|
|
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:November 2, 2006Mr. Kurt M. HaasGeneral Manager Big Rock Point Nuclear Plant Consumers Energy Company 10269 U.S. 31 North Charlevoix, MI 49720SUBJECT:BIG ROCK POINT INSPECTION REPORTS 050-00155/06-02(DNMS) AND072-00043/06-01(DNMS) | | {{#Wiki_filter:ber 2, 2006 |
| | |
| | ==SUBJECT:== |
| | BIG ROCK POINT INSPECTION REPORTS 050-00155/06-02(DNMS) AND 072-00043/06-01(DNMS) |
|
| |
|
| ==Dear Mr. Haas:== | | ==Dear Mr. Haas:== |
| On October 18, 2006, the NRC completed inspection activities at the Big Rock PointRestoration Project. The purpose of the inspection was to conduct radiological confirmatory surveys and evaluate the biennial exercise of the Emergency Plan. At the conclusion of on-siteinspection on October 18, the inspectors discussed the inspection findings with you and members of your staff. This inspection consisted of independent radiological confirmatory surveys of areas of the BigRock Point site that had not been previously surveyed by the NRC, and the observation and evaluation of the Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan exercise. Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection included a selective examination of procedures and representative records, observations of activities in progress, and interviews with personnel.Based on the results of this inspection, the NRC did not identify any violations. | | On October 18, 2006, the NRC completed inspection activities at the Big Rock Point Restoration Project. The purpose of the inspection was to conduct radiological confirmatory surveys and evaluate the biennial exercise of the Emergency Plan. At the conclusion of on-site inspection on October 18, the inspectors discussed the inspection findings with you and members of your staff. |
|
| |
|
| In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letterand its enclosure will be available electronically in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). The NRC's document system is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
| | This inspection consisted of independent radiological confirmatory surveys of areas of the Big Rock Point site that had not been previously surveyed by the NRC, and the observation and evaluation of the Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan exercise. Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection included a selective examination of procedures and representative records, observations of activities in progress, and interviews with personnel. |
|
| |
|
| K. Haas-2-We will gladly discuss any questions you may have regarding this inspection.
| | Based on the results of this inspection, the NRC did not identify any violations. |
| | |
| | In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). The NRCs document system is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection. |
|
| |
|
| Sincerely, | | Sincerely, |
| /RA/Jamnes L. Cameron, ChiefDecommissioning BranchDocket Nos. 050-00155; 072-00043License No. DPR-6 | | /RA/ |
| | Jamnes L. Cameron, Chief Decommissioning Branch Docket Nos. 050-00155; 072-00043 License No. DPR-6 |
|
| |
|
| ===Enclosures:=== | | ===Enclosures:=== |
| Inspection Reports 050-00155/06-02(DNMS); 072-00043/06-01(DNMS) | | Inspection Reports 050-00155/06-02(DNMS); 072-00043/06-01(DNMS) |
|
| |
|
| REGION IIIDocket Nos.:050-00155; 072-00043License No.:DPR-6 Report Nos.:050-00155/06-02(DNMS);072-00043/06-01(DNMS)Licensee:Consumers Energy Company Facility:Big Rock Point Restoration Project Location:10269 U.S. 31 NorthCharlevoix, MI 49720Dates:October 16 through 18, 2006 Inspectors:William G. Snell, Senior Health PhysicistSam J. Mulay, Health PhysicistApproved by:Jamnes L. Cameron, ChiefDecommissioning Branch, Division of Nuclear Materials Safety 2EnclosureEXECUTIVE SUMMARYConsumers Energy CompanyBig Rock Point Restoration ProjectNRC Inspection Reports 050-00155/06-02(DNMS) and 072-00043/06-01(DNMS)This routine decommissioning inspection involved confirmatory radiological surveys andobservation of a biennial exercise of the Independent Spent Fuel Storage Installation (ISFSI) | | REGION III== |
| Emergency Plan.Operation of an ISFSI*The licensee adequately demonstrated the effectiveness of the ISFSI Emergency Planand their ability to implement the Plan in response to an emergency. (Section 1.0)Inspection of Final Surveys*A review of licensee survey records and independent confirmatory surveys for residualradioactive contamination confirmed that the licensee is performing remediation and final status surveys consistent with the License Termination Plan. (Section 2.0) | | Docket Nos.: 050-00155; 072-00043 License No.: DPR-6 Report Nos.: 050-00155/06-02(DNMS); |
| 1A list of acronyms used in the report is included at the end of the Report Details.
