IR 05000285/2001005

From kanterella
Jump to navigation Jump to search
IR 05000285/2001-005; Omaha Public Power District, Fort Calhoun Station, Integrated Resident & Regional Inspection Report on 09/30-12/29/2001. No Findings Were Identified
ML020170152
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 01/17/2002
From: Kennedy K
Division of Nuclear Materials Safety IV
To: Ridenoure R
Omaha Public Power District
References
IR-01-005
Download: ML020170152 (20)


Text

ary 17, 2002

SUBJECT:

NRC INSPECTION REPORT 50-285/01-05

Dear Mr. Gambhir:

On December 29, 2001, the NRC completed an inspection at your Fort Calhoun Station. The enclosed report documents the inspection findings which were discussed September 30, 2001, through January 2, 2002, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

Within these areas, the inspection consisted of selected examination of procedures and representative records, observations of activities, and interviews with personnel.

Immediately following the terrorist attacks on the World Trade Center and the Pentagon, the NRC issued an advisory recommending that nuclear power plant licensees go to the highest level of security, and all promptly did so. With continued uncertainty about the possibility of additional terrorist activities, the Nation's nuclear power plants remain at the highest level of security and the NRC continues to monitor the situation. This advisory was followed by additional advisories and, although the specific actions are not releasable to the public, they generally include increased patrols, augmented security forces and capabilities, additional security posts, heightened coordination with law enforcement and military authorities, and more limited access of personnel and vehicles to the sites. The NRC has conducted various audits of your responses to these advisories and your ability to respond to terrorist attacks with the capabilities of the current design basis threat. From these audits, the NRC has concluded that your security program is adequate at this time.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Omaha Public Power District -2-Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

/RA/

Kriss M. Kennedy, Chief Project Branch C Division of Reactor Projects Docket: 50-285 License: DPR-40

Enclosure:

NRC Inspection Report 50-285/01-05

REGION IV==

Docket: 50-285 License: DPR-40 Report No.: 50-285/01-05 Licensee: Omaha Public Power District Facility: Fort Calhoun Station Location: Fort Calhoun Station FC-2-4 Adm P.O. Box 399, Hwy. 75 - North of Fort Calhoun Fort Calhoun, Nebraska Dates: September 30 through December 29, 2001 Inspectors: W. Walker, Senior Resident Inspector L. Willoughby, Resident Inspector L. Ricketson, P.E., Senior Health Physicist P. Elkmann, Emergency Preparedness Inspector W. Maier, Senior Emergency Preparedness Inspector J. Hanna, Resident Inspector, Callaway Plant Approved By: Kriss M. Kennedy, Chief, Project Branch C ATTACHMENT: Supplemental Information

SUMMARY OF FINDINGS Fort Calhoun Station NRC Inspection Report 50-285/01-05 IR 05000285-01-05; on 09/30-12/29/2001; Omaha Public Power District, Fort Calhoun Station, Integrated Resident & Regional Report. No findings were identified.

The inspection was conducted by resident inspectors, a region-based health physicist, and two region based emergency preparedness inspectors. The inspection identified no findings. The significance of issues is indicated by their color (Green, White, Yellow, Red) and was determined by the Significance Determination Process in Inspection Manual Chapter 0609.

Findings for which the significance determination process does not apply are indicated by No Color or by severity level of the applicable violation. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described at its Reactor Oversight Process website at http://www.nrc.gov/NRR/OVERSIGHT/index.html.

A. Inspector Identified Findings None.

B. Licensee Identified Findings A violation of very low significance identified by the licensee was reviewed by the inspector. Corrective actions taken or planned by the licensee appear reasonable. This violation is listed in Section 4OA7.

Report Details The Fort Calhoun Station began this inspection period at 100 percent power and maintained that level until November 29, 2001. On the afternoon of November 29, 2001, power was reduced to approximately 97 percent when a flow anomaly in the reactor coolant system hot legs affecting delta-temperature power indications on the reactor protection system was observed. The delta-temperature anomaly was investigated and the plant commenced a power ascension to 100 percent on November 30, 2001. The plant remained at full power throughout the rest of the inspection period.

1. REACTOR SAFETY Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity 1R01 Adverse Weather Protection (71111.01)

a. Inspection Scope During October 2001, the inspectors reviewed the licensees Operating Instruction OI-EW-1, Extreme Weather, Revision 7, for responding to extreme weather, specifically cold weather preparations. The inspectors verified that design features and implementation of the procedure were adequate to protect mitigating systems from the effects of adverse weather.

b. Findings No findings of significance were identified.

