OPENED AND CLOSED

05000285/2011005-01 NCV Failure to Follow Procedure Results in a Loss of Reactor Coolant (Section 1R04)

Attachment

OPENED AND CLOSED

05000285/2011005-02 NCV Inadequate Performance Monitoring Test for Component Cooling Water Heat Exchangers (Section 1R07)
05000285/2011005-03 NCV Failure to Follow Radiation Work Permit Instructions (Section 2RS04)
05000285/2011005-04 NCV Inadequate Licensee Procedure for Making Protective Action Recommendations (Section 4OA1)

LIST OF DOCUMENTS REVIEWED