MONTHYEARIR 05000155/20240012024-10-31031 October 2024 NRC Inspection Report No. 07200043/2024001; 05000155/2024001 Big Rock Point Independent Spent Fuel Storage Installation IR 07200043/20234012024-02-0505 February 2024 Public-Big Rock Point (BRP) Independent Spent Fuel Storage Installation (ISFSI) - NRC Security Inspection Report 07200043/2023401 IR 07200043/20214012021-07-29029 July 2021 Independent Spent Fuel Storage Installation Security Inspection Report 07200043/2021401 IR 05000155/20200012020-11-0202 November 2020 Inspection Report No. 07200043/2020001(DNMS) and 05000155/2020001(DNMS), Docket Nos. 07200043, 05000155, License No. DPR-6 IR 05000155/20180012018-11-26026 November 2018 NRC Inspection Report 07200043/2018001(DNMS); 05000155/2018001(DNMS) Big Rock Point Independent Spent Fuel Storage Installation IR 07200043/20184012018-05-31031 May 2018 Independent Spent Fuel Storage Installation - Security Inspection Report 07200043/2018401 (DRS-E.Bonano) IR 05000155/20170012017-05-17017 May 2017 Independent Spent Fuel Storage Installation, NRC Inspection Report 07200043/2017001 (DNMS) and 05000155/2017001(DNMS) IR 05000155/20140072014-10-31031 October 2014 IR 07200043/2014001 (DNMS) and 05000155/2014007 (Dnms), 10/7-8/2014, Big Rock Point Independent Spent Fuel Storage Installation IR 05000155/20120072013-03-11011 March 2013 Errata to Big Rock Point Independent Spent Fuel Storage Installation - Inspection Reports 07200043-12-001(DNMS) and 05000155-12-007(DNMS) IR 05000155/20120012013-01-0808 January 2013 IR 07200043-12-001 & 05000155-12-001, 12/18/2012, Big Rock Point Plant and Independent Spent Fuel Storage Installation IR 05000155/20124012012-12-18018 December 2012 IR 05000155-12-403, and 07200043-12-401, 11/29/2012, Big Rock Point ISFSI - Cover Letter IR 05000155/20124032012-12-18018 December 2012 IR 05000155-12-403, and 07200043-12-401, 11/29/2012, Big Rock Point ISFSI - Cover Letter IR 05000155/20080012008-11-13013 November 2008 IR 072-00043-08-001,050-00155-08-001(DNMS) on 10/22/08 - 10/24/08, Big Rock Point Independent Spent Fuel Storage Installation IR 05000155/20060022006-11-0202 November 2006 IR 05000155-06-002 (DNMS) and 07200043-06-001 (Dnms), on 10/18/06, Big Rock Point, Confirmatory Radiological Surveys and Observation of a Biennial Exercise of ISFSI Emergency Plan IR 05000155/20060012006-09-29029 September 2006 IR 05000155-06-001, on 05/08-09/2006, 06/02/2006, 06/13-15/2006, 07/05/2006, & 09/13/2006, Big Rock Point IR 05000155/20050052006-01-0505 January 2006 IR 05000155-05-005, on 10/18-20/2005, and 12/9-13/2005, Big Rock Point (DNMS) IR 05000155/20050042005-11-21021 November 2005 IR 05000155-05-004 on November 10, 2005 IR 05000155/20050022005-08-0303 August 2005 IR 05000155-05-002 (DNMS) & IR 07200043-05-001(DNMS), on 07/14/05, Big Rock Point, Routine Decommissioning Inspection IR 05000155/20050012005-04-0505 April 2005 IR 05000155-05-001(DNMS), on 01/19-21/2005 and 03/07-10/2005, Big Rock Point, Decommissioning Inspection IR 05000155/20040032005-01-18018 January 2005 IR 05000155-04-003 (Dnms), on 10/12/2004 - 10/15/2004, 11/01/2004 - 11/05/2004, 12/13/2004 - 12/16/2004 & 01/07/2005 and Notice of Violation - Big Rock Point, Decommissioning Activities IR 05000155/20040022004-10-0606 October 2004 IR 05000155-04-002, on 07/19-23/2004, 08/10-12/2004, 08/30/2004 - 09/03/2004 & 09/20-22/2004, Consumers Energy Co, Big Rock Point Restoration Project, Routine Decommissioning Inspections IR 05000155/20040012004-07-0202 July 2004 IR 05000155-04-001(DNMS), Big Rock Point, on 04/12/04 - 04/16/04, 05/11/04 - 05/14/04, and 06/01/04 - 06/04/04, Decommissioning Support Activities ML0407009702004-03-10010 March 2004 IR 05000155-03-007, on 