Annual Assessment Letter - Fort Calhoun Station (Report 05000285/2005001)
ML050610289
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 03/02/2005
From: Howell A
NRC/RGN-IV/DRP
To: Ridenoure R
Omaha Public Power District
References
IR-05-001
Download: ML050610289 (8)


Text

March 2, 2005

SUBJECT:

ANNUAL ASSESSMENT LETTER - FORT CALHOUN STATION (REPORT 05000285/2005001)

Dear Mr. Ridenoure:

On February 2, 2005, the NRC staff completed its end-of-cycle plant performance assessment of the Fort Calhoun Station. The end-of-cycle review for the Fort Calhoun Station involved the participation of the reactor technical divisions in evaluating performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2004. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections that may conflict with your plant activities.

This performance review and enclosed inspection plan do not include physical protection information. A separate end-of-cycle performance review letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan.

Overall, the Fort Calhoun Station operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter and the third quarter was within the Regulatory Response Column of the NRCs Action Matrix based on a White PI for Emergency AC Power System Unavailability (Mitigating Systems Cornerstone).

Diesel Generator 2 was unavailable for about 28 days because of an undetected fuse failure.

This fuse failure resulted in Diesel Generator 2 failing to reach rated voltage during testing on August 18, 2004. Analysis of the failure determined the fuse that caused the failure had actually failed during testing on July 21, 2004.

We plan to conduct a supplemental inspection in accordance with NRC Inspection Procedure 95001, Inspection for One or Two White Inputs in a Strategic Performance Area, to review the actions taken in response to this White PI. The purpose of this supplemental inspection will be to provide assurance that the root and contributing causes for the White PI are understood, to provide assurance that the extent of condition and extent of cause are identified, and to provide assurance that the corrective actions are sufficient to address the root and

Omaha Public Power District

- 2 -

contributing causes and prevent their recurrence. In addition, the risk significance of the Diesel Generator 2 condition is still under review as part of the Significance Determination Process.

Plant performance during the first two quarters of the assessment cycle was within the Licensee Response Column of the NRCs Action Matrix based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green).

The enclosed inspection plan details the inspections, less those related to physical protection scheduled through September 30, 2006. In addition to the baseline inspection program, Temporary Instruction 2515/150, Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-02), Temporary Instruction 2515/160, Pressurizer Penetration Nozzles and Steam Space Piping Connections (NRC Bulletin 2004-01), and inspections related to Steam Generator Replacement (Procedure 50001), Pressurizer Replacement (Procedure in draft) and Reactor Vessel Head Replacement (Procedure 71001) will be performed at Fort Calhoun Station during this inspection cycle. The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the midcycle review meeting.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Mr. Michael Hay at (817) 860-8144 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Arthur T. Howell III, Director Division of Reactor Projects Docket: 50-285 License: DPR-40 Enclosure:

Fort Calhoun Station Inspection/Activity Plan

Omaha Public Power District

- 3 -

cc w/enclosure:

John B. Herman, Manager Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550 Fort Calhoun, NE 68023-0550 David J. Bannister Manager - Fort Calhoun Station Omaha Public Power District Fort Calhoun Station FC-1-1 Plant P.O. Box 550 Fort Calhoun, NE 68023-0550 James R. Curtiss Winston & Strawn 1400 L. Street, N.W.

Washington, DC 20005-3502 Chairman Washington County Board of Supervisors P.O. Box 466 Blair, NE 68008 Sue Semerena, Section Administrator Nebraska Health and Human Services System Division of Public Health Assurance Consumer Services Section 301 Centennial Mall, South P.O. Box 95007 Lincoln, NE 68509-5007 Daniel K. McGhee Bureau of Radiological Health Iowa Department of Public Health 401 SW 7th Street, Suite D Des Moines, IA 50309 Timothy F. Dunning, Sheriff Douglas County 3601 N. 156th Street Omaha, NE 68116 Carol McBride Pirsch, Chairperson Douglas County Board of Commissioners Civic Center 1819 Farnam LC2 Omaha, NE 68183 Steve Lee, Director Douglas County Emergency Management Agency Civic Center, EOC, Room 114 1819 Farnam Street Omaha, NE 68183 Todd Baber Emergency Management Agency Harrison County 111 South 1st Avenue Logan, IA 51546-1305 Terry Baxter, Sheriff Harrison County 111 South 1st Avenue Logan, IA 51546 Rolland Roberts, Chairman Harrison County Board of Supervsiors 111 North 2nd Avenue Logan, IA 51546 The Honorable Doris Stillwell Mayor of Missouri Valley City Hall 223 E. Erie Missouri Valley, IA 51555 Terry Hummel, Coordinator Pottawattamie County Emergency Management Coordinator 227 S. 6th Street, Court House Council Bluffs, IA 51501