| | 072-00043/06-01(DNMS) |
| | Licensee: Consumers Energy Company Facility: Big Rock Point Restoration Project Location: 10269 U.S. 31 North Charlevoix, MI 49720 Dates: October 16 through 18, 2006 Inspectors: William G. Snell, Senior Health Physicist Sam J. Mulay, Health Physicist Approved by: Jamnes L. Cameron, Chief Decommissioning Branch, Division of Nuclear Materials Safety Enclosure |
| | |
| | EXECUTIVE SUMMARY Consumers Energy Company Big Rock Point Restoration Project NRC Inspection Reports 050-00155/06-02(DNMS) and 072-00043/06-01(DNMS) |
| | This routine decommissioning inspection involved confirmatory radiological surveys and observation of a biennial exercise of the Independent Spent Fuel Storage Installation (ISFSI) |
| | Emergency Plan. |
| | |
| | Operation of an ISFSI |
| | * The licensee adequately demonstrated the effectiveness of the ISFSI Emergency Plan and their ability to implement the Plan in response to an emergency. (Section 1.0) |
| | Inspection of Final Surveys |
| | * A review of licensee survey records and independent confirmatory surveys for residual radioactive contamination confirmed that the licensee is performing remediation and final status surveys consistent with the License Termination Plan. (Section 2.0) |
| | 2 Enclosure |
| | |
| | Report Details1 1.0 Operation of an ISFSI (60855) |
| | 1.1 Inspection Scope The inspectors observed and evaluated the conduct of the Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan biennial exercise. |
| | |
| | 1.2 Observations and Findings Section 12.2.2 of Volume 35 of the ISFSI Emergency Plan requires the licensee to perform a biennial exercise to demonstrate emergency response capabilities and the effectiveness of the Emergency Plan. On October 17, 2006, the licensee conducted a biennial exercise based on a simulated earthquake that caused a spent fuel storage cask to tip over. In response to the event, the license appropriately implemented the Emergency Plan, correctly classified the event, augmented personnel as necessary, made timely notifications, conducted appropriate radiological monitoring, and ensured the safety of site personnel. |
| | |
| | 1.3 Conclusion The licensee adequately demonstrated the effectiveness of the ISFSI Emergency Plan and their ability to implement the Plan in response to an emergency. |
| | |
| | 2.0 Inspection of Final Surveys (83801) |
| | 2.1 Inspection Scope The inspectors performed independent radiological confirmatory surveys of selected on-site areas. Licensee records of final status surveys were also reviewed. |
| | |
| | 2.2 Observations and Findings Independent radiological gamma scan surveys were performed of the following survey areas using sodium iodide (NaI) scintillation detectors coupled to ratemeters with audible indication: South11C11 (50% scanned); 20C11 (80% scanned); South19C12 (30% scanned); North21C12 (50% scanned); eastern 20% of East22C12 (50% scanned); |
| | and an area of about 50 square meters in the northeast corner of 18C13 (50% scanned). |
| | |
| | In all areas surveyed, the inspectors did not identify elevated levels of direct gamma radiation in excess of background. |
| | |
| | A list of acronyms used in the report is included at the end of the Report Details. |
| | |
| | 3 Enclosure |
| | |
| | The following nine licensee final status survey records were reviewed, which included the Survey Area Requirements, Data Quality Objects, and the Final Status Survey (FSS) |
| | Design: |
| | Class 2 FSS Release Record, North21C12, Northeast Transport Route Class 1 FSS Release Record, 20C11, East Radwaste Staging Area Class 1 FSS Release Record, North11C11, North Radwaste Staging Area Class 1 FSS Release Record, South11C11, South Radwaste Staging Area Class 2 FSS Release Record, North19C12, Northwest Transport Route Class 2 FSS Release Record, South21C12, Southeast Transport Route Class 2 FSS Release Record, South19C12, Southwest Transport Route Class 2 FSS Release Record, West22C12, West Powerline Corridor Class 2 FSS Release Record, 15(1)C12, Eastern Section Woods Road Area The Survey Area Requirements, Data Quality Objects, and the Final Status Survey (FSS) Designs were adequate. For the above South Radwaste Staging Area (South11C11), and Southwest Transport Route (South19C12), the licensees survey scan results and the analytical results of soil samples were also reviewed. The final status survey soil sample results reviewed showed less than the derived concentration guideline levels (DCGLs) for soil of 11.93 picocuries per gram (pCi/g) for cesium-137 and 3.21 pCi/g for cobalt-60 as described in the licensees License Termination Plan (LTP). The licensees scan surveys indicated no elevated direct gamma radiation in excess of background 2.3 Conclusion A review of licensee survey records and independent confirmatory surveys for residual radioactive contamination confirmed that the licensee is performing remediation and final status surveys consistent with the LTP. |