12/01/2003 - 12/04/2003, 01/12/2004 - 01/15/2004 & 02/17/2004 - 02/20/2004, Big Rock Point Nuclear Plant Decommissioning Inspection IR 05000155/20030072004-03-10010 March 2004 Letter Form C. Miller to Kurt Haas Regarding Big Rock Point Inspection Report 05000155-03-007 IR 05000155/20030052003-11-0707 November 2003 IR 05000155-03-005, on 09/08/2003 - 10/09/2003, Big Rock Point, Decommissioning Inspection IR 05000155/20030042003-09-12012 September 2003 IR 05000155-03-004 (DNMS) Big Rock Point, 07/14/03 - 08/16/03. Review of Licensee'S Performance Related to Decommissioning Support Activities and Radiological Safety IR 07200043/20030032003-08-29029 August 2003 IR 07200043-03-003, on 8/12/03 Through 8/14/03, for Consumers Energy Co., Charlevoix, Mi; Security Measures for Independent Spent Fuel Storage Installations and Verification of Compliance with Interim Compensatory Measures Order IR 05000155/20030032003-07-16016 July 2003 IR 05000155-03-003, on 05/27/2003 - 06/19/2003, for Big Rock Point Nuclear Plant; Big Rock Point Restoration Project IR 05000155/20030022003-06-18018 June 2003 Letter from C. Miller to Kurt Haas Regarding Big Rock Point IR 05000155-03-002 & IR 07200043-03-002 ML0317002202003-06-18018 June 2003 IR 05000155-03-002 & IR 07200043-03-002(DNMS), on 03/17 - 05/19/2003, Big Rock Point. No Violations Noed ML0308508012003-03-25025 March 2003 Memo 03/25/03 Big Rock Point Re DRS Input to DNMS Report 50-155/03-02 IR 05000155/20030012003-03-12012 March 2003 IR 05000155-03-001(DNMS) on 01/06/03 and 02/21/03 for Big Rock Point, Reviewing Licensee'S Performance Related to Spent Fuel Safety and Radiological Safety IR 05000155/20020072003-01-16016 January 2003 IR 05000155-02-007, on 11/11/2002 - 12/23/2002, Big Rock Point. Big Rock Point Restoration Project IR 07200043/20020022003-01-0909 January 2003 IR 07200043-02-002, on 11/04/2002 - 12/13/2002, Big Rock Point ML0234506212002-12-0909 December 2002 Closeout of Confirmatory Action Letter RIII-01-003 Big Rock Point IR 05000155/20020052002-11-0707 November 2002 IR 05000155-02-005, on 09/10/2002 - 09/18/20022002, Big Rock Point, Facilities Management & Control & Radiological Safety IR 05000155/20020042002-08-22022 August 2002 IR 05000155-02-004(DNMS), on 07/29-08/07/02, Big Rock. Decommissioning Activities Inspected Were Being Adequately Conducted IR 05000155/20020022002-05-0303 May 2002 IR 05000155/2002-002(DNMS) - Big Rock Point IR 05000155/20020012002-02-25025 February 2002 IR 05000155/2002-001(DNMS), Big Rock Point. Inspection on 02/07/2002 Related to Facilities Management and Control and Spent Fuel Safety. No Violations Noted IR 05000155/19990051999-09-30030 September 1999 Insp Rept 50-155/99-05 on 990731-0921,site Insp & 990929 Public Meeting.No Violations Noted.Major Areas Inspected: Routine Decommissioning Insp Covered Aspects of Facility Mgt & Control & Decommissioning Support Activities IR 05000155/19990041999-08-12012 August 1999 Insp Rept 50-155/99-04 on 990609-0730.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities Including Security, Spent Fuel Safety & Radiological Safety IR 05000155/19990031999-06-21021 June 1999 Insp Rept 50-155/99-03 on 990416-0608.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990021999-04-26026 April 1999 Insp Rept 50-155/99-02 on 990226-0415.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990011999-03-19019 March 1999 Insp Rept 50-155/99-01 on 990113-0225.One non-cited Violation Noted.Major Areas Inspected:Aspects of Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980091999-01-15015 January 1999 Insp Rept 50-155/98-09 on 981201-990112.No Violations Noted. Major Areas Inspected:Licensee Management & Control, Decommissioning Support Activities,Sf Safety & Radiological Safety IR 05000155/19980081998-12-0303 December 1998 Insp Rept 50-155/98-08 on 980827-1130.No Violations Noted. Major Areas Inspected:Radiological Safety IR 05000155/19980071998-10-14014 October 1998 Insp Rept 50-155/98-07 on 980827-1007.