Omaha Public Power District

- 4 -

Delbert King, Chairman Pottawattamie County Board of Supervisors 227 South 6th Street Council Bluffs, IA 51501 Mike Robinson, Sheriff Washington County Courthouse 1535 Culfax Blair, NE 68008 John Shotwell, President Blair City Council 218 S. 16th Street Blair, NE 68008 The Honorable Jim Realph Mayor of Blair 218 South 16th Street Blair, NE 68008 The Honorable Paul Oestmann Mayor of Fort Calhoun P.O. Box 394 Fort Calhoun, NE 68023 David Genoways, President Fort Calhoun City Council P.O. Box 577 Fort Calhoun, NE 68023 Bill Pook, Director Region 5/6 Emergency Management 435 N. Park Avenue, Suite 400 Fremont, NE 68025 Dick Hainje, Regional Director Federal Emergency Management Agency Region VII 2323 Grand Blvd., Suite 900 Kansas City, MO 64108-2670 Dianne Munns, Chairperson Department of Commerce Utilities Division Iowa Utilities Board 350 Maple Street Des Moines, IA 50319-0069 Donald A. Flater, Chief Bureau of Environmental Health Iowa Department of Public Health 401 SW 7th, Suite D Des Moines, IA 50309 Robert Leopold, Administrator Nebraska Health and Human Services Division of Public Health Assurance Department of Regulation and Licensure 301 Centennial Mall, South P.O. Box 95007 Lincoln, NE 68509-5007 John Blackhawk Tribal Chairman Winnebago Tribe of Nebraska P.O. Box 687 Winnebago, NE 68071-0687 Donald Grant Tribal Chairperson Omaha Tribal Council P.O. Box 368 Macy, NE 68039-0368 Al Berndt, Assistant Director Nebraska Emergency Management Agency 1300 Military Road Lincoln, NE 68508-1090 Institute of Nuclear Power Operations (INPO)

Records Center 700 Galleria Parkway SE, Suite 100 Atlanta, GA 30339

Omaha Public Power District

- 5 -

Omaha Public Power District

- 6 -

Electronic distribution by RIV:

Regional Administrator (BSM1)

DRP Director (ATH)

DRS Director (DDC)

DRS Deputy Director (MRS)

Senior Resident Inspector (JDH1)

Branch Chief, DRP/C (MCH2)

Senior Project Engineer, DRP/C (WCW)

Team Leader, DRP/TSS (RLN1)

RITS Coordinator (KEG)

RidsNrrDipmIipb V. Dricks, PAO (VLD)

W. Maier, RSLO (WAM)

C. Gordon (CJG)

DRS Branch Chiefs (LJS, MPS1, ATG, JAC)

S. Richards, Chief, NRR/DIPM/IIPB (SAR)

M. Case, Deputy Dir. for Inspection and Programs (MJC)

B. Sheron, Associate Dir. for Project Licensing and Technical Analysis (BWS)

B. Wetzel, Acting Chief, ROPMS, OEDO (BAW)

H. Berkow, Director, LPD4, NRR/DLPM (HNB)

R. Gramm, Chief, PDIV-2, NRR/DLPM (RAG)

A. Wang, NRR Project Manager (ABW)

SISP Review Completed: __ath___ ADAMS: / Yes G No Initials: _ath____

/ Publicly Available G Non-Publicly Available G Sensitive

/ Non-Sensitive S:\\DRP\\DRPDIR\\EOC 04\\Assessment Letters\\FCS.wpd RIV:C:DRP/C D:DRS D:DRP MCHay;df DDChamberlain ATHowell III

/RA/

/RA/

/RA/

2/23/05 2/25/05 3/2/05 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

Fort Calhoun Inspection / Activity Plan 03/04/2005 - 09/30/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/01/2005 08:34:26 Report 22

TI-150

- TI-150 RESIDENT PORTION Safety Issues 02/25/2005 04/21/2005 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-02 IP 2515/150

2 TI-160

- TI-160 RESIDENT PORTION Safety Issues 02/25/2005 04/21/2005 Pzr Pene Nozzles & Stm Space Piping Connections in U.S. PWRs [NRC Bulletin 2004-01]

IP 2515/160

1 ACRSA

- ACCESS CONTROLS TO RAD SIGNIFICANT AREAS Baseline Inspections 03/14/2005 03/18/2005 Access Control to Radiologically Significant Areas IP 7112101

1 EB08P

- ISI - VESS VOL (TI 150/152) AS REQ Baseline Inspections 03/14/2005 03/18/2005 Inservice Inspection Activities - PWR IP 7111108P

Baseline Inspections 04/11/2005 04/18/2005 Inservice Inspection Activities - PWR IP 7111108P

1 ALARA2

- ALARA PLANNING AND CONTROLS Baseline Inspections 04/04/2005 04/08/2005 ALARA Planning and Controls IP 7112102