| | |
| | 3.0 Exit Meeting Summary The inspectors presented preliminary inspection findings to members of the licensee management team at the conclusion of onsite inspection activities on October 18, 2006. |
| | |
| | ATTACHMENT: SUPPLEMENTAL INFORMATION 4 Enclosure |
| | |
| | SUPPLEMENTAL INFORMATION PARTIAL LIST OF PERSONS CONTACTED Consumers Energy Company |
| | * Kurt Haas, Site General Manager |
| | * Ken Pallagi, Radiation Protection & Environmental Services Manager |
| | * Persons present at the exit meetings. |
| | |
| | INSPECTION PROCEDURES USED IP 60855 Operation of an ISFSI IP 83801 Inspection of Final Surveys at Permanently Shutdown Reactors ITEMS OPENED, CLOSED, AND DISCUSSED Opened None Closed None Discussed None PARTIAL LIST OF DOCUMENTS REVIEWED Licensee documents reviewed and utilized during the course of this inspection are specifically identified in the Report Details above. |
|
| |
|
| 3EnclosureReport Details 11.0Operation of an ISFSI (60855)1.1Inspection ScopeThe inspectors observed and evaluated the conduct of the Independent Spent FuelStorage Installation (ISFSI) Emergency Plan biennial exercise.1.2Observations and FindingsSection 12.2.2 of Volume 35 of the ISFSI Emergency Plan requires the licensee toperform a biennial exercise to demonstrate emergency response capabilities and the effectiveness of the Emergency Plan. On October 17, 2006, the licensee conducted a biennial exercise based on a simulated earthquake that caused a spent fuel storage cask to tip over. In response to the event, the license appropriately implemented the Emergency Plan, correctly classified the event, augmented personnel as necessary, made timely notifications, conducted appropriate radiological monitoring, and ensured the safety of site personnel.1.3ConclusionThe licensee adequately demonstrated the effectiveness of the ISFSI Emergency Planand their ability to implement the Plan in response to an emergency.2.0Inspection of Final Surveys (83801)2.1Inspection ScopeThe inspectors performed independent radiological confirmatory surveys of selected on-site areas. Licensee records of final status surveys were also reviewed. 2.2Observations and FindingsIndependent radiological gamma scan surveys were performed of the following surveyareas using sodium iodide (NaI) scintillation detectors coupled to ratemeters with audible indication: South11C 11 (50% scanned); 20C 11 (80% scanned); South19C 1 2(30% scanned); North21C 12 (50% scanned); eastern 20% of East22C 12 (50% scanned);and an area of about 50 square meters in the northeast corner of 18C 13 (50% scanned). In all areas surveyed, the inspectors did not identify elevated levels of direct gamma radiation in excess of background.
| | LIST OF ACRONYMS USED ADAMS Agencywide Documents Access and Management System DCGL Derived Concentration Guideline Level DNMS Division of Nuclear Materials Safety FSS Final Status Survey ISFSI Independent Spent Fuel Storage Installation LTP License Termination Plan NRC Nuclear Regulatory Commission pCi/g picocuries per gram Attachment |
|
| |
|
| 4EnclosureThe following nine licensee final status survey records were reviewed, which includedthe Survey Area Requirements, Data Quality Objects, and the Final Status Survey (FSS)
| | 6 Attachment |
| Design:Class 2 FSS Release Record, North21C 12, Northeast Transport Route Class 1 FSS Release Record, 20C 11, East Radwaste Staging AreaClass 1 FSS Release Record, North11C 11, North Radwaste Staging AreaClass 1 FSS Release Record, South11C 11, South Radwaste Staging AreaClass 2 FSS Release Record, North19C 12, Northwest Transport Route Class 2 FSS Release Record, South21C 12, Southeast Transport Route Class 2 FSS Release Record, South19C 12, Southwest Transport Route Class 2 FSS Release Record, West22C 12, West Powerline Corridor Class 2 FSS Release Record, 15(1)C 12, Eastern Section Woods Road Area The Survey Area Requirements, Data Quality Objects, and the Final Status Survey(FSS) Designs were adequate. For the above South Radwaste Staging Area (South11C 11), and Southwest Transport Route (South19C 12), the licensee's surveyscan results and the analytical results of soil samples were also reviewed. The final status survey soil sample results reviewed showed less than the derived concentration guideline levels (DCGLs) for soil of 11.93 picocuries