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Physical Security,Spent Fuel Safety & Radiological Safety IR 05000155/19980061998-09-0303 September 1998 Insp Rept 50-155/98-06 on 980716-0826.No Violations Noted. Major Areas Inspected:Aspects of Licensee Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980031998-08-25025 August 1998 Discusses NRC Insp Rept 50-155/98-03 on 980527.Violations Noted.Insp Findings Documented in NRC Insp Rept Sent to Util by Ltr IR 05000155/19980051998-07-24024 July 1998 Insp Rept 50-155/98-05 on 980528-0715.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety 2024-02-05
[Table view] Category:Letter
MONTHYEARML24344A0692024-12-0909 December 2024 Proof of Financial Protection 10 CFR 140.15 IR 05000155/20240012024-10-31031 October 2024 NRC Inspection Report No. 07200043/2024001; 05000155/2024001 Big Rock Point Independent Spent Fuel Storage Installation PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 PNP 2024-019, Updated Final Hazards Summary Report, Revision 192024-06-0404 June 2024 Updated Final Hazards Summary Report, Revision 19 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 07200043/20234012024-02-0505 February 2024 Public-Big Rock Point (BRP) Independent Spent Fuel Storage Installation (ISFSI) - NRC Security Inspection Report 07200043/2023401 L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point PNP 2023-015, License Termination Plan, Revision 42023-05-16016 May 2023 License Termination Plan, Revision 4 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 PNP 2023-007, And Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports2023-04-19019 April 2023 And Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports PNP 2023-013, 2022 Radiological Environmental Operating Report2023-04-12012 April 2023 2022 Radiological Environmental Operating Report 05000155/LER-1923-001, Human Performance Error Resulted in Compensatory Measures Not Properly Employed2023-04-11011 April 2023 Human Performance Error Resulted in Compensatory Measures Not Properly Employed L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance PNP 2023-009, Report of Changes, Tests and Experiments and Summary of Commitment Changes2023-03-28028 March 2023 Report of Changes, Tests and Experiments and Summary of Commitment Changes PNP 2023-003, Independent Spent Fuel Storage Installation Radioactive Effluent Release Report2023-02-15015 February 2023 Independent Spent Fuel Storage Installation Radioactive Effluent Release Report L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22215A1472022-08-0303 August 2022 & Big Rock Point Plant - Update Report for Holtec Decommissioning International (HDI) Fleet Decommissioning Quality Assurance Program (DQAP) Revision 2 ML22213A0092022-07-27027 July 2022 2022 Holtec Palisades, LLC and Holtec Decommissioning International, LLC ANI Certified Copy Endorsements for Palisades Nuclear Plant and Big Rock Point Nuclear Generating Plant ML22182A4982022-07-0101 July 2022 And Big Rock Point Plant, Indemnity Agreements ML22173A1732022-06-28028 June 2022 And Big Rock Point Plant - Issuance of Amendment Nos. 129 and 273 Order Approving Transfer of Licenses and Conforming License Amendments (EPIDs L-2022-LLM-0002 and L-2020-LLM-0003) PNP 2022-019, & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals2022-06-24024 June 2022 & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals ML22178A0772022-06-24024 June 2022 (HDI) Satisfactory Documentary Evidence Required Before the Planned Closing Date of the Purchase and Sale Transaction of Palisades Nuclear Plant and Big Rock Point Plant ML22096A3042022-05-0909 May 2022 And Big Rock Point Plant - New Information Regarding Order Approving Transfer of Licenses (EPIDs L-2022-LLM-0002 and L-2020-LLM-0003) PNP 2022-003, And Big Pock Point Plant - 2021 Annual Radioactive Effluent Release and Waste Disposal Report2022-04-25025 April 2022 And Big Pock Point Plant - 2021 Annual Radioactive Effluent Release and Waste Disposal Report ML22104A0782022-04-14014 April 2022 Annual Report for Entergy Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d). Notification of Application of Approved Appendix B to 10 CFR 72 Subpart G ML22088A2552022-03-29029 March 2022 Change for NRC Distribution Lists Re Entergys Vice President, Regulatory Assurance ML22087A5002022-03-28028 March 2022 And Palisades Nuclear Power Plant - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) -- Entergy Nuclear Operations, Inc ML22081A2992022-03-21021 March 2022 Entergy Operations, Inc - Summary of Property Damage Insurance Coverage ML22073A1892022-03-14014 March 2022 River Bend Nuclear Station; and Waterford Steam Electric Station, Unit 3 - Proof of Financial Protection (10 CFR 140.15) PNP 2022-001, 2021 ISFSI Annual Radioactive Effluent Release Report2022-02-24024 February 2022 2021 ISFSI Annual Radioactive Effluent Release Report ML22025A3422022-01-25025 January 2022 And Big Rock Point - Changes to Site Organization ML22021B6702022-01-21021 January 2022 And Big Rock Point - Supplement to Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments ML21354A7452021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination ML21349A3742021-12-15015 December 2021 ISFSI, Decommissioning Funding Plans (10 CFR 72.30) ML21292A1452021-12-13013 December 2021 And Big Rock Point Plant - Order Approving Transfer of Licenses and Draft Conforming Administrative License Amendments (EPID L-2020-LLM-0003) (Letter) ML21302A0642021-10-29029 October 2021 And Big Rock Point - Supplement to Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments IR 07200043/20214012021-07-29029 July 2021 Independent Spent Fuel Storage Installation Security Inspection Report 07200043/2021401 PNP 2021-023, Biennial Update License Termination Plan2021-05-19019 May 2021 Biennial Update License Termination Plan ML21111A1782021-04-21021 April 2021 And Big Rock Point, Submittal of 2020 Annual Radioactive Effluent Release and Waste Disposal Report ML21054A1322021-04-14014 April 2021 U.S. NRC Analysis of Entergy Nuclear Operations, Incs Initial and Updated Decommissioning Funding Plans for the Big Rock Point, Indian Point, Pilgrim, Palisades, Fitzpatrick, and Vermont Yankee Independent Spent Fuel Storage Installations ML21091A1472021-04-0101 April 2021 Annual Report for Entergy Quality Assurance Program Manual and Indian Point Energy Center Quality Assurance Program Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d) Notification of Application of Approved Appendix B to ML21089A3222021-03-30030 March 2021 Entergy Operations, Inc and Entergy Nuclear Operations, Inc. - Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML21084A8112021-03-25025 March 2021 Indian Point Nuclear Generating, Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) ML21084A7892021-03-25025 March 2021 Entergy Nuclear Operations, Inc. Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2020 - 10 CFR 50.82(a)(8)(vii) 2024-08-02
[Table view] |
Text
ber 12, 2003
SUBJECT:
BIG ROCK POINT INSPECTION REPORT 05000155/2003-004(DNMS)
Dear Mr. Haas:
On August 16, 2003, the NRC completed an inspection at the Big Rock Point Nuclear Plant.