1 PEB-12B

- MAINTENANCE RULE BIENNIAL Baseline Inspections 05/09/2005 05/13/2005 Maintenance Effectiveness IP 7111112B

5 OB-INIT

- INITIAL EXAM Not Applicable 06/20/2005 06/24/2005 FT. CALHOUN (04/05) - INITIAL EXAM X02281

Not Applicable 07/11/2005 07/15/2005 FT. CALHOUN (04/05) - INITIAL EXAM X02281

4 PEB-05T

- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 07/25/2005 07/29/2005 Fire Protection IP 7111105T

Baseline Inspections 08/08/2005 08/12/2005 Fire Protection IP 7111105T

3 EB21

- SSD&PCI Baseline Inspections 08/15/2005 08/19/2005 Safety System Design and Performance Capability IP 7111121

Baseline Inspections 08/29/2005 09/02/2005 Safety System Design and Performance Capability IP 7111121

1 ALARA3

- ALARA PLANNING AND CONTROLS Baseline Inspections 08/22/2005 08/26/2005 ALARA Planning and Controls IP 7112102

4 PEB-52

- FCS PIR INSPECTION Baseline Inspections 09/12/2005 09/16/2005 Identification and Resolution of Problems IP 71152B

Baseline Inspections 09/26/2005 09/30/2005 Identification and Resolution of Problems IP 71152B

2 EB-REPL1

- SG REPLACEMENT EARLY REVIEWS Other Routine 10/01/2005 12/31/2005 Steam Generator Replacement Inspection IP 50001

2 EB-REPL2

- RX VESSEL HEAD REPL EARLY DESIGN REVIEW Other Routine 10/01/2005 12/31/2005 Reactor Vessel Head Replacement Inspection IP 71007

3 OB-EP1

- EMERG PREPAREDNESS EXERCISE Baseline Inspections 12/05/2005 12/09/2005 Exercise Evaluation IP 7111401

Baseline Inspections 12/05/2005 12/09/2005 Emergency Action Level and Emergency Plan Changes IP 7111404

Baseline Inspections 12/05/2005 12/09/2005 Performance Indicator Verification IP 71151

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Fort Calhoun Inspection / Activity Plan 03/04/2005 - 09/30/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/01/2005 08:34:26 Report 22

EB-REPL3

- SG REPLACEMENT - PRE OUTAGE Other Routine 01/01/2006 09/01/2006 Steam Generator Replacement Inspection IP 50001

2 EB-REPL4

- RX VESSEL HEAD REPL - PRE OUTAGE Other Routine 01/01/2006 09/01/2006 Reactor Vessel Head Replacement Inspection IP 71007

1 ALARA1

- ALARA PLANNING AND CONTROLS Baseline Inspections 04/24/2006 04/28/2006 ALARA Planning and Controls IP 7112102

1 PEB

- HX PERFORMANCE Baseline Inspections 05/01/2006 05/05/2006 Heat Sink Performance IP 7111107B

3 RP TEAM

- RP SAFETY TEAM Baseline Inspections 05/08/2006 05/12/2006 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103

Baseline Inspections 05/08/2006 05/12/2006 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201

Baseline Inspections 05/08/2006 05/12/2006 Radioactive Material Processing and Transportation IP 7112202

Baseline Inspections 05/08/2006 05/12/2006 Radiological Environmental Monitoring Program IP 7112203

1 OB-EP1

- EMERG PREP PROGRAM Baseline Inspections 06/19/2006 06/23/2006 Alert and Notification System Testing IP 7111402

Baseline Inspections 06/19/2006 06/23/2006 Emergency Response Organization Augmentation Testing IP 7111403

Baseline Inspections 06/19/2006 06/23/2006 Emergency Action Level and Emergency Plan Changes IP 7111404

Baseline Inspections 06/19/2006 06/23/2006 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405

Baseline Inspections 06/19/2006 06/23/2006 Performance Indicator Verification IP 71151

3 OB-RQ

- FCS REQUALIFICATION INSP Baseline Inspections 08/07/2006 08/11/2006 Licensed Operator Requalification Program IP 7111111B

3 EB17/02

- PERMANENT MODS/50.59 Baseline Inspections 08/07/2006 08/11/2006 Evaluation of Changes, Tests, or Experiments IP 7111102

Baseline Inspections 08/07/2006 08/11/2006 Permanent Plant Modifications IP 7111117B

3 EB-REPL5

- SG REPLACEMENT - OUTAGE Other Routine 09/01/2006 12/31/2006 Steam Generator Replacement Inspection IP 50001

3 EB-REPL6

- RX VESSEL HEAD REPL - OUTAGE Other Routine 09/01/2006 12/31/2006 Reactor Vessel Head Replacement Inspection IP 71007

1 ACRSA

- ACCESS CONTROL TO RAD SIGNIFICANT AREAS Baseline Inspections 09/18/2006 09/22/2006 Access Control to Radiologically Significant Areas IP 7112101

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.