per gram (pCi/g) for cesium-137 and 3.21 pCi/g for cobalt-60 as described in the licensee's License Termination Plan (LTP). The licensee's scan surveys indicated no elevated direct gamma radiation in excess of background2.3ConclusionA review of licensee survey records and independent confirmatory surveys for residualradioactive contamination confirmed that the licensee is performing remediation and final status surveys consistent with the LTP.3.0Exit Meeting SummaryThe inspectors presented preliminary inspection findings to members of the licenseemanagement team at the conclusion of onsite inspection activities on October 18, 2006.ATTACHMENT: SUPPLEMENTAL INFORMATION AttachmentSUPPLEMENTAL INFORMATIONPARTIAL LIST OF PERSONS CONTACTEDConsumers Energy Company* Kurt Haas, Site General Manager* Ken Pallagi, Radiation Protection & Environmental Services Manager* Persons present at the exit meetings.INSPECTION PROCEDURES USEDIP 60855Operation of an ISFSIIP 83801Inspection of Final Surveys at Permanently Shutdown ReactorsITEMS OPENED, CLOSED, AND DISCUSSEDOpened None Closed None Discussed NonePARTIAL LIST OF DOCUMENTS REVIEWEDLicensee documents reviewed and utilized during the course of this inspection are specificallyidentified in the "Report Details" above.LIST OF ACRONYMS USEDADAMSAgencywide Documents Access and Management SystemDCGL Derived Concentration Guideline Level DNMSDivision of Nuclear Materials Safety FSSFinal Status Survey ISFSIIndependent Spent Fuel Storage Installation LTPLicense Termination Plan NRCNuclear Regulatory Commission pCi/g picocuries per gram Attachment 6
| |
| }} | | }} |
|
---|
Category:Inspection Report
MONTHYEARIR 05000155/20240012024-10-31031 October 2024 NRC Inspection Report No. 07200043/2024001; 05000155/2024001 Big Rock Point Independent Spent Fuel Storage Installation IR 07200043/20234012024-02-0505 February 2024 Public-Big Rock Point (BRP) Independent Spent Fuel Storage Installation (ISFSI) - NRC Security Inspection Report 07200043/2023401 IR 07200043/20214012021-07-29029 July 2021 Independent Spent Fuel Storage Installation Security Inspection Report 07200043/2021401 IR 05000155/20200012020-11-0202 November 2020 Inspection Report No. 07200043/2020001(DNMS) and 05000155/2020001(DNMS), Docket Nos. 07200043, 05000155, License No. DPR-6 IR 05000155/20180012018-11-26026 November 2018 NRC Inspection Report 07200043/2018001(DNMS); 05000155/2018001(DNMS) Big Rock Point Independent Spent Fuel Storage Installation IR 07200043/20184012018-05-31031 May 2018 Independent Spent Fuel Storage Installation - Security Inspection Report 07200043/2018401 (DRS-E.Bonano) IR 05000155/20170012017-05-17017 May 2017 Independent Spent Fuel Storage Installation, NRC Inspection Report 07200043/2017001 (DNMS) and 05000155/2017001(DNMS) IR 05000155/20140072014-10-31031 October 2014 IR 07200043/2014001 (DNMS) and 05000155/2014007 (Dnms), 10/7-8/2014, Big Rock Point Independent Spent Fuel Storage Installation IR 05000155/20120072013-03-11011 March 2013 Errata to Big Rock Point Independent Spent Fuel Storage Installation - Inspection Reports 07200043-12-001(DNMS) and 05000155-12-007(DNMS) IR 05000155/20120012013-01-0808 January 2013 IR 07200043-12-001 & 05000155-12-001, 12/18/2012, Big Rock Point Plant and Independent Spent Fuel Storage Installation IR 05000155/20124012012-12-18018 December 2012 IR 05000155-12-403, and 07200043-12-401, 11/29/2012, Big Rock Point ISFSI - Cover Letter IR 05000155/20124032012-12-18018 December 2012 IR 05000155-12-403, and 07200043-12-401, 11/29/2012, Big Rock Point ISFSI - Cover Letter IR 05000155/20080012008-11-13013 November 2008 IR 072-00043-08-001,050-00155-08-001(DNMS) on 10/22/08 - 10/24/08, Big Rock Point Independent Spent Fuel Storage Installation IR 05000155/20060022006-11-0202 November 2006 IR 05000155-06-002 (DNMS) and 07200043-06-001 (Dnms), on 10/18/06, Big Rock Point, Confirmatory Radiological Surveys and Observation of a Biennial Exercise of ISFSI Emergency Plan IR 05000155/20060012006-09-29029 September 2006 IR 05000155-06-001, on 05/08-09/2006, 06/02/2006, 06/13-15/2006, 07/05/2006, & 09/13/2006, Big Rock Point IR 05000155/20050052006-01-0505 January 2006 IR 05000155-05-005, on 10/18-20/2005, and 12/9-13/2005, Big Rock Point (DNMS) IR 05000155/20050042005-11-21021 November 2005 IR 05000155-05-004 on November 10, 2005 IR 05000155/20050022005-08-0303 August 2005 IR 05000155-05-002 (DNMS) & IR 07200043-05-001(DNMS), on 07/14/05, Big Rock Point, Routine Decommissioning Inspection IR 05000155/20050012005-04-0505 April 2005 IR 05000155-05-001(DNMS), on 01/19-21/2005 and 03/07-10/2005, Big Rock Point, Decommissioning Inspection IR 