1R04 Equipment Alignment (71111.04)

a. Inspection Scope

  • The inspectors performed a partial equipment alignment inspection on the Diesel Generator 1 Fuel Oil system on October 16, 2001. The inspectors walked down accessible portions of the system and verified that the system alignment was in accordance with Fuel Oil Flow Diagram P & ID DWG 11405-M-262 SH. 1, Revision 54.
  • On November 27, the inspectors performed a partial inspection of the Diesel Generator 2 Air Start Supply System to verify that all valves were in their required positions for operability of the system. The inspectors compared the position of the valves to the required position as specified in Piping and Instrumentation Drawing, Starting Air System Schematic DWG B120F07001 SH. 2, Revision 22.
  • On December 27, the inspectors performed a partial inspection of the 4.16 kV Auxiliary Power Electrical System, the 480 V Auxiliary Power Electrical System, to verify that all breakers were in their proper positions. The inspectors used Piping and Instrumentation Drawing 11405-E-3, 4.16 kV, Auxiliary Power One

-2-Line Diagram, Revision 19; Drawing 11405-E-4, 480 Volt Auxiliary Power One Line Diagram - Sheet 1, Revision 29; and Drawing 11405-E-5, 480 Volt Auxiliary Power One Line Diagram - Sheet 2, Revision 29.

b. Findings No findings of significance were identified.

1R05 Fire Protection (71111.05)

.1 Routine Fire Protection Inspections a. Inspection Scope The inspectors reviewed the following areas to determine if the licensee had implemented a fire protection program that adequately controlled combustibles and ignition sources within the plant, effectively maintained fire detection and suppression capabilities, and maintained passive fire protection features in good material condition.

The following areas were reviewed:

  • New fuel storage area in the auxiliary building on November 12, 2001
  • Emergency feedwater storage tank room in the control building on December 12, 2001
  • East safety injection pump room in the auxiliary building on December 19, 2001 The inspectors assessed these areas and verified that combustibles were being properly controlled in accordance with the following:
  • Updated Safety Analysis Report, Chapter 9.11, Fire Protection System
  • Standing Order SO-G-28, Station Fire Plan, Revision 47
  • Standing Order SO-G-58, Control of Fire Protection Impairments, Revision 29
  • Standing Order SO-G-91, Control and Transportation of Combustible Materials, Revision 15

-3-b. Findings No findings of significance were identified.

.2 Annual Inspection of Fire Brigade Drill a. Inspection Scope On October 3, 2001, the inspectors observed a fire brigade drill in the control building.

The simulated fire scenario involved fighting a fire in the essential battery rooms. This required full dress out in fire gear and required actual use of self-contained breathing apparatus.

b. Findings No findings of significance were noted.

1R06 Flood Protection Measures (71111.06)

a. Inspection Scope The inspectors conducted an inspection of the air compressor room, the C and D Raw Water/Component Cooling Water Heat Exchanger Room and the B Shutdown Heat Exchanger Room to verify that the equipment was not subject to damage resulting from internal flooding. The inspectors reviewed the internal flooding analysis performed to demonstrate that the safety-related equipment in the rooms were not vulnerable to internal flooding. They also reviewed the design basis for the site and the contingency actions to verify that the auxiliary building was not vulnerable to external flooding events.

The following documents and calculations were used as criteria for the inspection:

  • Probability Risk Assessment Summary Notebook Table 7.1.2, Summary of Estimated Flood Levels for Auxiliary Building Propagation Paths
  • Updated Safety Analysis Report Section 2.7, Hydrology, and Section 9.8, Raw Water System
  • Repair - Rework Instructions, PE-RR-AE-1000, Flood Control Preparedness for Floodgates b. Findings No findings of significance were identified.

-4-1R11 Licensed Operator Requalifications (71111.11)

a. Inspection Scope On October 9, 2001, the inspectors observed a licensed operator simulator exercise.

The simulator exercise evaluated the operators ability to recognize, diagnose, and respond to equipment problems. The simulator scenario included a reactor coolant pump seal failure, followed by a second reactor coolant pump seal failure. Included in the scenario was a failure of the motor-driven and diesel-driven auxiliary feedwater pumps to start. The inspectors evaluated the operator performance using the following:

Emergency Operating Procedure EOC-00, Standard Post Trip Actions, Revision 5; Emergency Operating Procedure EOP-06, Loss of All Feedwater, Revision 10; Abnormal Operating Procedure AOP-35,Reactor Coolant Pump Malfunctions, Revision 1; and Abnormal Operating Procedure AOP-28, Auxiliary Feedwater Pump Failure, Revision 3.