The purpose of the inspection was to determine whether decommissioning activities were conducted safely and in accordance with NRC requirements. Specifically, the inspectors evaluated decommissioning support activities and radiological safety. At the conclusion of on-site inspections on August 16, 2003, the inspectors discussed the inspection findings with you and members of your staff.
This inspection consisted of an examination of decommissioning activities at the Big Rock Point Nuclear Plant as they relate to safety and compliance with the Commissions rules and regulations. Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection consisted of a selective examination of procedures and representative records, observations of activities in progress, and interviews with personnel.
Based on the results of this inspection, the NRC did not identify any violations. The decommissioning activities reviewed were being conducted in accordance with applicable regulations and license conditions.
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
We will gladly discuss any questions you may have regarding this inspection.
Sincerely,
/RA/
Christopher G. Miller, Chief Decommissioning Branch Docket No. 05000155 License No. DPR-6
Enclosure:
Inspection Report 05000155/2003-004(DNMS)
See Attached Distribution DOCUMENT NAME: C:\ORPCheckout\FileNET\ML032550527.wpd To receive a copy of this document, indicate in the box:"C" = Copy without enclosure "E"= Copy with enclosure"N"= No copy OFFICE RIII RIII RIII NAME Snell:mb Kulzer Miller DATE 09/12/03 09/12/03 09/12/03 OFFICIAL RECORD COPY
REGION III==
Docket No. 05000155 License No. DPR-06 Report No. 05000155/2003-004(DNMS)
Licensee: Consumers Energy Company Facility: Big Rock Point Nuclear Plant Location: 10269 U.S. 31 North Charlevoix, MI 49720 Dates: July 14 - August 16, 2003 Inspector: William Snell, Health Physics Manager Ed Kulzer, Radiation Protection Specialist Approved by: Christopher G. Miller, Chief Decommissioning Branch Division of Nuclear Materials Safety
EXECUTIVE SUMMARY Big Rock Point Restoration Project NRC Inspection Report 05000155/2003-004(DNMS)
This routine decommissioning inspection involved review of the licensees performance related to decommissioning support activities and radiological safety. During this inspection period, major activities included cleaning and draining the spent fuel pool and preparations for removal of the reactor vessel and steam drum.
Decommissioning Support Activities
Management of the decommissioning organization and staffing levels were adequate to effectively implement the decommissioning process. (Section 1.1)
Radiological Safety
Training and records for 14 new radiation and junior radiation protection technicians met program requirements. The technicians used appropriate techniques during radiological surveys. There were no concerns in this area. (Section 2.1)
The licensee integrated As-Low-As-Reasonably-Achievable (ALARA) radiation protection practices into the work activities associated with the lifting of the reactor vessel for placement into the shipping cask. (Section 2.2)
The final radiological survey packages for the Lawn and Tool Building, the Butler Building, and the Source Check Building were very thorough, well organized, and complete. The inspectors identified no concerns with the demolition of these buildings.
(Section 2.3)
No concerns were identified regarding the information provided in the Big Rock Point Radioactive Environmental Report, January 1, 2002 - December 31, 2002" and the Big Rock Point Annual Radiological Effluent Release Report, January 1, 2002 -
December 31, 2002." (Section 2.4)
The Waste Disposition Interim Action document issued by the licensee provided guidance for adequate management oversight to prevent radioactive waste from being mixed into the non-radioactive waste streams leaving the site. (Section 2.5)
The licensee complied with regulatory requirements while releasing batch quantities of water from the site. (Section 2.6)
Report Details1 1.0 Decommissioning Support Activities 1.1 Organization, Management and Cost Controls (36801)
a. Inspection Scope The inspectors evaluated the licensees decommissioning organization and staffing to determine whether adjustments were made to accommodate changes in the status of decommissioning activities.
b. Observations and Findings Based on attendance at the licensees daily management meetings where decommissioning issues such as project status, performance indicators, schedules, condition reports, radiation protection, the As-Low-As-Reasonably-Achievable (ALARA)
program, safety, changing conditions at the facility, and accident trends were discussed, the inspectors observed the management team effectively working together to implement the sites decommissioning program.