05000155/20040032005-01-18018 January 2005 IR 05000155-04-003 (Dnms), on 10/12/2004 - 10/15/2004, 11/01/2004 - 11/05/2004, 12/13/2004 - 12/16/2004 & 01/07/2005 and Notice of Violation - Big Rock Point, Decommissioning Activities IR 05000155/20040022004-10-0606 October 2004 IR 05000155-04-002, on 07/19-23/2004, 08/10-12/2004, 08/30/2004 - 09/03/2004 & 09/20-22/2004, Consumers Energy Co, Big Rock Point Restoration Project, Routine Decommissioning Inspections IR 05000155/20040012004-07-0202 July 2004 IR 05000155-04-001(DNMS), Big Rock Point, on 04/12/04 - 04/16/04, 05/11/04 - 05/14/04, and 06/01/04 - 06/04/04, Decommissioning Support Activities ML0407009702004-03-10010 March 2004 IR 05000155-03-007, on 12/01/2003 - 12/04/2003, 01/12/2004 - 01/15/2004 & 02/17/2004 - 02/20/2004, Big Rock Point Nuclear Plant Decommissioning Inspection IR 05000155/20030072004-03-10010 March 2004 Letter Form C. Miller to Kurt Haas Regarding Big Rock Point Inspection Report 05000155-03-007 IR 05000155/20030052003-11-0707 November 2003 IR 05000155-03-005, on 09/08/2003 - 10/09/2003, Big Rock Point, Decommissioning Inspection IR 05000155/20030042003-09-12012 September 2003 IR 05000155-03-004 (DNMS) Big Rock Point, 07/14/03 - 08/16/03. Review of Licensee'S Performance Related to Decommissioning Support Activities and Radiological Safety IR 07200043/20030032003-08-29029 August 2003 IR 07200043-03-003, on 8/12/03 Through 8/14/03, for Consumers Energy Co., Charlevoix, Mi; Security Measures for Independent Spent Fuel Storage Installations and Verification of Compliance with Interim Compensatory Measures Order IR 05000155/20030032003-07-16016 July 2003 IR 05000155-03-003, on 05/27/2003 - 06/19/2003, for Big Rock Point Nuclear Plant; Big Rock Point Restoration Project IR 05000155/20030022003-06-18018 June 2003 Letter from C. Miller to Kurt Haas Regarding Big Rock Point IR 05000155-03-002 & IR 07200043-03-002 ML0317002202003-06-18018 June 2003 IR 05000155-03-002 & IR 07200043-03-002(DNMS), on 03/17 - 05/19/2003, Big Rock Point. No Violations Noed ML0308508012003-03-25025 March 2003 Memo 03/25/03 Big Rock Point Re DRS Input to DNMS Report 50-155/03-02 IR 05000155/20030012003-03-12012 March 2003 IR 05000155-03-001(DNMS) on 01/06/03 and 02/21/03 for Big Rock Point, Reviewing Licensee'S Performance Related to Spent Fuel Safety and Radiological Safety IR 05000155/20020072003-01-16016 January 2003 IR 05000155-02-007, on 11/11/2002 - 12/23/2002, Big Rock Point. Big Rock Point Restoration Project IR 07200043/20020022003-01-0909 January 2003 IR 07200043-02-002, on 11/04/2002 - 12/13/2002, Big Rock Point ML0234506212002-12-0909 December 2002 Closeout of Confirmatory Action Letter RIII-01-003 Big Rock Point IR 05000155/20020052002-11-0707 November 2002 IR 05000155-02-005, on 09/10/2002 - 09/18/20022002, Big Rock Point, Facilities Management & Control & Radiological Safety IR 05000155/20020042002-08-22022 August 2002 IR 05000155-02-004(DNMS), on 07/29-08/07/02, Big Rock. Decommissioning Activities Inspected Were Being Adequately Conducted IR 05000155/20020022002-05-0303 May 2002 IR 05000155/2002-002(DNMS) - Big Rock Point IR 05000155/20020012002-02-25025 February 2002 IR 05000155/2002-001(DNMS), Big Rock Point. Inspection on 02/07/2002 Related to Facilities Management and Control and Spent Fuel Safety. No Violations Noted IR 05000155/19990051999-09-30030 September 1999 Insp Rept 50-155/99-05 on 990731-0921,site Insp & 990929 Public Meeting.No Violations Noted.Major Areas Inspected: Routine Decommissioning Insp Covered Aspects of Facility Mgt & Control & Decommissioning Support Activities IR 05000155/19990041999-08-12012 August 1999 Insp Rept 50-155/99-04 on 990609-0730.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities Including Security, Spent Fuel Safety & Radiological Safety IR 05000155/19990031999-06-21021 June 1999 Insp Rept 50-155/99-03 on 990416-0608.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990021999-04-26026 April 1999 Insp Rept 50-155/99-02 on 990226-0415.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990011999-03-19019 March 1999 Insp Rept 50-155/99-01 on 990113-0225.One non-cited Violation Noted.Major Areas Inspected:Aspects of Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980091999-01-15015 January 1999 Insp Rept 50-155/98-09 on 981201-990112.No Violations Noted. Major Areas Inspected:Licensee Management & Control, Decommissioning Support Activities,Sf Safety & Radiological Safety IR 05000155/19980081998-12-0303 December 1998 Insp Rept 50-155/98-08 on 980827-1130.No Violations Noted. Major Areas Inspected:Radiological Safety IR 05000155/19980071998-10-14014 October 1998 Insp Rept 50-155/98-07 on 980827-1007.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Physical Security,Spent Fuel Safety & Radiological Safety IR 05000155/19980061998-09-0303 September 1998 Insp Rept 50-155/98-06 on 980716-0826.No Violations Noted. Major Areas Inspected:Aspects of Licensee Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980051998-07-24024 July 1998 Insp Rept 50-155/98-05 on 980528-0715.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980041998-07-0808 July 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-155/98-04 2024-02-05