On October 16, 2001, the inspectors observed a licensed operator simulator exercise.

The simulator exercise evaluated the operators ability to recognize, diagnose, and respond to equipment problems. The simulator scenario included a steam generator pressure instrument failure, a steam generator tube rupture, and two stuck rods on a reactor trip. The inspectors evaluated operator performance using the following:

Abnormal Operating Procedure AOP-22, Reactor Coolant Leak, Revision 9; Abnormal Operating Procedure AOP-05, Emergency Shutdown, Revision 7; Emergency Operating Procedure EOC-00, Standard Post Trip Actions, Revision 5; Emergency Operating Procedure EOC-20, Functional Recovery Procedure, Revision 6; and Technical Specifications.

b. Findings No findings of significance were identified.

1R12 Maintenance Rule Implementation (71111.12)

a. Inspection Scope During the inspection period, the inspectors reviewed licensee implementation of the maintenance rule. The inspectors verified structure and component scoping, characterization, safety significance, performance criteria, and the appropriateness of goals and corrective actions. The inspectors compared the licensees implementation of the maintenance rule to the requirements outlined in 10 CFR 50.65, the licensees administrative procedures, Regulatory Guide 1.160, Monitoring the Effectiveness of Maintenance at Nuclear Power Plants, Revision 2, and summary reports from various expert technical panel meetings. The inspectors reviewed the following components:

  • Ventilation and Air Conditioning System components (VA-46A and VA-46B)
  • Chemical and Volume Control System Flow Element (FE236)

-5-

  • Boric Acid Control Valve unable to control in automatic b. Findings No findings of significance were identified.

1R13 Maintenance Risk Assessments and Emergent Work Evaluation 71111.13 a. Inspection Scope The inspectors reviewed the licensees risk assessments for equipment outages as a result of planned and emergent maintenance to evaluate the licensees effectiveness in assessing risk for planned and emergent activities. The inspectors compared the licensees risk assessment and risk management activities against requirements of 10 CFR 50.65 (a)(4) and the recommendations of NUMARC 93-01, Industry Guideline for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants, Revision 2.

The inspectors also discussed the planned and emergent work activities with planning and maintenance personnel. They reviewed and observed emergent work on the following systems/components/activities:

  • October 31, 2001 Troubleshooting of Diesel Generator 1 failure to start from local panel
  • November 1, 2001 Activities performed in response to Component Cooling Water Inlet Relief Valve AC-183 repair
  • November 8, 2001 Activities performed in response to repair of Intake Screen C
  • November 29, 2001 Activities performed to replace Motor-Driven Auxiliary Feedwater Pump FW-6 bearing
  • December 12, 2001 Activities performed in response to Containment Ventilation Filtered Inlet Damper HCV-725A repair b. Findings No findings of significance were identified.

-6-1R15 Operability Evaluations 71111.15 a. Inspection Scope The inspectors reviewed the technical adequacy of an operability evaluation to verify it was sufficient to justify continued operation of a system or component. The inspectors verified that, although equipment was degraded, the operability evaluation provided adequate justification that the equipment could still meet its Technical Specification, Updated Safety Analysis Report, and design bases requirements and that any potential risk increase that contributed to the degradation of equipment was throughly evaluated.

The following evaluation was reviewed:

  • November 24, 2001 Low Pressure Safety Injection Pump SI-1B, two of four bolts connecting Suction Valve HCV-2937 air piston operator to the valve bonnet were loose.

b. Findings No findings of significance were identified.

1R19 Postmaintenance Testing (71111.19)

a. Inspection Scope The inspectors verified that postmaintenance tests were adequate to verify system operability and functional capabilities. The inspectors verified that testing met design and licensing bases requirements, Technical Specifications, the Updated Safety Analysis Report, inservice testing, and licensee administrative procedures. The inspectors verified testing results for the following components tested on the dates indicated below:

  • October 5, 2001 Raw Water Strainer AC-12B
  • October 17, 2001 Diesel Generator 2
  • November 28, 2001 Diesel Generator 1
  • December 19, 2001 Containment Isolation Valve HCV-500B b. Findings No findings of significance were identified.

-7-1R22 Surveillance Testing (71111.22)

a. Inspection Scope The inspectors observed or reviewed the following surveillance test to ensure the system tested was capable of performing its safety function and to assess its operational readiness. Specifically, the inspectors verified that the following surveillance test met Technical Specifications, the Updated Safety Analysis Report, and licensee procedural requirements.