Although plant staffing had increased due to an increase in decommissioning activities, the additional personnel were being effectively integrated into the work activities. No degradation in work performance was noted based on the addition of new personnel.
c. Conclusions Management of the decommissioning organization and staffing levels were adequate to effectively implement the decommissioning process.
2.0 Radiological Safety 2.1 Occupational Radiation Exposure (83750)
a. Inspection Scope The inspectors reviewed training records and on-the-job training for 14 new radiation and junior radiation protection technicians.
b. Observations and Findings Training requirements are contained in Big Rock Point Administrative Procedure 1.7, titled Master Training Program. Specific training requirements for radiation protection are covered in Big Rock Point Program No. D19.0, titled, Big Rock Point Radiation &
Environmental Services Program.
A list of acronyms used in the report is included at the end of the Report Details.
The licensee created a new position classification titled junior radiation protection technician. This new classification will require the same training as that required for the radiation protection technician except that it does not require confined space entry and respirator training.
The inspectors randomly selected and reviewed the training records of 3 of the 14 new technicians. Individual training records were consistent with the requirements in the Master Training Program and Big Rock Point Radiation & Environmental Services Program.
These new radiation and junior radiation technicians were observed conducting radiological field surveys during the surveying of the Maintenance Building scheduled for dismantlement and removal to another site.
c. Conclusions Training and records for fourteen new radiation and junior radiation protection technicians met program requirements. The technicians used appropriate techniques during radiological surveys. There were no concerns in this area.
2.2 Occupational Radiation Exposure (83750)
a. Inspection Scope The inspectors evaluated ALARA activities associated with the lifting of the reactor vessel for placement into its shipping cask.
b. Observations and Findings The inspector attended pre-job briefings and observed licensee activities during initial efforts to lift the reactor vessel and move it into a shipping cask. Dose rate levels on the exterior of the vessel were as high as 50 rem per hour (rem/hr) on contact, while components in the vicinity of the vessel were as high as 2-3 rem/hr. These high dose rates became an issue when various obstructions prevented the vessel from being lifted more than 8 to 9 inches. This required numerous additional entries into the high dose areas to remove material manually or by cutting with an acetylene torch. Throughout this evolution the licensee was consistently conscious of personnel dose. Workers were rotated to minimize the dose to each worker, and the job briefings constantly emphasized the need to minimize stay times and to maintain an awareness of where the high dose areas were located. Health physics personnel effectively monitored work activities in progress, including monitoring workers electronic dosimetry at least every 15 minutes.
c. Conclusions The licensee integrated ALARA radiation protection practices into the work activities associated with the lifting of the reactor vessel for placement into the shipping cask.
2.3 Inspection of Final Surveys at Permanently Shutdown Reactors (83801)
a. Inspection Scope The inspectors reviewed the final radiological survey packages for three buildings to verify the documentation was adequate in scope and content to support the remediation and demolition of the buildings.
b. Observations and Findings The inspectors reviewed the final radiological survey packages for three buildings; the Lawn and Tool Building (B-22), the Butler Building (B-21), and the Source Check Building (B-13). For each of these buildings the inspectors reviewed the Quality Review Form, the Information Package, and the Verification Surveys. The information provided in the survey closure packages was very thorough, well organized, and complete. The survey data indicated that the buildings had been adequately remediated and could be demolished and disposed of via the bulk monitoring program. No concerns were identified in the survey packages for these buildings.
c. Conclusions The final radiological survey packages for the Lawn and Tool Building, the Butler Building, and the Source Check Building were very thorough, well organized, and complete. The inspectors identified no concerns with the demolition of these buildings.