[Table view] Category:Letter
MONTHYEARIR 05000155/20240012024-10-31031 October 2024 NRC Inspection Report No. 07200043/2024001; 05000155/2024001 Big Rock Point Independent Spent Fuel Storage Installation PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 PNP 2024-019, Updated Final Hazards Summary Report, Revision 192024-06-0404 June 2024 Updated Final Hazards Summary Report, Revision 19 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 07200043/20234012024-02-0505 February 2024 Public-Big Rock Point (BRP) Independent Spent Fuel Storage Installation (ISFSI) - NRC Security Inspection Report 07200043/2023401 L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point PNP 2023-015, License Termination Plan, Revision 42023-05-16016 May 2023 License Termination Plan, Revision 4 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 PNP 2023-007, And Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports2023-04-19019 April 2023 And Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports PNP 2023-013, 2022 Radiological Environmental Operating Report2023-04-12012 April 2023 2022 Radiological Environmental Operating Report 05000155/LER-1923-001, Human Performance Error Resulted in Compensatory Measures Not Properly Employed2023-04-11011 April 2023 Human Performance Error Resulted in Compensatory Measures Not Properly Employed L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance PNP 2023-009, Report of Changes, Tests and Experiments and Summary of Commitment Changes2023-03-28028 March 2023 Report of Changes, Tests and Experiments and Summary of Commitment Changes PNP 2023-003, Independent Spent Fuel Storage Installation Radioactive Effluent Release Report2023-02-15015 February 2023 Independent Spent Fuel Storage Installation Radioactive Effluent Release Report L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22215A1472022-08-0303 August 2022 & Big Rock Point Plant - Update Report for Holtec Decommissioning International (HDI) Fleet Decommissioning Quality Assurance Program (DQAP) Revision 2 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22213A0092022-07-27027 July 2022 2022 Holtec Palisades, LLC and Holtec Decommissioning International, LLC ANI Certified Copy Endorsements for Palisades Nuclear Plant and Big Rock Point Nuclear Generating Plant ML22182A4982022-07-0101 July 2022 And Big Rock Point Plant, Indemnity Agreements ML22173A1732022-06-28028 June 2022 And Big Rock Point Plant - Issuance of Amendment Nos. 129 and 273 Order Approving Transfer of Licenses and Conforming License Amendments (EPIDs L-2022-LLM-0002 and L-2020-LLM-0003) ML22178A0772022-06-24024 June 2022 (HDI) Satisfactory Documentary Evidence Required Before the Planned Closing Date of the Purchase and Sale Transaction of Palisades Nuclear Plant and Big Rock Point Plant PNP 2022-019, & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals2022-06-24024 June 2022 & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals ML22096A3042022-05-0909 May 2022 And Big Rock Point Plant - New Information Regarding Order Approving Transfer of Licenses (EPIDs L-2022-LLM-0002 and L-2020-LLM-0003) PNP 2022-003, And Big Pock Point Plant - 2021 Annual Radioactive Effluent Release and Waste Disposal Report2022-04-25025 April 2022 And Big Pock Point Plant - 2021 Annual Radioactive Effluent Release and Waste Disposal Report ML22104A0782022-04-14014 April 2022 Annual Report for Entergy Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d). Notification of Application of Approved Appendix B to 10 CFR 72 Subpart G ML22088A2552022-03-29029 March 2022 Change for NRC Distribution Lists Re Entergys Vice President, Regulatory Assurance ML22087A5002022-03-28028 March 2022 And Palisades Nuclear Power Plant - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) -- Entergy Nuclear Operations, Inc ML22081A2992022-03-21021 March 2022 Entergy Operations, Inc - Summary of Property Damage Insurance Coverage ML22073A1892022-03-14014 March 2022 River Bend Nuclear Station; and Waterford Steam Electric Station, Unit 3 - Proof of Financial Protection (10 CFR 140.15) PNP 2022-001, 2021 ISFSI Annual