  • December 4, 2001 Surveillance Test IC-ST-RPS-034, Quarterly Functional Test of Channel A Axial Power Distribution (APD) Calculator, Revision 11 b. Findings No findings of significance were identified.

1R23 Temporary Plant Modifications (71111.23)

a. Inspection Scope The inspectors performed a detailed review of the following temporary modification:

  • EC#28787 modification that temporarily installed a soft patch on the 5-inch fire protection main piping header at the east end of Corridor 4 about 15 feet above the floor.

The inspectors reviewed the detailed modification package and compared them to the installed configuration in the field. This included reviewing the 10 CFR 50.59 screening against the design basis as specified in the Updated Safety Analysis Report and the Technical Specifications. The inspectors also verified that drawings and procedures were properly updated to reflect the modified configuration of the systems.

b. Findings No findings of significance were identified.

Cornerstone: Emergency Preparedness 1EP1 Exercise Evaluation (71114.01)

a. Inspection Scope The inspectors reviewed the objectives and scenario for the 2001 exercise to determine if the exercise would acceptably test major elements of the emergency plan. The scenario included simulated response to an onsite fire, equipment and electrical power

-8-failures, a loss of reactor coolant, a loss of core cooling causing core damage, and a radiological release to the environment to demonstrate the licensee's capabilities to implement the emergency plan.

The inspectors evaluated exercise performance by focusing on the risk-significant activities of classification, notification, protective action recommendations, and assessment of offsite dose consequences in the following emergency response facilities:

  • Simulator Control Room
  • Operations Support Center
  • Emergency Operations Facility The inspectors also assessed personnel recognition of abnormal plant conditions, the transfer of emergency responsibilities between facilities, communications, protection of emergency workers, emergency repair capabilities, and the overall implementation of the emergency plan to verify compliance with the requirements of 10 CFR 50.47(b) and Appendix E to Part 50.

The inspectors attended the postexercise critiques in each of the above facilities to evaluate the initial licensee self-assessment of exercise performance. The inspectors also attended a subsequent presentation of critique items to plant management.

b. Findings No findings of significance were identified.

1EP4 Emergency Action Level and Emergency Plan Changes (71114.04)

a. Inspection Scope The inspector reviewed Revision 11A to Section I and Revision 16A to Section J of the Fort Calhoun Station Radiological Emergency Plan, submitted September 21, 2001, against 10 CFR 50.54(q) to determine if the revision decreased the effectiveness of the plan.

b. Findings No findings of significance were identified.

-9-2. RADIATION SAFETY Cornerstone: Occupational Radiation Safety 2OS2 ALARA Planning and Controls (71121.02)

a. Inspection Scope The inspector attended a prejob briefing and observed the movement of a container of radioactive resin within a restricted high radiation area. The inspector also interviewed radiation protection personnel involved in the high dose rate job for information to meet the inspection procedure requirements. Independent radiation surveys of selected work areas within the radiologically controlled area were conducted by the inspector to verify that areas were correctly posted and controlled. The inspector attended the ALARA Committee Meeting conducted October 18, 2001. The following items were reviewed and compared with regulatory requirements:

  • Work control procedure
  • Processes used to estimate and track exposures
  • Plant collective exposure history for the past 3 years, current exposure trends, and 3-year rolling average dose information
  • Three radiation work permit packages from online work activities which resulted in the highest personnel collective exposures during the inspection period (2001-3004, 2001-3014, and 2001-3543)
  • Use of engineering controls to achieve dose reductions
  • Hot spot tracking and reduction program
  • Temporary shielding requests (2001-37, 2001-38, and 2001-41)
  • Source term reduction strategy and initiatives
  • Radiological work planning
  • Self-assessments (CHP-01-20 and SA-10) and surveillance (H3-01-1) which reviewed ALARA performance
  • Selected corrective action documentation involving higher than planned exposures and radiation worker practice deficiencies since the last inspection in this area (200102038, 200102506, 200102619, 200102644, 200102659, and 200102754)

-10-b. Findings No findings of significance were identified.

4. OTHER ACTIVITIES 4OA1 Performance Indicator Verification (71151)

.1 Drill and Exercise Performance a. Inspection Scope The inspectors verified a sample of the licensees reported results for the drill and exercise performance indicator by reviewing records for licensee exercises, actual declared emergencies, drills, and simulator training scenarios conducted from the third calendar quarter of 2000 through the third calendar quarter of 2001 to verify the accuracy of the reported performance indicator data for that period. The inspectors evaluated licensee performance indicator collection and reporting practices against the standards of NEI 99-02, Regulatory Assessment Performance Indicator Guideline.

b. Findings No findings of significance were identified.