2.4 Review of Annual Radioactive Environmental and Effluent Release Reports (84750)
a. Inspection Scope The Big Rock Point Radioactive Environmental Report, January 1, 2002 -
December 31, 2002" and the Big Rock Point Annual Radiological Effluent Release Report, January 1, 2002 - December 31, 2002" were reviewed. The review included evaluations of the summaries, interpretations, and statistical evaluations provided within the Environmental Report and the summary of the quantities of radioactive liquid and gaseous effluents and solid waste released provided within the Effluent Release Report.
b. Observations and Findings The inspectors verified that the scope and content of the above two reports were consistent with the requirements of Sections 6.7.2 and 6.7.3 of the Big Rock Point Defueled Technical Specifications. The inspectors reviewed data in the reports and agreed with the licensees determination that the calendar year 2002 data was consistent with related data from previous years, and no unusual or anomalous data were identified.
c. Conclusions No concerns were identified regarding the information provided in the Big Rock Point Radioactive Environmental Report, January 1, 2002 - December 31, 2002" and the Big Rock Point Annual Radiological Effluent Release Report, January 1, 2002 -
December 31, 2002."
2.5 Solid Radioactive Waste Management and Transportation of Radioactive Materials (86750)
a. Inspection Scope The inspectors reviewed the adequacy of a Waste Disposition Interim Action issued by the licensee.
b. Observations and Findings The licensee issued a Waste Disposition Interim Action dated July 15, 2003, to ensure demolition debris would be dispositioned to the appropriate waste streams as identified in each work package. The action requires an approval signature from one of three individuals; the ALARA/Work Control Coordinator, the Bulk Material Field Supervisor, or the ALARA Superintendent as a means of ensuring adequate management oversight of the disposition of waste.
The above action was taken to prevent radioactive waste from being mixed into the non-radioactive waste streams leaving the site.
c. Conclusions The Waste Disposition Interim Action issued by the licensee provided adequate management oversight to prevent radioactive waste from being mixed into the non-radioactive waste streams leaving the site.
2.6 Radwaste Treatment, and Environmental and Effluent Monitoring (84750)
a. Inspection Scope The inspector verified that batch releases of water from Big Rock Point were in compliance with regulatory requirements.
b. Observations and Findings To reduce the volume of water on site during the spent fuel clean-up work, the licensee conducted batch releases of water to the environment during May and June 2003. Prior to release, the water was analyzed as required by Procedure No. TV-05/RCP-7, Analysis of Liquid Radioactive Batch, Revision 40. TV-05/RCP-7 ensures that the levels of radioactivity in the water meet the release limits specified in the Offsite Dose Calculation Manual, Volume 25, Section 2.2, Liquid Effluents Concentration, Revision 23.
The inspector reviewed the adequacy of Procedure No. TV-05/RCP-7 and the analysis results for five batch releases. This included two releases from a tank in a sealand container that were approximately 2,000 gallons and 3,600 gallons, and three releases from the Condensate Storage Tank that were 13,900 gallons, 23,100 gallons and 24,000 gallons.
c. Conclusions Batch releases of water from Big Rock Point were being made in compliance with regulatory requirements.
3.0 Exit Meetings The inspectors presented preliminary inspection results to members of licensee management at the conclusion of onsite inspections on July 17, 2003, and August 16, 2003. The licensee acknowledged the findings presented. The licensee did not identify any documents or processes reviewed by the inspectors as proprietary.
PARTIAL LIST OF PERSONS CONTACTED Licensee K. Haas, Plant General Manager K. Pallagi, Radiation Protection & Environmental Services Manager W. Trubilowicz, Dry Fuel Storage Manager G. Withrow, Engineering, Operations & Licensing Manager INSPECTION PROCEDURES USED IP 36801 Organization, Management and Cost Controls IP 83750 Occupational Radiation Exposure IP 83801 Inspection of Final Surveys at Permanently Shutdown Reactors IP 84750 Review of Annual Radioactive Environmental and Effluent Release Reports IP 86750 Solid Radioactive Waste Management and Transportation ITEMS OPENED, CLOSED, AND DISCUSSED Opened None Closed None Discussed None LICENSEE DOCUMENTS REVIEWED Licensee documents reviewed and utilized during the course of this inspection are specifically identified in the Report Details above.
LIST OF ACRONYMS USED ALARA As-Low-As-Reasonably-Achievable BRP Big Rock Point DNMS Division of Nuclear Materials Safety NRC Nuclear Regulatory Commission