Radioactive Effluent Release Report2022-02-24024 February 2022 2021 ISFSI Annual Radioactive Effluent Release Report ML22025A3422022-01-25025 January 2022 And Big Rock Point - Changes to Site Organization ML22021B6702022-01-21021 January 2022 And Big Rock Point - Supplement to Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments ML21354A7452021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination ML21349A3742021-12-15015 December 2021 ISFSI, Decommissioning Funding Plans (10 CFR 72.30) ML21292A1452021-12-13013 December 2021 And Big Rock Point Plant - Order Approving Transfer of Licenses and Draft Conforming Administrative License Amendments (EPID L-2020-LLM-0003) (Letter) ML21302A0642021-10-29029 October 2021 And Big Rock Point - Supplement to Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments IR 07200043/20214012021-07-29029 July 2021 Independent Spent Fuel Storage Installation Security Inspection Report 07200043/2021401 PNP 2021-023, Biennial Update License Termination Plan2021-05-19019 May 2021 Biennial Update License Termination Plan PNP 2021-015, and Big Rock Point, Submittal of 2020 Annual Radioactive Effluent Release and Waste Disposal Report2021-04-21021 April 2021 and Big Rock Point, Submittal of 2020 Annual Radioactive Effluent Release and Waste Disposal Report ML21054A1322021-04-14014 April 2021 U.S. NRC Analysis of Entergy Nuclear Operations, Inc'S Initial and Updated Decommissioning Funding Plans for the Big Rock Point, Indian Point, Pilgrim, Palisades, Fitzpatrick, and Vermont Yankee Independent Spent Fuel Storage Installations ML21091A1472021-04-0101 April 2021 Annual Report for Entergy Quality Assurance Program Manual and Indian Point Energy Center Quality Assurance Program Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d) Notification of Application of Approved Appendix B to ML21089A3222021-03-30030 March 2021 Entergy Operations, Inc and Entergy Nuclear Operations, Inc. - Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML21084A8112021-03-25025 March 2021 Indian Point Nuclear Generating, Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) ML21084A7892021-03-25025 March 2021 Entergy Nuclear Operations, Inc. Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2020 - 10 CFR 50.82(a)(8)(vii) PNP 2021-009, 2020 ISFSI Annual Radioactive Effluent Release Report2021-02-25025 February 2021 2020 ISFSI Annual Radioactive Effluent Release Report 2024-08-02
[Table view] |
Text
ber 2, 2006
SUBJECT:
BIG ROCK POINT INSPECTION REPORTS 050-00155/06-02(DNMS) AND 072-00043/06-01(DNMS)
Dear Mr. Haas:
On October 18, 2006, the NRC completed inspection activities at the Big Rock Point Restoration Project. The purpose of the inspection was to conduct radiological confirmatory surveys and evaluate the biennial exercise of the Emergency Plan. At the conclusion of on-site inspection on October 18, the inspectors discussed the inspection findings with you and members of your staff.
This inspection consisted of independent radiological confirmatory surveys of areas of the Big Rock Point site that had not been previously surveyed by the NRC, and the observation and evaluation of the Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan exercise. Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection included a selective examination of procedures and representative records, observations of activities in progress, and interviews with personnel.
Based on the results of this inspection, the NRC did not identify any violations.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). The NRCs document system is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection.
Sincerely,
/RA/
Jamnes L. Cameron, Chief Decommissioning Branch Docket Nos. 050-00155; 072-00043 License No. DPR-6
Enclosures:
Inspection Reports 050-00155/06-02(DNMS); 072-00043/06-01(DNMS)
REGION III==
Docket Nos.: 050-00155; 072-00043 License No.: DPR-6 Report Nos.: 050-00155/06-02(DNMS);
072-00043/06-01(DNMS)
Licensee: Consumers Energy Company Facility: Big Rock Point Restoration Project Location: 10269 U.S. 31 North Charlevoix, MI 49720 Dates: October 16 through 18, 2006 Inspectors: William G. Snell, Senior Health Physicist Sam J. Mulay, Health Physicist Approved by: Jamnes L. Cameron, Chief Decommissioning Branch, Division of Nuclear Materials Safety Enclosure
EXECUTIVE SUMMARY Consumers Energy Company Big Rock Point Restoration Project NRC Inspection Reports 050-00155/06-02(DNMS) and 072-00043/06-01(DNMS)
This routine decommissioning inspection involved confirmatory radiological surveys and observation of a biennial exercise of the Independent Spent Fuel Storage Installation (ISFSI)
Emergency Plan.