.2 Emergency Response Organization Readiness Performance Indicator Verification a. Inspection Scope The inspectors verified the licensees reported results for the emergency response organization drill participation performance indicator for the third calendar quarter of 2000 through the third calendar quarter of 2001 by reviewing drill participation attendance records for a sample of 12 key emergency responders. The inspectors evaluated licensee performance indicator collection and reporting practices against the standards of NEI 99-02, Regulatory Assessment Performance Indicator Guideline.

b. Findings No findings of significance were identified.

.3 Alert and Notification System Reliability Performance Indicator Verification (71151)

a. Inspection Scope The inspectors verified the licensees reported results for the alert and notification system reliability performance indicator by reviewing a sample of offsite siren test results performed from the third calendar quarter of 2000 through the third calendar quarter of 2001 to verify the accuracy of the reported performance indicator data for that period.

-11-The inspectors evaluated licensee performance indicator collection and reporting practices against the standards of NEI 99-02, Regulatory Assessment Performance Indicator Guideline.

b. Findings No findings of significance were identified.

.4 Barrier Integrity a. Inspection Scope The inspectors verified the accuracy and completeness of the data used to calculate and report selected performance indicators. Specifically, a sampling of control room logs and chemistry data were reviewed for the following performance indicators:

4OA6 Meetings, including Exit The inspector presented the inspection results to Mr. S. Gambhir, Division Manager, Nuclear Oversight Division, and other members of licensee management at the conclusion of the inspections on October 19, 26, and 29, 2001, and on January 2, 2002.

During each meeting, the licensee management acknowledged the findings presented.

Additionally, the inspector asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.

-12-4OA7 Licensee Identified Violations The following finding of very low significance was identified by the licensee and is a violation of NRC requirements which meet the criteria of Section VI of the NRC Enforcement Policy, NUREG-1600 for being dispositioned as a noncited violation (NCV).

NCV Tracking Number Requirement Licensee Failed to Meet (1) NCV 50-285/01005-01 Technical Specification 5.8.1 requires the implementation of procedures listed in Regulatory Guide 1.33, Appendix A.

Standing Order SO-G-101, "Radiation Worker Practices,"

Revision 17, requires individuals to exit the radiological controlled area immediately if a self-reading dosimeter alarms for any reason. On August 10, 2001, two individuals failed to follow procedural guidance when they failed to exit the radiological controlled area after receiving dose and dose rate alarms. This resulted in the individuals receiving higher than planned doses. This occurrence was documented in the licensee's corrective action program by Condition Report 200102659. This is being treated as a noncited violation.

ATTACHMENT KEY POINTS OF CONTACT Licensee R. Andrews, Special Assignee, Nuclear Operations Division D. Bannister, Manager, Operations J. Chase, Division Manager, Nuclear Assurance R. Clemens, Plant Manager S. Coufal, ALARA Technician, Radiation Protection D. Dryden, Engineer, Station Licensing M. Frans, Manager, Nuclear Licensing S. Gambhir, Division Manager Nuclear Operations Division G. Gates, Vice President, Nuclear E. Matzke, Station Licensing Engineer M. Puckett, Manager, Radiation Protection R. Reno, ALARA and Radiological Equipment Supervisor, Radiation Protection H. Sefick, Manager, Security and Emergency Planning K. Steele, Operations Supervisor, Radiation Protection C. Simmons, Supervisor, Emergency Planning C. Williams, ALARA Technician, Radiation Protection NRC W. Walker, Senior Resident Inspector L. Willoughby, Resident Inspector ITEMS OPENED, CLOSED, AND DISCUSSED Opened and Closed During this Inspection 50-285/01005-01 NCV Failure to follow procedure and exit RCA after electronic dosimeter alarmed (Section 4OA7)

-2-DOCUMENTS REVIEWED The following documents were selected and reviewed by the inspectors to accomplish the objectives and scope of the inspection and to support any findings:

Emergency Plan and Implementing Procedures:

N/A Fort Calhoun Station Radiological Emergency Response Plan Revision 29 EPIP-OSC-1 Emergency Classification Revision 34 EPIP-OSC-2 Command and Control Position Actions/Notifications Revision 39 EPIP-EOF-6 Dose Assessment Revision 31 EPIP-EOF-7 Protective Action Guidelines Revision 13 EPIP-EOF-21 Potassium Iodide Issuance Revision 4 Other Procedures:

EPDM-14 Emergency Preparedness Performance Indicator Program Revision 3 LIST OF ACRONYMS USED CFR Code of Federal Regulations NCV noncited violation