Operation of an ISFSI
- The licensee adequately demonstrated the effectiveness of the ISFSI Emergency Plan and their ability to implement the Plan in response to an emergency. (Section 1.0)
Inspection of Final Surveys
- A review of licensee survey records and independent confirmatory surveys for residual radioactive contamination confirmed that the licensee is performing remediation and final status surveys consistent with the License Termination Plan. (Section 2.0)
2 Enclosure
Report Details1 1.0 Operation of an ISFSI (60855)
1.1 Inspection Scope The inspectors observed and evaluated the conduct of the Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan biennial exercise.
1.2 Observations and Findings Section 12.2.2 of Volume 35 of the ISFSI Emergency Plan requires the licensee to perform a biennial exercise to demonstrate emergency response capabilities and the effectiveness of the Emergency Plan. On October 17, 2006, the licensee conducted a biennial exercise based on a simulated earthquake that caused a spent fuel storage cask to tip over. In response to the event, the license appropriately implemented the Emergency Plan, correctly classified the event, augmented personnel as necessary, made timely notifications, conducted appropriate radiological monitoring, and ensured the safety of site personnel.
1.3 Conclusion The licensee adequately demonstrated the effectiveness of the ISFSI Emergency Plan and their ability to implement the Plan in response to an emergency.
2.0 Inspection of Final Surveys (83801)
2.1 Inspection Scope The inspectors performed independent radiological confirmatory surveys of selected on-site areas. Licensee records of final status surveys were also reviewed.
2.2 Observations and Findings Independent radiological gamma scan surveys were performed of the following survey areas using sodium iodide (NaI) scintillation detectors coupled to ratemeters with audible indication: South11C11 (50% scanned); 20C11 (80% scanned); South19C12 (30% scanned); North21C12 (50% scanned); eastern 20% of East22C12 (50% scanned);
and an area of about 50 square meters in the northeast corner of 18C13 (50% scanned).
In all areas surveyed, the inspectors did not identify elevated levels of direct gamma radiation in excess of background.
A list of acronyms used in the report is included at the end of the Report Details.
3 Enclosure
The following nine licensee final status survey records were reviewed, which included the Survey Area Requirements, Data Quality Objects, and the Final Status Survey (FSS)
Design:
Class 2 FSS Release Record, North21C12, Northeast Transport Route Class 1 FSS Release Record, 20C11, East Radwaste Staging Area Class 1 FSS Release Record, North11C11, North Radwaste Staging Area Class 1 FSS Release Record, South11C11, South Radwaste Staging Area Class 2 FSS Release Record, North19C12, Northwest Transport Route Class 2 FSS Release Record, South21C12, Southeast Transport Route Class 2 FSS Release Record, South19C12, Southwest Transport Route Class 2 FSS Release Record, West22C12, West Powerline Corridor Class 2 FSS Release Record, 15(1)C12, Eastern Section Woods Road Area The Survey Area Requirements, Data Quality Objects, and the Final Status Survey (FSS) Designs were adequate. For the above South Radwaste Staging Area (South11C11), and Southwest Transport Route (South19C12), the licensees survey scan results and the analytical results of soil samples were also reviewed. The final status survey soil sample results reviewed showed less than the derived concentration guideline levels (DCGLs) for soil of 11.93 picocuries per gram (pCi/g) for cesium-137 and 3.21 pCi/g for cobalt-60 as described in the licensees License Termination Plan (LTP). The licensees scan surveys indicated no elevated direct gamma radiation in excess of background 2.3 Conclusion A review of licensee survey records and independent confirmatory surveys for residual radioactive contamination confirmed that the licensee is performing remediation and final status surveys consistent with the LTP.
3.0 Exit Meeting Summary The inspectors presented preliminary inspection findings to members of the licensee management team at the conclusion of onsite inspection activities on October 18, 2006.
ATTACHMENT: SUPPLEMENTAL INFORMATION 4 Enclosure
SUPPLEMENTAL INFORMATION PARTIAL LIST OF PERSONS CONTACTED Consumers Energy Company
- Kurt Haas, Site General Manager
- Ken Pallagi, Radiation Protection & Environmental Services Manager
- Persons present at the exit meetings.
INSPECTION PROCEDURES USED IP 60855 Operation of an ISFSI IP 83801 Inspection of Final Surveys at Permanently Shutdown Reactors ITEMS OPENED, CLOSED, AND DISCUSSED Opened None Closed None Discussed None PARTIAL LIST OF DOCUMENTS REVIEWED Licensee documents reviewed and utilized during the course of this inspection are specifically identified in the Report Details above.
LIST OF ACRONYMS USED ADAMS Agencywide Documents Access and Management System DCGL Derived Concentration Guideline Level DNMS Division of Nuclear Materials Safety FSS Final Status Survey ISFSI Independent Spent Fuel Storage Installation LTP License Termination Plan NRC Nuclear Regulatory Commission pCi/g picocuries per gram Attachment
6 Attachment